BUSINESS PROCESS DIAGRAMS OF COMMISSIONING PROCESS COAL FIRED POWER PLANT PLTU 2 JAWA BARAT PELABUHAN RATU 3x(300-400)

) MW CONTRACTOR
START

FUEL & ELECTRICITY INFORMATION PLTU 2 JAWA BARAT PELABUHAN RATU 3x(300-400) MW PLN P3B JB REMARKS

PLN JASER

PLN JMK

PLN UPK

Engineering Documents: - Contract Document - Design Drawing - Construction Drawing - Technical Specification - Test Report / Factory Acceptance Test

Commissioning Proposal from Contractor

Test Procedure Application from Contractor Test Procedure Application TOP (Taking Over Package) Accepted ? YES Evaluation/ Check Accepted ? YES COMMISSIONING Commissioning Test duration for each individual system +/- 10 days

NO

NO

NO

Evaluation/ Check Accepted ?

YES Start-Up, Synchron Application from Contractor is issued after Commissioning result is accepted

Start-Up, Synchron Application

PLN JMK check the punchlist based on concerned start-up Unit PLN JASER review the proposal based on concerned start-up Unit NO

Evaluation/Check Accepted ?
PLN UPK review and give acknowledge on concerned startup Unit

YES

NO PLN UPK submit the Application for Synchron Permit to PLN P3B JB

Recommendation for Start-Up & Loading Test / Synchron to Grid System, Performance Test

Synchron Permit Application

Application Accepted ?

YES ** Since Synchron Permit is Accepted, the Energy Delivery is started to be counted (issued by BERITA ACARA PENGIRIMAN ENERGI LISTRIK) ** Loading Test to include 10% overspeed, Full Load Rejection Test IMPROVEMENT OF INSTALLATION NO

ENERGIZING, SYNCHRON/LOADING TEST, RELIABILITY RUN (RR), PERFORMANCE TEST (PT) **

Evaluation, Inspection and Testing Result Accepted ?

** Reliability Run duration 30 days, to include 96 hours full continuous load then load varies subject system demand ** Performance Test duration for each individual Unit +/- 10 days YES TOP (Taking Over Package) Accepted ? After the Synchron/Loading Test, RR, and PT has been accepted, PLN JASER issue the Sertifikat Layak Operasi (SLO) and PLN UPK issue the Taking Over Certificate (TOC) to the Contractor

NO

YES

Sertifikat Layak Operasi (SLO), Taking Over Certificate (TOC)

FINISH