INSPECTION SCHEDULE FOR 16MVA TRANSFORMER PO. No. D/PRO/2005/0198 Dated 01.03.05.

Please include the tests shown in red in your test schedule. With these comments the test schedule is approved as per the contract.

Sr. No 1

Test Description Measurement of Voltage Ratio, Polarity test

IS CLAUSE REF IS 2026, PART 1, CL .16.3

DAY DAY 1

Measurement of Insulation resistance at 20,60,120 and 600 sec, calculation of Absorption Ratio & PI.PI shall be at least 2.

CL. 16.6

DAY 1

3 4 5

Vector group test. Load loss and impedance voltage measurement No load loss measurement at 90%,100%,110% of rated voltage and no load amp. measurement

CL. 16.3 CL. 16.4 CL .16.5

DAY 1 DAY 1 DAY 1

Measurement of winding resistance at different taps in ascending order & descending order

CL 16.2

DAY 1

7 8 9 10 11 12

Measurement of transformer oil breakdown voltage Separate source voltage withstand test Induced overvoltage withstand test. Report preparation and signature Magnetic Balance test Capacitance & Tan delta test on T/F winding with LV set / HV set

IS 335 CL. 16.7 CL. 16.7 --

DAY 1 DAY 1 DAY 1 DAY 2

13 14

CT Polarity test of all CTs Insulation Resistance Measurement of Core insulation with 2kV AC/DC

15 16 17

2kV test on Marshalling Panel Functional test of Buchholtz, OTI,WTI,CCU,PRV etc Please show the incorporation of JSL/Mecon comments on the T/F to JSL inspector

18

T/F efficiency and regulation calculation

Please note that all test instruments/equipments have valid calibration certificates traceable to National Laboratories and shall be made available to JSL inspector.