) MW CONTRACTOR
START
FUEL & ELECTRICITY INFORMATION PLTU 2 JAWA BARAT PELABUHAN RATU 3x(300-400) MW PLN P3B JB REMARKS
PLN JASER
PLN JMK
PLN UPK
Engineering Documents: - Contract Document - Design Drawing - Construction Drawing - Technical Specification - Test Report / Factory Acceptance Test
Test Procedure Application from Contractor Test Procedure Application TOP (Taking Over Package) Accepted ? YES Evaluation/ Check Accepted ? YES COMMISSIONING Commissioning Test duration for each individual system +/- 10 days
NO
NO
NO
YES Start-Up, Synchron Application from Contractor is issued after Commissioning result is accepted
PLN JMK check the punchlist based on concerned start-up Unit PLN JASER review the proposal based on concerned start-up Unit NO
Evaluation/Check Accepted ?
PLN UPK review and give acknowledge on concerned startup Unit
YES
NO PLN UPK submit the Application for Synchron Permit to PLN P3B JB
Recommendation for Start-Up & Loading Test / Synchron to Grid System, Performance Test
Application Accepted ?
YES ** Since Synchron Permit is Accepted, the Energy Delivery is started to be counted (issued by BERITA ACARA PENGIRIMAN ENERGI LISTRIK) ** Loading Test to include 10% overspeed, Full Load Rejection Test IMPROVEMENT OF INSTALLATION NO
** Reliability Run duration 30 days, to include 96 hours full continuous load then load varies subject system demand ** Performance Test duration for each individual Unit +/- 10 days YES TOP (Taking Over Package) Accepted ? After the Synchron/Loading Test, RR, and PT has been accepted, PLN JASER issue the Sertifikat Layak Operasi (SLO) and PLN UPK issue the Taking Over Certificate (TOC) to the Contractor
NO
YES
FINISH