ISI KANDUNGAN
Lokasi Projek Ringkasan projek Matlamat jangka masa pendek dan panjang projek Golongan sasaran projek Jangka masa projek sehingga siap
Coastal Highway 1
Coastal Highway
Abu Bakar - Skudai
Yahya Awal & Abu Bakar Interchange Skudai - Senai Highway Ulu Tiram Interchange Jalan Kolam Air
JSNAC INT
DANGA INT
CH 14515
CH 9500
CH 2400
NUSAJAYA INT
SECTION 3
SECTION 2
SECTION 1
CH 0
RINGKASAN PROJEK
Mainline Dual-3 lane carriageway with paved shoulders Mainline Length 14.5 km
Interchanges Ten (10) Interchanges at: No 1 - TAR No.2 - DB1 Access No 3 - Danga No 4 - Perling No 5 - Bukit Indah No 6 - Taman Tema 2 No 7 -Taman Tema 1 No 8 - JASNAC No.9 - Medini North underpass No 10 - Nusajaya Left-in/ Left-out Junctions at selected locations Danga Development Taman Perling Development Horizon Hill Development
River Bridges River bridges at: 1. Sg. Kempas (Mainline) 2. Sg. Skudai & Sg. Danga (Mainline) 3. Sg. Melayu at Taman Tema 1 4. Sg. Lalang 5. Sg Melayu Tributary (for 2 Slip Road Bridges)
Works involved: Site Clearance and Earthworks Relocation of Utilities Traffic Management Bridge and Retaining Structures Ground Treatments at soft ground areas Drainages Pavement works Road Furniture and Street Lightings Landscape
To open up and expedite new economic growth area estimated GDV about RM 8.72 Billion as follows :
Medini - RM 4.2 billion APH Petroleum Hub - RM 1.4 billion Cahaya Jauhar - RM 1 billion IDR Resort - RM 0.87 billion Pinewood Studio - RM 0.4 billion Indoor Theme Park - RM 0.35 billion
To provide job opportunities and to improve quality of life. To improve on traffic dispersal and to reduce congestion. To link between Johor Bahru City Centre to New Administration
at Kota Iskandar .
PERANCANGAN
IRDA JKR & OTHER TECHNICAL AGENCY
MAIN DESIGN & BUILD CONTRACTOR SJIC BINA SDN. BHD. PROJECT MANAGEMENT CONSULTANT IDMS SDN. BHD. WORKS DESIGN & BUILD CONTRACTOR PEMBINAAN KS TEBRAU SDN. BHD.
PERLAKSANAAN
IRDA
IRDA
SUPERVISION CONSULTANT MAIN DESIGN & BUILD CONTRACTOR SJIC BINA SDN. BHD. PROJECT MANAGEMENT CONSULTANT IDMS SDN. BHD.
PENYERAHAN
IRDA
IRDA SUPERVISION CONSULTANT MAIN DESIGN & BUILD CONTRACTOR SJIC BINA SDN. BHD. PROJECT MANAGEMENT CONSULTANT IDMS SDN. BHD. WORKS DESIGN & BUILD CONTRACTOR PEMBINAAN KS TEBRAU SDN. BHD.
JKR MALAYSIA
Note: IRDA will certify the project as completed once JKR has inspected and verified the project as satisfactorily executed according to specification and standards
PROJECT COMPLETED
ISKANDAR REGIONAL DEVELOPMENT AUTHORITY (IRDA)
STATUS REPORT FOR : PROJECT 1 MEMBINA LEBUHRAYA PESISIR PANTAI DARI JOHOR BAHRU KE NUSAJAYA, JOHOR BAHRU, JOHOR DARUL TAKZIM. CONSULTANTS: PMC- IDMS Sdn. Bhd. C&S Zaidun-Leeng QS PNFL Sdn Bhd PHYSICAL PROGRESS
30 JULAI 2010
FINANCIAL PROGRESS AHEAD / DELAY 1.22%
945,798,602.35
23-Dec-08
22-Dec-11
36
Financial Status
IPC Certified Paid Outstanding
IRDA (RM) No. 01 - No. 18 (July 2010) RM 456,856,578.79 No.01- 17 & Advance Payment RM 384,104,057.02
No. 18 RM 32,630,041.90
Retention Sum RM 45,192,677.67 Adv. Recoupment RM 4,929,802.20
ISKANDAR REGIONAL DEVELOPMENT AUTHORITY (IRDA)
Remarks
BELANJAWAN PROJEK
No Project Name Date and Amount of Allocation Received (RMmil) Consultants Contractors Land Consultants Consultants Contractors 301.5 ( 26 Aug 2008) 4 Drainage System Consultants Contractors Land Planning Fees & Earthworks Contribution Fees Trust Fund Contractors Consultants Total Utilisation as at 31 July 2010 (RMmil) 5.0 729.6 252.7 1.3 1.7 88.9 2.8 110.4 2.6 0.2 0.5 0.2 88.1 10.1 59.4 13.1 1.4 9.3 2.0 3.1 0.5 9.6 987.3 1.3 90.6
2
3
115.8
99.1
River Cleaning Squatters Relocation Blueprints Kulai Interchange Security Initiatives Public Transportation Enhancement IM Exhibition Centre Human Capital Development Programme Total
7 8
9 10 11 12
1,564.5
ISKANDAR REGIONAL DEVELOPMENT AUTHORITY (IRDA)
1,392.5
1,392.5
SUMBER PEMBIAYAAN
Allocation from Development Expenditure (DE) for RMKe-9 under Jabatan Perdana Menteri
Original Ceiling (RM Million) Contract Amount (RM Million) Land (RM Million) Consultancy (RM Million) Total (RM Million)
477.00
945.80
219.16
2.92
948.71
Year
190.00 610.00
800.00
Cumm Cumm Actual Planned Overall (RM Overall (RM '000) '000) Months
RM (RM '000)
1,000,000
100,000
200,000
300,000
400,000
500,000
600,000
700,000
800,000
900,000
0 0 0 28,847 41,710 52,776 2009 69,800 98,268 141,775 154,543 182,445 230,680 307,101 329,800 363,660 408,585 457,388 486,897 523,783 478,007 525,769 569,087 618,552 663,667 704,336 748,978 787,377 825,588 862,095 897,847 923,951 935,868 942,015 943,056 944,664 945,799 427,501 384,183 Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 342,190 May-10 305,966 Apr-10 264,351 Mar-10 224,722 Feb-10 179,796 Jan-10 136,290 Dec-09 100,255 Nov-09 70,084 Oct-09 44,358 Sep-09 25,158 Aug-09 10,782 Jul-09 5,296 Jun-09 1,230 May-09 473 Apr-09 189 Mar-09 0 Feb-09
Jan-09
Period (Month)
Years 2010
Preparation of LA Plan
Valuation
Formal Possession
Enquiry
Certificate of Urgency (If necessary) Reference to High Court (If necessary) Continuation of Title
INSTRUCTION FOR IRDA TO ISSUE L.O.I ON DESIGN AND BUILD PACKAGE DIRECT NEGO WITH SJIC BINA (MAIN TURNKEY) DIRECT NEGO WITH KS TEBRAU (WORKS TURNKEY)
DESIGN ARAHAN TEKNIK 2A/85,2B/85,2C/85,2E/85,5/85,6/85 (Pindaan 1/88),7/85, 11/87, 13/87, 14/87, 18/97,20/98 REAM GL2/2002, GL3/2004, GL3/2002,GL4,2002,GL6/2004,GL8/2004,GL9/2006 GUIDELINE FOR THE SAFETY AUDIT OF ROADS AND ROAD PROJECT IN MALAYSIA CONTRACT Standard form of design and build/turnkey contract (PWD Form DB/T) 2002 EDITION
No
Yes
IRDA
Construction Team Engineering Team Contractor Construction Manager / Design Manager Contractor
RFI Form
No
Follow up for prompt verbal or written advise Proceed with the works PD/PDR advise/response Update the RFI Register
No
RFI Register
Inspection Checklist
Conformance
Yes
No
Inform the Employer / Consultant by using the Request For Work Inspection (RFWI)
Inspection Checklist
Record & sign off the Inspection Checklist and Request for Work Inspection
Conformance
No
Result OK
Not OK
Test Result
Update the Test Status Register Proceed with the next activity/ phase of Construction
Consulting Engineer
Document Controller
Document Controller
Register Drawings
Drawing Register
Document Controller
Project Manager
Project Manager
Not OK Review Document Controller Not OK OK Refer to RFI flowchart Submit RFI to RE
Submit to Employer
Document Controller
Document Controller
Document Controller
IF URGENT No
Yes
Document Controller
Update Drawing Register Document Controller Update Originals on Rack Distribute Drawings using Document/Drawing Transmittal Document Controller Stamp Superseded The Drawings Attach with Drawings Document Controller
Document/Drawing Transmittal
Sub-Contractor
Document Controller
Stamp Received
Shop Drawing Register
Document Controller
Document Controller
Project Manager
Not OK
Project Manager
Inform the Manufacturer/Subcontractor on the required date to submit the sample to SJIC To Resubmit
Manufacturer/ Subcontractor
Project Manager
Review and check Status C Incorporate the comment & re-submit if necessary Yes Fill up the Sample Submittal Tag Status B Review/IRDA
No
Review
Status A
Implementation & Installation
Project Manager Check and Sign by Project Manager Project Manager Sample Submittal Tag Update the Sample Submittal Status Register Status A Reviewed Status B Reviewed with comment Status C Rejected
NCR Register
Document Controller
Approve Yes Carry out the rectification works To use the Request for Work Inspection forms
No
Fail
Inspection Pass
7
TMN TEMA 1 INT
8 9 10
CH 9500 DANGA INT
Sg.Kempas Bridge
JSNAC INT
CH 14515
CH 2400
11 12
NUSAJAYA INT
SECTION 3
SECTION 2
SECTION 1
CH 0
NO 1
ISSUES
STATUS
COMPLAINT BY EXISTING BUSINESS OWNERS AT JALAN RESOLVED BY REVISING THE RAWA, TAMAN PERLING AND TAMAN BAIDURI ON DESIGN CONSTRAINT OF THE PARKING LOTS AND ACCESS ROAD DUE TO THE CONSTRUCTION OF PERLING INTERCHANGE. COMPLAINT BY LOCAL RESIDENT OF SG DANGA ON RIVER POLUTION RESOLVED BY CLEARING UP THE AREA AND MAINTAINING THE CLEANLINESS OF THE SITE. RESOLVED BY ENHANCING AND IMPROVING THE TEMPORARY SINGAGES
COMPLAINT OF ROAD USERS ON UNCLEAR DIRECTIONAL TEMPORARY ROAD SIGNAGES THAT CAUSED JAM AT JLN SKUDAI LEADING TO JLN TAR
TERIMA KASIH
LAMPIRAN
TAR INTERCHANGE
JOHOR BAHRU
BRIDGE 1 SG KEMPAS
Bridge view
JOHOR BAHRU NUSAJAYA
Pier 2
Pier 5
JOHOR BAHRU
DANGA INTERCHANGE
JOHOR BAHRU
NUSAJAYA
PERLING INTERCHANGE
Pier 4 in progress
JOHOR BAHRU
NUSAJAYA
Bridge view
Bridge view
ACBC in progress
NUSAJAYA
JOHOR BAHRU
ACBC in progress
ACBC in progress
Bridge view
JOHOR BAHRU
JSNAC INTERCHANGE
ACBC done
MEDINI INTERCHANGE
NUSAJAYA
JOHOR BAHRU
Pier in progress
NUSAJAYA INTERCHANGE
Bridge 8B