MAHARASHTRA JEEVAN PRADHIKARAN

KONKAN REGION
SCHEDULE OF RATES FOR THE YEAR 2007 - 2008 GENERAL NOTES
1. These rates are applicable to all M.J.P. works in the KONKAN REGION with effect from 19th December-2007. 2. Item of excavation is inclusive of normal manual dewatering; however, separate item for dewatering shall be proposed in the estimate where underground water is anticipated in significant magnitude. 3. The rates of excavation for O & M works, where limited working space is available and work is required to be carried out on emergency basis. The rate should be adopted as per the actual rate analysis which shall be approved by concerned S.E. for that particular work only. 4. Rates for all types of materials are inclusive of VAT and other taxes levied by Central Government, State Government or Local Bodies. For pipes, specials and valves, octroi of local bodies is not included in the rates. 5. For all completed items, initial lead of 5 kms. is considered for collection of materials like sand, bricks,metal, stone etc. Appropriate addition for lead charges for these materials shall be done while estimation. No lead charges shall be added to cement, steel. 6. These rates are applicable to water supply and sewerage schemes and its allied works only. Items requried for General construction, Buildings, Roads,Irrigation works etc.shall be adopted from the current schedule of rates of P.W.D. or Irrigation department, in respective areas. For bore wells, C.S.R. of G.S.D.A. shall be followed. Increase in percentage over normal schedule of rates will also be as per norms of respective C.S.R. 7. For mechanical and electrical items related to water supply and sewerage schemes, C.S.R 2007 -2008 prepared by Superintending Engineer (Mechanical), Maharashtra Jeevan Pradhikaran shall be adopted. 8. Following increase in % over normal schedule of rates of MJP for 2007 - 2008 will be applicable. (Ref. PWD G.R. No. DSR / 1091 / CR-6577 / Planning- 3, dated 08/07/2003)

GENERAL NOTES

M.M.R.D.A. & Mumbai Municipal Corporation Works in Corporation area Works in tribal area / hilly and inaccessible area Sugar cane area Prison / Jail area Defence area Matheran Municipal area Rajbhavan / Malbar Hill (Mumbai) Excavation for pipeline work along National Highway Excavation for Dist. System pipe lines, Sewerage Systems in towns. 9.

10% 5% 10% 5% 15% 20% 30% 20% 10% 10%

In any case, more than one percentage increase on basic rates becomes admissible, instead of adding both, the higher percentage only be taken. (e.g. if any Municipal Council falls in hilly area, additional percentage in rate will be only 10% and not ( 2% + 10%). This additional percentage is only on completed item of work and not applicable to items of supply of materials like steel, pipes,valves. specials etc.

10. For hilly and inaccessible areas / Tribal areas approved by Government, Plannining Departmants Circular Nos. (1) 1089 /CR-66 / Plan-19 dt. 23/11/1990 and (2) 1094 / P-36 / K-1455 dt. 02/09/ 1994, shall be followed.( refer pages - 347 onwards) In addition to amendment notification by the planning department time to time. 11. For Action Plan Notified Area, Governments Circulars in force from time to time shall be followed. 12. Whenever completed rates are increased by percentage given at Sr. No. 8, the issue rates of materials to be supplied by the Department (if any ) for these items shall be increased by same percentage. 13. This schedule of rates is based on following basic rates for important materials : a) b) c) d) e) Cement Mild Steel Tor Steel / CTD bars Structural Steel Corrosion Resistant Steel (Fe 500) Rs. 5,200/- per M. T. Rs. 31,000/- per M.T. Rs. 31,000/- per M.T. Rs. 36,000/- per M.T. Rs. 36,000/- per M.T.

14. Details of standard cement consumption and standard weight of various pipes are incorporated in this C.S.R. 15. Rates for supply of various types of pipes, specials and valves are inclusive of excise duty, central sales tax / VAT, third party inspection charges and transportation of materials upto divisional stores and stacking.
2
GENERAL NOTES

16. Cost of carting of pipes and valves from Departmental stores to site of works is not considered in rate analysis, hence, this item must be incorporated in each scheme. While inviting tenders, if supply is from Departmenal Stores, then this item shall appear in the tender, and if the supply is by Contractor then this item shall not appear in the tender. even though same is provided in the sanctioned scheme, because the contractor is supposed to bring the pipes & valves directly at site. 17. Though the contractor is required to do refilling before hydraulic testing to avoid traffic hurdle, no payment for refilling of the trenches of pipe line shall be payable till satisfactory hydraulic testing is given. Re-excavation required, if any, during testing, shall be done by the contractor at his own cost. 18. 10% of cost of items of water retaining structures, such as G.S.R./ E.S.R. / M.B.R. shall be retained till satisfactory hydraulic testing as per IS code. 19. 10% of cost of total sub-work of pipeline work shall be retained till satisfactory hydraulic testing is given as per IS code. 20. In case of supply of pipes / valves etc. by contractor, only 85% payment shall be released after supply and 15 % after satisfactory hydraulic testing. 21. AC, PVC and HDPE pipes are not to be used in Urban Areas.

22. Provision for octroi charges for pipes, specials and valves are not considered in the CSR 20072008. Provision of 4% of cost of pipes, specials and valves to be used in corporation area, shall be made while framing the estimate for works included in corporation limits. Octroi charges shall be reimbursed to contractor on production of receipt for payment for the materials actually to be used in corporation area, if there is specific provision to that effect in the contract. 23. For use of ready mix cement concrete, prior permission of the Chief Engineer shall be obtained. 24. For Dams, Balancing Tanks, Aerated Lagoons and similar structures, the rates for film membrances as per prevailing rates for Irrigation Depertment will be followed. 25. Capacity of ESR / GSR to be constructed shall be rounded out to nearest 1000 litres- always on higherside i.e. if required capacity is 1,23,570 litres, it shall be rounded to 1,24,000 liters Similarly, if required capacity is 8,26,070 litres, it shall be rounded to 8,27,000 litres. 26. Capacity of Unconventionl / Convetional Traeament Plants shall be rounded to nearest 0.5 MLD
GENERAL NOTES

always on higher side i.e. if WTP of 2.37 MLD is required, it shall be rounded to 2.5 MLD. For WTP having capacity less than 0.5 MLD, package type W. T. P. should be considered. 27. Provision for insurance is not considered in rate analysis of CSR 2007-2008. This provision shall be made at 1% of net cost of estimate for each sub work while framing the estimates. This provision shall be considered for tender evaluation purpose only. 28. Rates given in this CSR are for estimation purpose only.

29. The makes of Sluice valves / butterfly valves to be used for Inlet/Outlets of E.S.R./ G.S.R./ M. B.R / WTP / pumping main / rising main should be from approved makes of MJP for pumping machinery works. 30. Mechanical CSR rates for respective items shall be followed while estimation and the list of approved makes shall be given in the Item. For civil works other than that mentioned above, makes approved by MJP from time to time are acceptable. 31. As per Govt. Circular Materials used for drinking water supply scheme upto 1st storage and pipes of more than 200 mm diameter are exempted from excise duty. However, necessary certificate from the project authority i.e. District Collector / Dy. Commissioner shall be obtained. 32. The royalty charges are considerd in the rate analyis of CSR 2007-2008 as per Government Circular No. Rev. & Forest deptt. No.Gaukhani-10/0206/C.R.-57/kh(1) dated 15/12/2006. 33. As per Central Government notification dated 1/3/2007 the pipes required for water supply are only eligible for excise duty exemption. Since there is no mention of excise duty exemption to pipes required for sewerage schemes, the rates of pipes shall be increase by multiplying factor of 1.1577 and then adopted for sewerage scheme. 34 For Gharapuri Island for transportation of materials ,the actual rate analysis should be prepaid, for
transportation with barrage and head load if requires , and shall be appeard by concerned SE for this particular work.

GENERAL NOTES

SECTION - A: MATERIALS Sr. No.


1

Description
2

Unit
3

Rate (in Rs.) 2007-2008 4

Rate (in Rs.) 2008-2009 5

1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. 26. 27. 28.

A. C.cowl type ventilator Alum Grade I Barbed wire G.I, CTW Battens ( 25mm x 12mm) CTW Battens ( 50mm x 25mm) Binding Wire Bitumen Washers Black enamel paint ( anti -corrosive ) Bricks Bullies, strutts ( 125 mm dia 1.5 M long ) C. C. T. W.Planks ( 3 x 6) Cement ( Bags ) Cement Cement Sulpher resistant Charcoal Coarse Sand Collapsible door including channel, pivot picket Colour Glazed Tiles Corrosion resitant Steel Corrugated A.C. sheets ( 6 mm thick ) Corrugated G.I.sheet ( 22 Guage ) Diesel Dry distemper Epoxy paint Fuse G.I. Screw G.I. Sheet 22 BWG ( 6 x 4) G.I. Washers

No. MT.. Kg Rmt Rmt Kg. Dozen Ltr No Rmt Cu.m. Bag. M.T. M.T Kg. Cum. Sqm. No. M.T.. Sqm. M.T. Ltr. Kg. Kg. No Kg. No Kg

55.00 3,250.00 50.00 25.00 50.00 43.00 17.00 125.00 2.75 120.00 45,000.00 260.00 5,200.00 5,500.00 18.00 500.00 1,650.00 15.00 36,000.00 175.00 45,000.00 35.00 35.00 350.00 15.00 45.00 550.00 45.00

SECTION - A: MATERIALS

Sr. No.
1

Description
2

Unit
3

Rate (in Rs.) 2007-2008 4

Rate (in Rs.) 2008-2009 5

29. 30. 31. 32. 33. 34. 35. 36. 37. 38. 39. 40. 41. 42. 43. 44. 45. 46. 47. 48 49. 50. 51. 52. 53. 54. 55. 56. 57.

Glass ( 3mm) Glass ( 4mm) Glass ( 5mm) Glazed coloured Tiles .... 8 x 12 Glazed Tile (white) ......... 6 x 6 Grey Cement Tiles Gun powder Housing Box Inferol 49 W thick Khandkies Linsed oil Liquid chlorine container ( 100 Kg. Dept. container)
(Container Supplied by departrment )

Sqm. Sqm. Sqm. Dozen Dozen Sqm. Kg. Box Ltr. No. Ltr. No No No No Ltr. Kg. MT. Kg. Kg.. Kg. MT No No Sqm. Sqm. Kg Kg.. Ltr.

250.00 300.00 330.00 350.00 150.00 120.00 85.00 920.00 160.00 25.00 85.00 3,550.00 3,600.00 14,200.00 14,325.00 130.00 40.00 31,000.00 31.00 38.00 30.00 95,000.00 200.00 10.00 160.00 200.00 46.00 46.00 130.00

Liquid chlorine container ( 100Kg. supplier container )


(Container Supplied by Contractor )

Liquid chlorine container ( 900 Kg. Dept. container) Liquid chlorine container ( 900Kg. supplier container ) Lubricant oil M.S.Angle ( 50 mm x 50 mm x 6mm ) M.S.Bars M.S.Bars ( in Kgs. ) M.S.Flats( 40 mm x 3 mm ) M.S.Plate as per SAIL Maganafloc coagulant aid Manglore Tiles Glasses Manglore Tiles ( 16 x 91/4) Marble mosaic tiles Marble mosaic tiles in white cement Mild Steel Grill Mild Steel Grilled railing Mobile oil

SECTION -A: MATERIALS

Sr. No. 1

Description 2

Unit 3

Rate (in Rs.) 2007-2008 4

Rate (in Rs.) 2008-2009 5

58. 59. 60. 61. 62. 63. 64. 65. 66. 67. 68 69. 70. 71. 72. 73. 74. 75. 76. 77. 78. 79. 80. 81. 82. 83. 84. 85. 86. 87

Murum Nails Neeru Nut - Bolts Oil Bond Distemper Oxalic Acid Powder Petrol Plain A.C. Sheet (4 mm thick) Plain / Gray cement tiles Plain / Colour tiles Plastic emulsion paint Polished kadappa stone slab 25mm thick Polished shahabad stone slab 25mm thick Poling Boards
( Godhra, Gokak, Kanhan, Yesagi Sand )Rapid Sand Gravity

Cu.m.. Kg. Kg Kg. Ltr. Kg. Ltr. Sqm. Sqm. Sqm. Ltr. Sqm. Sqm. Cum. Ltr. LS Cum. MT.. Cum. Cum. Ltr. Ltr. Ltr. Ltr. Ltr. Ltr. Ltr. No M.T. No

125.00 45.00 4.50 60.00 75.00 50.00 75.00 135.00 115.00 135.00 225.00 275.00 220.00 15,000.00 100.00 35.00 175.00 35,000.00 750.00 750.00 200.00 125.00 160.00 100.00 90.00 170.00 105.00 25.00 350.00 50.00

Primer ( Building ) Putty Quarry Spalls R.S.Joists, channels etc. Rapid Sand Gravity Filter Media at source Rapid Sand Gravity Filter Gravel at Source Ready Mix Aluminium Paint Ready Mixed lead /zinc paint Ready Mixed oil Paint Ready Mixed Primer Ready Mixed Primer for steel Ready Mixed Synthetic enamel Paint Ready Mixed White Primer Ridge and hip tiles Ridge Cap Ridge piece

SECTION - A: MATERIALS

Sr. No. 1

Description

Unit 3

Rate (in Rs.) 2007-2008 4

Rate (in Rs.) 2008-2009 5

88. 89. 90. 91. 92. 93. 94. 95. 96. 97. 98. 99. 100. 101. 102. 103. 104. 105. 106. 107. 108. 109. 110. 111. 112. 113. 114. 115. 116. 117. 118. 119. 120. 121.

Rolling shutters with all acessories ( 18Gauge ) Rolling shutters with all acessories ( 20Gauge ) Rough shahabad undressed stone slab 25-30 mm thick Rough shahabad undressed stone slab 40-50 mm thick Rubber Gasket ( 8mm thick) Sand Kasarde Sand (for mortar lining work) Screws (1 1/4 ) Semi - corrugated A.C. sheets 6mm thick Spun yarn Steel ( M.S.) Steel Window frame with Shutters Stone ( quoins ) Stone ( Rubble) Stone aggregate -10mm Stone aggregate -20mm Stone aggregate -40mm Stone at quarry - 45cm x30cm x20cm Structural steel T. W. Battens ( 75 x 65 mm) Bidding ( 50x15mm ) Tarring TCL ( Bleaching Powder ) Grade - I ( 10Kg. pack) TCL ( Bleaching Powder )Grade - I ( 25Kg. pack) TCL ( Bleaching Powder )Grade - I ( 5Kg. pack) Teak wood Through Stones Tor steel Turpentine Ventilator steel frame Walling (100 mm x 100 mm) Waterproof cement paint Waterproofing compound White cement White Glazed Tiles
8

Sqm. Sqm. Sqm. Sqm. Kg. Cum. Cum. No. Sqm. Kg Kg Sqm No Cu.m Cu.m Cu.m Cu.m Cu.m MT Cu.m Kg. Kg Kg. Kg Cu.m No. MT Ltr. Sqm Cum. Kg. Kg Kg. No

1,500.00 1,400.00 115.00 130.00 50.00 500.00 350.00 1.25 160.00 60.00 31.00 16.00 40.00 250.00 600.00 600.00 550.00 170.00 36,000.00 45,000.00 30.00 13.00 13.00 14.00 42,000.00 25.00 31,000.00 45.00 700.00 15,000.00 35.00 30.00 25.00 13.00

SECTION -A: MATERIALS

Sr. No. 1

Description 2

Unit 3

Rate (in Rs.) 2007-2008 4

Rate (in Rs.) 2008-2009 5

122. 123. 124. 125. 126. 127. 128. 129. 130. 131. 132. 133. 134. 135. 136. 137. 138. 139. 140. 141. 142.

White lead White lime Wire Ready Mix Concrete ( including 25 km. Lead) M-100 a) M - 150 b) M - 200 c) M - 250 d) M - 300 e) M - 350 Oiling baterns with one coat linsed oil Welding Rod having weight 5.25 kg Welding Rod having weight 5.25 kg 4.00 mm Welding Rod having weight 5.25 kg 3.2 mm Welding Rod having weight 5.25 kg 2.5 mm Welding Rod having weight 5.25 kg 2.0 mm Welding Rod having weight 5.25 kg 1.5 mm Oxygen Gas (Refill) Acetylene Gas Additional Rate for Static Pumping Mobile Pumping

Kg. Qtl. Kg Cum Cum Cum Cum Cum Cum Sq.M. Packet Packet Packet Packet Packet Packet m3 m3 cum cum

80.00 600.00 43.00 3,319.00 3,375.00 3,572.00 3,712.00 3,937.00 4,162.00 85.00 924.00 966.00 1008.00 1335.00 1948.00 2420.00 35.00 220.00 175.00 250.00

SECTION - B: LABOUR AND MACHINERY

SECTION - B - LABOUR AND MACHINERY Sr. No.


1

Description
2

Unit
3

Rate (in Rs.) 2007-2008 4

Rate (in Rs.) 2008-2009 5

1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23.

Assistant fitter Bandhani Bhisti (with pakhal) Black smith Breaker Carpenter (1st class) Carpenter (IInd class) Chiseller Excavator Fitter (1st class) Glazier Helper Hole driller Mason (I st class) Mason (II nd class) Mazdoor (female) Mazdoor (heavy) Mazdoor (light) Mazdoor (male) Maistri Mukadam Painter (for colouring) Painter

No. No. No. No. No. No. No. No. No. No. No. No. No. No. No. No. No. No. No. No. No. No. No.

165.00 163.00 163.00 165.00 163.00 171.00 171.00 163.00 160.00 171.00 165.00 160.00 163.00 176.00 165.00 160.00 163.00 160.00 160.00 165.00 171.00 165.00 171.00

SECTION - B: LABOUR AND MACHINERY

10

Sr. No.
1

Description
2

Unit
3

Rate (in Rs.) 2007-2008 4

Rate (in Rs.) 2008-2009 5

24. 25. 26. 27. 28. 29. 30. 31. 32.

Polisher Pump driver Stone cutter or dresser Tile layer Welder White washer Tile turner L. M. V. Driver Electrician

No. No. No. No. No. No. No. No. No.

163.00 163.00 163.00 175.00 175.00 163.00 163.00 171.00 165.00

MACHINERY
Sr. No.
1

Description
2

Unit
3

Rate (in Rs.) 2007-2008 4

Rate (in Rs.) 2007-2008 5

1. 2. 3. 4. 5. 6. 7. 8.

Rent charges for Polishing Machine Rent & run charges of polishing machine with crew Rent charges for Chain pulley block with tripod Rent charges for pump Rent charges for Mechanical Mixer with fuel & Crew Rent charges for Vibrator with fuel & Crew Rent charges for welding set with electrict set. Rent charges for welding set with generator.

Day Day Day


BHP/Day

375.00 450.00 200.00 60.00 1,500.00 350.00 400.00 1,200.00

Day Day Day Day

SECTION - B: LABOUR AND MACHINERY

11

SECTION - C : TRANSPORTATION
Sr. No. Item of Work Unit

STATEMENT - I

2007-2008

Collecting the Unloading the Loading the Lifting the railway receipt material from material into materials from etc and unload- railway platform, truck including truck from ing the consignstacking in loading into truck. departmental ment from stores or site of derpartmental railway wagon stores or site of work. and keeping on work. railway platform Consignment booked in 4 5 6 7

1 (A)

2 MANUAL HANDLING (Weight upto and including 300 kg.) C.I./D.I./M.S./H.D.P.E. pipes of all classes upto and including 200 mm dia pipes of any length R. C. C. pipes of all classes upto and including 350 mm dia A. C. pipes of all classes and dia. P. V. C. pipes of all classes and dia. All other materials such as C. I. specials of individual weight upto 300 kg. Mild steel / tor steel / R. S. J. Cement / bleaching powder / alum CRANE HANDLING (Materials having individual weight above 300 kg.) C.I./D.I./ B. W.S.C. / M. S. / R.C.C. pipes of all classes having individual weight more than 300 kg. and also other heavy materials, valves, machinery having individual weight more than 300 kg.

1.

M.T.

157.00

192.00

50.00

50.00

2.

M.T.

157.00

192.00

50.00

50.00

3. 4. 5.

M.T. M.T. M.T.

83.00 83.00 157.00

117.00 117.00 192.00

30.00 30.00 50.00

30.00 30.00 50.00

6. 7. (B)

M.T. M.T.

99.00 48.00

134.00 73.00

75.00 38.00

75.00 38.00

1.

M.T.

111.00

141.00

101.00

101.00

1) 2) 3)

The above rates in column 1 to 5 are applicable only for railway clearance purpose only and not for other carting. The rates given in colum 6 to7 shall be adopted for estimate purpose only, however, actual quotations/ D tender will prevail. Irrespective of supply of CI/DI pipes as per rate contract, when pipes are directly supplied by the firms by road, railway freight upto destination station and carting as per schedule from railway station to work site is allowed.In such cases, rate of Mathadi Kamgar shall not be applicable for carting and normal loading, unloading, carting shall be allowed.
SECTION - C : TRANSPORTATION

11

STATEMENT NO. V TRANSPORTATION CHARGES

Excluding loading & unloading.


Lead in Kms. (L) Cost per trip. Pay Load 1 2 Bulk Asphalt in Bouzer. 5.25 MT 5 Cement (M. T.) 9.00 M.T. 3 M. S. Bars 9.00 M.T. 4 Sand 5.75 Cu.m 5

per M. T.
0.50 1.00 1.50 2.00 2.50 3.00 3.50 4.00 4.50 5.00 6.00 7.00 8.00 9.00 10.00 15.00 20.00 25.00 30.00 35.00 40.00 45.00 50.00 60.00 70.00 80.00 90.00 100.00 125.00 150.00 175.00 200.00 250.00 300.00 400.00 500.00 600.00 700.00 800.00 900.00 1000.00 169.46 190.69 211.70 232.22 252.91 273.36 293.59 313.61 333.43 353.06 393.00 432.55 471.42 509.88 547.20 703.20 888.61 991.51 1165.91 1284.55 1450.99 1617.42 1783.86 1910.48 2215.86 2521.23 2826.60 3001.57 3732.40 4463.23 5194.06 5924.89 7386.55 8717.80 11597.65 14477.51 17357.36 20237.21 23117.06 25996.92 28876.77 32.28 36.32 40.32 44.23 48.17 52.07 55.92 59.74 63.51 67.25 74.86 82.39 89.79 97.16 104.23 133.94 169.26 188.86 222.08 244.68 276.38 308.08 339.78 363.90 422.07 480.23 538.40 571.73 710.93 850.14 989.34. 1128.55 1406.96 1660.53 2209.08 2757.62 3306.16 3854.71 4403.25 4951.79 5500.34

per M. T.
24.21 27.24 30.24 33.17 36.13 39.05 41.94 44.80 48.63 50.44 56.14 61.79 67.35 72.84 78.17 100.46 126.94 141.64 166.56 183.51 207.28 231.06 254.84 272.93 316.55 360.18 403.80 428.80 533.20 637.60 742.01 846.41 1055.22 1245.40 1656.81 2068.22 2479.62 2891.03 3302.44 3713.85 4125.25

per M. T.
18.83 21.19 23.52 25.80 28.10 30.37 32.62 34.85 37.05 39.23 43.67 48.06 52.38 56.65 60.80 78.13 98.73 110.17 129.55 142.73 161.22 179.71 198.21 212.28 246.21 280.14 314.07 333.51 414.71 495.91 577.12 658.32 820.73 968.64 1288.63 1608.61 1928.07 2248.58 2568.56 2888.55 3208.53

per Cum.
29.47 33.16 36.82 40.39 43.98 47.54 51.06 54.54 57.99 61.40 68.35 75.23 81.99 88.67 95.17 122.30 154.54 172.44 202.77 223.40 252.35 281.29 310.24 332.26 385.37 438.47 491.58 522.01 649.11 776.21 903.31 1030.42 1284.62 1516.14 2016.58 2517.83 3018.37 3519.51 4020.36 4521.20 5022.05

17