PROJECT TITLE:

WORK TITLE:

PRE-PILING INSPECTION CHECK LIST


DATE LOCATION BUILDING NO. OF PILE TYPE OF PILE TYPE OF HAMMER START OF INSPECTION FINISH OF INSPECTION OK NO

PROJECT OWNER:

CONSULTANT:

CONTRACTOR:

: : : : : : : :

SUBMITTAL DESCRIPTION No. 1 RFI 2 Shop Drawing (approved) 3 Method of Statement (approved) 4 Final Set Calculation (approved) 5 Pile Material (approved) 6 Pile Equipment (certificate) 7 Survey Equipment (certificate) 8 Welder Certificate 9 Surveyor Certificate SETTING OUT DESCRIPTION No. 1 Surveyor (as per submitted certificate) 2 Theodolite (recommended 2 units) 3 Piling Point (< 75 mm) 4 Ground RL (taken and mentioned) 5 Plumbed Bob (additional) 6 Perpendicular Observation 7 Verticality Observation PILING MATERIAL DESCRIPTION No. 1 Type of Pile 2 Diameter of Pile (not less, not exceed 6mm) 3 Amount of Pile (1 starter, n extension) 4 Pile Condition 5 Length of Pile PILING EQUIPMENT DESCRIPTION No. 1 Pile Equipment (available and working) 2 Piler 3 Pile Recorder (stand by with form & tools) 4 Weight of Hammer (subject to pile) 5 Drop of Hammer (as per set calculation) 6 Final Set Tools JOINT AND WELDING No. DESCRIPTION 1 Welding Equipment (available and working) 2 Welder (as per submitted certificate) 3 Joint Plate Thickness 4 Joint Plate Dimension (width and heigth) 5 Joint Plate Bending (check against pile) 6 Type of Electrode 7 Amount of Electrode 8 Dye Penetrant Set 9 Grinder 10 'Light Chipping' Hammer (not for pecking) 11 Iron Brush INSPECTED BY: VERIFIED BY:

REMARKS

OK

NO

REMARKS

OK

NO

REMARKS

OK

NO

REMARKS

OK

NO

REMARKS

DATE:

DATE:

You might also like