VILLA MARIA, CIUDAD MI JARDIN, ARTESANOS Y BARRANCOS DEL CENTRO POBLADO SAN ANTONIO, PROVINCIA DE MARISCAL NIETO MOQUEGUA
e=
S/C
150 kg/m2
3.50 m hp: 3.80 H: 4.40 6 B1= 0.45 m 2 7 A dentechn 2*D1 0.45 m B: 2.40 m 54.55% t2: 0.45 m D1: 0.45 m H1= 0.60 m Df= 0.90 m 3 1
DISEO DE PANTALLA
ka: coeficiente de empuje activo Ka= 1- sen 1+ sen 0.33 0.5000 1.5000 E=Empuje E1= Ka * s/c*hp E1= 0.19 Ton E2= Ka*ys*hp^2 2 E2= E2= hp: 3.80 m 9.912 2 4.96 Ton
Ka=
= E1*(hp/2) + E2*(hp/3) E1+E2 = = 0.361 1.29 m Ep* 6.64 Ton-m + 5.15 6.2827
Ep= Ep=
Mp= Mp=
CHEQUEO POR CORTE b= 100 cm Eup= 1,7*Ep = Vv/= d= t2 - 6 8.76 Ton 10.30 Ton
29.95
>
11.22
ok
Pgina 1
PROYECTO: MEJORAMIENTO DEL TRANSITO PEATONAL Y VEHICULAR EN LAS CALLES DE LAS ASOCIACIONES ALTO TIWINZA, SOLARI, LAS VEGAS, VILLA MARIA, CIUDAD MI JARDIN, ARTESANOS Y BARRANCOS DEL CENTRO POBLADO SAN ANTONIO, PROVINCIA DE MARISCAL NIETO MOQUEGUA
DISEO POR FLEXIN Aceros comerciales cant pulg 1 3/8 = 1 1/2 = 1 5/8 = 1 3/4 = 1 1 =
@ @ @ @ @ @
ACERO VERTICAL: CARA INTERIOR Mup= 1,7*Mp Mup= 11.29 Ton-m bd^2= 152,100.00 p min 0.0024 Ku= 1,129,423.33 152,100.00 7.43
Ku=
p=
0.00210
>
p=
0.0024
El espesor de la pantalla es mayor 20 cm => colocamos acero en 02 capas As= p*b*d As= 9.36 cm2 As= 4.68 cm2 N de barillas= Espaciamiento 4 25.00 cm 1 para 1 metro 5/8 = 2.36 @ 25.000 cm
ACERO: TRANSVERSAL cuanta min para vertical ph= 0.002 As= p*b*t As= 9.00 cm2 como son dos capas As= 4.50 cm2 Distribucin del acero Cara Exterior EXTERIOR acero abajo acero medio acero arriba 1/3 As 3.00 cm2 2.33 cm2 1.67 cm2 3/8 '' ESPACIA. 0.237 m 0.304 m 0.426 m hp: 3.80 m 1 9 7 4 resto @0.050 m @0.150 m @0.175 m @0.300 m @0.300 m 0.71 ESPACIA. 0.150 m 0.175 m 0.300 m
Cara Interior INTERIOR acero abajo acero medio acero arriba 2/3 As 6.00 cm2 4.67 cm2 3.33 cm2 1/2 '' ESPACIA. 0.212 m 0.272 m 0.381 m hp: 3.80 m 1 9 7 5 resto @0.050 m @0.150 m @0.175 m @0.250 m @0.250 m 1.27 ESPACIA. 0.150 m 0.175 m 0.250 m
N de barillas= Espaciamiento
3.41 @
25.000 cm
25.00 cm
Pgina 2
PROYECTO: MEJORAMIENTO DEL TRANSITO PEATONAL Y VEHICULAR EN LAS CALLES DE LAS ASOCIACIONES ALTO TIWINZA, SOLARI, LAS VEGAS, VILLA MARIA, CIUDAD MI JARDIN, ARTESANOS Y BARRANCOS DEL CENTRO POBLADO SAN ANTONIO, PROVINCIA DE MARISCAL NIETO MOQUEGUA
CHEQUEO DE DESLIZAMIENTO ka= E1= E1= H= E2= E2= E2= 0.33 Ka * s/c*H 0.22 Ton 4.40 m Ka*ys*H^2 2 13.29 2 6.64 Ton 0.45 m 0.25 m = E1*(H/2) + E2*(H/3) E1+E2 = = Mt= Mt= 0.48 1.49 m Ep* 10.22 Ton-m 0.15 m + 6.86 9.75 ET= ET= E1+E2 6.86 Ton
3.80 m
0.60 m
0.45 m
0.45 m
Wi (ton) a 1 metro 3.80 m 2.40 Ton/m3 0.60 m 2.40 Ton/m3 3.80 m 2.08 Ton/m3 1.90 m 2.08 Ton/m3 0.15 Ton/m 0.45 m 2.40 Ton/m3 1.90 m 2.40 Ton/m3 wi= FSD= FSD=
= 2.28 Ton = 3.46 Ton = 11.86 Ton = 0.79 Ton = 0.23 Ton = 0.16 Ton = 0.91 Ton = 19.68 Ton Fr Et 11.81 Ton 6.86 Ton 1.72
Fr= Fr=
1.72
> ok
1.50
FSD=
Nota: si no pasara se aumentara las dimenciones del talon y se reducira la punta se colocar un dentelln de pie Se utilizar el dentelln
no
0.45 m
0.15 m
empuje pasivo: Base de dentelln 0.45 m fuerza pasiva superior en dentelln Fs=*ka*Df^2 0.56 ton/m
0.25 m
fuerza pasiva inferior en dentelln Fi= *ka*(Df+D1)^2 1.25 ton/m 3.80 m fuerza pasiva que actua sobre el dentelln Fr = (Fs+Fi)* D1 2 0.60 m Fr= 1.50 m 1.50 m N 1 2 3 rec. 3 trian. 4 5 6 0.45 m 0.45 m 0
Wi (ton) a 1 metro 3.80 m 2.40 Ton/m3 0.60 m 2.40 Ton/m3 3.80 m 2.08 Ton/m3 1.90 m 2.08 Ton/m3 0.15 Ton/m 0.45 m 2.40 Ton/m3 1.90 m 2.40 Ton/m3
= 2.28 Ton = 3.46 Ton = 11.86 Ton = 0.79 Ton = 0.23 Ton = 0.16 Ton = 0.91 Ton
Pgina 3
PROYECTO: MEJORAMIENTO DEL TRANSITO PEATONAL Y VEHICULAR EN LAS CALLES DE LAS ASOCIACIONES ALTO TIWINZA, SOLARI, LAS VEGAS, VILLA MARIA, CIUDAD MI JARDIN, ARTESANOS Y BARRANCOS DEL CENTRO POBLADO SAN ANTONIO, PROVINCIA DE MARISCAL NIETO MOQUEGUA
0.45 m
0.45 m
/6
=( /2
/6
=( /2
Pgina 4
PROYECTO: MEJORAMIENTO DEL TRANSITO PEATONAL Y VEHICULAR EN LAS CALLES DE LAS ASOCIACIONES ALTO TIWINZA, SOLARI, LAS VEGAS, VILLA MARIA, CIUDAD MI JARDIN, ARTESANOS Y BARRANCOS DEL CENTRO POBLADO SAN ANTONIO, PROVINCIA DE MARISCAL NIETO MOQUEGUA
Fr= Fr=
FSD= FSD=
1.72
> ok
1.50
FSD=
CHEQUEO DE VOLTEO i 1 2 3 rec. 3 trian. 4 5 6 7 Wi(ton) 2.28 3.46 11.86 0.79 0.23 0.16 0.91 0.00 X(m) 0.58 1.20 1.65 0.83 1.65 0.58 0.77 1.73 Mi= Mi(ton-m) 1.31 4.15 19.56 0.66 0.37 0.09 0.70 0.00 26.84 Ton-m
FSV
FSV=
2.0 26.84 Ton-m 11.81 Ton-m 2.27 Ton-m 2.00 CHEQUEO DE PRESIONES ok
ex=(B/2)-Xo ex= 0.36 m 1,2= (P/B)(1+/- (6ex/B)) P= B= 19.68 Ton 2.40 m PUNTA TALN
0.40
/6
=( /2
0.36
ok
1= 2=
s=
25.79 Tn/m2 ok
FUERZA DE ROTURA
Ev= 1,7*Et Ev= 1.7 Ev= 11.67 Ton Wv= 1,4*wi Wv= 1.4 Wv= 27.55 Ton
* 6.86 Ton
Mt= 1,7*Mt Mt= 1.7 * 10.22 Ton-m Mt= 17.38 Ton-m Mu= 1,4*Mi Mu= 1.4 * 26.84 Ton-m Mu= 37.58 Ton-m
* 19.68 Ton
DIAGRAMA DE PRESIONES AMPLIFICADA Xo= Mu - 1,7*Mt 1,4*wi B= 2.40 m B/6= 0.40 ex=(B/2)-Xo ex= 0.47 m L= 1v= Xo= 37.58 Ton-m - 17.38 Ton-m 27.55 Ton Xo= 0.73 m
0.47
/6
=( /2
0.40
ok
1.00 m
2 * Wv 3 *L B - e 2 1v= 25.06 Tn/m2
ex= B - x 2 3
x=
B - ex 2
x=
2.20 m
0.20 m
2.20 m
Pgina 5
PROYECTO: MEJORAMIENTO DEL TRANSITO PEATONAL Y VEHICULAR EN LAS CALLES DE LAS ASOCIACIONES ALTO TIWINZA, SOLARI, LAS VEGAS, VILLA MARIA, CIUDAD MI JARDIN, ARTESANOS Y BARRANCOS DEL CENTRO POBLADO SAN ANTONIO, PROVINCIA DE MARISCAL NIETO MOQUEGUA
1v=
25.06 Tn/m2
Pgina 6
PROYECTO: MEJORAMIENTO DEL TRANSITO PEATONAL Y VEHICULAR EN LAS CALLES DE LAS ASOCIACIONES ALTO TIWINZA, SOLARI, LAS VEGAS, VILLA MARIA, CIUDAD MI JARDIN, ARTESANOS Y BARRANCOS DEL CENTRO POBLADO SAN ANTONIO, PROVINCIA DE MARISCAL NIETO MOQUEGUA
100.00 cm
38.40 FLEXION Mu= Wv *L^2 2 Mu= Mu= Ku = 0.36 -3.84 Ton - m 383,995.24 250,000.00 Aceros comerciales cant pulg 1 1 1 1 1 3/8 1/2 5/8 3/4 1 = = = = = AS cm2 0.71 1.27 1.98 2.85 5.07 @ @ @ @ @ @ Ku = 1.54 - v3*L^2 2 3.59 - (v1-v3)*L 2 * L 2 0.62 3
10.84
ok
se trabaja con la cuanta mayor p= As= As= N de barillas= Espaciamiento FLEXION EN LA CARA SI: d= b= Ku = Ku = 54.00 cm 100.00 cm 13,932.08 291,600.00 0.048 1 1 1 1 1 0.00053 p*b*d 2.67 cm2 4 25.00 cm Mu= 1 para 1 metro 3/4 = 3.16 @ - 0.06 Ton-m 25.000 cm = 0.14 Ton-m p= As= As= 0.0018 p*b*d 9.00 cm2
0.20 Ton-m Aceros comerciales cant pulg 3/8 1/2 5/8 3/4 1 p min = = = = =
@ @ @ @ @ @
p=
0.0001
>
0.0018
p= p + p/3
0.00013
se trabaja con la cuanta mayor p= As= As= N de barillas= Espaciamiento 0.00013 p*b*d 0.72 cm2 5 20.00 cm 1 para 1 metro 5/8 = 4.91 @ 20.000 cm p= As= As= 0.0018 p*b*d 9.72 cm2
Pgina 7
PROYECTO: MEJORAMIENTO DEL TRANSITO PEATONAL Y VEHICULAR EN LAS CALLES DE LAS ASOCIACIONES ALTO TIWINZA, SOLARI, LAS VEGAS, VILLA MARIA, CIUDAD MI JARDIN, ARTESANOS Y BARRANCOS DEL CENTRO POBLADO SAN ANTONIO, PROVINCIA DE MARISCAL NIETO MOQUEGUA
1 1 3/4 = @
5/8
20.000 cm
25.000 cm
DISEO DE TALN CM: Ppz= Pps= 0.60 m 3.80 m 2.40 Tn/m2 1.70 Tn/m2 SUMA Wv= Wv= 1.4 11.32 ton/m 1.00 m 1.50 m 0.30 m 11.3 ton/m * 7.90 1.44 ton/m 6.46 ton/m 7.90 ton/m + 1.70 * 0.15 CV: s/c= 0.150 ton/m2
v6=
F'c= CORTE: d=
Vv= Wv*L - (v6 *L/2) Vv= Vv= 8.52 Ton 8.5234 0.85 = 10.03 Ton
Vc= 0,53* RAIZ(f'c) *b*d Vc= 38.40 Ton 38.40 FLEXION: Mv= Wv * l^2 v5*( l - 0,2) (l-0,2) 2 Mv= Ku= 2 8.88 Ton-m 887,811.65 250,000.00 p min p= se trabaja con la cuanta mayor p= As= As= 0.00180 p*b*d 9.00 cm2 1 1 1 1 1 N de barillas= Espaciamiento 5 20.00 cm 1 0.0010 > cant pulg 3/8 1/2 5/8 3/4 1 = = = = = 4.55 @ 20.000 cm 0.0018 AS cm2 0.71 1.27 1.98 2.85 5.07 @ @ @ @ @ @ cm 0.05 0.09 0.14 0.2 0.36 Ku= 3.551 . 3 > 10.03 ok DATOS: Wv= L= v5= b= d= 11.32 ton/m 1.50 m 13.67 Tn/m2 100.00 cm 50.00 cm
Pgina 8
PROYECTO: MEJORAMIENTO DEL TRANSITO PEATONAL Y VEHICULAR EN LAS CALLES DE LAS ASOCIACIONES ALTO TIWINZA, SOLARI, LAS VEGAS, VILLA MARIA, CIUDAD MI JARDIN, ARTESANOS Y BARRANCOS DEL CENTRO POBLADO SAN ANTONIO, PROVINCIA DE MARISCAL NIETO MOQUEGUA
DISTRIBUCIN FINAL DE ACERO 0.250 m As. Cara interior As. Cara exterior 1 5/8 = @ 25.00 1 5/8 = @ 25.00
5/8
5/8
@ 20.00
0.30 m 0.60 m
0.25
Pgina 9