You are on page 1of 35

DAFTAR ANALISA BIAYA

ANALISA (1) JBT

JENIS PEKERJAAN (2) 1 M2 PEMBERSIHAN LAPANGAN 0.0250 Hr Pekerja 0.0010 Hr Mandor 1 M' PENGUKURAN BOUWPLANK 0.0040 Hr Pekerja 0.0200 Hr Tukang 0.0200 Hr Mandor 0.0250 M3 Papan Sembarang 0.0010 Kg Paku 1 M3 GALIAN TANAH 0.7500 Hr Buruh tak terlatih 0.0250 Hr Mandor 1 M3 URUGAN TANAH 0.3750 Hr Buruh tak terlatih 0.0120 Hr Mandor 1 M3 TIMBUNAN TANAH BIASA 0.2500 Hr Pekerja 0.0120 Hr Mandor 1.2000 M3 Tanah Timbun 1 M2 URUGAN PASIR 0.2500 Hr Buruh tak terlatih 0.0120 Hr Mandor 1.2000 M3 Pasir Urug 1 M3 BETON TAK BERTULANG K.175 6.0000 Hr Pekerja 1.0000 Hr Tukang 0.1000 Hr Kepala Tukang 0.0300 Hr Mandor 6.8000 Zak Semen 0.5000 M3 Pasir 1.0000 M3 Kerikil 0.4000 M3 Papan Begisting 4.0000 Kg Paku 2.4096 Jam Concrete Mixer 1 M3 BETON BERTULANG K.175

HARGA SATUAN (Rp.) (3)

UPAH (Rp.) (4)

BAHAN (Rp.) (5)

JUMLAH UPAH+BAHAN (Rp.) (6)

45,000.00 47,500.00 Jumlah 45,000.00 52,500.00 47,500.00 1,300,000.00 10,000.00 Jumlah 35,000.00 47,500.00 Jumlah 35,000.00 47,500.00 Jumlah 45,000.00 47,500.00 30,000.00 Jumlah 35,000.00 47,500.00 55,000.00 Jumlah 45,000.00 52,500.00 55,000.00 47,500.00 30,000.00 65,000.00 70,750.00 1,700,000.00 10,000.00 23,424.11 Jumlah

1,125.00 47.50 1,172.50 180.00 1,050.00 950.00 0.00 26,250.00 1,187.50 27,437.50 13,125.00 570.00 13,695.00 11,250.00 570.00 11,820.00 8,750.00 570.00 9,320.00 270,000.00 52,500.00 5,500.00 1,425.00 329,425.00

0.00 32,500.00 10.00 32,510.00 0.00 0.00 36,000.00 36,000.00 66,000.00 66,000.00 204,000.00 32,500.00 70,750.00 680,000.00 40,000.00 56,442.73 1,083,692.73

1,125.00 47.50 1,172.50 180.00 1,050.00 950.00 32,500.00 10.00 32,510.00 26,250.00 1,187.50 27,437.50 13,125.00 570.00 13,695.00 11,250.00 570.00 36,000.00 47,820.00 8,750.00 570.00 66,000.00 75,320.00 270,000.00 52,500.00 5,500.00 1,425.00 204,000.00 32,500.00 70,750.00 680,000.00 40,000.00 56,442.73 1,413,117.73

JBT

JBT

JBT

JBT

JBT

JBT

JBT

0.6000 0.1000 0.0300 0.0100 1.0000 110.0000 2.0000 JBT

Hr Hr Hr Hr M3 Kg Kg

Pekerja Tukang Mandor Kepala Tukang Beton K.175 Tulangan Baja Kawat Beton

45,000.00 52,500.00 47,500.00 55,000.00 1,413,117.73 6,500.00 5,000.00 Jumlah 45,000.00 52,500.00 47,500.00 55,000.00 65,000.00 65,000.00 30,000.00 Jumlah 45,000.00 52,500.00 47,500.00 55,000.00 2,000,000.00 10,000.00 Jumlah 45,000.00 47,500.00 85,000.00 85,000.00 6,500.00 65,000.00 32,500.00 Jumlah 45,000.00 52,500.00 47,500.00 55,000.00 65,000.00 30,000.00 Jumlah 45,000.00 47,500.00 7,500.00 12,000.00 Jumlah 45,000.00 47,500.00 18,000.00 Jumlah 45,000.00 47,500.00

27,000.00 5,250.00 1,425.00 550.00 34,225.00 202,500.00 78,750.00 10,687.50 8,250.00 300,187.50 2,160.00 7,875.00 95.00 825.00 10,955.00 23,625.00 1,235.00 24,860.00 18,000.00 10,500.00 950.00 1,100.00 30,550.00 63,000.00 16,625.00 12,000.00 91,625.00 63,000.00 16,625.00 79,625.00 4,500.00 -

1,413,117.73 715,000.00 10,000.00 2,138,117.73 78,000.00 33,800.00 97,200.00 209,000.00 798,000.00 25,900.00 823,900.00 2,550.00 5,950.00 26,000.00 1,300.00 16,250.00 52,050.00 780.00 4,890.00 5,670.00 2,625.00 2,625.00 6,300.00 6,300.00 237.50

27,000.00 5,250.00 1,425.00 550.00 1,413,117.73 715,000.00 10,000.00 2,172,342.73 202,500.00 78,750.00 10,687.50 8,250.00 78,000.00 33,800.00 97,200.00 509,187.50 2,160.00 7,875.00 95.00 825.00 798,000.00 25,900.00 834,855.00 23,625.00 1,235.00 2,550.00 5,950.00 26,000.00 1,300.00 16,250.00 76,910.00 18,000.00 10,500.00 950.00 1,100.00 780.00 4,890.00 36,220.00 63,000.00 16,625.00 2,625.00 12,000.00 94,250.00 63,000.00 16,625.00 6,300.00 85,925.00 4,500.00 237.50

1 M3 PASANGAN BATU BELAH 4.5000 Hr Pekerja 1.5000 Hr Tukang 0.2250 Hr Mandor 0.1500 Hr Kepala Tukang 1.2000 M3 Batu Kali 0.5200 M3 Pasir 3.2400 Kg Semen (PC) 1 M3 MEMASANG LANTAI JEMBATAN 0.0480 Hr Pekerja 0.1500 Hr Tukang 0.0020 Hr Mandor 0.0150 Hr Kepala Tukang 0.3990 M3 Kayu Kelas II 2.5900 Kg Paku 1 M2 LAPIS PENUTUP LANTAI 0.5250 Hr Pekerja 0.0260 Hr Mandor 0.0300 M3 Batu Pecah 2/3 0.0700 M3 Batu Pecah 5/7 4.0000 Kg Aspalt 0.0200 M3 Pasir 0.5000 Lbr Seng Plat BJLS. 20 1 M2 PEKERJAAN PLESTERAN 0.4000 Hr Pekerja 0.2000 Hr Tukang 0.0200 Hr Mandor 0.0200 Hr Kepala Tukang 0.0120 M3 Pasir 0.1630 Kg Semen (PC) 1 M2 PENGECETAN LOANNING 1.4000 Hr Pekerja 0.3500 Hr Mandor 0.3500 Kg Cat Tembok 1.0000 Set Alat Bantu 1 M2 PENGECETAN SANDARAN 1.4000 Hr Pekerja 0.3500 Hr Mandor 0.3500 Kg Cat Besi 1 M2 PEMBERSIHAN DAN PENGETERAN 0.1000 Hr Pekerja 0.0050 Hr Mandor

JBT

JBT

JBT

JBT

JBT

JBT

0.3500

Kg

Teer

6,500.00 Jumlah

4,500.00

2,275.00 2,512.50

2,275.00 7,012.50

DAFTAR ANALISA BIAYA


PEKERJAAN LOKASI KABUPATEN PROPINSI : : : : NORMALISASI SUNGAI DESA LANCANG PASILO JUMERANG PIDIE NANGGROE ACEH DARUSSALAM

ANALISA (1) A. 1 2

KOMPONEN (2) TENAGA Pekerja Mandor

SATUAN (3)

PERKIRAAN VOLUME (4)

HARGA SATUAN (Rp.) (5)

JUMLAH HARGA (Rp.) (6)

Jam Jam

0.625 6,428.57 0.077 6,785.71 Jumlah Harga Tenaga A

4,017.86 522.50 4,540.36

B. 1 2 C. D E

PERALATAN Excavator Alat Bantu JUMLAH HARGA DAN PERALATAN (A + B) OVERHEAD & PROPIT = 10 % x C HARGA SATUAN PEKERJAAN ( C + D ) Jam Set 0.051 247,475.36 1.000 12,000.00 Jumlah Harga Tenaga B 12,621.24 12,000.00 24,621.24 29,161.60 2,916.16 32,077.76

URAIAN ANALISA HARGA SATUAN


PEKERJAAN LOKASI KABUPATEN PROPINSI : : : : NORMALISASI SUNGAI DESA LANCANG PASILO JUMERANG PIDIE NANGGRO ACEH DARUSSALAM

NO. I. 1 2 3 4 5 II. 1 2 3

URAIAN ASUMSI Menggunakan alat berat ( cara mekanik ) Lokasi pekerjaan : Kondisi drainase : selesai dibersihkan Jam kerja efektif Luas penampang saluran URUTAN KERJA Penggalian sungai dengan menggunakan Alat Berat Excavator Hasil galian ditimbun disamping sungai dan membentuk tanggul Sekelompok pekerja membersihkan daerah galian dan merapikan hasil galian, sekaligus membentuk tanggul saluran PEMAKAIAN ALAT DAN TENAGA 1 ALAT - Excavator Kapasitas Bucket Faktor Bucket Faktor Efisiensi Alat Waktu Siklus :

KODE

KOEF.

SATUAN

KETERANGAN

Ttk L

7.00 1.50

Jam M2

III.

C03 V Fb Fa TS1

Ls 0.65 0.90 0.83 M3

Menggali dan menimbun Lain - lain = V x Fb x fa x 60 TS1 = = Galian Saluran Q1 1 (2 + 1)/2 x 1 Q1

Kap. Produksi/Jam Koef. Alat/Km

T1 T2 TS1 Q1

0.50 0.50 1.00 29.13

Menit Menit M3/Jam -

C03 C10

0.05

Jam

ALAT BANTU - Cangkul - Sekop 2 TENAGA Produksi Kebutuhan Tenaga - Pekerja - Mandor Koefisien Tenaga : - Pekerja (P x Tk) : Q1 - Mandor (M x Tk) : Q1

Ls

Q1 P M L01 L02

22.41 2.00 0.25 0.625 0.077

M3 Jam Jam Jam Jam

URAIAN ANALISA HARGA SATUAN ALAT


JENIS ALAT SATUAN LOKASI KABUPATEN PROPINSI : : : : : BULDOZER 100 -150 HP DESA LANCANG PASILO JUMERANG PIDIE NANGGRO ACEH DARUSSALAM

NO. A. 1 2 3 4

URAIAN URAIAN PERALATAN Jenis Peralatan Tenaga Kapasitas Alat Baru : a. Umur Ekonomis b. Jam Kerja dalam 1 Tahun c. Harga Alat Alat yang dipakai : a. Umur Ekonomis b. Jam Kerja dalam 1 Tahun c. Harga Alat ( * ) BIAYA PASTI PER JAM KERJA 1 2 3 Nilai sisa alat = 10 % x B Faktor Angsuran Modal = Biaya pasti per jam : a. Biaya pengembalian modal = b. Asuransi dan lain - lain = Biaya pasti per jam = ( E + F ) 1 x (1+1) ^ A' (1+1) ^ A' - 1 ( B' - C ) x D W' 0,002 x B' W'

KODE

KOEFISIEN

SATUAN

KETERANGAN

Pw Cp A W B A' W' B'

BULDOZER 100 - 150 HP 140.00

HP

5.00 1,600.00 512,500,000.00 5.00 1,600.00 410,000,000.00

Tahun Jam Rupiah Tahun Jam Rupiah

B.

C D

41,000,000.00 0.65 0.90 0.83 0.50 0.50 1.00 29.13

Rupiah M3

E F G

Rupiah Rupiah Rupiah

C. 1 2 3 4 5

BIAYA PASTI PER JAM KERJA Bahan Bakar = ( 0,175 Ltr/HP/Jam ) x Pw x Ms Pelumas = ( 0,01 Ltr/HP/Jam ) x Pw x Mp Perawatan dan Perbaikan = ( 12,5 % ) x B W' Operator = ( 1 orang/Jam ) x U1 Pembantu Operator = ( 1 orang/Jam ) x U2 Biaya Operasi per Jam = ( H + 1 + K + L + M ) H I K L M P S 22.41 2.00 0.25 0.05 Rupiah Rupiah Rupiah Rupiah Rupiah Rupiah Rupiah

D. E. 1 2 3 4 5 6

TOTAL SEWA ALAT PER JAM = ( G + P ) LAIN - LAIN Tingkat suku bunga Upah operator/sopir Upah pembantu operator/pembantu sopir Bahan Bakar bensin Bahan bakar solar Minyak Pelumas

i U1 U2 Mb Ms Mp

9,500.00 6,000.00 4,500.00 4,300.00 12,500.00

%/Tahun Rp./Jam Rp./Jam Liter Liter Liter

URAIAN ANALISA HARGA SATUAN ALAT

LIST OF WAGES, BUILDING MATERIAL AND EQUIPMENT UNIT


PROJECT WORK ITEM CODE NAME OF OWNER LOCATION : : : : :

REHABILITATION OF FISHPOND KEMBANG TANJUNG SUB DISTRIC PIDIE DISTRIC NANGGROE ACEH DA REPLACEMENT OF SEMI PERMANENT BRIDGE WITH 6 METER SPAN

JEUMANANG, PASI LHOK, LANCANG VILLAGES WAGE/DAY (Rp.) (4) WAGE/HOUR S (Rp.) (5)

NO. (1) A. 1 2 3 4 5 6 7 8 9 10

EXPLANATION (2) WAGES UNIT PRICE Non Skill Laborer Laborer Foremen Skill Laborer Chief Laborer Heavy Duty Operator Chain Saw Operator Assistent Operator Surveyor Assistent Surveyor

UNIT (3)

Man-hours Man-hours Man-hours Man-hours Man-hours Man-hours Man-hours Man-hours Man-hours Man-hours

35,000.00 45,000.00 60,750.00 67,500.00 80,500.00 67,500.00 67,500.00 45,000.00 75,000.00 50,000.00

5,000.00 6,428.57 8,678.57 9,642.86 11,500.00 9,642.86 9,642.86 6,428.57 10,714.29 7,142.86

NO. (1) B. 1 2 3 4 5 6 7 8 9

EXPLANATION (2)

UNIT (3)

UNIT PRICE (Rp.) (4)

TRANSPORTA TION (Rp.) (5)

BUILDING MATERIAL UNIT PRICE Common Timber M3 1st Class Timber M3 2nd Class Timber M3 Log Timber dia. 15 Cm Bh Nail Kg Plywood Nail Kg Zincplate Nail Kg Porland Cement @ 50 Kg Zak Soil for Filler M3

750,000.00 3,000,000.00 2,500,000.00 5,200.00 9,250.00 9,250.00 19,000.00 41,000.00 30,000.00

10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44

Sand for Filler Sand for Mortar Sand for Concrete Gravel River Stone Crushed Stone 2/3 Crushed Stone 5/7 Reinforced Concrete Steel Reinforced Concrete Wire IWF 300.150.6,5.9 Steel IWF 150.75.5.7 Steel IWF 250.125.6.9 Steel IWF 125.60.6.8 Steel L 75.75.7 Steel Profile L 60.60.6 Steel Profile Steel Aungkur Bolt Corrugated Zinc BJLS 20 K Zinc Rige BJLS 35 K Rubber Block Cast Iron dia. 1,5" PVC Pipe dia. 3/4" PVC Pipe dia. 4" Acrylic Painting Oil Painting Tinner for Painting Filler for Painting Base Painting Sand Paper Wood Painting Teer Zinc Plate Gasoline Solar Grase

M3 M3 M3 M3 M3 M3 M3 Kg Kg M' M' M' M' M' M' Unit Unit Unit Unit Unit M1 M1 M1 Kg Kg Kg Kg Kg Piece Kg Kg M2 Litre Litre Litre

55,000.00 79,500.00 79,500.00 70,750.00 65,000.00 65,000.00 65,000.00 8,000.00 10,000.00 480,000.00 188,000.00 340,000.00 130,000.00 88,000.00 64,000.00 7,200.00 3,500.00 45,000.00 30,000.00 23,000.00 15,000.00 12,000.00 30,000.00 7,500.00 23,000.00 5,200.00 4,500.00 18,000.00 2,750.00 15,000.00 6,500.00 32,500.00 4,500.00 4,300.00 12,500.00

NO. (1) C. 1

EXPLANATION (2)

UNIT (3)

PRICE (Rp.) (4)

RENTAL COST/HOURS (Rp.) (5)

EQUIPMENT RENTAL UNIT PRICE Chain Saw Unit

4,510,000.00

25,995.80

2 3 4 5 6 7 8 9 10

Concrete Mixer Excavator 80 - 140 HP Buldozer 100 - 150 HP Dump Truck 3 - 4 M3 Dump Truck Stamper Jack Hammer Generator Set Supporting Equipment

Unit Unit Unit Unit Unit Unit Unit Unit Unit

9,840,000.00 410,000,000.00 512,500,000.00 110,700,000.00 123,000,000.00 6,150,000.00 5,330,000.00 41,000,000.00 12,000.00

23,424.11 247,475.36 354,640.56 109,978.54 131,678.96 11,008.29 16,306.18 151,168.79 12,000.00

STRIC NANGGROE ACEH DARRUSALAM DGE WITH 6 METER SPAN

NOTE (6)

PRICE ON LOCATION (Rp.) (6)

750,000.00 3,000,000.00 2,500,000.00 5,200.00 9,250.00 9,250.00 19,000.00 41,000.00 30,000.00

55,000.00 79,500.00 79,500.00 70,750.00 65,000.00 65,000.00 65,000.00 8,000.00 10,000.00 480,000.00 188,000.00 340,000.00 130,000.00 88,000.00 64,000.00 7,200.00 3,500.00 45,000.00 30,000.00 23,000.00 15,000.00 12,000.00 30,000.00 7,500.00 23,000.00 5,200.00 4,500.00 18,000.00 2,750.00 15,000.00 6,500.00 32,500.00 4,500.00 4,300.00 12,500.00

NOTE (6)

DAFTAR HARGA SATUAN UPAH DAN BAHAN


NO. (1) A. 1 2 3 4 5 6 7 8 9 10 URAIAN (2) HARGA SATUAN UPAH Buruh Tak Terlatih Pekerja Mandor Tukang kayu Kepala Tukang Operator Alat Berat Operator Chain Saw Pembantu Operator Juru Ukur Pembantu Juru Ukur SATUAN (3) UPAH/HARI (Rp.) (4) UPAH/JAM (Rp.) (5) KETERANGAN (6)

OH OH OH OH OH OH OH OH OH OH

35,000.00 45,000.00 47,500.00 52,500.00 55,000.00 66,500.00 55,500.00 42,000.00 65,000.00 45,000.00

5,000.00 6,428.57 6,785.71 7,500.00 7,857.14 9,500.00 7,928.57 6,000.00 9,285.71 6,428.57

NO. (1) B. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44

URAIAN (2) HARGA SATUAN BAHAN Kayu /Papan Sembarang Kayu / Papan kelas II Kayu / Papan kelas III Kayu Bulat dia. 15 Cm Paku Biasa Paku Triplek Paku Seng / Atap Semen PC (40 Kg) Tanah Timbun Pasir Urug Pasir Pasang Pasir Beton Kerikil Batu Kali Batu Belah 2/3 Batu Belah 5/7 Besi beton Kawat beton Besi IWF 300.150.6,5.9 Besi IWF 150.75.5.7 Besi IWF 250.125.6.9 Besi IWF 125.60.6.8 Besi L 75.75.7 Besi L 60.60.6 Angker/Sengkang Angkur/Baut Seng Gelombang BJLS 20 K Rabung Seng BJLS 35 K Karet Mati Saluran Air Bersih Pipa dia. 1,5" Saluran Air Kotor Pipa dia. 3/4" Saluran Air Kotor Pipa dia. 4" Cat tembok Cat Minyak Minyak Cat Dempul Cat Menie Amplas Cat Kayu Teer Seng Plat Minyak Bensin Minyak Solar Minyak Pelumas

SATUAN (3)

HARGA SATUAN (Rp.) (4)

ONGKOS ANGKUT (Rp.) (5)

JLH HARGA DILOKASI (Rp.) (6)

M3 M3 M3 Bh Kg Kg Kg Zak M3 M3 M3 M3 M3 M3 M3 M3 Kg Kg M' M' M' M' M' M' Bh Bh Bh Bh Bh M1 M1 M1 Kg Kg Kg Kg Kg Lbr Kg Kg M2 Ltr Ltr Ltr

1,300,000.00 2,000,000.00 1,700,000.00 1,200.00 10,000.00 9,250.00 19,000.00 30,000.00 30,000.00 55,000.00 65,000.00 79,500.00 70,750.00 65,000.00 85,000.00 65,000.00 6,500.00 5,000.00 480,000.00 188,000.00 340,000.00 130,000.00 88,000.00 64,000.00 7,200.00 3,500.00 45,000.00 30,000.00 23,000.00 15,000.00 12,000.00 30,000.00 7,500.00 23,000.00 5,200.00 4,500.00 18,000.00 2,750.00 15,000.00 6,500.00 32,500.00 4,500.00 4,300.00 12,500.00

1,300,000.00 2,000,000.00 1,700,000.00 1,200.00 10,000.00 9,250.00 19,000.00 30,000.00 30,000.00 55,000.00 65,000.00 79,500.00 70,750.00 65,000.00 85,000.00 65,000.00 6,500.00 5,000.00 480,000.00 188,000.00 340,000.00 130,000.00 88,000.00 64,000.00 7,200.00 3,500.00 45,000.00 30,000.00 23,000.00 15,000.00 12,000.00 30,000.00 7,500.00 23,000.00 5,200.00 4,500.00 18,000.00 2,750.00 15,000.00 6,500.00 32,500.00 4,500.00 4,300.00 12,500.00

NO. (1) C. 1 2 3 4 5 6 7 8 9 10

URAIAN (2) HARGA SATUAN ALAT Chain Saw Concrete Mixer Excavator 80 - 140 HP Buldozer 100 - 150 HP Dump Truck 3 - 4 M3 Dump Truck Stamper Jack Hammer Generator Set Alat Bantu

SATUAN (3)

HARGA SATUAN (Rp.) (4)

ONGKOS ANGKUT (Rp.) (5)

JLH HARGA DILOKASI (Rp.) (6)

OH OH OH OH OH OH OH OH OH OH

4,510,000.00 9,840,000.00 495,000,000.00 512,500,000.00 110,700,000.00 123,000,000.00 6,150,000.00 5,330,000.00 41,000,000.00 12,000.00

25,995.80 23,424.11 247,475.36 354,640.56 109,978.54 131,678.96 11,008.29 16,306.18 151,168.79 12,000.00

10,077.92

Hal. 1 WORK COST ESTIMATE ANALIZE ANALISA PERKIRAAN BIAYA PEKERJAAN DEEP SOIL EXCAVATION GALIAN TANAH DALAM CODE KODE K.224 A

FRENCH RED CROSS


PALANG MERAH PERANCIS

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG, KEMBANG TANJUNG SUB DISTRICT PIDIE NANGGROE ACEH DARUSSALAM PROVINCE REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM EXPLANATION 1 Soil excavation doing by man power 2 Result of soil excavation be moved from digging 3 Depth excavation be containing water and having balance factor ASUMTION 1 2 3 4 5 Using man power Capacity of working group 100/ day Average of excavation up to 3 m For the stony the work with code K.224 be multiplicated by 1,5 factor For drying be suporting by pump

URAIAN :

1 Penggalian tanah dengan tenaga manusia 2 Tanah galian disingkirkan dari galian 3 Galian dalam terdapat air dan adanya faktor kesesuaian

ANGGAPAN :

1 2 3 4 5

Penggunaan tenaga manusia Kapasitas kerja kelompok 100/ hari Kedalaman rata - rata s/d 3 m Untuk jenis berbatu harga satuan pekerjaan K.224 dikalikan dengan faktor 1,5 Untuk proses pengeringan perlu dibantu pompa

LABOUR PEKERJA

TOTAL PERSONEL JUMLAH ORANG 1.000 8.000

DAYS HARI

TOTAL MAN/DAYS JUMLAH HARI/ORANG 1.000 8.000

Foreman Non skill Laborer

1.000 1.000

BILLING RATE (Rp./Days/Man) UPAH (Rp./Hr/Orang 47,500.00 35,000.00

COST (Rp.) BIAYA (Rp.) 47,500.00 280,000.00

SUB TOTAL A (Rp.) SUB JUMLAH A (Rp.)

MATERIAL BAHAN

SUM JUMLAH

UNIT SATUAN

UNIT (Rp.) HARGA SATUAN (Rp.) -

COST (Rp.) BIAYA (Rp.)

327,500.00 SUB TOTAL B (Rp.) SUB JUMLAH B (Rp.)

EQUIPMENT PERALATAN

TOTAL EQUIPMENT JUMLAH ALAT

WORK DAYS HARI KERJA

WORK HOURS JAM KERJA

UNIT PRICE (Rp.) HARGA SATUAN (Rp.)

COST (Rp.) BIAYA (Rp.)

SUB TOTAL C (Rp.) SUB JUMLAH C (Rp.)

0.00 JUMLAH (Rp.) VOLUME E 2.000 SATUAN D/E M3 HARGA SATUAN (Rp.) 40,937.50 Per M3 327,500.00

Hal. 2 WORK COST ESTIMATE ANALIZE ANALISA PERKIRAAN BIAYA PEKERJAAN SOIL FILLER FOR OPRIT TIMBUNAN TANAH/OPRIT CODE KODE K.225

FRENCH RED CROSS


PALANG MERAH PERANCIS

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG, KEMBANG TANJUNG SUB DISTRICT PIDIE NANGGROE ACEH DARUSSALAM PROVINCE REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

EXPLANATION

1 For the pilling of building material must be clean from the organic matter 2 Construction of filling doing layer by layer

ASUMTION

1 2

Material cost be calculated on the job site Compaction coefisien 1,30

ANGGAPAN :

1 2

Harga bahan sampai di lokasi pekerjaan Koefisien pemadatan 1,30

URAIAN :

1 Tempat penimbunan bahan untuk konstruksi bersih dari bahan organik 2 Pekerjaan ditempatkan untuk timbunan pada konstruksi lapis demi lapis.

LABOUR PEKERJA

TOTAL PERSONEL JUMLAH ORANG 1.000 4.000 1.000

DAYS HARI

TOTAL MAN/DAYS JUMLAH HARI/ORANG 1.000 4.000 1.000

Foreman Non skill Laborer Operator

1.000 1.000 1.000

BILLING RATE (Rp./Days/Man) UPAH (Rp./Hr/Orang 47,500.00 35,000.00 66,500.00 UNIT (Rp.) HARGA SATUAN (Rp.)

COST (Rp.) BIAYA (Rp.) 47,500.00 140,000.00 66,500.00 COST (Rp.) BIAYA (Rp.)

SUB TOTAL A (Rp.) SUB JUMLAH A (Rp.)

MATERIAL BAHAN

SUM JUMLAH

UNIT SATUAN

254,000.00 SUB TOTAL B (Rp.) SUB JUMLAH B (Rp.)

Soil Filler

26.000

M3

30,000.000

780,000.00 780,000.00

EQUIPMENT PERALATAN

TOTAL EQUIPMENT JUMLAH ALAT

WORK DAYS HARI KERJA

WORK HOURS JAM KERJA

UNIT PRICE (Rp.) HARGA SATUAN (Rp.) 55,500.00

COST (Rp.) BIAYA (Rp.)

SUB TOTAL C (Rp.) SUB JUMLAH C (Rp.)

Roller Stell Whell

1.000

3.000

166,500.00 166,500.00 JUMLAH (Rp.) 1,200,500.00

VOLUME E

1.000

SATUAN D/E

M3 HARGA SATUAN (Rp.) 150,062.50 Per M3

Hal. 3 WORK COST ESTIMATE ANALIZE ANALISA PERKIRAAN BIAYA PEKERJAAN SOIL RE-FILL URUGAN TANAH KEMBALI CODE KODE 1/2 A.1

FRENCH RED CROSS


PALANG MERAH PERANCIS

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG, KEMBANG TANJUNG SUB DISTRICT PIDIE NANGGROE ACEH DARUSSALAM PROVINCE REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

EXPLANATION

1 Soil from excavation be filled to the digging location 2 The organic disposal from digging be throwing 1 Tanah bekas galian diurug ke bekas galian 2 Membuang sampah - sampah dari bekas galian

ASUMTION

Tanah urugan diratakan dan dipadatkan dengan cara menumbuk. Soil filler be flated and be compacted by hand compaction

ANGGAPAN :

URAIAN :

LABOUR PEKERJA

TOTAL PERSONEL JUMLAH ORANG 0.012 0.375

DAYS HARI

TOTAL MAN/DAYS JUMLAH HARI/ORANG 0.012 0.375

Foreman Non skill Laborer Operator

1.000 1.000

BILLING RATE (Rp./Days/Man) UPAH (Rp./Hr/Orang 47,500.00 35,000.00

COST (Rp.) BIAYA (Rp.) 570.00 13,125.00 COST (Rp.) BIAYA (Rp.)

SUB TOTAL A (Rp.) SUB JUMLAH A (Rp.)

MATERIAL BAHAN

SUM JUMLAH

UNIT SATUAN

UNIT (Rp.) HARGA SATUAN (Rp.) -

13,695.00 SUB TOTAL B (Rp.) SUB JUMLAH B (Rp.)

EQUIPMENT PERALATAN

TOTAL EQUIPMENT JUMLAH ALAT

WORK DAYS HARI KERJA

WORK HOURS JAM KERJA

UNIT PRICE (Rp.) HARGA SATUAN (Rp.) 0.00

COST (Rp.) BIAYA (Rp.)

SUB TOTAL C (Rp.) SUB JUMLAH C (Rp.)

Water Pump

0.00 JUMLAH (Rp.) 13,695.00

VOLUME E

1.000

SATUAN D/E

M3 HARGA SATUAN (Rp.) 1,711.88 Per M3

Hal. 4 WORK COST ESTIMATE ANALIZE ANALISA PERKIRAAN BIAYA PEKERJAAN LOG TIMBER 15 s/d 20 Cm FOR PILLING PENGADAAN TIANG PANCANG 15 s/d 20 Cm CODE KODE K.900

FRENCH RED CROSS


PALANG MERAH PERANCIS

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG, KEMBANG TANJUNG SUB DISTRICT PIDIE NANGGROE ACEH DARUSSALAM PROVINCE REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

EXPLANATION

1 Material on out of job site 2 Transportation the material by power to the job site 3 Material be pilled on the pic up 3 The distance of pick up location 5 km Bahan/material berada diluar lokasi pekerjaan 2 Bahan diangkut oleh tenaga manusia ketempat pekerjaan 3 Bahan ditumpuk ditempat 4 Jarak pengambilan maksimum 5
1

ASUMTION

1 2

Cost of material franco on pick up location Length of timber 7 M be lifted by 4 man

ANGGAPAN :

1 2

Harga bahan sesuai dengan tempat pengambilan Panjang kayu kurang lebih 7 M diangkut oleh 4 orang

URAIAN :

LABOUR PEKERJA

TOTAL PERSONEL JUMLAH ORANG 0.010 0.030 0.250 0.100

DAYS HARI

TOTAL MAN/DAYS JUMLAH HARI/ORANG 0.010 0.030 0.250 0.100

Foreman Chief Laborer Skill Laborer Non skill Laborer

1.000 1.000 1.000 1.000

BILLING RATE (Rp./Days/Man) UPAH (Rp./Hr/Orang 47,500.00 55,000.00 52,500.00 35,000.00 UNIT (Rp.) HARGA SATUAN (Rp.)

COST (Rp.) BIAYA (Rp.) 475.00 1,650.00 13,125.00 3,500.00 COST (Rp.) BIAYA (Rp.)

SUB TOTAL A (Rp.) SUB JUMLAH A (Rp.)

MATERIAL BAHAN

SUM JUMLAH

UNIT SATUAN

18,750.00 SUB TOTAL B (Rp.) SUB JUMLAH B (Rp.)

Timber

0.220

M3

1,300,000.000

286,000.00

286,000.00

EQUIPMENT PERALATAN

TOTAL EQUIPMENT JUMLAH ALAT

WORK DAYS HARI KERJA

WORK HOURS JAM KERJA

UNIT PRICE (Rp.) HARGA SATUAN (Rp.) -

COST (Rp.) BIAYA (Rp.)

SUB TOTAL C (Rp.) SUB JUMLAH C (Rp.)

0.00 JUMLAH (Rp.) VOLUME E 7.000 SATUAN D/E M' HARGA SATUAN (Rp.) 43,535.71 Per M' 304,750.00

Hal. 5 WORK COST ESTIMATE ANALIZE ANALISA PERKIRAAN BIAYA PEKERJAAN LOG TIMBER 15 s/d 20 Cm PILLING PEMANCANGAN TIANG PANCANG KAYU CEROCOK dia. 15 S/D 20 CM CODE KODE K.901

FRENCH RED CROSS


PALANG MERAH PERANCIS

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG, KEMBANG TANJUNG SUB DISTRICT PIDIE NANGGROE ACEH DARUSSALAM PROVINCE REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

EXPLANATION

1 Material and equipment stand by on job site by supplyer 2 Material be located near job site 1 Bahan/Alat siap dilapangan oleh supplier 2 Bahan diletakkan kedudukannya dekat dengan lokasi pekerja

ASUMTION

1 2 3 4

Weight of hammer minimum 0.75 - 1 Ton Pilling be stoped after 10 kali ditumbuk masuk = 1 cm Foundation using the timber piling and pillar Pile set up be diging before

URAIAN :

ANGGAPAN :

1 2 3 4

Berat penumbuk minimal 0.75 - 1 Ton Penghentian pemancangan setelah 10 kali ditumbuk masuk = 1 cm Pondasi digunakan pemancang kayu dan pilar Letak pancang dilubangi lebih dahulu.

LABOUR PEKERJA

TOTAL PERSONEL JUMLAH ORANG 0.050 0.030 1.800 0.350

DAYS HARI

TOTAL MAN/DAYS JUMLAH HARI/ORANG 0.050 0.030 1.800 0.350

Foreman Chief Laborer Skill Laborer Non skill Laborer

1.000 1.000 1.000 1.000

BILLING RATE (Rp./Days/Man) UPAH (Rp./Hr/Orang 47,500.00 55,000.00 52,500.00 35,000.00 UNIT (Rp.) HARGA SATUAN (Rp.)

COST (Rp.) BIAYA (Rp.) 2,375.00 1,650.00 94,500.00 12,250.00 COST (Rp.) BIAYA (Rp.)

SUB TOTAL A (Rp.) SUB JUMLAH A (Rp.)

MATERIAL BAHAN

SUM JUMLAH

UNIT SATUAN

110,775.00 SUB TOTAL B (Rp.) SUB JUMLAH B (Rp.)

EQUIPMENT PERALATAN

TOTAL EQUIPMENT JUMLAH ALAT

WORK DAYS HARI KERJA

WORK HOURS JAM KERJA

UNIT PRICE (Rp.) HARGA SATUAN (Rp.) 11,415.00

COST (Rp.) BIAYA (Rp.)

SUB TOTAL C (Rp.) SUB JUMLAH C (Rp.)

Hammer

1.000

0.140

1,598.10 1,598.10 JUMLAH (Rp.) 112,373.10

VOLUME E

1.000

SATUAN D/E

M' HARGA SATUAN (Rp.) 112,373.10 Per M'

Hal. 6 WORK COST ESTIMATE ANALIZE ANALISA PERKIRAAN BIAYA PEKERJAAN SAND FILLER UNDER THE FOUNDATION URUGAN PASIR PADA BAWAH PONDASI CODE KODE A. 18

FRENCH RED CROSS


PALANG MERAH PERANCIS

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG, KEMBANG TANJUNG SUB DISTRICT PIDIE NANGGROE ACEH DARUSSALAM PROVINCE REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

EXPLANATION

1 Filling be compacted each 20 cm per layer 1 Timbunan harus dipadatkan setiap lapisan setebal 20 cm

ASUMTION

1 2 1 2

Material cost be calculated on the job site Capacity of working group 100/ day Harga bahan sampai dilokasi pekerjaan Kapasitas kerja kelompok 100/ hariKoefisien

URAIAN :

ANGGAPAN :

LABOUR PEKERJA

TOTAL PERSONEL JUMLAH ORANG 0.012 0.375 -

DAYS HARI

TOTAL MAN/DAYS JUMLAH HARI/ORANG 0.012 0.375 -

Foreman Skill Laborer Operator

1.000 1.000 -

BILLING RATE (Rp./Days/Man) UPAH (Rp./Hr/Orang 47,500.00 52,500.00 0.00 UNIT (Rp.) HARGA SATUAN (Rp.) 55,000.00

COST (Rp.) BIAYA (Rp.) 570.00 19,687.50

SUB TOTAL A (Rp.) SUB JUMLAH A (Rp.)

MATERIAL BAHAN

SUM JUMLAH

UNIT SATUAN

COST (Rp.) BIAYA (Rp.)

20,257.50 SUB TOTAL B (Rp.) SUB JUMLAH B (Rp.)

Sand Filler

1.200

M3

66,000.00 66,000.00

EQUIPMENT PERALATAN

TOTAL EQUIPMENT JUMLAH ALAT

WORK DAYS HARI KERJA

WORK HOURS JAM KERJA

UNIT PRICE (Rp.) HARGA SATUAN (Rp.)

COST (Rp.) BIAYA (Rp.)

SUB TOTAL C (Rp.) SUB JUMLAH C (Rp.)

0.00 JUMLAH (Rp.) VOLUME E 1.000 SATUAN D/E M3 HARGA SATUAN (Rp.) 10,782.19 Per M3 86,257.50

Hal. 7 WORK COST ESTIMATE ANALIZE ANALISA PERKIRAAN BIAYA PEKERJAAN RIVER STONE PAIRING CONTRUCTION KONSTRUKSI PASANGAN BATU CODE KODE K.810

FRENCH RED CROSS


PALANG MERAH PERANCIS

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG, KEMBANG TANJUNG SUB DISTRICT PIDIE NANGGROE ACEH DARUSSALAM PROVINCE REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

EXPLANATION

1 Material and equipment stand by on job site by supplyer 2 Stone crushed be install with PC and Sand mortar 1 Material disiapkan di lokasi oleh supplier 2 Batu belah dipasang dengan spesi semen PC + Pasir

ASUMTION

URAIAN :

2 3 4 ANGGAPAN : 1

Using culvert, bridge and shear wall and ather structure with stone pairing wit water proofing mortar Material be delivered on job site Not included the excavation and filling Mortar 1 : 3 Digunakan pada gorong - gorong, jembatan, tembok penahan dan struktur-struktur yang lain yang menggunakan pasangan batu kedap air Material dikirim sampai lokasi tidak termasuk pekerjaan galian/timbunan Adukan spesi 1 : 3

2 3 4

LABOUR PEKERJA

TOTAL PERSONEL JUMLAH ORANG 0.010 4.000 12.000

DAYS HARI

TOTAL MAN/DAYS JUMLAH HARI/ORANG 0.010 4.000 12.000

Foreman Skill Laborer Non Skill Laborer

1.000 1.000 1.000

BILLING RATE (Rp./Days/Man) UPAH (Rp./Hr/Orang 47,500.00 52,500.00 35,000.00 UNIT (Rp.) HARGA SATUAN (Rp.) 65,000.000 65,000.000 30,000.000

COST (Rp.) BIAYA (Rp.) 475.00 210,000.00 420,000.00 COST (Rp.) BIAYA (Rp.) 325,000.00 81,250.00 450,000.00

SUB TOTAL A (Rp.) SUB JUMLAH A (Rp.)

MATERIAL BAHAN

SUM JUMLAH

UNIT SATUAN

630,475.00 SUB TOTAL B (Rp.) SUB JUMLAH B (Rp.) 856,250.00 SUB TOTAL C (Rp.) SUB JUMLAH C (Rp.)

Batu belah 10-15 cm Pasir Semen (40 Kg)

5.000 1.250 15.000

M3 M3 zak

EQUIPMENT PERALATAN

TOTAL EQUIPMENT JUMLAH ALAT

WORK DAYS HARI KERJA

WORK HOURS JAM KERJA

UNIT PRICE (Rp.) HARGA SATUAN (Rp.) -

COST (Rp.) BIAYA (Rp.)

0.00 JUMLAH (Rp.) VOLUME E 5.000 SATUAN D/E M3 HARGA SATUAN (Rp.) 297,345.00 Per M3 1,486,725.00

Hal. 8 WORK COST ESTIMATE ANALIZE ANALISA PERKIRAAN BIAYA PEKERJAAN PLESTERING PLESTERAN CODE KODE K.811

FRENCH RED CROSS


PALANG MERAH PERANCIS

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG, KEMBANG TANJUNG SUB DISTRICT PIDIE NANGGROE ACEH DARUSSALAM PROVINCE REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

EXPLANATION

1 Material and equipment stand by on job site by supplyer 2 Material be located near job site 1 Bahan/Alat siap dilapangan oleh supplier 2 Bahan diletakkan kedudukannya dengan pekerja

ASUMTION

1 2 3 4

Weight of hammer minimum 0.75 - 1 Ton Pilling be stoped after 10 kali ditumbuk masuk = 1 cm Foundation using the timber piling and pillar Pile set up be diging before Berat penumbuk minimal 0.75 - 1 Ton Penghentian pemancangan setelah 10 kali ditumbuk masuk = 1 cm Pondasi digunakan pemancang kayu dan pilar Letak pancang dilubangi lebih dahulu.

URAIAN :

ANGGAPAN :

1 2 3 4

LABOUR PEKERJA

TOTAL PERSONEL JUMLAH ORANG 1.000 1.000 6.000 12.000

DAYS HARI

TOTAL MAN/DAYS JUMLAH HARI/ORANG 1.000 1.000 6.000 12.000

Foreman Chief Laborer Skill Laborer Non skill Laborer

1.000 1.000 1.000 1.000

BILLING RATE (Rp./Days/Man) UPAH (Rp./Hr/Orang 47,500.00 55,000.00 52,500.00 35,000.00 UNIT (Rp.) HARGA SATUAN (Rp.) 65,000.000 30,000.000

COST (Rp.) BIAYA (Rp.) 47,500.00 55,000.00 315,000.00 420,000.00 COST (Rp.) BIAYA (Rp.) 50,700.00 237,000.00

SUB TOTAL A (Rp.) SUB JUMLAH A (Rp.)

MATERIAL BAHAN

SUM JUMLAH

UNIT SATUAN

837,500.00 SUB TOTAL B (Rp.) SUB JUMLAH B (Rp.) -

Concrete Sand PC @40 Kg

0.780 7.900

M3 zak

EQUIPMENT PERALATAN

TOTAL EQUIPMENT JUMLAH ALAT

WORK DAYS HARI KERJA

WORK HOURS JAM KERJA

UNIT PRICE (Rp.) HARGA SATUAN (Rp.)

COST (Rp.) BIAYA (Rp.)

SUB TOTAL C (Rp.) SUB JUMLAH C (Rp.)

0.00 JUMLAH (Rp.) VOLUME E 50.000 SATUAN D/E M2 HARGA SATUAN (Rp.) 16,750.00 Per M2 837,500.00

Hal. 9 WORK COST ESTIMATE ANALIZE ANALISA PERKIRAAN BIAYA PEKERJAAN CONCRETE FORM WORK PEKERJAAN CETAKAN UNTUK BETON CODE KODE K. 890

FRENCH RED CROSS


PALANG MERAH PERANCIS

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG, KEMBANG TANJUNG SUB DISTRICT PIDIE NANGGROE ACEH DARUSSALAM PROVINCE REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

EXPLANATION

1 The equipment be installed on concrete or stone pairing with the slope to below or ather 2 To be installed palm fibre round dalam peralon. 1 Memasang peralatan pada pasangan batu/beton pada talud dengan miring ke bawah bagian lainnya 2 Memasang ijuk disekeliling dalam peralon.

ASUMTION

1 2 3 4

Material cost be calculated on the job site Cutting of PVC pipe dia. 2 " depend on wall thickess wall thickess. Palm fibre be install on the end of PVC PVC be calculated @ 40 m' Harga bahan dihitung ditempat pekerjaan Setiap potongan peralon 2 " panjang tergantung tebal dinding. Ijuk dipasang diujung sekeliling peralon bagian Hitungan peralon per 40 m'

ANGGAPAN : URAIAN :

1 2 3 4

LABOUR PEKERJA

TOTAL PERSONEL JUMLAH ORANG 1.000 4.000 -

DAYS HARI

TOTAL MAN/DAYS JUMLAH HARI/ORANG 1.000 4.000 -

Foreman Non Skill Laborer Operator

1.000 1.000 -

BILLING RATE (Rp./Days/Man) UPAH (Rp./Hr/Orang 47,500.00 35,000.00 0.00 UNIT (Rp.) HARGA SATUAN (Rp.) 15,000.00 4,000.00

COST (Rp.) BIAYA (Rp.) 47,500.00 140,000.00

SUB TOTAL A (Rp.) SUB JUMLAH A (Rp.)

MATERIAL BAHAN

SUM JUMLAH

UNIT SATUAN

COST (Rp.) BIAYA (Rp.) 600,000.00 80,000.00

187,500.00 SUB TOTAL B (Rp.) SUB JUMLAH B (Rp.)

Paralon 2 " Ijuk

40.000 20.000

M' Kg

680,000.00 EQUIPMENT PERALATAN TOTAL EQUIPMENT JUMLAH ALAT WORK DAYS HARI KERJA WORK HOURS JAM KERJA UNIT PRICE (Rp.) HARGA SATUAN (Rp.) COST (Rp.) BIAYA (Rp.) SUB TOTAL C (Rp.) SUB JUMLAH C (Rp.)

0.00 JUMLAH (Rp.) VOLUME E 40.000 SATUAN D/E M' HARGA SATUAN (Rp.) 21,687.50 Per M3 867,500.00

Hal. 9a WORK COST ESTIMATE ANALIZE ANALISA PERKIRAAN BIAYA PEKERJAAN CANAL REPLECEMENT BY HEAVY DUTY EQ. MEMBUAT SALURAN (MENGGUNAKAN ALAT BERAT) CODE KODE K. 110 A

FRENCH RED CROSS


PALANG MERAH PERANCIS

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG, KEMBANG TANJUNG SUB DISTRICT PIDIE NANGGROE ACEH DARUSSALAM PROVINCE REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

EXPLANATION

1 Canal excavation doing by Excavation 2 Soil from canal excavation be throwing on side of canal 3 Man power be throwing the roots and ather disposal 1 Menggali saluran dengan excavator 2 Tanah galian diangkat ke samping saluran yang digali. 3 Tenaga manusia membuang akarakar kayu dan sampah-sampah lainnya.

ASUMTION

1 2

Using the excavator (140 M3/hari) Tree and any planting be clean up following the dykes be construction. Menggunakan alat berat exavator (140 M3/hari) Pohon-pohon dan semak belukar sudah dibersihkan pada waktu pembentukan tanggul samping.

ANGGAPAN :

1 2

URAIAN :

LABOUR PEKERJA

TOTAL PERSONEL JUMLAH ORANG 1.000 1.000 1.000 5.000

DAYS HARI

TOTAL MAN/DAYS JUMLAH HARI/ORANG 1.000 1.000 1.000 5.000

Foreman Skill Operator Operator Ass. Non Skill Laborer

1.000 1.000 1.000 1.000

BILLING RATE (Rp./Days/Man) UPAH (Rp./Hr/Orang 47,500.00 66,500.00 42,000.00 35,000.00 UNIT (Rp.) HARGA SATUAN (Rp.)

COST (Rp.) BIAYA (Rp.) 47,500.00 66,500.00 42,000.00 175,000.00 COST (Rp.) BIAYA (Rp.)

SUB TOTAL A (Rp.) SUB JUMLAH A (Rp.)

MATERIAL BAHAN

SUM JUMLAH

UNIT SATUAN

331,000.00 SUB TOTAL B (Rp.) SUB JUMLAH B (Rp.)

0.00 EQUIPMENT PERALATAN TOTAL EQUIPMENT JUMLAH ALAT WORK DAYS HARI KERJA WORK HOURS JAM KERJA UNIT PRICE (Rp.) HARGA SATUAN (Rp.) 247,475.36 COST (Rp.) BIAYA (Rp.) SUB TOTAL C (Rp.) SUB JUMLAH C (Rp.)

Exavator 140 HP

1.000

1.000

5.000

1,237,376.80 1,237,376.80 JUMLAH (Rp.) 1,568,376.80

VOLUME E

140.000

SATUAN D/E

M3 HARGA SATUAN (Rp.) 11,202.69 Per M3

Hal. 10 WORK COST ESTIMATE ANALIZE ANALISA PERKIRAAN BIAYA PEKERJAAN CONCRETE FORM WORK PEKERJAAN CETAKAN UNTUK BETON CODE KODE K. 710

FRENCH RED CROSS


PALANG MERAH PERANCIS

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG, KEMBANG TANJUNG SUB DISTRICT PIDIE DISTRICT NANGGROE ACEH DARUSSALAM PROVINCE REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM EXPLANATION URAIAN :
1 Menyiapkan bahan memotong, pada mengergaji, memaku dan memasang 2 Membongkar cetakan setelah beton mengeras.

ASUMTION ANGGAPAN :

1 1/3 dari bahan masih dapat digunakan lagi untuk cetakan lain. 2 Kapasitas produksi = 2 M3 / hari.

10 Formwork 10 Cetakan dibongkar oleh pekerja atau ijin Direksi.

LABOUR PEKERJA

TOTAL PERSONEL JUMLAH ORANG 1.000 1.000 6.000 4.000

DAYS HARI

TOTAL MAN/DAYS JUMLAH HARI/ORANG 1.000 1.000 6.000 4.000

Foreman Chief Laborer Skill Laborer Non Skill Laborer

1.000 1.000 1.000 1.000

BILLING RATE (Rp./Days/Man) UPAH (Rp./Hr/Orang 47,500.00 55,000.00 52,500.00 35,000.00 UNIT (Rp.) HARGA SATUAN (Rp.) 1,300,000.00 10,000.00

COST (Rp.) BIAYA (Rp.) 47,500.00 55,000.00 315,000.00 140,000.00 COST (Rp.) BIAYA (Rp.) 1,040,000.00 80,000.00

SUB TOTAL A (Rp.) SUB JUMLAH A (Rp.)

MATERIAL BAHAN

SUM JUMLAH

UNIT SATUAN

557,500.00 SUB TOTAL B (Rp.) SUB JUMLAH B (Rp.)

Kayu Begisting Paku

0.800 8.000

M3 Kg

1,120,000.00 EQUIPMENT PERALATAN TOTAL EQUIPMENT JUMLAH ALAT WORK DAYS HARI KERJA WORK HOURS JAM KERJA UNIT PRICE (Rp.) HARGA SATUAN (Rp.) COST (Rp.) BIAYA (Rp.) SUB TOTAL C (Rp.) SUB JUMLAH C (Rp.)

0.00 JUMLAH (Rp.) VOLUME E 2.000 SATUAN D/E M3 HARGA SATUAN (Rp.) 671,000.00 Per M3 1,677,500.00

Hal. 11 WORK COST ESTIMATE ANALIZE ANALISA PERKIRAAN BIAYA PEKERJAAN CLEANING AND COATING PEMBERSIHAN DAN CAT TEMBOK CODE KODE K.813

FRENCH RED CROSS


PALANG MERAH PERANCIS

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG, KEMBANG TANJUNG SUB DISTRICT PIDIE DISTRICT NANGGROE ACEH DARUSSALAM PROVINCE REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM EXPLANATION URAIAN : 1 Membersihkan tempat yang akan dicat. 2 Cat dituang kedalam baskom dan dicatkan dengan roll kuas. ASUMTION ANGGAPAN : 2 3

Bahan dihitung ditempat pekerjaan. 1 kg can be covered on 6 m2 1 kg dapat menghasilkan 6 m2 Calculated per 1 m2 Hitungan per 1 m2

LABOUR PEKERJA

TOTAL PERSONEL JUMLAH ORANG 1.000 1.000 -

DAYS HARI

TOTAL MAN/DAYS JUMLAH HARI/ORANG 0.010 0.200 -

Foreman Skill Laborer Operator

1.000 1.000 -

BILLING RATE (Rp./Days/Man) UPAH (Rp./Hr/Orang 47,500.00 52,500.00 UNIT (Rp.) HARGA SATUAN (Rp.)

COST (Rp.) BIAYA (Rp.) 475.00 10,500.00 COST (Rp.) BIAYA (Rp.)

SUB TOTAL A (Rp.) SUB JUMLAH A (Rp.)

MATERIAL BAHAN

SUM JUMLAH

UNIT SATUAN

10,975.00 SUB TOTAL B (Rp.) SUB JUMLAH B (Rp.)

Cat Tembok

0.300

Kg

7,500.000

2,250.00 2,250.00

EQUIPMENT PERALATAN

TOTAL EQUIPMENT JUMLAH ALAT

WORK DAYS HARI KERJA

WORK HOURS JAM KERJA

UNIT PRICE (Rp.) HARGA SATUAN (Rp.)

COST (Rp.) BIAYA (Rp.)

SUB TOTAL C (Rp.) SUB JUMLAH C (Rp.)

0.00 JUMLAH (Rp.) VOLUME E 1.000 SATUAN D/E M2 HARGA SATUAN (Rp.) 13,225.00 Per M2 13,225.00

Hal. 12 WORK COST ESTIMATE ANALIZE ANALISA PERKIRAAN BIAYA PEKERJAAN CONCRETE REINFORCEMENT PENULANGAN BETON CODE KODE K. 715

FRENCH RED CROSS


PALANG MERAH PERANCIS

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG, KEMBANG TANJUNG SUB DISTRICT PIDIE DISTRICT NANGGROE ACEH DARUSSALAM PROVINCE REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

EXPLANATION

1 Bahan disediakan oleh Supplier 2 Besi dipotong dibentuk dan diikat. 1 Bahan disediakan oleh Supplier 2 Besi dipotong dibentuk dan diikat.

ASUMTION

URAIAN :

1 200 Kg besi dapat disiapkan dalam 1 hari 2 Cost of material besed on job site 2 Harga material berdasarkan ditempat pekerjaan. Pemakaian bahan tulangan dilebihkan 10 % untuk 3 membengkok dan penyambungan. 1 200 Kg besi dapat disiapkan dalam 1 hari 2 Cost of material besed on job site 2 Harga material berdasarkan ditempat pekerjaan. Pemakaian bahan tulangan dilebihkan 10 % untuk 3 membengkok dan penyambungan.

ANGGAPAN :

LABOUR PEKERJA

TOTAL PERSONEL JUMLAH ORANG 1.000 1.000 2.000 2.000

DAYS HARI

TOTAL MAN/DAYS JUMLAH HARI/ORANG 1.000 1.000 2.000 2.000

Foreman Laborer Skill Laborer Non skill Laborer

1.000 1.000 1.000 1.000

BILLING RATE (Rp./Days/Man) UPAH (Rp./Hr/Orang 47,500.00 52,500.00 45,000.00 35,000.00 UNIT (Rp.) HARGA SATUAN (Rp.) 6,500.00 5,000.00

COST (Rp.) BIAYA (Rp.) 47,500.00 52,500.00 90,000.00 70,000.00 COST (Rp.) BIAYA (Rp.) 1,430,000.00 10,000.00

SUB TOTAL A (Rp.) SUB JUMLAH A (Rp.)

MATERIAL BAHAN

SUM JUMLAH

UNIT SATUAN

260,000.00 SUB TOTAL B (Rp.) SUB JUMLAH B (Rp.)

Besi Beton Kawat Ikat

220.000 2.000

Kg Kg

1,440,000.00 EQUIPMENT PERALATAN TOTAL EQUIPMENT JUMLAH ALAT WORK DAYS HARI KERJA WORK HOURS JAM KERJA UNIT PRICE (Rp.) HARGA SATUAN (Rp.) COST (Rp.) BIAYA (Rp.) SUB TOTAL C (Rp.) SUB JUMLAH C (Rp.)

0.00 JUMLAH (Rp.) VOLUME E 2.000 SATUAN D/E M3 HARGA SATUAN (Rp.) 850,000.00 Per M3 1,700,000.00

Hal. 13 WORK COST ESTIMATE ANALIZE ANALISA PERKIRAAN BIAYA PEKERJAAN CONCRETE K. 175 B E T O N K. 175 CODE KODE K.725

FRENCH RED CROSS


PALANG MERAH PERANCIS

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG, KEMBANG TANJUNG SUB DISTRICT PIDIE DISTRICT NANGGROE ACEH DARUSSALAM PROVINCE REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

EXPLANATION

1 Material and equipment stand by on job site by supplyer 2 Before using the agregat must be cleaning 3 Concrete be mixed by mechanical mixer and near the job site.

ASUMTION

1 2 3 4 5

Material cost be calculated on the job site Productivity of concrete mixer is 10 M3/hari. Mix design 1 : 2 : 3. Length of mixing is 9 minute The weight of 1 M3 concrete 2.400 Kg and 1 Pocket PC 40 Kg. Harga/material dihitung dilokasi pekerjaan. Kapasitas produksi adukan beton 10 M3/hari. Campuran 1 : 2 : 3. Lamanya setiap kali pengadukan 9 menit 1 M3 beton beratnya 2.400 Kg dan 1 Zak PC beratnya

ANGGAPAN : URAIAN : 1 2 3 Bahan/material disediakan oleh Supplier. Sebelum digunakan agregat harus dibersihkan dahulu Beton diaduk dengan pengaduk mekanis didekat lokasi

1 2 3 4 5

LABOUR PEKERJA

TOTAL PERSONEL JUMLAH ORANG 1.000 1.000 1.000 8.000 1.000

DAYS HARI

TOTAL MAN/DAYS JUMLAH HARI/ORANG 1.000 1.000 1.000 8.000 1.000

Foreman Chief Laborer Skill Laborer Non skill Laborer Operator Non skill

1.000 1.000 1.000 1.000 1.000

BILLING RATE (Rp./Days/Man) UPAH (Rp./Hr/Orang 47,500.00 55,000.00 52,500.00 35,000.00 35,000.00 UNIT (Rp.) HARGA SATUAN (Rp.) 70,750.000 30,000.000 79,500.000

COST (Rp.) BIAYA (Rp.) 47,500.00 55,000.00 52,500.00 280,000.00 35,000.00 COST (Rp.) BIAYA (Rp.) 116,737.50 494,400.00 85,860.00

SUB TOTAL A (Rp.) SUB JUMLAH A (Rp.)

MATERIAL BAHAN

SUM JUMLAH

UNIT SATUAN

470,000.00 SUB TOTAL B (Rp.) SUB JUMLAH B (Rp.) 696,997.50 SUB TOTAL C (Rp.) SUB JUMLAH C (Rp.)

Batu Kerikil Semen PC Pasir Beton

1.650 16.480 1.080

M3 Zak M3

EQUIPMENT PERALATAN

TOTAL EQUIPMENT JUMLAH ALAT

WORK DAYS HARI KERJA

WORK HOURS JAM KERJA

UNIT PRICE (Rp.) HARGA SATUAN (Rp.) 23,424.11

COST (Rp.) BIAYA (Rp.)

Concrete Mixer

1.000

8.000

187,392.88 187,392.88 JUMLAH (Rp.) 1,354,390.38

VOLUME E

2.000

SATUAN D/E

M3 HARGA SATUAN (Rp.) 677,195.19 Per M3

Hal. 14 WORK COST ESTIMATE ANALIZE ANALISA PERKIRAAN BIAYA PEKERJAAN REINFORCEMENT CONCRETE BETON BERTULANG LANDASAN PLAT INJAK DAN GLAGAR CODE KODE K.725 A

FRENCH RED CROSS


PALANG MERAH PERANCIS

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG, KEMBANG TANJUNG SUB DISTRICT PIDIE DISTRICT NANGGROE ACEH DARUSSALAM PROVINCE REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

EXPLANATION

1 Reinforcement steel and concrete workform be ready in jab site 2 Concrete be mixing by mechanic mixer and near the concrete location 1 Bahan besi dan cetakan telah siap ditempat. 2 Beton diaduk dengan mesin pengaduk mekanis didekat lokasi pengecoran.

ASUMTION

1 2 3 1 2 3

Concrete mixing 1 : 2 : 3 Capacity are 2 M3/days Material cost be calculated on the job site Campuran beton 1 : 2 : 3 Kapasitas 2 M3/hari Haraga bahan dilokasi pekerjaan.

ANGGAPAN :

URAIAN :

LABOUR PEKERJA

TOTAL PERSONEL JUMLAH ORANG 1.000 1.400 0.400 1.000

DAYS HARI

TOTAL MAN/DAYS JUMLAH HARI/ORANG 1.000 1.400 0.400 1.000

Pek. Beton Pek. Besi Pek. Cetakan Operator

1.000 1.000 1.000 1.000

BILLING RATE (Rp./Days/Man) UPAH (Rp./Hr/Orang 470,000.00 260,000.00 557,500.00 42,000.00 UNIT (Rp.) HARGA SATUAN (Rp.) 696,997.50 1,440,000.00 1,120,000.00

COST (Rp.) BIAYA (Rp.) 470,000.00 364,000.00 223,000.00 42,000.00 COST (Rp.) BIAYA (Rp.) 696,997.50 2,016,000.00 448,000.00

SUB TOTAL A (Rp.) SUB JUMLAH A (Rp.)

MATERIAL BAHAN

SUM JUMLAH

UNIT SATUAN

1,099,000.00 SUB TOTAL B (Rp.) SUB JUMLAH B (Rp.)

Beton Besi Cetakan

1.000 1.400 0.400

(1) (1) (1)

3,160,997.50 EQUIPMENT PERALATAN TOTAL EQUIPMENT JUMLAH ALAT WORK DAYS HARI KERJA WORK HOURS JAM KERJA UNIT PRICE (Rp.) HARGA SATUAN (Rp.) 23,424.11 COST (Rp.) BIAYA (Rp.) SUB TOTAL C (Rp.) SUB JUMLAH C (Rp.)

Concrete Mixer

1.000

8.000

187,392.88 187,392.88 JUMLAH (Rp.) 4,447,390.38

VOLUME E

2.000

SATUAN D/E

M3 HARGA SATUAN (Rp.) 2,223,695.19 Per M3

Hal. 15 WORK COST ESTIMATE ANALIZE ANALISA PERKIRAAN BIAYA PEKERJAAN INSTALL THE TIMBER BEAM AND BRANCHING MEMASANG GELAGAR/SEKUR CODE KODE K.900E

FRENCH RED CROSS


PALANG MERAH PERANCIS

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG, KEMBANG TANJUNG SUB DISTRICT PIDIE DISTRICT NANGGROE ACEH DARUSSALAM PROVINCE REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

EXPLANATION

1 Balok pemikul dipasang diatas tiang pancang. 2 Gelagar dipasang diatas balok pemikul. 3 Untuk perkuatan masing-masing sambungan memakai baut/paku dan begel. 1 Balok pemikul dipasang diatas tiang pancang. 2 Gelagar dipasang diatas balok pemikul. 3 Untuk perkuatan masing-masing sambungan memakai baut/paku dan begel.

ASUMTION

1 2 3 4 1 2 3 4

With man pawer Main Beam 25/30 Timber 5/30 Be calculated per 1 M3 Dengan tenaga manusia Balok utama ukuran 25/30 Balok melintang ukuran 25/30 Dihitung per 1 M3

ANGGAPAN :

URAIAN :

LABOUR PEKERJA

TOTAL PERSONEL JUMLAH ORANG 1.000 1.000 2.000 6.000

DAYS HARI

TOTAL MAN/DAYS JUMLAH HARI/ORANG 1.000 1.000 2.000 6.000

Foreman Chief Laborer Skill Laborer Laborer

1.000 1.000 1.000 1.000

BILLING RATE (Rp./Days/Man) UPAH (Rp./Hr/Orang 47,500.00 55,000.00 52,500.00 45,000.00 UNIT (Rp.) HARGA SATUAN (Rp.) 10,000.000 2,000,000.000 7,200.000

COST (Rp.) BIAYA (Rp.) 47,500.00 55,000.00 105,000.00 270,000.00 COST (Rp.) BIAYA (Rp.) 65,000.00 2,000,000.00 21,708.00

SUB TOTAL A (Rp.) SUB JUMLAH A (Rp.)

MATERIAL BAHAN

SUM JUMLAH

UNIT SATUAN

477,500.00 SUB TOTAL B (Rp.) SUB JUMLAH B (Rp.) 2,086,708.00 SUB TOTAL C (Rp.) SUB JUMLAH C (Rp.)

Paku/baut Kayu Besi begel

6.500 1.000 3.015

Kg M3 Bh

EQUIPMENT PERALATAN

TOTAL EQUIPMENT JUMLAH ALAT

WORK DAYS HARI KERJA

WORK HOURS JAM KERJA

UNIT PRICE (Rp.) HARGA SATUAN (Rp.) 12,000.000

COST (Rp.) BIAYA (Rp.)

Alat bantu

1.000

Set

12,000.00

12,000.00

JUMLAH (Rp.) VOLUME E 1.000 SATUAN D/E M3 HARGA SATUAN (Rp.) 2,576,208.00

2,576,208.00

M3

Hal. 16 WORK COST ESTIMATE ANALIZE ANALISA PERKIRAAN BIAYA PEKERJAAN INSTALL THE TIMBER RUNNING FLOOR PEKERJAAN KAYU BANTALAN LANTAI CODE KODE K. 903

FRENCH RED CROSS


PALANG MERAH PERANCIS

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG, KEMBANG TANJUNG SUB DISTRICT PIDIE DISTRICT NANGGROE ACEH DARUSSALAM PROVINCE REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

EXPLANATION

1 Kayu diketam terlebih dahulu. 2 Kayu dipotong sesuai dengan dalam desain. 1 Kayu diketam terlebih dahulu. 2 Kayu dipotong sesuai dengan dalam desain.

ASUMTION

1 2 1 2

Material cost be calculated on the job site Be calculate per 1 M3 Hitungan bahan ditempat pekerjaan. Dihitung per 1 M3

ANGGAPAN : URAIAN :

LABOUR PEKERJA

TOTAL PERSONEL JUMLAH ORANG 0.200 1.200 12.000 4.000

DAYS HARI

TOTAL MAN/DAYS JUMLAH HARI/ORANG 0.200 1.200 12.000 4.000

Foreman Chief Laborer Skill Laborer Laborer

1.000 1.000 1.000 1.000

BILLING RATE (Rp./Days/Man) UPAH (Rp./Hr/Orang 47,500.00 55,000.00 52,500.00 45,000.00 UNIT (Rp.) HARGA SATUAN (Rp.) 10,000.000 1,300,000.000

COST (Rp.) BIAYA (Rp.) 9,500.00 66,000.00 630,000.00 180,000.00 COST (Rp.) BIAYA (Rp.) 7,500.00 1,300,000.00

SUB TOTAL A (Rp.) SUB JUMLAH A (Rp.)

MATERIAL BAHAN

SUM JUMLAH

UNIT SATUAN

885,500.00 SUB TOTAL B (Rp.) SUB JUMLAH B (Rp.) 1,307,500.00 SUB TOTAL C (Rp.) SUB JUMLAH C (Rp.)

Paku Kayu

0.750 1.000

Kg M3

EQUIPMENT PERALATAN

TOTAL EQUIPMENT JUMLAH ALAT

WORK DAYS HARI KERJA

WORK HOURS JAM KERJA

UNIT PRICE (Rp.) HARGA SATUAN (Rp.) -

COST (Rp.) BIAYA (Rp.)

0.00 JUMLAH (Rp.) VOLUME E 1.000 SATUAN D/E M3 HARGA SATUAN (Rp.) 2,193,000.00 Per M3 2,193,000.00

Hal. 17 WORK COST ESTIMATE ANALIZE ANALISA PERKIRAAN BIAYA PEKERJAAN COATING FOR RAILING PENGECATAN SANDARAN CODE KODE K.813 A

FRENCH RED CROSS


PALANG MERAH PERANCIS

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG, KEMBANG TANJUNG SUB DISTRICT PIDIE DISTRICT NANGGROE ACEH DARUSSALAM PROVINCE REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

EXPLANATION

1 Membersihkan tempat yang akan dicat. 2 Cat dikerjakan dengan kuas. 1 Membersihkan tempat yang akan dicat. 2 Cat dikerjakan dengan kuas.

ASUMTION

1 2 3 1 2 3

Material cost be calculated on the job site 1 Kg anty terminete can be covered 3 m2 area Calculated per 1 m2 Bahan dihitung ditempat pekerjaan 1 Kg dapat menghasilkan 3 M2 Hitungan per 1 M2

URAIAN :

ANGGAPAN :

LABOUR PEKERJA

TOTAL PERSONEL JUMLAH ORANG 1.000 0.200 2.000 4.000

DAYS HARI

TOTAL MAN/DAYS JUMLAH HARI/ORANG 1.000 0.200 2.000 4.000

Foreman Chief Laborer Skill Laborer Laborer

1.000 1.000 1.000 1.000

BILLING RATE (Rp./Days/Man) UPAH (Rp./Hr/Orang 47,500.00 45,000.00 52,500.00 55,000.00 UNIT (Rp.) HARGA SATUAN (Rp.) 10,000.00 1,700,000.00

COST (Rp.) BIAYA (Rp.) 47,500.00 9,000.00 105,000.00 220,000.00 COST (Rp.) BIAYA (Rp.) 65,000.00 1,700,000.00

SUB TOTAL A (Rp.) SUB JUMLAH A (Rp.)

MATERIAL BAHAN

SUM JUMLAH

UNIT SATUAN

381,500.00 SUB TOTAL B (Rp.) SUB JUMLAH B (Rp.)

Nail/Bolt Timber

6.500 1.000

Kg M3

1,765,000.00 EQUIPMENT PERALATAN TOTAL EQUIPMENT JUMLAH ALAT WORK DAYS HARI KERJA WORK HOURS JAM KERJA UNIT PRICE (Rp.) HARGA SATUAN (Rp.) 12,000.000 COST (Rp.) BIAYA (Rp.) SUB TOTAL C (Rp.) SUB JUMLAH C (Rp.)

Suporting Eq.

1.000

Set

12,000.00

12,000.00

JUMLAH (Rp.) VOLUME E 1.000 SATUAN D/E M3 HARGA SATUAN (Rp.) 2,158,500.00

2,158,500.00

Per M3

Hal. 18 WORK COST ESTIMATE ANALIZE ANALISA PERKIRAAN BIAYA PEKERJAAN INSTALL THE TMBER FOR BRIDGE FLOORING MEMASANG LANTAI JEMBATAN CODE KODE K.902

FRENCH RED CROSS


PALANG MERAH PERANCIS

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG, KEMBANG TANJUNG SUB DISTRICT PIDIE DISTRICT NANGGROE ACEH DARUSSALAM PROVINCE REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

EXPLANATION

1 Papan diketam terlebih dahulu. 2 Papan dipotong sesuai lebar jembatan. 3 Papan dibaut pada kayu bantalan lantai 1 Papan diketam terlebih dahulu. 2 Papan dipotong sesuai lebar jembatan. 3 Papan dibaut pada kayu bantalan lantai

ASUMTION

1 2 3 1 2 3

Material cost be calculated on the job site Papan lantai tebal 8 Cm dan lebar 20 - 25 Cm Hitungan per 1 M2 Hitungan bahan ditempat pekerjaan Papan lantai tebal 8 Cm dan lebar 20 - 25 Cm Hitungan per 1 M2

ANGGAPAN :

URAIAN :

LABOUR PEKERJA

TOTAL PERSONEL JUMLAH ORANG 1.000 1.000 2.000 6.000

DAYS HARI

TOTAL MAN/DAYS JUMLAH HARI/ORANG 1.000 1.000 2.000 6.000

Foreman Chief Laborer Skill Laborer Non Skill Laborer

1.000 1.000 1.000 1.000

BILLING RATE (Rp./Days/Man) UPAH (Rp./Hr/Orang 47,500.00 55,000.00 52,500.00 35,000.00 UNIT (Rp.) HARGA SATUAN (Rp.) 10,000.00 1,300,000.00

COST (Rp.) BIAYA (Rp.) 47,500.00 55,000.00 105,000.00 210,000.00 COST (Rp.) BIAYA (Rp.) 65,000.00 1,300,000.00

SUB TOTAL A (Rp.) SUB JUMLAH A (Rp.)

MATERIAL BAHAN

SUM JUMLAH

UNIT SATUAN

417,500.00 SUB TOTAL B (Rp.) SUB JUMLAH B (Rp.)

Nail/Bolt Timber

6.500 1.000

Kg M3

1,365,000.00 EQUIPMENT PERALATAN TOTAL EQUIPMENT JUMLAH ALAT WORK DAYS HARI KERJA WORK HOURS JAM KERJA UNIT PRICE (Rp.) HARGA SATUAN (Rp.) COST (Rp.) BIAYA (Rp.) SUB TOTAL C (Rp.) SUB JUMLAH C (Rp.)

0.00 JUMLAH (Rp.) VOLUME E 1.000 SATUAN D/E M2 HARGA SATUAN (Rp.) 1,782,500.00 Per M2 1,782,500.00

Hal. 19 WORK COST ESTIMATE ANALIZE ANALISA PERKIRAAN BIAYA PEKERJAAN INSTALL THE TIMBER FOR FLOORING COVER LAPIS PENUTUP LANTAI CODE KODE K. 813 B

FRENCH RED CROSS


PALANG MERAH PERANCIS

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG, KEMBANG TANJUNG SUB DISTRICT PIDIE DISTRICT NANGGROE ACEH DARUSSALAM PROVINCE REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

EXPLANATION

1 Membersihkan kayu yang akan diteer. 2 Teer dioleskan dengan kuas. 1 Membersihkan kayu yang akan diteer. 2 Teer dioleskan dengan kuas.

ASUMTION

1 2 3 1 2 3

Material cost be calculated on the job site 1 Kg anty terminete can be covered 3 m2 area Calculated per 1 m2 Bahan dihitung ditempat pekerjaan. 1 Kg teer mengerjakan 3 m2 luasan Hitungan per 1 m2

URAIAN :

ANGGAPAN :

LABOUR PEKERJA

TOTAL PERSONEL JUMLAH ORANG 1.000 6.000 -

DAYS HARI

TOTAL MAN/DAYS JUMLAH HARI/ORANG 1.000 6.000 -

Foreman Laborer Operator

1.000 1.000 -

BILLING RATE (Rp./Days/Man) UPAH (Rp./Hr/Orang 47,500.00 52,500.00 0.00 UNIT (Rp.) HARGA SATUAN (Rp.) 65,000.00 85,000.00 6,500.00 65,000.00 45,000.00

COST (Rp.) BIAYA (Rp.) 47,500.00 315,000.00

SUB TOTAL A (Rp.) SUB JUMLAH A (Rp.)

MATERIAL BAHAN

SUM JUMLAH

UNIT SATUAN

COST (Rp.) BIAYA (Rp.) 4,550.00 2,550.00 26,000.00 1,300.00 22,500.00

362,500.00 SUB TOTAL B (Rp.) SUB JUMLAH B (Rp.)

Stone Crush 5/7 cm Stone Crush 2/3 cm Terminite (Teer) Sand Seng Plat BJLS 20

0.070 0.030 4.000 0.020 0.500

M3 M3 Kg M3 Lbr

56,900.00 EQUIPMENT PERALATAN TOTAL EQUIPMENT JUMLAH ALAT WORK DAYS HARI KERJA WORK HOURS JAM KERJA UNIT PRICE (Rp.) HARGA SATUAN (Rp.) 12,000.000 COST (Rp.) BIAYA (Rp.) SUB TOTAL C (Rp.) SUB JUMLAH C (Rp.)

Supporting Eq.

2.000

Set

24,000.00

24,000.00

JUMLAH (Rp.) VOLUME E 1.000 SATUAN D/E M2 HARGA SATUAN (Rp.) 419,400.00

419,400.00

Per M2

Hal. 20 WORK COST ESTIMATE ANALIZE ANALISA PERKIRAAN BIAYA PEKERJAAN CLEAN OUT AND TERMINITE COATING PEMBERSIHAN DAN PENGETERAN CODE KODE K. 813 B

FRENCH RED CROSS


PALANG MERAH PERANCIS

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG, KEMBANG TANJUNG SUB DISTRICT PIDIE DISTRICT NANGGROE ACEH DARUSSALAM PROVINCE REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

EXPLANATION

URAIAN :

1 Membersihkan kayu yang akan diteer. 2 Anty termite painting be coating by shaving brush 1 Membersihkan kayu yang akan diteer. 2 Teer dioleskan dengan kuas.

ASUMTION

1 2 3 1 2 3

Material cost be calculated on the job site 1 Kg anty terminete can be covered 3 m2 area Calculated per 1 m2 Bahan dihitung ditempat pekerjaan. 1 Kg teer mengerjakan 3 m2 luasan Hitungan per 1 m2

ANGGAPAN :

LABOUR PEKERJA

TOTAL PERSONEL JUMLAH ORANG 0.080 0.540 -

DAYS HARI

TOTAL MAN/DAYS JUMLAH HARI/ORANG 0.080 0.540 -

Foreman Skill Laborer Operator

1.000 1.000 -

BILLING RATE (Rp./Days/Man) UPAH (Rp./Hr/Orang 47,500.00 52,500.00 0.00 UNIT (Rp.) HARGA SATUAN (Rp.) 6,500.00

COST (Rp.) BIAYA (Rp.) 3,800.00 28,350.00

SUB TOTAL A (Rp.) SUB JUMLAH A (Rp.)

MATERIAL BAHAN

SUM JUMLAH

UNIT SATUAN

COST (Rp.) BIAYA (Rp.)

32,150.00 SUB TOTAL B (Rp.) SUB JUMLAH B (Rp.)

Termite

0.400

Kg

2,600.00 2,600.00

EQUIPMENT PERALATAN

TOTAL EQUIPMENT JUMLAH ALAT

WORK DAYS HARI KERJA

WORK HOURS JAM KERJA

UNIT PRICE (Rp.) HARGA SATUAN (Rp.)

COST (Rp.) BIAYA (Rp.)

SUB TOTAL C (Rp.) SUB JUMLAH C (Rp.)

0.00 JUMLAH (Rp.) VOLUME E 1.000 SATUAN D/E M2 HARGA SATUAN (Rp.) 34,750.00 Per M2 34,750.00

You might also like