Sequencing
Day 1
Reinforcement
Day 2
Reinforcement Formwork
Day 3
Reinforcement Formwork Column
Column Formwork
Man Power
Reinforcement
2 man gang to erect 6 columns in 1 day
Formwork
2 man gang strike and erect 6 columns in 1 day
Concrete
4 man gang pouring concrete for 6 columns in 1 day
Case Study