STANDARD OPERATION PROCEDURE (S.O.P.

)
FOR APARTMENT BUILDING DESIGN AND DEVELOPMENT
PROCESS.

STEP: 1
BEFORE SIGNING THE LAND
PREPARATION OF CONCEPTUAL DRAWINGS FOR THE LAND OWNER(S)
INCLUDING:

1) FLOOR PLANS AND GROUND FLOOR PLAN FOR REGULAR


PROJECTS
*** 3D ANIMATED VIEW FOR THE POTENTIAL PROJECTS.

STEP: 2
AFTER SIGNING THE LAND

1) LAND DOCUMENTS SHOULD BE SUPPLIED TO:


A) CUSTOMER CARE DEPARTMENT
B) LOGISTIC DEPARTMENT
C) ENGINEERING DEPARTMENT.

2) ENGINEERING DEPARTMENT SHOULD FOLLOW UP


A) DIGITAL SURVEY.
B) SOIL TEST. TIME FRAME: 2
WEEKS

3)
FINALIZATION OF CONCEPTUAL DRAWINGS SHOULD BE DONE AND
PROPERLY SIGNED
IN ASSOCIATION WITH:

A) CHIEF ARCHITECT
B) STRUCTURE ENGINEER.
C) MARKETING DEPARTMENT (AUTHORIZED REPRESENTATIVE)
D) LAND OWNER. (AUTHORIZED REPRESENTATIVE)TIME FRAME: 2
WEEKS

THESE FINAL DRAWINGS WOULD BE CALLED: MARKETING DRAWINGS,


HEREINAFTER.
INCLUDING: -
E) FLOOR PLANS AND
F) GROUND FLOOR PLAN
G) ROOF PLAN
4)
PREPARATION AND SUBMISSION OF: RAJUK DRAWINGS. TIME
FRAME: 2 WEEKS
5)
PREPARATION OF: TENTATIVE COST ANALYSIS. TIME FRAME: 2
WEEKS

*** MARKETING CAN BE STARTED HEREINAFTER.


*** SITE PREPARATION AND UTILITY (LOGISTIC WORK) CAN BE STARTED
HEREINAFTER.

STEP: 3
AFTER SIGNING THE MARKETING DRAWINGS

A) 3D PERSPECTIVE VIEW SHOULD BE DONE BY ARCHITECTURAL


DEPT.
B) STRUCTURE DRAWINGS (UP TO GL) WITH MATERIAL ESTIMATION;
SHOULD BE DONE, BY ENGINEERING DEPT.
TIME FRAME: 3 WEEKS
STEP: 4

A) CORRECTED FINAL MARKETING PLANS, SHOULD BE DONE,


BY ARCHITECTURAL DEPT. (IF NEEDED)

NOTIFICATION TO:
1) ENGINEERING DEPARTMENT FOR ANY CHANGES IN STRUCTURAL
DRAWINGS.
2) MARKETING DEPARTMENT FOR ANY CHANGES IN SQFT.

B) PREPARATION OF: BROCHURE DESIGN. (IF NEEDED)


TIME FRAME: 1 WEEK

*** FOUNDATION WORK IN THE FIELD CAN BE STARTED


HEREINAFTER.

STEP: 5
1) PREPARATION AND SUBMISSION OF ARCHITECTURAL WORKING
DRAWINGS BY ARCHITECTURAL DEPT; TO:

A) ENGINEERING DEPARTMENT.( CONSULTANTS)


B) PROJECT CO-ORDINATOR.
TIME FRAME: 3 WEEKS
STEP: 6
A) SUBMISSION OF: STRUCTURE DRAWINGS.
B) SUBMISSION OF: ELECTRICAL AND PLUMBING DRAWINGS.
C) SUBMISSION OF: DETAIL COSTING AND SPECIFICATIONS AND WORK
SCHEDULE.

TO: PROJECT CO-ORDINATOR. TIME FRAME: 3 WEEKS

*** FULL FLEDGED PROJECT OPERATION CAN BE STARTED


HEREINAFTER.
(FOLLOWING THE WORK SCHEDULE)

*** IN CASE OF POTENTIAL PROJECTS DRAWINGS CAN BE DOUBLE CHECKED BY OUT


HOUSE.

STEP: 7
AFTER COMPLETION OF THE PROJECTS

PREPARATION AND SUBMISSION OF AS BUILD DRAWINGS TO:


A) PROJECT CO-ORDINATOR.
B) RAJUK AND
C) FLAT OWNERS.