PORT CONCEPTUAL DEVELOPMENT COST ESTIMATES

APPENDIX V

In developing the conceptual construction estimates for the five marine terminal modules, the following assumptions were taken into consideration: Taxes and customs fees are not included. Construction permitting costs are not included. Environmental mitigation and permitting costs are not included. Construction management fees and administration fees, staking and surveying, materials lab and testing fees, and other construction consultant fees are not included. The cost of removing possible underground structures is not included. Off-site construction and bringing utilities to the site are not included. Cost for Relocating existing utilities is not included. Channel dredging and fill costs are not included. Property acquisition and related costs are not included. Administrative costs associated with move-in and start-up are not included. Insurance and bonding costs are not included. Fuel, electricity, telephone and water bills are not included. Integrated computer systems for managing, controlling and operating the terminal is not included. Terminal operations and maintenance costs and special warranties are not included. A 20% contingency has been added to the construction estimates to account for some of the differences in material costs, permitting costs and any costs not revealed at this conceptual level of the terminals design. Exhibits V-1 through V-5 present the cost estimates for the five marine terminal modules.

Latin American Trade & Transportation Study

A V-1

PORT CONCEPTUAL DEVELOPMENT COST ESTIMATES

Exhibit V-1 CONCEPTUAL DEVELOPMENT COST CONTAINER MODULE


Latin American Trade & Transportation Study (LATTS) Conceptual Cost Estimate

NEW 40 ACRE CONTAINERIZED CARGO TERMINAL


DATE: June 16, 2000

CONCEPTUAL DEVELOPMENT PLAN CONSTRUCTION COSTS


Task No. Item No. Item Quantity Unit Unit Cost Item Cost Remarks

Approximate Itemized Costs - New Containerized Cargo Terminal Module


Assumes typical demolition

Clear and Grub

LS

$330,000

$330,000

and removal, but no hazardous material Assumes 30 acres graded and paved for storage areas, includes fencing, signage, etc. Berth Dredging included in Wharf Cost Not Applicabble

Civil Site Work

40 1,742,400 0 0 0 0 0

ACRE SF SF CY ACRE SF LF

$3

$5,227,200

Dredging

$8

$0

Fill

$8 $2,000

$0 $0
Included in Wharf Cost Construct New Concrete Wharf Structures, Crane Rails, Paved Backlands, etc. Lighting, Electrical Sub-Stations, etc. Assumes Passive Cathodic Protection System Includes SD/FW/DW/SS.

Bulkheading

New Concrete Wharf Construction

1,000

LF

$10,000

$10,000,000

Site Electrical

40

AC

$35,000

$1,400,000

Cathodic Protection

LS

$400,000

$400,000

Site Mechanical

40

ACRE

$30,000

$1,200,000

10

Yard Light Standards

12

EA

$50,000

$600,000

Assume 100' light poles Includes Scales, PreCheck Booths, Conc. Curbs & Other Utilities, etc. Canopies and/or Other Structures Administrative Building

11

Gate Site Work

4 174,240 7,500

ACRE SF SF

$1,742,400 $10 $75 $562,500

12

Gate Facility

13

Administration Building

18,000

SF

$110

$1,980,000

14

Maintenance & Repair Building

41,000

SF

$75

$3,075,000

M & R Building

15

Marine Building

7,000

SF

$50

$350,000

Marine Building

SUB-TOTAL ALL TASKS


INCLUDE CONTINGENCY OF TOTAL CONSTRUCTION COST 20%

$26,867,100
$5,373,420 $32,240,520

TOTAL BUDGET ESTIMATE FOR CONTAINER TERMINAL (Rounded)

$32,000,000

A V-2

Latin American Trade & Transportation Study

PORT CONCEPTUAL DEVELOPMENT COST ESTIMATES

Exhibit V-2 CONCEPTUAL DEVELOPMENT COST BREAK-BULK MODULE


Latin American Trade & Transportation Study (LATTS) Conceptual Cost Estimate

NEW 10 ACRE BREAK-BULK CARGO TERMINAL


DATE: June 16, 2000

CONCEPTUAL DEVELOPMENT PLAN CONSTRUCTION COSTS


Task No. Item No. Item Quantity Unit Unit Cost Item Cost Remarks

Approximate Itemized Costs - New Break-Bulk Cargo Terminal Module


Assumes typical demolition

Clear and Grub

LS

$100,000

$100,000

and removal, but no hazardous material Assumes 4 acres graded and paved for storage areas, includes fencing, signage, etc. Berth Dredging included in Wharf Cost Not Applicabble

Civil Site Work

4 174,240 0 0 0 0 0

ACRE SF SF CY ACRE SF LF

$2.6

$453,024

Dredging

$8

$0

Fill

$8 $2,000

$0 $0
Included in Wharf Cost Construct New Concrete Wharf Structures

Bulkheading

New Concrete Wharf Construction

700

LF

$7,500

$5,250,000

Site Electrical

10

AC

$35,000

$350,000

Lighting, Electrical Sub-Stations, etc. Assumes Passive Cathodic Protection System Includes SD/FW/DW/SS.

Cathodic Protection

LS

$200,000

$200,000

Site Mechanical

10

ACRE

$30,000

$300,000

10

Yard Light Standards

EA

$25,000

$150,000

Assume standard 60' light poles Includes Scales, Conc. Curbs & Other Utilities, etc. Guard Booths, Canopies and/or Other Structures Administrative offices and maintenance functions included inside warehouse Not Applicabble

11

Gate Site Work

0.25 10,890 200

ACRE SF SF

$108,900 $10 $75 $15,000

12

Gate House

13

Covered Storage/Warehouse

120,000

SF

$85

$10,200,000

14

Maintenance & Repair Building

SF

$85

$0

SUB-TOTAL ALL TASKS


INCLUDE CONTINGENCY OF TOTAL CONSTRUCTION COST 20%

$17,126,924
$3,425,385 $20,552,309

TOTAL BUDGET ESTIMATE FOR BREAK-BULK CARGO (Rounded)

$20,600,000

Latin American Trade & Transportation Study

A V-3

PORT CONCEPTUAL DEVELOPMENT COST ESTIMATES

Exhibit V-3 CONCEPTUAL DEVELOPMENT COST NEO-BULK MODULE


Latin American Trade & Transportation Study (LATTS) Conceptual Cost Estimate

NEW 10 ACRE NEO BULK CARGO TERMINAL


DATE: June 16, 2000

CONCEPTUAL DEVELOPMENT PLAN CONSTRUCTION COSTS


Task No. Item No. Item Quantity Unit Unit Cost Item Cost Remarks

Approximate Itemized Costs - New Neo Bulk Cargo Terminal Module


Assumes typical demolition

Clear and Grub

LS

$100,000

$100,000

and removal, but no hazardous material Assumes 6 acres graded and paved for storage areas, includes fencing, signage, etc. Berth Dredging included in Wharf Cost Not Applicabble

Civil Site Work

6 261,360 0 0 0 0 0

ACRE SF SF CY ACRE SF LF

$2.4

$627,264

Dredging

$8

$0

Fill

$8 $2,000

$0 $0
Included in Wharf Cost Construct New Concrete Wharf Structures

Bulkheading

New Concrete Wharf Construction

700

LF

$7,500

$5,250,000

Site Electrical

10

AC

$35,000

$350,000

Lighting, Electrical Sub-Stations, etc. Assumes Passive Cathodic Protection System Includes SD/FW/DW/SS.

Cathodic Protection

LS

$200,000

$200,000

Site Mechanical

10

ACRE

$30,000

$300,000

10

Yard Light Standards

EA

$25,000

$150,000

Assume standard 60' light poles Includes Scales, Conc. Curbs & Other Utilities, etc. Guard Booths, Canopies and/or Other Structures Administrative offices and maintenance functions included inside warehouse Not Applicabble

11

Gate Site Work

0.25 10,890 200

ACRE SF SF

$108,900 $10 $75 $15,000

12

Gatehouse

13

Covered Storage/Warehouse

60,000

SF

$85

$5,100,000

14

Maintenance & Repair Building

SF

$75

$0

SUB-TOTAL ALL TASKS


INCLUDE CONTINGENCY OF TOTAL CONSTRUCTION COST 20%

$12,201,164
$2,440,233 $14,641,397

TOTAL BUDGET ESTIMATE FOR NEO BULK TERMINAL (Rounded)

$14,600,000

A V-4

Latin American Trade & Transportation Study

PORT CONCEPTUAL DEVELOPMENT COST ESTIMATES

Exhibit V-4 CONCEPTUAL DEVELOPMENT COST DRY BULK MODULE


Latin American Trade & Transportation Study (LATTS) Conceptual Cost Estimate

NEW 20 ACRE DRY BULK CARGO TERMINAL


DATE: June 16, 2000

CONCEPTUAL DEVELOPMENT PLAN CONSTRUCTION COSTS


Task No. Item No. Item Quantity Unit Unit Cost Item Cost Remarks

Approximate Itemized Costs - New Dry Bulk Cargo Terminal Module


Assumes typical demolition

Clear and Grub

LS

$200,000

$200,000

and removal, but no

Civil Site Work

20 871,200 0

ACRE SF LF

$2.7 $2,000

hazardous material Assumes 10 acres graded and paved for open storage areas, $2,352,240 includes fencing, signage, etc.

Bulkheading

$0

Included in Wharf Cost Construct New Concrete Wharf Structures

New Concrete Wharf Construction

1,000

LF

$7,500

$7,500,000

Site Electrical

20

AC

$35,000

$700,000

Lighting, Electrical Sub-Stations, etc. Assumes Passive Cathodic Protection System Includes SD/FW/DW/SS.

Cathodic Protection

LS

$300,000

$300,000

Site Mechanical

20

ACRE

$30,000

$600,000

Yard Light Standards

EA

$25,000

$150,000

Assume standard 60' light poles

Silo Storage Tanks

30

EA

$50,000

$1,500,000

Assumes 50,000 CF Storage Capacity Each Assumes conventional conveyors or elevators, etc. Includes Scales, Conc. Curbs & Other Utilities, etc. Guard Booths, Canopies and/or Other Structures Administrative Building

10

Conveyors/Elevators, etc.

LS

$500,000

$500,000

11

Gate Site Work

2 87,120 200

ACRE SF SF

$174,240 $2 $75 $15,000

12

Gate House

13

Administration Building / Office

5,000

SF

$110

$550,000

14

Truck (Un)Loading Shed

2,000

SF

$75

$150,000

Truck (Un)Loading Shed

SUB-TOTAL ALL TASKS


INCLUDE CONTINGENCY OF TOTAL CONSTRUCTION COST 20%

$14,691,480
$2,938,296 $17,629,776

TOTAL BUDGET ESTIMATE FOR DRY BULK CARGO (Rounded)

$17,600,000

Latin American Trade & Transportation Study

A V-5

PORT CONCEPTUAL DEVELOPMENT COST ESTIMATES

Exhibit V-5 CONCEPTUAL DEVELOPMENT COST LIQUID BULK MODULE


Latin American Trade & Transportation Study (LATTS) Conceptual Cost Estimate

NEW 20 ACRE LIQUID BULK CARGO TERMINAL


DATE: June 16, 2000

CONCEPTUAL DEVELOPMENT PLAN CONSTRUCTION COSTS


Task No. Item No. Item Quantity Unit Unit Cost Item Cost Remarks

Approximate Itemized Costs - New Liquid Bulk Cargo Terminal Module


Assumes typical demolition

Clear and Grub

LS

$200,000

$200,000

and removal, but no

Civil Site Work

20 871,200 0

ACRE SF LF

$2.50 $2,000

hazardous material Assumes 12 acres graded and paved for tank storage areas, $2,178,000 includes fencing, earthen berm, etc.

Bulkheading

$0

Not Applicabble Construct New Pile Supported Mooring Structures Lighting, Electrical Sub-Stations, etc. Assumes Passive Cathodic Protection System Includes SD/FW/DW/SS.

New Wharf Construction

1,000

LF

$4,250

$4,250,000

Site Electrical

20

AC

$35,000

$700,000

Cathodic Protection

LS

$300,000

$300,000

Site Mechanical

20

ACRE

$30,000

$600,000

Yard Light Standards

EA

$25,000

$150,000

Assume standard 60' light poles

Storage Tanks

30

EA

$200,000

$6,000,000

Assumes 115,000 Barrel Storage Capacity Each Assumes conventional pipelines, manifolds, etc. Includes Scales, Conc. Curbs & Other Utilities, etc. Guard Booths, Canopies and/or Other Structures Administrative Building

10

Pipelines/ Manifolds, etc.

LS

$1,000,000

$1,000,000

11

Gate Site Work

2 87,120 200

ACRE SF SF

$217,800 $2.50 $75 $15,000

12

Gate House

13

Administration Building / Office

4,000

SF

$110

$440,000

14

Covered Storage/Warehouse

SF

$85

$0

Not Applicabble

SUB-TOTAL ALL TASKS


INCLUDE CONTINGENCY OF TOTAL CONSTRUCTION COST 20%

$16,050,800
$3,210,160 $19,260,960

TOTAL BUDGET ESTIMATE FOR LIQUID BULK CARGO (Rounded)

$19,300,000