Method Statement For Waterproofing Works

(Document No. CP 300B-DS-(MS)-G-CV-0000 )

01

17 - Sept. - 2011

MS

GROUP - 3

J. W. Kim

S. B. Lee

00

17-August-2011

Initial Release

R. D. Pelagio

J. W. Kim

S. B. Lee

REV

DATE

DESCRIPTION

Prepared by

Reviewed by

Approved by

Hamad Medical City - CP 300B, Hospital Fit-Out


Title: Method Statement for Waterproofing Works

Rev. No. Sheet No.

01 2 of 10

Revision Control Table


REV. NO. 00 01 REV. DATE REVISED PAGE All Pages All Pages DESCRIPTIONS OF REVISION

17-August-2011 17 - Sept. - 2011

Initial Release

Hamad Medical City - CP 300B, Hospital Fit-Out


Title: Method Statement for Waterproofing Works

Rev. No. Sheet No.

01 3 of 10

TABLE OF CONTENTS

1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 11.0

Objective Scope of Work Reference Documents Responsibilities Work Procedure Manpower Materials Equipment & Tools Quality Control Safety Control Attachments

Hamad Medical City - CP 300B, Hospital Fit-Out


Title: Method Statement for Waterproofing Works

Rev. No. Sheet No.

01 4 of 10

1.0Objectives:
The intention of this Method Statement is to describe, establish and control the steps to be taken for achieving specified requirements for the waterproofing works consistent with the approved project drawings and specifications.

2.0Scope of Works:
This Method Statement describes the application of waterproofing which will be used to carry out the work. It gives details of how the work will be executed in proper way and in accordance to contract & specifications.

3.0Reference Documents:
3.1 Material submittals Rubberized Bitumen Emulsion Paints Bitumen Impregnated Protection Boards Accessories such as waterproof sealants, waterproofing strips, corner tapes etc. 3.2 Project specification 3.2.1 Section 07115 Bituminous waterproofing 3.2.2 Section 07130 General waterproofing 3.2.3 Section 07430 Exterior metal panel fixing surface waterproofing (if required) 3.3 Relevant IFC & shop drawings

4.0Responsibilities:
4.1 Construction Manager 4.1.1 Will be in charge of the Project and will coordinate with the specialist sub-contractors, suppliers and the company staff in discharging the contractual responsibilities in the contract. 4.1.2 Will provide all technical guidance and obtain any specialized consultancy services from outside organizations as required, in providing the technical and managerial requirements of the contract. 4.1.3 Will participate in any special discussions with the "Engineer" in monitoring the progress and problems in the execution of the contract.

Hamad Medical City - CP 300B, Hospital Fit-Out


Title: Method Statement for Waterproofing Works

Rev. No. Sheet No.

01 5 of 10

4.2 QA/QC Engineer 4.2.1 Shall ensure that the works are carried out strictly in accordance with approved method statement and quality plan. 4.2.2 Will check the waterproofing works and workmanship in compliance with relevant specification and ensure that the required QA/QC checks are carried out. 4.3 Site Engineer 4.3.1 Will be responsible for planning and executing waterproofing works under the contract. 4.3.2 Will be a team member in the preparation of the method statement and he will follow the procedures outlined in the method statement to ensure that the work is carried out according to the highest safety requirements. 4.3.3 Will ensure that all safety procedures are properly followed prior to waterproofing works and organize tool box meetings with his staff on regular basis. 4.3.4 Will obtain the required information and shop drawings required for the work and ensure that the work is carried out as per the plan agreed with the "Engineer" . 4.3.5 Will maintain all documentations as required by the project management team and ensure that proper and correct information is given to all concerned. 4.3.6 Will ensure all related materials are tested conformant prior to using them. 4.3.7 Will coordinate with the PM and Foreman responsible to adopt the correct procedures and direct responsible for the quality of work. 4.4 Safety Officer 4.4.1 Will be responsible to the HSE for all his job functions and will follow up the safety procedures to be adopted at site. 4.4.2 Will instruct and coordinate with the Engineers and the Foreman and the workers to strictly enforce the safety procedures for the different aspects of work to be handled by the company staff. 4.4.3 Will conduct tool box meetings where safety aspects are discussed and the Housekeeping matters are taken up and resolved. 4.4.4 Will liaise with the HSE staff and monitor the work of the people released for house- keeping functions, as per the requirements of the contract. 4.4.5 Waste management and environmental management at site.

Hamad Medical City - CP 300B, Hospital Fit-Out


Title: Method Statement for Waterproofing Works

Rev. No. Sheet No.

01 6 of 10

5.0Work Procedures:
5.1 Verification of Working Conditions 5.1.1 Ensure that all preceding activities or activities completed which cannot be accessed after waterproofing works are inspected, released and approved. 5.1.2 Rectify non-conforming conditions prior to commencing the waterproofing works. 5.1.3 Ensure work of other trades, to be fix prior to waterproof works is properly located and installed. 5.1.4 Obtain MEP clearance and clearance from other specialist trades which may not be accessible after waterproofing, prior to commencing waterproofing works. 5.2 Surface Preparation 5.2.1 All surfaces to receive waterproofing to be clean, dry and free from dirt, dust, oil and grease. 5.2.2 Wall Protrusions that likely to punch through the waterproofing films to be removed either by using a chipping hammer or grinder. 5.2.3 Prepare and level the concrete surfaces for waterproofing either by chipping, hacking or scraping the surface. 5.2.4 Repair the excessive pinholes, and similar imperfections (if any) to eliminate uneven surface. 5.2.5 Barricade the working area as to be a non trafficking passage. 5.2.6 Raise an inspection request for surface preparation (RFI) prior to the waterproofing work commences. 5.3 Installation of Accessories and marking of Waterproofing Levels 5.3.1 Immediately after the inspection use Viscose Elastic type adhesive tape at week joints and sharp edges. 5.3.2 Marking of waterproofing application levels can be commenced at this stage. 5.3.3 Levels should be true, square and in plumb at locations as indicated on the approved shop drawings/IFC drawings. 5.3.4 Use suitable fasteners where required.

5.3.5 Install waterproof level pads also to serve as guides in controlling the final thickness of the waterproof and the finished plane of the waterproofed surface, relative to the accessories installed.

Hamad Medical City - CP 300B, Hospital Fit-Out


Title: Method Statement for Waterproofing Works 5.4 Rubberized 5.4.1 Bitumen Emulsion Paint

Rev. No. Sheet No.

01 7 of 10

application

and

Bitumen

Impregnated Protection Boards Ensure all other trades in the said location are put on hold during the waterproof application so to protect and avoid any damage to the waterproofing layers. 5.4.2 5.4.3 5.4.4 Apply first coat using a manual brush application uniformly at a Floor application should continue to the vertical wall face up to a Ensure all surfaces to receive waterproofing fluid Application firmly workable consistency. minimum of 150mm as per the project specifications. to achieve good adhesion and to be in one continuous operation. 5.4.5Subsequent coats of waterproof may be commenced immediately after setting of the previous coat approximately 3 to 5 hours and as per the manufactures recommendations. 5.4.6 5.4.7 5.4.8 Second coat should be applied at a right angle to the first coat. Finish coats to be fairly true to the plane with a homogenous finish. Bitumen Impregnated Protection Boards to have sufficient lapping as

per the manufactures recommendation. 5.5.8 Leave at least 72 hours between the final coat and water ponding test. 5.5 Water Ponding Test. 5.5.1 5.5.2 5.5.3 Water Ponding test to be carried out for the water logging areas After testing, repair works (if any) and re-testing work to be carry out Separate method statement to be submitted for such remedial such as toilet floors and water tank areas as per the specifications. immediately after drying the waterproof surface. activities prior to the execution. 5.6 Cleaning and Protection 5.6.1 Pump out and remove ponding water after the testing and leave until complete dry out.

5.6.2

Temporary covering (polythene or fiber sheets) to be used for

horizontal surfaces for protection and maintain conditions in a manner to ensure no damages or deterioration to the waterproof areas until subsequent trade work begin. 5.6.3 Remove excessive protective materials and waterproof materials from adjacent surfaces.

Hamad Medical City - CP 300B, Hospital Fit-Out


Title: Method Statement for Waterproofing Works

Rev. No. Sheet No.

01 8 of 10

6.0Manpower: Category Construction Manager QA/QC Engineer Site Engineer Safety Officer Foreman Team Leader Skilled Labour Total 7.0Materials:
7.1Rubberized Bitumen Emulsion Paints 7.2Bitumen Impregnated Protection Boards 7.3Accessories such as waterproof sealants, waterproofing strips, corner tapes etc.

Quantity 1 1 1 1 3 5 45 57

Unit No. No. No. No. Nos. Nos. Nos. Nos.

Remarks

Hamad Medical City - CP 300B, Hospital Fit-Out


Title: Method Statement for Waterproofing Works

Rev. No. Sheet No.

01 9 of 10

8.0Equipment & Tools:


The following equipments will be used in a combination or in total for the waterproofing works.

Category
Powered Tools - grinders

Quantity 06 06 03

Unit nos nos nos

Remarks

- cutters
Water Pumps Hand Tools Nylon brushes, flickers, chisels, hammers, wire brushes, brooms, squeegees

02 02 10 05

nos nos nos nos nos

sufficient quantities

Bobcats Dumpers Wheelbarrows Pallet trucks

9.0Quality Control:
Surveillance inspection will be carried out by all the parties: 9.1Prior to the commencement of Works 9.1.1 For Materials site storage conditions at site. (Store away from direct sunlight and protect from freezing) 9.2During the waterproofing activities 9.2.1 For the different activities such as preparation & finishing as per the ITP's 9.3After completion of works and prior to handing over of the finished area. 9.3.1 Protection is required for the finished waterproof surfaces.

Hamad Medical City - CP 300B, Hospital Fit-Out


Title: Method Statement for Waterproofing Works

Rev. No. Sheet No.

01 10 of 10

10.0

Safety Control:

10.1 A safety meeting and risk assessment for the personnel involved will be conducted in accordance with type of activity to be carried out. 10.2 Prime importance shall be given to safety or personnel on site. It will be ensured that the personnel involved are thoroughly aware of the company safety regulations and safety requirements. 10.3 Safety Engineer/Officer should be present during execution of works at site to implement the safety procedures and requirements. 10.4 Safety tools such as protective clothing, gloves, eye/face protection must use during execution of work. 10.5 Housekeeping shall be maintained on site.

11.0
11.1 11.2 11.3

Attachments :
Inspection and test plan for waterproofing work (ITP) Risk assessment form Typical detail drawing for waterproofing in wet areas

*********************************************