Professional Documents
Culture Documents
CHAPTER
The rapid development and expansion of public water supply systems at the beginning of the 20th century led to the establishment of public health standards for drinking water systems. An area of major concern for these systems was the storage facilities. Early steel reservoirs and standpipes were of riveted construction. Modern welded-steel reservoirs can be built to very large capacities with either domed or column-supported roofs. In the 1970s, it became common for smaller-capacity reservoirs and standpipes to use bolted construction technology, originally developed for industrial and agricultural uses. Prefabricated panels and bolted connections reduced erection costs and made these structures popular in rural areas. The advent of factory-applied ceramic coatings reduced future maintenance costs, adding to the tanks attractiveness to water supply systems with limited nancial resources. Bolted tanks with diameters greater than 30 ft (9 m) are often built with low-maintenance aluminum geodesic domed roofs, a technology
1
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Chapter One
commonly found on wastewater plant storage tanks as well. Figure 1-1 shows a geodesic dome on a bolted reservoir. The earliest elevated storage tanks were constructed of wood in the manner of water relling stations for steam-powered trains. Some were built on stone or brick columns. Limitations as to size and durability, as well as public health concerns, led to steel becoming the material of choice for elevated tanks. Most steel elevated tanks constructed before 1950 were riveted, their legs consisting of opposed channels connected by latticework bracing. Roofs on most small tanks and many larger ones were the familiar cone or witchs hat design (Fig. 1-2). Some larger elevated tanks had hemispherical or ellipsoidal roof designs. Welded construction became the industry norm by the early 1950s and remains the standard for most elevated tanks. Legged tanks continued to be built in great numbers; however, the lattice legs replaced tubular sections. Many larger-capacity legged tanks were of the radial arm design shown in Fig. 1-3. These have been phased out in favor of the toroelliptical legged tank style. Early prototypes of single-pedestal tanks were developed in the 1940s and became a common alternative to legged tanks by the 1950s. The more efcient shape of these structures provided the advantage of lower maintenance costs. In the 1960s, the uted-column singlepedestal design was introduced, which provided a usable area in the column for pumping equipment, storage, ofces, and other municipal uses. Legged tanks continue to be built primarily in sizes up to 1 million gallons (mil gal) (3.8 million liters [ML]) as a lower-cost alternative to single-pedestal or uted-column tanks. Single-pedestal tanks are widely specied from very small to large capacities. Larger capacities
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Ta n k H i s t o r y, C o n f i g u r a t i o n s , L o c a t i n g , S i z i n g , S e l e c t i n g
FIGURE 1-2 Witchs hat roof design.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Chapter One
(0.75 to 2 mil gal [2.8 to 7.6 ML] or more) are generally single-pedestal or uted-column tanks. Some uted-column tanks have even larger capacities. In the late 1980s, composite-tank technology combined a concrete pedestal with the steel-bowl geometry of the uted-column tank. This addressed one of the concerns of the uted-column designthe large steel surface area and resulting higher repainting costs. Built generally to hold 0.75 to 2 mil gal (2.8 to 7.6 ML) of water, composite tanks are now in use throughout the United States and Canada. Other materials and technologies are available for specialized applications. However, the steel, glass-lined steel, concrete, and composite tanks discussed in this chapter comprise the large majority of tanks currently in use and being specied for new construction.
Reservoirs
A reservoir is a ground-supported, at-bottom cylindrical tank with a shell height less than or equal to its diameter. Reservoirs are one of the most common types of water storage structure. They are used as a part of the distribution system as well as to hold treated water for pumping into the distribution system. Of the three types of steel water tanks, a reservoir, because of its low height, is generally the most economical to fabricate, erect, and maintain. See Figs. 1-4 and 1-5 for a photo and a cross-sectional view of a welded-steel reservoir; see Figs. 1-6 and 1-7 for a photo and a cross-sectional view of a bolted-steel reservoir. Table 1-1 gives typical sizes of welded-steel reservoirs, and Table 1-2 gives capacities of glass-coated, bolted-steel reservoirs and standpipes. Storage reservoirs for potable water are covered by roof structures, which may be either column supported or self-supporting. Standard tank accessories may include shell and roof manholes, screened roof vents, inside or outside ladders, and connections for pipes as required.
Standpipes
Standpipes are ground-supported, at-bottom cylindrical storage tanks that are taller than their diameter. They are usually built where there is little elevated terrain and where extra height is needed to create pressure for water distribution. See Figs. 1-8 and 1-9 for a photo and a cross-sectional view of a welded-steel standpipe and Figs. 1-10 and 1-11 for a photo and a cross-sectional view of a bolted-steel standpipe. Table 1-3 gives capacities and sizes of typical welded-steel standpipes. Standpipe systems are often designed so that the water in the tank, until it reaches a certain low level, maintains the system pressure. When that low level is reached, pumps come on, valving is changed,
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Ta n k H i s t o r y, C o n f i g u r a t i o n s , L o c a t i n g , S i z i n g , S e l e c t i n g
Roof manholes Overflow pipe 12 in. (0.3 m) 34 in. (19 mm) Weir box (optional)
Roof vent
Approved ladder, cage, platform, or safety devices complying with Occupational Safety and Health Act
Splash pad
Column bases
FIGURE 1-5 Cross-sectional view of welded-steel reservoir. (Source: AWWA Manual M42, Steel Water-Storage Tanks)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Chapter One
Overflow pipe
Splash pad
Grade level
FIGURE 1-7 Cross-sectional view of bolted-steel reservoir. (Source: AWWA Manual M42, Steel Water-Storage Tanks)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Range of Sizes Available Diameter (ft [in.]) 19 [3] 21 [0] 23 [6] 23 [6] 27 [0] 26 [0] 30 [3] 28 [6] 33 [0] 33 [0] 38 [3] 37 [0] 42 [9] 40 [6] 46 [9] 46 [6] 54 [0] 46 [6] 52 [0] 60 [6] 51 [0] 57 [0] 57 [0] 64 [0] 66 [0] 74 [0] 80 [6] 90 [6] 93 [0] 104 [6] 114 [0] 127 [6] 131 [6] 147 [6] 147 [0] 165 [0] 180 [0] 201 [6] 233 [0] 208 [0] Height to Diameter Height to TCL (ft [in.]) (m) TCL (m) 24 [0] 5.9 7.3 24 [0] 6.4 7.3 24 [0] 7.2 7.3 32 [0] 7.2 9.8 24 [0] 8.2 7.3 32 [0] 7.9 9.8 24 [0] 9.2 7.3 32 [0] 8.7 9.8 24 [0] 10.0 7.3 32 [0] 10.0 9.8 24 [0] 11.7 7.3 32 [0] 11.3 9.8 24 [0] 13.0 7.3 32 [0] 12.3 9.8 24 [0] 14.3 7.3 32 [0] 14.2 9.8 24 [0] 16.5 7.3 40 [0] 14.2 12.2 32 [0] 15.9 9.8 24 [0] 18.4 7.3 40 [0] 15.6 12.2 32 [0] 17.4 9.8 40 [0] 17.4 12.2 32 [0] 19.5 9.8 40 [0] 20.1 12.2 32 [0] 22.6 9.8 40 [0] 24.5 12.2 32 [0] 27.6 9.8 40 [0] 28.4 12.2 32 [0] 31.9 9.8 40 [0] 34.7 12.2 32 [0] 38.9 9.8 40 [0] 40.1 12.2 32 [0] 44.9 9.8 40 [0] 44.8 12.2 32 [0] 50.3 9.8 40 [0] 54.9 12.2 32 [0] 61.4 9.8 32 [0] 71.0 9.8 40 [0] 63.5 12.2
3,000,000 11,356 4,000,000 15,142 5,000,000 18,927 7,500,000 28,391 10,000,000 37,854
Source: AWWA Manual M42, Steel Water-Storage Tanks. Note: TCL = top capacity level.
7
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
8
Nominal Height (ft) Capacity in Thousands of Gallons
49 70 96 159 238 327 436 628 836 54 78 106 176 263 363 483 696 59 86 117 193 289 398 531 65 93 122 210 320 434 578 70 101 137 227 340 469 75 108 148 244 365 505 80 116 158 261 391 86 123 168 278 416 91 96 101 107 131 139 146 154 179 189 199 210 296 313 330 347 442 112 161 220 364 117 169 230 122 177 241 128 184 251 133 192 261 139 199 272
19
24
28
14 17 20 25 31 36 42 50 62 70 81 90 101 120
16 22 27 32 24 31 39 47 33 43 53 64 54 71 88 105 81 107 132 158 114 149 185 220 151 199 246 294 218 286 355 423 326 326 428 530 421 553 685 816 567 744 921 1,099 691 906 1,122 1,337 874 1,147 1,420 1,247 1,637
To convert feet to meters, multiply by 0.3048. Capacity in thousands of gallons. To convert gallons to cubic meters, multiply by 0.0037854. Source: AWWA Manual M42, Steel Water-Storage Tanks.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
TABLE 1-2
Ta n k H i s t o r y, C o n f i g u r a t i o n s , L o c a t i n g , S i z i n g , S e l e c t i n g
FIGURE 1-8 Welded-steel standpipe with decorative pilasters.
and water is pumped from the lower portion of the standpipe into the system. As with reservoirs, steel standpipes are covered with a roof structure and may be provided with ornamental trim. Standard accessories may include shell and roof manholes, roof vent(s), a xed outside ladder, and connections or pipes as required. Inside ladders are not recommended in locations where freezing weather can be expected.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
10
Chapter One
Roof vent
Capacity level
Painters trolley rail Approved ladder, cage, platform, or safety devices complying with Occupational Safety and Health Act
Tank bottom crowned at center Inlet outlet (optional) Shell manholes (two required) Base elbow or valve pit Splash pad
Concrete foundation
FIGURE 1-9 Cross-sectional view of typical welded-steel standpipe. (Source: AWWA Manual M42, Steel Water-Storage Tanks)
coatings should be applied to all surfaces deemed necessary from a cost/benet standpoint.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Roof access
Top elbow
Overflow pipe
Inletoutlet (optional)
Splash pad
Grade level
FIGURE 1-11 Cross-sectional view of bolted-steel standpipe. (Source: AWWA Manual M42, Steel Water-Storage Tanks)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
12
Chapter One
Capacity (US gal) 50,000 60,000 75,000 100,000 125,000 150,000 200,000 250,000 300,000 400,000 500,000 600,000 750,000 1,000,000 1,500,000 2,000,000 2,500,000 (m3 ) 189 227 284 379 473 568 757 946 1,136 1,514 1,893 2,271 2,839 3,785 5,678 7,571 9,464 Diameter (ft [in.]) 14 [9] 16 [2] 18 [0] 19 [0] 21 [3] 23 [3] 24 [10] 27 [9] 28 [5] 32 [10] 34 [7] 37 [10] 42 [6] 46 [4] 56 [9] 65 [6] 69 [10] 76 [6] 84 [6] 94 [6] Range of Sizes Available Height to Diameter Height to TCL (ft [in.]) (m) TCL (m) 40 [0] 40 [0] 40 [0] 48 [0] 48 [0] 48 [0] 56 [0] 56 [0] 64 [0] 64 [0] 72 [0] 72 [0] 72 [0] 80 [0] 80 [0] 80 [0] 88 [0] 88 [0] 96 [0] 96 [0] 4.5 4.9 5.5 5.8 6.5 7.1 7.6 8.5 8.7 10.0 10.5 11.5 12.9 14.1 17.3 20.0 21.3 23.3 25.8 28.8 12.2 12.2 12.2 14.6 14.6 14.6 17.1 17.1 19.5 19.5 21.9 21.9 21.9 24.4 24.4 24.4 26.8 26.8 29.3 29.3
Source: AWWA Manual M42, Steel Water-Storage Tanks. Note: TCL = top capacity level.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Ta n k H i s t o r y, C o n f i g u r a t i o n s , L o c a t i n g , S i z i n g , S e l e c t i n g
3 16-in. (4.7-mm) lap-welded roof plate Capacity level One or more supporting columns
13
Top angle
Vent
Channel rafters
FIGURE 1-12 Tank with column- and rafter-supported cone roof. (Source: AWWA Manual M42, Steel Water-Storage Tanks)
should be avoided if possible, because they may create corrosion problems. In addition, the trusses should be kept above the water line to prevent damage by ice and accelerated rates of corrosion. A modication of the self-supporting dome is the toriconical roof. This consists of a rolled or pressed knuckle and a higher-pitched selfsupporting center. Aluminum dome roofs are sometimes erected on bolted-steel or welded-steel tanks. These aluminum domes are usually constructed
Knuckle plate
12 in. (0.3 m)
3/16 in. (4.7-mm) lap-welded roof plate Capacity level One or more supporting columns
Radius
FIGURE 1-13 Column- and rafter-supported roof with knuckle. (Source: AWWA Manual M42, Steel Water-Storage Tanks)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
14
Chapter One
3 16-in. (4.7-mm) minimum thickness lap- or butt-welded Cap plate roof plate
Vent
Top angle
Capacity level
us di ra . al ax ric . m in. he D . m Sp 1.2 0 D = .8 0
FIGURE 1-14 Self-supporting dome roof or umbrella roof. (Source: AWWA Manual M42, Steel Water-Storage Tanks)
of triangulated space truss (geodesic) panels. The dead weight of these domes is usually 3 lb/ft2 (143 N/m2 ) or less, compared with 3.8 lb/ft2 (181 N/m2 ) for a bolted-steel roof and 7.6 lb/ft2 (364 N/m2 ) for a welded-steel roof.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Ta n k H i s t o r y, C o n f i g u r a t i o n s , L o c a t i n g , S i z i n g , S e l e c t i n g
14-in. (6.4-mm) minimum thickness and butt welded in area filled with water Area above capacity level may be lap welded Vent
15
Kn u
le ck
Capacity level
FIGURE 1-15 Self-supporting ellipsoidal roof. (Source: AWWA Manual M42, Steel Water-Storage Tanks)
Elevated Tanks
An elevated steel water tank has two primary components: the tank itself and its supporting structure. Such tanks are ordinarily used where there is insufcient elevated terrain to ensure distribution of water at suitable pressure by gravity. These tanks are of welded construction. Elevated tanks can be categorized into several different types. The various diameters and head ranges for the tanks described in the remaining gures and tables in this chapter are only representative and may vary with individual fabricators. Specic diameter/head range combinations should be determined by the tank fabricator within the limits indicated in the tables. Height should be specied by the purchaser as the dimension between the top of the foundation and the top capacity level of the tank. Further dimensions, which are a function of the fabricators standard, should not be specied. To minimize cost, desired operating ranges should be specied to fall within standard available tank dimensions. However, individual operating needs may dictate nonstandard operating ranges.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
16
Chapter One
FIGURE 1-16 Double-ellipsoidal tank. (Photo: Gay Porter DeNileon, AWWA)
top capacity level (TCL) in the roof several feet or meters above the top of the cylindrical shell. Although in the past they were constructed in capacities up to 1 mil gal (3.8 ML), today, double-ellipsoidal tanks are typically constructed only in capacities of 200,000 gal (760,000 L) or less. See Figs. 1-16 and 1-17 for a photo and a cross-sectional view of a small-capacity elevated (double-ellipsoidal) tank. Table 1-4 gives capacities and sizes of typical double-ellipsoidal elevated tanks.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Ta n k H i s t o r y, C o n f i g u r a t i o n s , L o c a t i n g , S i z i n g , S e l e c t i n g
Diameter
17
Head range
Purchaser to specify
As required
FIGURE 1-17 Cross-sectional view of double-ellipsoidal tank. (Source: AWWA Manual M42, Steel Water-Storage Tanks)
Large-capacity elevated tanks (>500,000 gal [>1,893 m3 ]) provide economical service for communities that need to store a substantial volume of water. Lower operating and pumping costs are ensured because of the low head range, which achieves minimum variation of water pressure throughout the system. See Figs. 1-20 and 1-21 for a photo and a cross-sectional view of a large-capacity elevated tank. Table 1-6 gives capacities and sizes of typical large-capacity elevated tanks.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
18
Chapter One
Capacity (US gal) 25,000 30,000 40,000 50,000 60,000 75,000 100,000 125,000 150,000 200,000 (m3 ) 95 114 151 189 227 284 379 473 568 757 Diameter (ft) 1820 1820 2223 2224 2225 2630 2330 3032 3234 3638 Range of Sizes Available Head Range (ft) 12.515.5 15.016.5 15.017.0 18.020.0 19.023.0 16.024.0 20.025.0 23.028.0 24.529.5 28.029.5 Diameter (m) 5.56.1 5.56.1 5.77.0 6.77.3 6.77.6 7.99.1 3.59.1 9.19.7 9.710.4 11.011.6 Head Range (m) 3.34.7 4.65.0 4.65.2 5.56.1 5.37.0 4.97.3 6.17.6 7.08.5 7.59.0 8.59.0
FIGURE 1-18 Medium-capacity welded-steel elevated tank. (Photo: Gay Porter DeNileon, AWWA)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Ta n k H i s t o r y, C o n f i g u r a t i o n s , L o c a t i n g , S i z i n g , S e l e c t i n g
19
Head Range
Purchaser to specify
As required
6 in. min.
FIGURE 1-19 Cross-sectional view of medium-capacity, torus-bottom weldedsteel elevated tank. (Source: AWWA Manual M42, Steel Water-Storage Tanks)
Ladders to the container and roof are inside to protect against unauthorized access. These tanks are usually constructed in capacities of 200,000 gal (760,000 L) or less. See Figs. 1-22 and 1-23 for a photo and a cross-sectional view of a small-capacity single-pedestal tank. Table 1-7 gives capacities and sizes of typical small-capacity single-pedestal tanks. Small-capacity elevated tanks are also constructed as various combinations of cones and cylinders. An alternative design is shown in Fig. 1-24.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
20
Chapter One
Capacity (US gal) 200,000 250,000 (m3 ) 757 946 Diameter (ft) 3638 3840 4345 4650 5056 510 570 5665 6465 Range of Sizes Available Height to TCL (ft [in.]) 28 [30] 28 [33] 28 [31] 30 [36] 29 [38] 40 [0] 32 [0] 34 [45] 45 [46] Diameter (m) 11.011.6 11.612.2 13.113.7 14.015.2 15.217.1 15.6 17.4 Height to TCL (m) 8.59.1 8.510.1 8.59.4 9.111.0 8.811.5 12.2 9.8
300,000 1,136 400,000 1,514 500,000 1,893 600,000 2,271 750,000 2,839 1,000,000 3,785
FIGURE 1-20 Large-capacity elevated tank. (Photo courtesy of Landmark Structures, Inc.)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Ta n k H i s t o r y, C o n f i g u r a t i o n s , L o c a t i n g , S i z i n g , S e l e c t i n g
Diameter
21
Head range
Purchaser to specify
As required
FIGURE 1-21 Cross-sectional view of large-capacity, multicolumn elevated tank. (Source: AWWA Manual M42, Steel Water-Storage Tanks)
Capacity (US gal) 500,000 600,000 750,000 1,000,000 1,500,000 2,000,000 2,500,000 (m3 )
Diameter Head Diameter Head (ft) Range (ft) (m) Range (m) 1,893 6065 2425 18.319.8 7.37.9 2,271 2,839 3,785 5,678 6570 7076 7587 9198 2425 2530 2535 3035 3436 3941 3540 19.821.3 21.323.2 22.925.5 27.729.9 7.37.9 7.69.1 7.610.7 9.110.7
TABLE 1-6 Capacities and Sizes of Typical Large-Capacity Welded-Steel Elevated Tanks
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
22
Chapter One
FIGURE 1-22 Spherical single-pedestal tanks give pleasant silhouette. (Photo: Walter Baas, AWWA)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Head range
Purchaser to specify
As required
FIGURE 1-23 Cross-sectional view of small-capacity spherical single-pedestal tank. (Source: AWWA Manual M42, Steel Water-Storage Tanks)
Capacity (US gal) 25,000 30,000 40,000 50,000 60,000 75,000 100,000 125,000 150,000 200,000 (m3 ) 95 114 151 189 227 284 379 473 568 757 Diameter (ft) 1920 2021 2123 2324 2426 2528 2930 3133 3334 3638
Range of Sizes Available Head Range (ft) 1517 1518 1922 1923 2224 2327 2530 2732 3034 3638 Diameter (m) 5.86.1 6.16.4 6.47.0 7.07.3 7.37.9 7.98.5 8.89.1 9.410.0 10.110.4 11.011.6 Head Range (m) 4.65.2 4.65.5 5.86.7 5.87.0 6.77.3 7.08.2 7.69.1 8.29.7 9.110.4 11.011.6
23
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
24
Chapter One
or a low-cost exterior coating for aesthetic purposes. The steel bowl construction is similar to that found on the uted-column tanks; the bowl can be built with either a cone or a domed roof. The most common designs use a domed concrete oor with a steel liner. Commonly built to store between 750,000 gal and 2 mil gal (2.8 and 7.6 ML), these tanks provide many of the benets of a uted-column tank with signicantly less area that requires painting, thereby reducing maintenance costs. The diameter of the concrete column is generally somewhat smaller (30 to 60 ft [9 to 18 m]) than for a uted-column tank, so the area in the column for other uses is reduced. See Figs. 1-29 and 1-30 for a photo and cross-sectional view of a composite elevated tank.
Ta n k H i s t o r y, C o n f i g u r a t i o n s , L o c a t i n g , S i z i n g , S e l e c t i n g
25
r What are the local utility costs of pumping during daily and
peak demand periods? Proximity to Users r Where is the growth in the community taking place now and projected to be in the future?
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
26
Chapter One
Diameter
As required
FIGURE 1-26 Cross-sectional view of large-capacity single-pedestal elevated tank. (Source: AWWA Manual 42, Steel Water-Storage Tanks)
Capacity (US gal) 200,000 250,000 300,000 400,000 500,000 750,000 1,000,000 1,250,000 1,500,000 2,000,000 (m3 ) 757 946 1,136 1,514 1,893 2,839 3,785 4,732 5,678 7,571 Diameter (ft) 4042 4347 4648 5053 5560 6466 7478 7680 8590 9095
Range of Sizes Available Head Range (ft) 2730 2532 3033 3040 3040 3842 3540 4045 4550 5055 Diameter (m) 12.212.8 13.114.3 14.014.6 15.216.1 16.318.3 19.520.1 22.523.8 22.924.4 25.927.4 27.429.0 Head Range (m) 8.29.1 7.69.7 9.110.1 9.112.2 9.112.2 11.612.3 10.712.2 12.213.7 13.715.2 15.216.3
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Ta n k H i s t o r y, C o n f i g u r a t i o n s , L o c a t i n g , S i z i n g , S e l e c t i n g
27
FIGURE 1-27 Folded-plate design of a modied single-pedestal tank support. (Photo courtesy of Tnemec/STI/SPFA)
Acquiring Land r What is the cost of the tank site being considered? Is the land even available?
electrical power at each site being considered? Zoning r Is a zoning map available, and are the potential sites zoned to allow a tank project? Federal Aviation Administration (FAA) r Would the FAA allow a tank at the required height to be built on the potential site? at the potential site?
Size of Site Is the site large enough for r Erection equipment, steel storage, staging operations, ground assembly, and crane operations with a safe and adequate distance for items that may be dropped from the tank during erection?
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
28
Chapter One
Diameter
Head range
Fluted column
Range of Sizes Available Diameter Head (ft) Range (ft) 4143 2931 4345 2931 4964 3039 6365 3740 7378 3542 7680 4045 8587 3946 97102 3846 107110 4345 109120 4045 Diameter (m) 12.513.1 13.113.7 14.919.5 19.219.8 22.223.8 22.924.4 25.926.5 29.631.1 32.633.5 33.336.6 Head Range (m) 8.89.4 8.89.4 9.111.9 11.312.2 10.712.8 12.213.7 11.914.0 11.614.0 13.113.7 12.213.7
250,000 946 300,000 1,136 500,000 1,893 750,000 2,839 1,000,000 3,785 1,250,000 4,732 1,500,000 5,678 2,000,000 7,571 2,500,000 9,464 3,000,000 11,356
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
As required
Purchaser to specify
Ta n k H i s t o r y, C o n f i g u r a t i o n s , L o c a t i n g , S i z i n g , S e l e c t i n g
29
r Maintenance of the tank and piping after completion? r Abrasive blasting and painting of the tank now and in the
future? Topography Does the site haveor can it be made to havegood drainage to ease construction operations and minimize standing water around the completed tank? Access to Site r Is the site accessible on public roads by concrete and large semitrailer tractor rigs?
Will permission be given to build a road? Who will pay for the road? Will it be a permanent or temporary road? If temporary, will it be necessary to remove it at the end of the project? Soil Conditions r Is the soil bearing strength at the bottom of the tank foundation adequate to support the tank without requiring expensive deep foundations?
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
30
Chapter One
Upper roof cone
Lower cone
Concrete column
r Where is the water table? Will the foundation need to be der Is the earth rm enough to support construction equipment
during normal weather conditions or will gravel, crane mats, and other earth-stabilizing methods be required? Hazards and Construction r Are there power lines or other obstructions above or beside the site or proposed access road that would interfere with the safety of site trafc, construction, painting, or maintenance operations? Will a power line be closer than 40 ft (12.2 m) from the tank? or buried electrical or telephone lines? Were there mines or burial grounds on this site? watered during construction?
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Ta n k H i s t o r y, C o n f i g u r a t i o n s , L o c a t i n g , S i z i n g , S e l e c t i n g r If pile driving is required, will it disturb or cause failure of or r Will pile driving, excavation, steel erection, or abrasive blastr Will the tank be in an area frequented by small children or
vandals and, if so, could this be mitigated by site fencing? Environmental Assessment r Has an environmental assessment been completed on the site? long will approvals take? NIMBY (Not in My Backyard) r Will the tank obstruct the view of historical landmarks or other items of concern to the citizens? proximity? Determining answers to these questions can help you to better analyze and compare costs of alternate sites, so you can select the most desirable location for your new tank. Additionally, you will want to understand and consider the following criteria during your site selection. ing cause noise unacceptable to a neighbor such as a school, hospital, or nursing home? damage to neighboring foundations or other structures?
31
Hydraulics
Other issues that affect site selection include the required pressure at hydrants and residences, the required site elevation, compatibility with the distribution system, the geographic size and location of the demand area, and the tanks proximity to the water supply. Rules of thumb for required water pressure are shown in Table 1-10. Check the local standards or codes for more specic requirements. One hundred sixty-two US and Canadian water utilities responded to an AWWA network modeling survey that requested the actual minimum and maximum distribution system pressures that
Pressure (psi/kPa) 35/241
Comments 20-psi (0.138-kPa) minimum at other re hydrants not directly serving the re Higher pressures may need to use a pressure-reducing valve
5075/ 0.3450.517
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
32
Chapter One
Min. psi 100 4% 10% 80 28% 4049 psi 12% 62% 60 Percent 55% 34% 3039 psi 60 Percent 25% 110129 psi 130149 psi > 60 psi 5059 psi 80 100 Max. psi 14% 10% > 170 psi 150169 psi
40
they provided. Figure 1-31 shows the percentage of utilities in each pressure range. If the pressures provided are more than 75 psi (0.517 kPa), it may be necessary to provide a pressure-reducing valve to prevent home appliances from being overpressurized. The required pressure can be provided through pumping, gravity ow, or a combination of the two. How pressure is provided depends on the sites available and the type of tank to be used.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Ta n k H i s t o r y, C o n f i g u r a t i o n s , L o c a t i n g , S i z i n g , S e l e c t i n g
33
= 115.4 ft [35.1 m] ( 115 ft [ 35 m]) or Height (for 50 psi [345 kPa] minimum) = 50 psi [345 kPa] = 115.4 ft [35.1 m] (62.4 lb/ft3/144 sq in./sq ft)
To this calculated height, add the additional height required to meet the friction loss of the water in the distribution piping. Alternatively, one can use a conversion chart to nd the required height at which to store the water to provide the pressure needed. Figure 1-32 shows how various types of tanks provide this pressure using gravity ow.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
34
Chapter One
Elevated tank
Standpipe
tank is emptied during the day; water demand peaks sometime between 5 p.m. and 9 p.m. Electric utilities charge more for electricity during their peak demand period (see sample rates in Fig. 1-34). By overlaying the sample electric rates on the water usage graph (Fig. 1-35), one can see that the peak demands for electricity and water occur about the same time of day. Using these data, one can make the following calculations:
Peak demand
Emptying tank
Midnight
6:00 A.M.
Noon
6:00 P.M.
Midnight
Time
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Ta n k H i s t o r y, C o n f i g u r a t i o n s , L o c a t i n g , S i z i n g , S e l e c t i n g
$0.14 Average cost per kilowatt-hour $0.12 $0.10 $0.08 $0.06 $0.04 $0.02 $0.00
Midnight 3:00 A.M. 6:00 A.M. 9:00 A.M. Noon 3:00 P.M. 6:00 P.M. 9:00 P.M. Midnight
35
Time
r Nonpeak demand pumping costs: $0.1080/kWh average utilr Tank lling costs: $0.0675/kWh average daily utility cost to
ll the tank by pumping. In this case, utility costs during peak demand are almost 75 percent more than the cost of the average rate used to ll the tank, while even nonpeak costs are about 60 percent more. These calculations should be modied for your system using your local daily water usage and utility rates. Regardless of the local factors, pumping during peak
$0.14 Peak demand Average cost per kilowatt-hour $0.12 $0.10 Constant pumping rate $0.08 Filling tank $0.06 Usage rate $0.04 $0.02 $0.00 Midnight Emptying tank
ity cost to pump the other half of the daily water demand to end users.
6:00 A.M.
Noon Time
6:00 P.M.
Midnight
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
36
Chapter One
electricity rates to meet peak water demand is usually more expensive than gravity ow and can become quite costly over time. Additionally, if you lack sites with hills or higher elevations and choose to pump to meet the pressure and water demand, incorporate the following initial and lifetime costs into your present-value analysis as follows:
r The additional daily costs of pumping over and above gravity r The added cost of a variable-speed pump (usually required; r Cost of a backup pump or pumps r Cost for additional piping and controls for the backup r Cost of backup generator r Expense of enlarging the pump building to house the addir Cost to maintain and replace all of these as needed.
Often, when these additional costs are considered, it is most likely that the extra initial costs to provide gravity ow may actually be a more cost-effective solution over time. tional pumps and piping pump(s) larger than the constant-speed pump used at night for a gravity-ow tank) ow (peak and nonpeak)
Gravity ow One can save these peak-demand electricity costs by peak shaving. To peak shave, start by locating a ground storage tank on the side of a hill, or build an elevated tank or standpipe. A smaller pump can then be used to pump the water up into the tank during the night and early morning at a constant rate when electricity rates are much lower. Then, during the demand period, water can be provided at the needed pressure by using gravity ow. This avoids the much higher electricity rates during this time period and allows use of a smaller, less costly pump. Because of these advantages, gravity ow is the preferred method of providing water pressure. If possible, place the tank on a hill or elevate it to take advantage of this method. The ideal location: For any type of storage tank, the ideal location is on a hill that is in the middle of the demand area and is owned by the community.
Proximity to Users
When choosing a site for a new water-storage tank, the prospective tank owner should consider the growth in residential demand (singlefamily, multifamily, and high-rise structures) and commercial demand (industry, schools, and hospitals). A new residential development on
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Ta n k H i s t o r y, C o n f i g u r a t i o n s , L o c a t i n g , S i z i n g , S e l e c t i n g
the north side of the service area and a new tank on the south side would result in very little water pressure for residents of the new development. The ideal situation is to construct a new water-storage tank in the service area before the area experiences population growth and buildup. This way, you have a better chance to get the right piece of land at the right time and at the right price.
37
Acquiring Land
When acquiring land, the prospective tank owner must consider the availability and suitability of the land for a tank project; the costs for the land, required support utilities, and the length of connections to the existing distribution system; and the surrounding conditions.
NIMBY (not in my back yard!) One of the biggest issues that a water utility can face when attempting to locate a new water-storage tank is the public concern of NIMBY! Despite these concerns, even the most appearance-conscious communities can agree to a mutually benecial solution to this stumbling block. The following are some successful approaches to be used in overcoming public concern:
r Help the public visualize the completed tank: Using an artists con-
Zoning Regulations
Once a site has been located, check on the zoning of the selected site to ensure that it is currently zoned for this use or can be rezoned. Obtaining proper zoning for a water tank is typically more difcult in a residential area than in an industrial area or in an area near public facilities such as schools, government property, and airports. Often, schools are built in the areas of population growth, and the school yard may make a good site for a tank. There are many aesthetically pleasing tank styles that limit access.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
38
Chapter One
FAA Considerations
Forms must be completed and led with the Federal Aviation Administration (FAA) to establish whether a tank can be built on the chosen site at the required height. The FAA is concerned about any obstruction to its airspace 200 ft (61 m) above ground level and any obstruction within an approach pattern to an airport runway. Lengths of approach pattern vary depending on the size of the airport, the length of the runway, and the direction of the runway, as follows:
r Large airport: No obstruction that exceeds a 100:1 surface r Small airport: No obstruction that exceeds a 50:1 surface within
within 20,000 ft (6.1 km) of an airport having at least one runway >3,200 ft (>975 m). 10,000 ft (3 km) of an airport whose longest runway is <3,200 ft (<975 m). 5,000 ft (1.5 km) of a heliport. If the FAA determines that the tank will be in the approach pattern, the tank may have to be equipped with aviation lighting or painted in a special aviation warning paint scheme. The most common of the aviation paint schemes is the red-and-white checked pattern found on tanks near airports. The following circulars, forms, and information regarding obstruction evaluation and airport airspace analysis are available on the FAA Web site (https:/ /oeaaa.faa.gov):
r For information on proposed tank construction projects, consult Proposed Construction or Alteration of Objects that may Affect the Navigable Airspace (Advisory Circular 70/74602K). are provided in Obstruction Marking and Lighting (Advisory Circular 70/7460-1K). 1) should be completed by the tank owner before the site is even purchased and certainly prior to construction. The form can now be completed and submitted online at the FAA Web site. Information required includes latitude, longitude, location marked on a US Geological Survey (USGS) map, elevation of site (mean sea level), and the greatest height of any part on the tank, including handrails or antennas upon completion. Once the FAA has reviewed the information on the form, it will make a determination on the proposed tank and location
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Ta n k H i s t o r y, C o n f i g u r a t i o n s , L o c a t i n g , S i z i n g , S e l e c t i n g
and post it online. The determination may be one of the following: r A tank can be built on this site at the height requested.
39
r A tank cannot be built on the proposed site at all. r A tank can be built on this site but not at the height rer A tank can be built on this site at the height requested, r A tank can be built on this site but not at the height requested and will require an obstruction light and/or obstruction marking. but will require an obstruction light and/or obstruction marking. quested.
Size of Site
Tank constructors recommend that the distance from the edge of the tank to the site boundary be a minimum of 50 to 75 ft (15.24 to 22.86 m). A tank may be constructed on a smaller site, but it will require extra handling and planning to stage materials in a disciplined sequence. Eliminating space constraints enables the tank contractor to build the tank more efciently and can reduce costs up to a point. Take into consideration the space needed for the following:
r Material storage during construction r Erection and painting operations r Support facilities such as pump houses, valve vaults, and r Future maintenance and repainting r Placement of tank at safe distance from private property and
utilities. parking areas
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
40
Chapter One
Topography
The tank site can have a major inuence on the cost of construction and on design details for the foundation. The site should allow good drainage away from the foundation(s), provide a level working surface for construction, and have some type of erosion protection. Standing or ponding water on the site can add dewatering costs to the project and may even require changes to the foundation design, leading to added costs. Consider these added costs when evaluating sites.
Access to Site
Access to the tank site is an important aspect of site selection. Developers and residents often want the tank to be located in the back of the development, away from the streets or even in off-road remote locations. This poses a problem getting the large trucks and equipment required for construction to the tank site. Other things that must be considered when assessing site access are the distance from paved roads, permanent versus temporary roads, accessibility by large trucks, and securing temporary easements for site access during construction, if needed. The best site access is via a permanent road up to the tank. The most economical means of achieving this is to put the tank access road in with the original subdivision roads.
Soil Conditions
A full soil investigation should be conducted before the nal site is chosen and certainly before it is purchased. The soil assessment will determine whether the soil is adequate to support the tank and its contents and what type of foundation must be designed. Some sites may require deep foundations (piles or drilled piers) that could add signicant costs to the design and construction of the tank. The soil investigation will provide needed information about the following issues:
r r r r r r r r
Soil bearing capacity (how much of a load the can soil support) Site classication for seismic design Excessive or uneven settlement Water table elevations Rock elevations if present Site history Substrata conditions Slope stability
The depth at which the required soil bearing is obtained to support the foundation along with the slope stability has implications for the
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Ta n k H i s t o r y, C o n f i g u r a t i o n s , L o c a t i n g , S i z i n g , S e l e c t i n g
size of the site required. For example, with a 1:1 slope stability and a 50-ft (15.24-m)-diameter foundation with the required soil bearing 15 ft (4.57 m) down, the minimum size of the hole for the foundation would be 15 ft + 50 ft + 15 ft = 80 ft (4.57 m + 15.24 m + 4.57 m = 24.38 m). To this, one would have to add room for digging equipment and room to store the excavated material on site. The results of the soils investigation can affect the design and costs of both the foundation and tank to such an extent that one could actually save money on the overall project by paying more for a site with better soil conditions. It is prudent to make the site purchase only after you have received the results of the soil investigation.
41
Obstructions/Hazards
Obstructions that must be avoided include overhead power lines, underground utilities, and existing structures. OSHA (Occupational Safety and Health Administration) and many tank contractors specify safe minimum work distances required from power lines depending on what voltage the lines carry. Construction hazards may include abrasive blasting, painting, pile-driving vibration, noise, and re. Waves and energy produced by AM antennas comprise one of the least understood obstructions. AM antennas are typically the tall, slender, red-and-white antennas that do not have dishes or whip antennas hanging off of them; the entire structure acts as the broadcast antenna. On the electromagnetic spectrum, AM waves are the longest waves generated and can be from 656 to 1,968 ft (200 to 600 m) long. These long waves carry energy. Metal objects used in tanks or tank construction such as rebar, steel plate, and even crane lines can act as receiving antennas that collect and store the AM wave energy. If a grounded worker touches these energized metal objects, the collected energy is released, possibly shocking the worker and making the work site unsafe. Whether the AM antenna has any effect on your tank site depends on how far the antenna is from your tank, what power it is broadcasting at, and whether it is a directional or nondirectional antenna. At the Federal Communications Commission (FCC) Web site (www.fcc.gov/mb/audio/ amq.html), one can insert the latitude and longitude of the centerline of the tank (also used in the FCC submittal) and use the Stations within a Radius input. The Web site will indicate if any AM antennas are present. If so, station details will indicate whether the transmission location is directional or nondirectional. Problems can be present for distances up to 0.6 mile (1 km) for nondirectional and 1.9 miles (3 km) for directional antennas. If you encounter an AM antenna that might be a problem and are seriously considering the site in question, you may want to hire a specialist to further examine the situation.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
42
Chapter One
If the expense and risks of dealing with these obstructions and hazards adds enough costs to your project, you might be better off paying more for a site that is free of such obstructions and hazards.
Environmental Issues
Environmental issues that come into play during tank construction include the protection of vegetation, wildlife, wetlands, and oodplains; historical landmarks and burial sites; and local wind and snow. Most states require that a permit request be submitted to the US Environmental Protection Association (USEPA) before construction to identify any such environmental issues.
Current average daily use This is the amount of water used on average in a 24-hour period. Calculate this by determining the average water usage currently per person and multiply this by the number of people that the new area currently serves.
r Peak demand: Peak demand typically occurs between 5:00 p.m. r Off-peak demand: This comprises the other half of the average
current daily usage. and 9:00 p.m. and is usually half of the current average usage.
Fire ow demand To the current average daily usage add an additional one-half to one-third of the current average daily usage. This gure varies depending on the local codes and standards. One should also check the requirements of the Insurance Service Organization (ISO) (www.iso.com) and other local standards and codes.
r Maintenance and piping breaks: As a contingency measure, conr For future demand, project the future population for the sersider adding 10 percent, plus or minus, to provide extra storage if the service area distribution piping has leaks. vice area and then multiply that by the current average daily water use in gallons (liters) per person. An alternate method
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Ta n k H i s t o r y, C o n f i g u r a t i o n s , L o c a t i n g , S i z i n g , S e l e c t i n g
43
Washin g
Montana
Idaho
Nevad
Ca lifor nia
Utah
Ar ka ns as
Missssippi
Alabama
Arizona
Indiana M ichiga n
Orego
Minnesota
ton
ire ampsh New H nt Vermoia ine an Ma nsylv Pen Massachusetts South ork Dakota New Y Rhode Island Wyoming Connecticut Iowa New Jersey Nebraska o hi io O District of Columbia Oh Illinois Delaware Colorado Maryland Kansas ia in y k g c West Vir Missouri Kentu North Virginia Carolina Tennessee New Oklahoma South Mexico Carolina
North Dakota
i sc
si n on
Texas
Georgia
r id Flo
Hawaii Alaska
U.S.Virgin Islands
Water withdrawals in milion gallons per day 0 to 2,000 2,000 to 5,000 5,000 to 10,000 10,000 to 20,000 20,000 to 52,000
would be to check with the US Geological Survey to learn what the average daily usage is per person by state (Fig. 1-36). Local standards and codes related to tank capacity should be consulted and complied with.
Turnover Tanks sized to meet peak demand must also have adequate turnover when demand for water is not at a peak. Unused water can become stagnant, generating unwanted tastes and odors. In cold climates, lack of turnover can cause tank icing. Water turnover problems can be solved by lling the tank to a lower capacity that matches the reduction in demand or by adding a recirculation system. Additionally, several mixing systems are available that can create a more uniform residual chlorine content, reduce stagnation, and help prevent the generation of unwanted tastes and odors. Volume/standard capacities For elevated tanks, the most economical storage is achieved by selecting a standard capacity and head range on the basis of the recommendations of the tank contractor. Typical capacity ranges of elevated tanks are given in Tables 1-8 and 1-9. The largest-capacity elevated tank built to date is 4 mil gal (15,142 m3 ). It may be possible to build larger capacity tanks, but they would be the rst of their kind. Reservoirs and standpipes are more exible in their height/ diameter limitation. It was once thought that reservoirs could only be constructed in height increments of 8 or 10 ft (2.44 or 3.05 m). Steel
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
a ian uis Lo
44
Chapter One
is now readily available in made-to-order heights (and widths) in addition to these. An economical tank can be built to whatever diameter and height is required (Tables 1-1 and 1-3).
Soil bearing The tank foundation and ultimately the soil must support the weight of both the water and the tank. Each cubic foot of water weighs 62.4 lb/ft3 . The calculation of the weight of a 1-ft2 column of water from the bottom of the tank to its top capacity height can give one an idea of the weight that must be supported. A sample calculation for a 40-ft (12-m) column of water would be 40 ft 62.4 lb/ft3 = 2,496 lb/ft2 or about 2,500 lb/ft2 . So, if a 2,500-lb/ft2 soil bearing is not available at the tank site, various foundation types could be evaluated to support the column height of water needed. Deep foundations or large mats may increase costs to the extent that it may actually be more economical to either change the height of the tank or evaluate other sites with higher soil bearing values. Earthquake Typically, the taller and thinner the tank, the more that earthquake may affect the design. Wind The taller and wider a tank, the more wind may affect the design. Here are some examples of diameters ( D) and heights ( H ) of ground storage tanks with typical design conditions that might make them more economical:
r D < H : For soil bearing values greater than 4,000 psf/ft2 , with
r D > H : For soil bearing values less than 4,000 psf, with high
earthquake factors and winds greater than 90 mph, a tank in which diameter is greater than height may be the most economical shape. In these tanks, there are more costs in the bottom and roof and fewer costs in the shell.
low earthquake factors and typical 90-mph wind design, a tank in which diameter is less than height may be the most economical shape. In these tanks, there are fewer costs in the bottom and roof and more costs in the shell.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Ta n k H i s t o r y, C o n f i g u r a t i o n s , L o c a t i n g , S i z i n g , S e l e c t i n g
It is important that you call your local tank contractor to help determine the most economical diameter and height combination for the design conditions at your site.
45
Aesthetics/Appearance
The aesthetic appeal of a new water-storage tank is often one of the most talked-about elements of tank selection. The public may want a tank that will blend into its surroundings, or be a highly visible landmark for the community, or match the systems existing tanks. The tank owner and security personnel may want to place the tank on a more visible site that can be readily secured and monitored. This decision must be handled on a case-by-case basis.
Ornamental Tanks
Highly stylized ornamental tanks can provide community or company identity and advertisement, be more aesthetically pleasing, or resolve NIMBY issues. Unique, decorative tanks have been constructed in many areas and, although more costly to construct, they are often landmarks in which the community takes pride.
Economics
Although the initial cost of constructing a tank has a signicant economic impact, the tanks operating cost, reliability, and maintenance requirements must also be considered.
Special Needs
Sometimes communities have special needs or desires; for example, a community may want to house the re department in the base of the
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
46
Chapter One
tank. Multiuse tanks can be constructed to match the communitys needs.
Liability
To limit liability, tank owners seek methods to control access. Some styles of tankssuch as single-pedestal spheroid, uted-pedestal, and composite elevated tanksdo not have exterior ladders, thereby efciently limiting access. On legged or ground tanks, ladder guards can be installed that limit access to the ladders.
Life-Cycle Costs
Anticipated need for and scheduling of tank repainting and maintenance are important considerations. The style of tank, its surface area, and the type of surface all directly inuence maintenance costs.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Source: Steel Water Storage Tanks: Design, Construction, Maintenance, and Repair
CHAPTER
Appurtenances, or accessories, for tanks are vital for the function, operation, and maintenance of the tank system. Appurtenances are covered in separate sections of American Water Works Association (AWWA) D100, Standard for Welded Carbon-Steel Tanks for Water Storage; AWWA D103, Standard for Factory-Coated Bolted-Steel Tanks for Water Storage; and AWWA Manual M42 Manual of Water Supply Practices, Steel Water-Storage Tanks; and in regulatory documents such as those issued by the Occupational Safety and Health Administration (OSHA). The majority of the appurtenances and attachments described for steel water-storage tanks are required by law, code, and industry standards to make the tank a safe and functional facility. Other accessories are optional and may be specied by the owner to improve the facilitys function or appearance. Accessory items on the tank structure should generally be located where they are readily accessible from a xed ladder or platform surface. An exception to this is the location of stub overows, which, when used, are purposely located away from ladders to avoid ladder icing. Specic tank accessories required by AWWA standards should be shown but not detailed on the bid drawings unless a specic detail is required, because each manufacturer has proprietary components that fulll the intent of the standards. Such details may cause problems if bidders are required to provide another constructors proprietary
47
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
48
C h a p t e r Tw o
apparatus. Accessory details and orientation should be developed and included in the shop drawing submittals after the contract is awarded. The governing requirement should be that the accessories meet the minimum requirements of the regulations, referenced AWWA standards, and the intent of the specications. If the owner elects to include components and operating systems in excess of those specied by AWWA standards, the engineer should provide specications and details that clearly dene the components required and the scope of related work.
Ground-Supported Tanks
Welded-Tank Shell Manholes
For safety and ease of interior access during construction activities and maintenance inspections, at least two opposing shell manholes are required on welded ground-supported tanks for ventilation during interior coating operations. On tanks more than 100 ft (30.5 m) in diameter, it may be desirable to have three or more shell manholes, keeping the maximum circumferential spacing at 100 ft (30.5 m) or less. AWWA D103 requires only one shell manhole on bolted tanks because a tank panel can be removed to provide additional ventilation, but the specier may elect to provide additional manholes.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
3/8
Typical
FIGURE 2-1 Inward-opening shell manhole detail. (Source: AWWA Manual M42, Steel Water-Storage Tanks)
B. C. d
1/4-in. (6.4-mm) hole on horizontal centerline A
ia
9 in. (229 mm)
Front elevation
Detail A
et er
Side elevation
Bolt holes 1/4 equally spaced to straddle centerline Isometric blowout Section AA
See Detail A
FIGURE 2-2 Outward-opening shell manhole detail. (Source: AWWA Manual M42, Steel Water-Storage Tanks)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
50
C h a p t e r Tw o
Shell
Section AA
3 ft (0.9 m)
Bottom plate
Nearest horizontal weld 15 in. (381 mm) min. 46 each 1-in.(25.4-mm)-diameter bolts, equally spaced (see API 650, Table 3-11)
Reinforcement plate
Note: Refer to API Section 650, Figure 3-8 Flush-Type Cleanout Fittings and Tables 3-11, 3-12, and 3-13
(API) Standard 650 for details and design requirements. Although the ush-type manhole is permitted in the AWWA standards, its use is not recommended in high-seismic regions where the additional stiffness of the reinforcing may cause stress concentrations or buckling in an earthquake.
Reinforcing
The shell plates where the manholes are located shall be reinforced to comply with AWWA D100 Section 3.13.2.5, and all portions of the manholes (including reinforcing of the neck, the bolting, and the cover) shall be designed to withstand the weight and pressure of the tank contents.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
51
Flush Manholes
Flush rectangular manholes (rectangular manholes mounted ush with the bottom of the tank) having a minimum length of 24 in. (610 mm) in the short direction and a maximum length of 48 in. (1,220 mm) in the long direction are also available. Such manholes are useful when a tank interior is being cleaned. Refer to AWWA D100 and API Standard 650 for details and design requirements.
Reinforcing
The shell plates where the manholes are located shall be reinforced to comply with AWWA D103 Section 3.11, and all portions of the manholes (including reinforcing of the neck, the bolting, and the cover) shall be designed to withstand the weight and pressure of the tank contents.
Pipe Connections
The number of tank-bottom or shell-piping connections should be kept to a minimum. The earlier practice was to use a common inlet/outlet drain connection through the tank bottom or on the tank shell (Figs. 2-4 and 2-5). If a bottom connection is used, a removable section of pipe 6 to 8 in. (150 to 200 mm) long may extend above the outlet at oor level to serve as a silt stop. The drainpipe shall be recessed to aid in draining the tank. Recent requirements concerning minimum and maximum detention time during which the water remains in the tank may require separate inlet and outlet connections. Bafes and ow diverters are also used to control detention time.
1/4 (typ.)
FIGURE 2-4 Recessed inletoutlet pipe bottom connection detail. (Source: AWWA Manual M42, Steel Water-Storage Tanks)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
52
C h a p t e r Tw o
Plan
Elevation
FIGURE 2-5 Nonrecessed inletoutlet bottom connection. (Source: AWWA Manual M42, Steel Water-Storage Tanks)
Piping connections through the tank bottom or shell are normally furnished in steel pipe welded or bolted to the shell or bottom. Ductileiron or cast-iron pipe connections must pass through a mechanical jointtype connection that is welded or bolted to the steel tank bottom. Pipe connections shall be of the size specied by the purchaser and are usually attached to the tank bottom. The point of attachment shall be designated by the purchaser. Connections to the tank or piping furnished by the tank constructor shall be made by the purchaser.
Silt Stop
If a removable silt stop is required, it shall be at least 4 in. (102 mm) high, and the tting or piping connection shall be ush with the tank oor when the stop is removed. If a removable silt stop is not required, then the tting or connecting pipe, or both, shall extend above the oor at least 4 in. (102 mm).
Drain Sump
To facilitate a more efcient and expedient removal of residual water remaining on the tank bottom after draining the tank, a new drain
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
53
Shell Connections
Shell connections are permitted as long as the purchaser makes adequate provisions to protect the pipe from freezing or vandalism and provides adequate pipe exibility to account for shell rotation and deections of the shell when the tank is lled and drained. These include sample taps, disinfection ttings, and re-hose ttings for the interior and exterior.
Piping Flexibility
Special piping exibility to accommodate seismic movements and settlement in the piping system shall be provided to protect the connection to the shell. AWWA D100 denes the distance from the shell intersection that through-the-tank-bottom piping connections may be located on unanchored tanks designed for seismic conditions. Bottom connections shall comply with AWWA D100 Section 13.5.1 as a minimum. Underbottom connections are not recommended on tanks in high-seismic zones. Tank sliding or uplift may impose additional stress on the connection and tear the bottom. Sidewall connections, which can readily be inspected after a seismic event, are preferred.
Overows
A properly sized overow is essential to protect the tank structure from excessive water levels caused by rapid variations in distribution system conditions. Exterior overows are recommended. In colder climates, ice buildup on an internal overow may become a problem and eventually break the overow pipe. Overow waters should be directed beyond the exterior perimeter of the tank to prevent damage to the tank grade or foundation during overow. Most state standards recommend that the overow on elevated tanks be extended down the side of the tank to within approximately 12 to 24 in. (305 to 610 mm) above grade. Extending the overow pipe prevents water discharged from the pipe from freezing on the tower structure and damaging it. In addition, most governing agencies require an air gap between the overow tank piping and nal drainage system to protect against backow. Figure 2-6 shows one type of overow-pipe air gap. Most states require a screen or ap/gate arrangement over the end of the pipe connected to the tank and a removable grate on the bottom portion of the pipe. The valve shall be a anged passive check opening with 2 in. (51 mm) of water and shall be able to withstand zero backpressure. As distribution systems and pumping capacities are increased, the vent and overow capacities of existing tanks should be
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
54
C h a p t e r Tw o
FIGURE 2-6 Overow air break with ap valve. (Source: AWWA Manual M42, Steel Water-Storage Tanks)
reevaluated to ensure their adequacy to relieve potential pressure or vacuum conditions in the tank. Overows should be easily accessible for maintenance, repair, and inspection.
Welded-Tank Overow
An overow protects the tank from overpressure, overload, and possible catastrophic failure should the pumps or altitude valve fail to shut off when the tank is lled to capacity. A properly operated tank should not overow during normal operation. An overowing tank is an emergency, and the malfunction causing the overow should be determined and corrected as soon as possible. The tank shall be equipped with an overow of the type and size specied by the purchaser. If a stub overow is specied, it shall project at least 12 in. (305 mm) beyond the tank shell. If an overow to ground is specied, it shall be placed down the side of the tank shell and supported at proper intervals with suitable brackets. The overow discharge shall be located such that it will not be obstructed by snow or ground clutter. The overow to the ground shall discharge over a drainage inlet structure or a splash block. It shall originate at the top in a weir box or other appropriate type of intake. A top stiffener shall not be cut or partially removed. The overow pipe and intake
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
55
Bolted-Tank Overow
The tank shall be equipped with an overow of the type and size specied by the purchaser. If a stub overow is specied, it shall project at least 12 in. (305 mm) beyond the tank shell. If an overow to the ground is specied, it shall be brought down the outside of the tank shell and supported at proper intervals with suitable brackets. The overow to the ground shall discharge over a drainage inlet structure or a splash block. It shall terminate at the top in a weir box or other appropriate intake. A top stiffener shall not be cut or partially removed. The overow pipe and intake shall have a capacity at least equal to the pumping rate as specied by the purchaser, with a water level not more than 6 in. (152 mm) above the weir. The overow pipe shall terminate at the bottom with an elbow. Unless otherwise specied by the purchaser, the overow pipe shall be steel pipe with screwed or welded connections if smaller than 4 in. (102 mm) in diameter, or anged or welded connections if 4 in. (102 mm) in diameter or larger. The external overow pipe shall have a minimum thickness of 3/16 in. (4.76 mm). The purchaser shall specify the maximum ow rate, in gallons or liters per minute, for which the overow shall be designed. Internal overows are not recommended but may be provided if specied by the purchaser. The internal overow pipe shall have a minimum thickness of 0.25 in. (6.35 mm).
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
56
C h a p t e r Tw o
Ladders
Safe access must be provided for authorized personnel who need to reach upper shell areas and the top of the tank facility.
Tank shell
1/4
FIGURE 2-7 Exterior caged ladder details. (Source: AWWA Manual M42, Steel Water-Storage Tanks)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
57
2.5 in. 2.5 in. 3/8 in. (63.5 mm 63.5 mm 0.38 mm) angle, two each Tie into platform Shell
Platform 1.5-in. (38-mm) pipe handrail along outer stair perimeter 30 in. (762 mm) min.
9 in. (228.6 mm) Stair treads 3/16 in. (0.1875 mm) plate, shape as shown 30 in. (762 mm) wide (typ. 53) 0.25 in. 12 in. (6.3 mm 305 mm) FB stairway runner inside and outside Stairway brace
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
58
C h a p t e r Tw o
Interior Ladders
Because of accelerated rates of corrosion and the potential for ice buildup in areas where freezing temperatures occur, ladders inside the tank container are not recommended. Ice buildup on an interior ladder can impose loads on the tank wall plates that are sufcient to pierce or rupture the tank container. Even in temperate climates, corrosion can damage interior ladders, making them unsafe. The use of stainless-steel ladders must include insulation (dielectric connections) separating the stainless steel from the carbon-steel tank, and all stainless-steel components must be coated to prevent corrosion of the carbon-steel tank. Ladders are installed inside dry risers and access tubes. There they are not subjected to corrosive conditions, and the access doors may be locked to deter access. In general, all interior ladders shall meet design criteria noted herein for exterior ladders.
Minimum requirements Minimum requirements for ladders, hatches, and so forth can be found in OSHA 29 Code of Federal Regulations (CFR) Part 1910, Occupational Safety and Health Standards, General Industry Standards.
Welded-Tank Ladders
Exterior tank ladder The contractor shall furnish a tank ladder on the outside of the shell beginning 8 ft (2.4 m), or as specied, above the level of the tank bottom and located to provide access to the roof manway. The minimum clear width of step surface for rungs shall be 16 in. (406 mm), and rungs shall be equally spaced 12 in. (280 mm) on center. The perpendicular distance from the centerline of the rungs to the tank wall shall not be less than 7 in. (178 mm). Rung size shall not be less than 3/4 in. (19 mm) in diameter or equivalent section. The maximum spacing of supports attaching the ladder to the tank shall not exceed 10 ft (3 m). The minimum design live load shall be two loads of 250 lb (113.6 kg) each concentrated between any two consecutive attachments to the tank. Each rung in the ladder shall be designed for a single concentrated load of 250 lb (113.6 kg) minimum. The design loads shall be considered to be concentrated at such a point or points as will cause the maximum stress in the structural ladder member being considered. Side rails may be of any shape having section properties adequate to support the design loads and providing a means of securely fastening each rung to the side rail so as to develop the full strength of the rung and to lock each rung to the side rails. Interior tank ladder Inside tank ladders are not recommended for cold climates where ice may form. If an inside ladder is required, it shall
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
59
Roof ladder For tanks with roofs, unless otherwise specied, the manufacturer shall furnish access to roof hatches and vents. Such access shall be reached from the outside tank ladder. A roof ladder is not required on portions of standpipe or reservoir roofs having a slope less than 2 inches per 12 inches of rise (2/12). A roof ladder shall be provided on roofs having a slope greater than 2/12. For roof slopes from 2/12 to 5/12, there shall be a nonskid walkway and a single handrail. For a roof slope greater than 5/12, a ladder or stairway shall be provided.
Bolted-Tank Ladders
Exterior ladders, cages, and platforms designed to meet OSHA standards are recommended. Either the ladder should terminate at least 8 ft (2.4 m) above grade, or a solid, locking door, provided to discourage unauthorized access to the tank, should be installed on the lower 8 to 20 ft (2.4 to 6.1 m) of the exterior ladder. Certain areas will require a locking door and anti-climb screening at the bottom of the ladder cage to discourage unauthorized access. The exterior ladder, roof hatch opening, and interior ladder (if specied) should be located close together to reduce the movement necessary by a climber on the tank roof.
Exterior tank ladder The constructor shall furnish a tank ladder on the outside of the shell beginning 8 ft (2.4 m), or as specied, above the level of the tank bottom and at a location to be designated by the purchaser, preferably near one of the manholes. The side rails shall not be less than 2 3/8 in. (51 9.5 mm), with a spacing between them not less than 16 in. (406 mm). The nonskid rungs shall not be less than 3/4-in. (19-mm) round or square bars spaced 12 in. (305 mm) apart on centers. Interior tank ladder Inside tank ladders are not recommended for cold climates where ice may form. If an inside ladder is required, the side rails shall not be less than 2 3/8 in. (51 9.5 mm), with a spacing between them of not less than 16 in. (406 mm). Rungs shall not be less than 3/4-in. (19-mm) round or square bars spaced 12 in. (305 mm) apart on centers. Roof ladder For standpipes and reservoirs with roofs, unless otherwise specied, the constructor shall furnish access to roof hatches and vents. Such access shall be reached from the outside tank ladder. Refer to AWWA D103 Section 5.4 for minimum requirements for roof ladders based on the slope of the roof.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
60
C h a p t e r Tw o
Minimum requirements Minimum requirements for ladders, hatches, and so forth can be found in OSHA 29 CFR Part 1910.
Ladder platforms For tanks with a total height in excess of 20 ft (6.1 m) or as required by OSHA, ladders with offset rest platforms (secondary platforms) are required every 20 ft (6.1 m) or as required by OSHA for the ladder assembly. This length may be extended to 30 ft (9.1 m) if an approved safety cage is used. If the ladder extends up the exterior of the tank, the ladder should be equipped with a locked guard to prevent unauthorized access to the tank exterior and roof. Conduits, xtures, pipes, valves, and other items should not interfere with the safety of the ladders or platforms. Roof safety railings In addition to exterior ladder safety devices, the most commonly installed safety items are safety railings at the roof where the exterior ladder terminates (Fig. 2-9). These railings protect personnel on the roof near the roof hatch. New handrailing shall be fabricated and installed to form a totally enclosed work area around the roof hatch. Existing pipe sections may be used, provided they meet current OSHA requirements. A self-closing hinged gate shall be provided at the exterior ladder opening. Handrailing layout shall be veried in the eld before handrails are fabricated. All safety railings installed on the tops of tanks and ladders should comply with minimum OSHA requirements or local building codes. Consult with the applicable agency in charge of tank location to determine the latest safety requirements. Total-perimeter handrails are not recommended in areas of high snow load. Ladder safe-climbing rails or cables In lieu of intermediate platforms, approved safe-climbing rails or cables may be used. Figure 2-10 shows a typical safe-climbing rail. Some tank owners may desire supplementary rest platforms in addition to the safety rail. Climbing rails can be galvanized or stainless steel. Painted carbon-steel rails are not recommended. Safety belts and sleeves should be furnished for the ladder safety devices. Safety sleeves should be checked for proper operation along the full height of the rails or cables. Any coating, deviations, or obstructions that prevent the free operation of the sleeve should be removed. Special dismount sections are available to ensure that the
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
61
Typical handrail post bottom Partial 1.5-in. (38-mm) standard black pipe 1/4 in. (6.3 mm) 1/4 in. (6.3 mm) Gate elevation See Detail A
6-in. (152-mm)-square pad Detail A 42 in. (1.06 m) 4 in. 1/4 in. (102 mm 6.3 mm) plate Rail elevation
FIGURE 2-9 Safety rail enclosure. (Note: For roof slope 2/12 or less, windy or wet conditions may require additional safety lines for areas outside enclosure.)
climber does not fall from the tank when the climber is dismounting onto the roof.
Roof fall prevention cable assemblies To prevent personnel who are working or walking on the tank roof from falling over the edge of the roof, furnish and install stainless-steel cable assemblies as shown in Fig. 2-11. Cable shall be stainless-steel aircraft cable of 7 19 construction. Cable collar around center vent shall be 0.25 in. (6.35 mm) in diameter placed in a plastic sleeve to prevent paint damage and connected
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
62
C h a p t e r Tw o
FIGURE 2-10 Safe-climbing rail for an outside ladder. (Source: AWWA Manual M42, Steel Water-Storage Tanks)
with stainless-steel cable clamps. The cable shall allow a maximum of 2 in. (51 mm) greater diameter than the center vent neck at the roof level. The cable shall rest freely on the roof after installation. The stainless-steel cables that prevent personnel from falling shall be 3/16 in. (4.76 mm) in diameter and shall be fabricated with a swaged loop at the center vent attaching point and a swaged carabiner doublelocking attachment at the hold-down point adjacent to the roof hatch work area. Each personnel cable shall terminate 42 in. (1,067 mm) from the outer perimeter of the roof when attached to center vent cable. A hold-down eye shall be welded at the attachment point described previously. The size of the eye and pad shall be as determined by the civil engineer and the structural engineer.
Roof Openings
At least two roof openings are required for personnel access and ventilation during maintenance and rehabilitation activities on weldedsteel tanks.
Primary Opening
The rst (primary) roof opening should be located near the tank sidewall close to the exterior ladder. The previous minimum size for this
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
63
Center vent
ble ca
Provide three carabiners compatible with the 1/2-in. (12.7-mm) round bar. Pad is for attachment when not in use. Attach carabiners to cable with a swaged loop as per Detail A.
Round bar 1/2 in. 10 in. (12.7 mm 254 mm) with large bend as shown 4 in. (101.6 mm) 1/4 in. (6.3 mm)
6 in. 6 in. 1/4 in. (152 mm 152 mm 6.4 mm) carbon-steel pad for attachment 3 in. (76 mm) Existing wood roof
Cable at center vent Swaging tool used at this point to secure the cable to itself
Safety cable attachment Detail B Install at exit to roof from enclosure area
roof opening was 15 24 in. (380 610 mm), but OSHA now requires a 30-in. (760-mm) square or round opening with a hinged cover and locking hasp to facilitate access to the tank interior. With the advent of diving inspections in tanks, which necessitate the use of a rubber raft for inspecting the underside of the roof, it may be prudent to use larger roof hatch assemblies. These can range in size from 48 to 60 in. (1,220 to 1,524 mm) and can be constructed of aluminum covers. A curb at least 4 in. (100 mm) high and a 2.in. (50-mm) downward cover overlap are mandatory on any roof opening to prevent rain or snowmelt from entering the tank (Fig. 2-12). Bolted and gasketed roof manways without the curb and overlap are allowed on bolted tanks.
Secondary Opening
The second roof opening should be located near the tank center or 180 circumferentially from the primary opening. Its diameter should be at least 20 in. (500 mm). If the center vent is of adequate size, is not obstructed, and has a removable cover, the vent may sufce as the secondary opening. The secondary opening, whether the center vent or a separate opening, should be designed with a removable cover to
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
64
C h a p t e r Tw o
316
316
Cover elevation
Curb elevation
Plan view
FIGURE 2-12 Roof manhole assembly details. (Source: AWWA Manual M42, Steel Water-Storage Tanks)
accommodate a bolted ventilation fan. All removable covers should be secured to the roof of the tank using hinges or chains. An additional safety rail may be required between the secondary roof openings and the edge of the roof. Roof manholes should be equipped with locks to prevent unauthorized entry into the tank. Tanks that have access tubes leading to the roof should have their roof manholes properly latched to prevent them from blowing open in a strong wind, and any access doors to the tank ladders should be locked. Shell manholes should be properly sealed to prevent leakage.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
65
Vents
For closed-top tanks, venting must be provided to safeguard against excess pressure or vacuum buildup during the maximum inow or outow of water. Structural failures of tanks can be caused by inadequate venting. When the vents are being sized, the area to which the overow pipe contributes should not be considered part of the ventilation area. A minimum of one vent is required; this should be located near the center of the roof. For larger-diameter tanks, several vents should be located around the periphery as well as at the center of the tank to facilitate crossow ventilation. The most common forms of tank vents are the mushroom, pan (Fig. 2-13), and 180-degree types. Vents with pressure- and vacuumreleasing pallets are recommended. A clog-resistant vent is shown in Fig. 2-14. All vents should be screened to protect against the entry of birds, animals, and insects. The screening should be stainless steel or some other type of corrosion-resistant material. Some health authorities require that shields be installed to keep dirt and debris from blowing into the tank. In areas of snow buildup, the vents should be protected or elevated to prevent them from being clogged by snow. Special vent designs may be necessary to prevent vents from clogging or freezing over, based on local conditions and operations.
(Outside diameter)
3/16
er ov C
Ve nt
di am .
Tank ro
(Inside diameter) (Outside diameter) (Hole in roof)
of
er et am di
Plan view
Section A-A
FIGURE 2-13 Pan deck vent detail. (Note: diam. = diameter.) (Source: AWWA Manual M42, Steel Water-Storage Tanks)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
66
C h a p t e r Tw o
Air
s pre
su
re
Pres sure
Air vacuum
FIGURE 2-14 Typical clog-resistant vent detail. (Note: Pallets should be removed during coating to prevent clogging of the screens. Periodic inspection and maintenance are required to keep in proper working condition. PTFE = polytetrauoroethylene.) (Source: AWWA Manual M42, Steel Water-Storage Tanks)
Many older riveted tanks do not have vents; instead, they have nial balls that provide limited or no ventilation area. These nial balls should be replaced with vents when maintenance or repair work is done on the tank. As distribution systems and pumping capacities are enlarged, the vent and overow capacities on existing tanks should be reevaluated. Tanks have failed because of pressure or vacuum resulting from inadequately sized or improperly maintained vents and overows. The maximum withdrawal rate is usually assumed to be either the value that occurs when the pipes at grade level break or the maximum rate pumped from low-elevation reservoir tanks.
Gauge Boards
Gauge boards are normally composed of a oat and target board on which water level indication is accomplished by noting the position of a target against a gauge board on the outside of the tank. The target
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
67
Altitude Valves
In many water distribution systems, altitude valves are used to control the water level in tanks for which the high water level is at a lower elevation than the pressure gradient of the system. Even some small one-tank systems have been designed with an altitude valve on the tank inlet/outlet line. Both of these are examples of improper use of altitude valves. Altitude-control systems can be designed and installed with timers that force the altitude valve to open, allowing water to ow into and out of the tank and ensuring more frequent turnover. Altitude valves may malfunction even in good weather. Freezing weather increases the likelihood of malfunction, with frozen pressuresensing lines giving the altitude valve false signals. This usually causes the tank to overow, but it may also cause the valve to remain closed, keeping the water in the tank static. Putting electrical heat tape and insulation on the control piping or heating the altitude valve enclosure minimizes these problems.
Remote Readings
A pressure transducer in the tank can indicate the water level at a remote readout some distance from the tank facility. The pressure transducer must be installed so that it is completely isolated from all inlet and outlet openings. Pressure transducers are sensitive enough to sense pressure changes created by water movement through a line that would cause a false reading. The pressure transducer can also control ow in and out of the tank by actuating pumps or valves.
Pressure Gauges
If freeze protection is provided, economical Bourdon pressure gauges may be connected directly to the tank or riser.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
68
C h a p t e r Tw o
Cold-Weather Operations
Designing Tanks for Cold Weather
Proper design of a tank will prevent most freezing problems and, if freezing does occur, will allow personnel to follow operating procedures to easily deal with it.
Inside appurtenances Tanks located in an area where the lowest oneday mean temperature (LODMT) is 5 F (15 C) or colder should not be equipped with inside ladders or overow pipes. As ice forms and moves up and down, it can exert tons of force on ladders and pipes, tearing them loose from their supports and possibly ripping or punching holes in the container. The resulting leak will occur at a very inopportune time. If an inside overow pipe is broken, the tank will rapidly lose all water down to the break, creating a large icy area on the ground below. If the vent is plugged with ice or snow, the tank roof may collapse when water evacuates the tank rapidly. It is acceptable to equip a tank with inside ladders and overow pipes if the tank is known to have a high turnover of warm water. A ladder and overow can also be installed at the center of the tank and supported by the access tube, as in single-pedestal tanks and extremely large column-type tanks. The use of interior girders, roof bracing, painters rails, or virtually any other protrusion below the high water line or within an area affected by oating or suspended ice is a poor design practice for areas with an LODMT of 20 F (29 C) or colder. Certain local conditions or tank usage patterns may cause equally severe icing problems in warmer areas. External features In addition to standard appurtenances and accessories discussed herein, several design issues for the tank exterior are signicant for cold-weather operation. Roof opening location Risers or inlet pipes should be directly below roof vents or manholes, or an auxiliary opening should be provided. This arrangement will facilitate thawing the tank if required. No pipe
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
69
T-pipe thread
Screwed models have B-pipe threads Padlock (by others) A-pipe thread
J-lift
C-max. opening (normal thread engagement) Flanged models have K-150 LB ASA mounting flange L-holes; M-dia. on S bolt circle
A 1 2 3
B 2 3 4
C 9 8 8
D 2 2 3
E 5 5 6
F 3 4 4
G 4 5 6
H 8 7 7
J 1
K 3 4 6
L 4 8 8
S 6 7 9
T 1 2 3
U 1 3
V 5 4 4
FIGURE 2-15 Double-seating, internal-closing drain valve. (Note: lb = pounds; 1 in. = 25.4 mm; 1 lb = 0.4 kg; ASA = American Standards Association [now ANSI].) (Source: American Water Works Manual M42, Steel Water-Storage Tanks)
opening should have a protective discharge cap that would preclude the dropping of a probe into the inlet pipe to thaw the ice blockage. Any gratings over piping should not be so restrictive as to prevent thawing lines or pipes from being lowered into the pipe. Gratings also conduct heat and promote freezing.
Static water projections Unless it is heated and insulated, piping that extends from the tank or from other piping should not contain static water. Drain valves extending on nipples will easily freeze. Drain valves should be of the double-seating, internal-closing type (Fig. 2-15). Additional outlets Side outlets on the riser pipe for use in pumping in steam or warm water to thaw the riser may be included in the design. These outlets should be plugged at the pipe outer diameter to eliminate an unheated projection. Frostproof vents Vents should be designed to avoid freezing over or to provide for pressure or vacuum relief. Some tank manufacturers have proprietary designs for this purpose. A unique freezing problem may occur when frost freezes solid over the ne screen in the vent and overow. This type of freezing usually occurs on the ne screen designed to keep insects out of the tank. Such freezing prevents the exchange
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
70
C h a p t e r Tw o
of air into the tank, resulting in a vacuum in the tank that can collapse (implode) the tank until there is a structural rupture to break the vacuum. Preliminary research indicates that berglass screen material is resistant to freezing.
Heating Heating a community water supply tank is usually not economically feasible, though industrial sprinkler tanks for re protection have been heated for many years. However, new insurance rate structures and better community water supply systems have allowed many factories either to dismantle the re protection tank or to discontinue heating it. In many cases, the insurance savings no longer offset the heating energy costs. Air bubblers Air-bubbler systems have been used successfully in ground storage tanks and in elevated tanks with large risers. A bubbler system is shown in Fig. 2-16. Research on the use of these systems
Riser Air compressor Aeration line
Aeration line
FIGURE 2-16 Tank riser bubbler system. (Source: AWWA Manual M42, Steel Water-Storage Tanks)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
71
Circulating pumps Circulating pumps that do not heat the water have been successful on tanks with small-diameter (6 to 12 in. [150 to 300 mm]) riser pipes in Iowa, Minnesota, North Dakota, and South Dakota. A circulating system is shown in Fig. 2-17. A relatively small (1.5-hp [1.1-kW]) pump draws water from the base elbow, pulling water down the insulated riser or from the connecting pipe. The pump discharges water into a line 1 in. (25 mm) in diameter that enters the
Bowl of tank
Drip ring
Foundation
FIGURE 2-17 Pumped circulation system for small riser pipes. (Source: AWWA Manual M42, Steel Water-Storage Tanks)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
72
C h a p t e r Tw o
riser at the base of the tank and discharges into the tank container. This creates circulation in the riser.
Insulation In many tank designs, it is a common practice to insulate riser pipes. Many ground storage tanks and a few elevated tanks have also had their exteriors sprayed with urethane foam to insulate them. This yields a rough appearance, however, and there may be problems maintaining adhesion between the foam and the steel. No matter how thick the insulation, the stored water will eventually freeze without heat input.
Elevated Tanks
Steel Riser
In localities where freezing temperatures do not occur, the purchaser may specify a small steel riser. In other locations and unless a small pipe is specied, a steel riser not less than 36 in. (910 mm) in outside diameter (OD) shall be furnished. Where the riser pipe supports a considerable load, the riser diameter and thickness shall preferably be determined by the constructor.
Cold Climates
The minimum riser diameter of 36 in. (910 mm) shall be increased in cold climates unless the riser is heated to prevent freezing. The proper diameter depends on the extent of the tanks use and the temperature of the water supplied. In extremely cold climates, a minimum diameter of 72 in. (1,830 mm) is recommended.
Manhole
Large-diameter risers shall contain a manhole about 3 ft (0.91 m) above the base of the riser. The manhole shall not be less than 12 18 in. (305 457 mm), and the opening shall be reinforced or the riser plate so designed that all stresses are provided for around the opening.
Safety Grill
A safety grill is intended to prevent a person from falling down the riser and shall be exempt from the design loads specied in AWWA D100 Section 3.1.6. When a safety grill is used in the top of the riser during erection, it shall be removed if the tank is located in climates where freezing is likely to occur. When grills are left in place, they
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
73
Expansion Joint
Where the riser is not load bearing, exibility to accommodate differential movements of the tank and riser foundation must be included. This exibility may be provided by an expansion joint or by riser layouts that have sufcient offset to be axially deformed without overstressing the riser, tank, or foundation.
Pipe Connection
The pipe connection shall be of the size specied by the purchaser, and it is usually attached to the riser bottom at a point designated by the purchaser. Connections to the tank or piping furnished by the tank constructor shall be made by the purchaser.
Silt Stop
If a removable silt stop is required, it shall be at least 6 in. (152 mm) high, and the tting or piping connection shall be ush with the riser oor when the stop is removed. If a removable silt stop is not required, the connecting pipe shall extend at least 6 in. (152 mm), and preferably about 2.59 ft (789 mm), above the riser oor.
Inlet Protection
In risers 36 in. (910 mm) in diameter or larger, the inlet pipe shall be protected against the entry of foreign materials dropping from above. This shall be done by terminating the inlet pipe or the top of the siltstop pipe with a tee, with the run of the tee placed horizontally, or by placing over the silt-stop or inlet pipe a circular plate 8 in. (203 mm) larger in diameter than the pipe and located horizontally above the end of the pipe or silt stop at a distance equal to the diameter of the pipe. The circular plate shall be attached to the pipe, silt stop, or riser bottom with a suitable bracket or welded bars. Adequate clearance shall be provided between the ends of the elbow or from the edge of the circular plate to the wall of the riser pipe to permit proper ow of water through the inlet pipe. Pipe connections to the riser shell are permitted, as long as adequate protection against freezing has been provided.
Overow
An overow protects the tank from overpressure, overload, and possible catastrophic failure should the pumps or altitude valve fail to shut off when the tank is lled to capacity. A properly operated tank should not overow during normal operation. An overowing tank
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
74
C h a p t e r Tw o
is an emergency, and the malfunction causing the overow should be determined and corrected as soon as possible. The tank shall be equipped with an overow of the type and size specied by the purchaser. If a stub overow is specied, it shall project at least 12 in. (304 mm) beyond the tank shell. For tanks equipped with balconies, the overow shall be extended to discharge below the balcony. If an overow to ground is specied, it shall be placed down the tank shell and supported at proper intervals with suitable brackets. The overow shall be located such that it will not be obstructed by snow or ground clutter. It shall terminate at the top in a weir box or other appropriate type of intake. The top angle shall not be cut or partially removed. The overow pipe and intake shall have a capacity at least equal to the inlet rate as specied by the purchaser, with a head not more than 6 in. (152 mm) above the lip of the overow and in no case more than 12 in. (304 mm) above the top capacity level, where a side openingtype overow is used. The overow pipe shall terminate at the bottom with an elbow, which shall be directed away from the foundation. Unless otherwise specied by the purchaser, the overow pipe shall be steel pipe, with screwed or welded connections if less than 4 in. (102 mm) in diameter, or with anged or welded connections if 4 in. (102 mm) or larger in diameter. Overows may be either internal or external as specied by the purchaser. Minimum external overow pipe thickness shall be 3/16 in. (4.8 mm). Internal overows are not recommended when tank usage and climatic conditions are such that ice damage may occur to the overow or its attachments. When specifying an internal overow, the purchaser should consider the consequences of an overow failure, which can empty the tank of its contents. Internal overow pipe shall be at least 0.25 in. (6.35 mm) thick. The end of the overow may be covered with a coarse, corrosion-resistant screen equivalent to 3/8 in. (9.5 mm) or larger mesh or with a ap valve, as specied by the purchaser.
Ladders
Tower Ladder
A tower ladder shall be furnished with side rails no less than 2 in. 3/8 in. (51 mm 9.5 mm), with a spacing between side rails of not less than 16 in. (406 mm) and with nonskid rungs not less than 0.75 in. (19 mm) round or square, spaced 12 in. (305 mm) apart on centers. The tower ladder shall extend from a point 8 ft (2.4 m) above the ground up to and connecting with either the horizontal balcony girder or the tank ladder, if no balcony is used. The ladder may be vertical but shall not in any place have a backward slope.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
75
Roof Ladder
Unless otherwise specied, the constructor shall furnish access to roof hatches and vents. Such access shall be reached from the outside tank ladder or riser ladder on pedestal tanks according to the following:
r For slopes 5/12 or greater, a ladder or stairway shall be pror Slopes less than 5/12 and greater than 2/12 shall be provided r Slopes 2/12 or less do not require a handrail or nonskid surface. with a single handrail and nonskid walkway. vided.
Ladder Requirements
Minimum requirements for ladders, hatches, and so forth can be found in OSHA 29 CFR Part 1910. Note: Regardless of the access protection provided to tank roof hatches and vents, weather conditions on tank roofs are extremely variable, and workers and their supervisors are expected to exercise good judgment in matters of safety. Among other things, this may include the use of safety lines when windy, icy, or other hazardous conditions exist.
Roof Openings
Above Top Capacity Level
An opening shall be provided above the top capacity level. It shall have a clear dimension of at least 24 in. (610 mm) in one direction and 15 in. (381 mm) in the other direction and shall be provided with a suitable hinged cover and a hasp to permit locking. The opening shall
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
76
C h a p t e r Tw o
have a curb of at least 4 in. (102 mm) high, and the cover shall have a downward overlap of at least 2 in. (51 mm).
Tank Center
An additional opening with a removable cover having an opening dimension or diameter of at least 20 in. (500 mm) and a neck at least 4 in. (102 mm) high shall be provided at, or near, the center of the tank. This opening may also be used for the attachment of exterior paint rigging. Where conveniently accessible to an outside balcony or platform, a shell manhole may be substituted for the additional opening. If properly designed, the shell manhole may be placed below the top capacity level.
Vent
If the tank roof is of tight construction, a suitable vent shall be furnished above the top capacity level, which shall have a capacity to pass air so that at the maximum ow rate of water either entering or leaving the tank, excessive pressure will not be developed. The overow pipe shall not be considered a tank vent. Warning: An improperly vented tank may cause external pressures to act on the tank that can cause buckling even at a low-pressure differential.
Location
One tank vent shall always be located near the center of the roof, even if more than one tank vent is required. For tanks with centrally located access tubes, a reasonable offset of the vent is permissible. The vent shall be designed and constructed to prevent the entrance of birds or animals.
Screening
When governing health authorities require screening against insects, a pressure-vacuum screened vent or a separate pressure-vacuum relief mechanism shall be provided that will operate if the screens frost over or become clogged with foreign material. The screens or relief mechanism shall not be damaged by the occurrence and shall return automatically to operating position after the blockage is cleared. Note: The purchaser should clean the screens and check the pallets or relief mechanism for operation at least once a year, but preferably each spring and fall.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
77
See
Manifold Inlets Shell Inlets Existing outlet Plan-outlet cross
Note
Outlet cross
Shell
Manifold
Existing inlet
FIGURE 2-18 Mixing system layout. (Notes: [1] Modication to inlet reservoir may be required in order to install mixing system. Detail of existing penetration must be provided. [2] Angle to be 30 degrees for water depth 30 ft [9 m] or below. Angle to be 45 degrees for water depth above 30 ft [9 m].)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
78
C h a p t e r Tw o
connected to a 90-degree elbow. Alternate designs may include separate inlet and outlet manifolds positioned either horizontally or vertically depending on the physical height and diameter of the reservoir. The size of the manifold piping and the placement, number, and size of the inlet and outlet valves can be determined through calculations resulting from hydraulic studies and/or computational uid dynamics (CFD) modeling. The types of materials used to construct the TMS manifolds is largely a function of budget limitations. Materials may include polyvinyl chloride (PVC), high-density polyethylene (HDPE), fusionbonded epoxy, liquid epoxy, or cement-mortar-lined (CML) and epoxy-coated carbon- or ductile-steel pipe and ttings. At the upper end of the scale, 316-grade stainless-steel pipe and fabricated ttings can give a lifetime of maintenance-free service. The choice of materials also depends on whether the TMS is being installed in a new tank (in which case the parts can be placed inside the shell before the roof goes on) or whether the project involves retrotting an existing reservoir with limited access.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
79
Antennas
The AWWA Steel Tank Committee has noted that the wireless communication industry has been installing antennas on ground and elevated tanks at an ever-increasing rate. The major tank contractors have all but forfeited these installations to non-tank constructors. Guidelines were added to the commentary for AWWA D10005 (see Appendix A) to provide the owners and their consultants with additional information when addressing these accessories. The guidelines consider functional, structural, future maintenance, and safety issues having to do with antenna and communication installations.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
80
C h a p t e r Tw o
Precautions shall be taken to prevent water contamination. Access to the tank interior water compartment should not be permitted. The paint system should be checked for hazardous metals. Where hazardous metals are found in the paint system, the environment, potable water, and workers must be protected from contamination. Fall protection should be provided for workers. This may consist of a safety rail around the installation or anchor points on the tank roof where safety lines can be attached. The addition of auxiliary ladders or safety lines for access to new equipment should be considered. Antenna cables should be supported at regular intervals (about 4 ft [1.2 m] on center) in exposed locations. Cables should be attached to ladders, as they present a safety hazard. Cable ladders or other commercially available cable support systems are available and should be installed separately on the tank. Manholes and other access ports should not be obstructed by the cable routing. Where space is limited (e.g., small-diameter 36-in. [915-mm] access tubes in pedestal tanks), cables should be tted to the access tube well to maximize clearance. Cables routed along balconies and platforms should be routed so as not to obstruct access. Consideration should be given to provide auxiliary painters-scaffold supports if the antenna installation renders the existing system unusable. Antenna cables should be raised off the tank surface to permit painting behind them.
Bibliography
Harper, W. B. 1986. Designing a More Corrosion-Free Water Storage Tank. In Proc. 1986 AWWA Annual Conference, Washington, D.C.; Denver, CO.: AWWA. Matchett, B. 2006. Introduction to Improved Water Sampling Stations for Steel Water Storage Tanks. NACE International, Channel Islands Section seminar Build a Tank in a Day, Oxnard, CA. Matchett, B. 2007. Introduction to Improved Tank Mixing Systems for Water Storage Tanks. NACE International, Channel Islands Section seminar Build a Tank in a Day, Oxnard, CA.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Source: Steel Water Storage Tanks: Design, Construction, Maintenance, and Repair
CHAPTER
Controlling Corrosion
Mike Bauer and Joe Davis
Tnemec
Anthony D. Ippoliti
Sherwin Williams
Jeff Rog
Corrpro
81
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
82
Chapter Three
FIGURE 3-1 How electrical potentials of various metals compare.
Active Magnesium alloy Zinc Aluminum alloy Cadmium Mild steel (new) Mild steel (old) Cast iron Stainless steel Copper, brass, bronze Titanium Gold Noble
electricity. The closure path, also called the return current path, is the electrical conductor (usually metal) that connects the anode and the cathode. If any one of these elements is missing, corrosion does not occur. For example, coating stops corrosion from occurring by providing a barrier to the current that ows between the metal and the electrolyte. A dry-cell battery is a corrosion cell. When the batterys anode (zinc) and cathode (carbon) are connected through a closure path (the lightbulb), the potential difference between the zinc and the carbon
Metallic path
Anode Cathode
OH +
Electrolyte
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
Controlling Corrosion
83
Water (electrolyte)
produces a current ow. The current continues to ow until the zinc anode is consumed by the corrosion process. It is important to consider why the current ows in the direction it does. The direction of ow is determined by the metals selected for the dry-cell batterys case and center post. If the center post was magnesium instead of carbon, the current ow would be reversed: The magnesium center post would be the anode (which corrodes), and the zinc base would be the cathode (which does not corrode). The current can also be forced to ow in the opposite direction if the standard carbon/zinc battery is connected to an outside current source instead of the lightbulb. In this situation, the anode and the cathode would also be reversedthat is, the battery case would become the cathode and would be protected from corrosion. In a steel water-storage tank, some portion of the metal will be the anode and some portion will be the cathode (Fig. 3-3). Which area takes on which function depends on impurities in the metal; surface conditions; oxygen concentrations in the water; the presence of any dissimilar metals; stresses caused by manufacturing, heat, or concentrated structural loads; and/or several other factors. At the anode, metal ions leave the surface, enter the water, and combine with oxygen to form rust. Electrons released from the anode travel through the metal to the cathode. At the cathode, an ion exchange occurs, but no metal is lost and no corrosion occurs. The presence of ladders, mixing systems, bafing systems, oats, or other accessories made of stainless steel that are electrically
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
84
Chapter Three
continuous with the carbon-steel tank causes accelerated corrosion in steel exposed at holidays (voids) in the coating. In such cases, the stainless-steel components are the cathodes and the exposed-steel portions of the tank are the anodes. Care must be taken when designing such accessories to eliminate the galvanic or dissimilar metal corrosion between the metals of different electrical potentials. Methods for addressing the corrosion caused by dissimilar metals are cathodic protection, using a homogenous metal (coated carbon steel), using a nonmetallic material such as berglass-reinforced plastic, coating the stainless steel to minimize the cathodic surface areas the carbon steel is reacting with, and/or electrical isolation of the dissimilar metals. A corrosion engineer should review situations in which dissimilar metals are used in steel water tank fabrication to determine the most effective solution(s) for controlling corrosion.
Impressed-Current Systems
In an impressed-current system of cathodic protection, an outside source of electrical power forces current into anodes submerged in the storage tanks water. The current ows from the anodes through the water (electrolyte) and onto the submerged walls of the tank, making the tank itself the cathode of the corrosion cell. An impressed-current cathodic protection system (Fig. 3-4) consists of a manual or automatic alternating current/direct current (AC/DC) converter (i.e., a rectier), feeder wires, and anodes inside the tank. The DC output voltage is typically adjusted and controlled automatically to account for a wide range of variables. To prevent damage to the coating, care must be exercised to ensure that the polarized voltage does not exceed a maximum value as noted in the industry standards; otherwise the coating may be damaged. Because excessive current output may damage the coating, manually controlled rectiers without automatic adjustment and potential limiting capabilities are typically not recommended for coated steel. The precise maximum negative voltage is dependent on the characteristics of the coating and other factors.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
Controlling Corrosion
FIGURE 3-4 Impressed-current system.
85
Galvanic Systems
In a galvanic system (Fig. 3-5), a block of specially selected metal called a sacricial anode is immersed in the electrolyte and electrically connected to the metal of the tank. The metal of the sacricial anode is selected so that it will become the anode of the corrosion cell, with the steel tank being the cathode. Magnesium is the most common anode material employed for corrosion control in potable water. The anodes are typically of an extruded-rod type that are either suspended in the water from the roof of the tank or suspended in the lower portion of the tank supported from the sidewalls or by supports on the tank oor. These anodes are fabricated with a copper lead wire connected to the core of the anode and then attached to the steel tank. When the connection is made and the anodes are submerged in the water, the current ow from anode to cathode (steel tank) begins; thus, the magnesium corrodes and the steel is protected. Galvanic systems have become increasingly popular because no electrical current is required. Output of the sacricial anodes may be monitored by using reference electrodes permanently installed in the tank below the surface of the water. The anode lead wires and reference electrode lead wires may be run into a test station installed at ground level to facilitate routine
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
86
Chapter Three
monitoring. A test station may also be equipped with a rheostat to control the output of the anodes by altering the circuit resistance. In the absence of a test station, routing testing is accomplished with a portable reference cell.
Protective Coatings
Cathodic protection is normally used in conjunction with a wellcoated tank surface. The coating reduces the rate of anode consumption and power use. Coatings typically have microscopic voids that expose the metal to the water and allow metal loss if cathodic protection is also not in place. The ideal corrosion control system combines a good dielectric coating (metallic coatings are not dielectric) and a properly designed, installed, and maintained cathodic protection system.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
Controlling Corrosion
87
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
88
Chapter Three
anode material. The approximate consumption rate is 17 to 20 lb/amp year for magnesium anodes. For platinized niobium, platinized titanium, or mixed-metal oxides on titanium, the approximate consumption rate is 0.00008 to 0.0013 lb/amp year (0.036 to 0.59 g/amp year).
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
Controlling Corrosion
89
A
FIGURE 3-7a Vertical system reservoir tank.
ice damage to the anodes should be considered. These suspension systems can provide year-round protection and may eliminate the need for annual anode replacement due to ice damage.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
90
Chapter Three
B
FIGURE 3-7b Horizontal system reservoir tank.
control corrosion. Personnel responsible for operating and maintaining the cathodic protection system should refer to the designers instructions to fully understand their responsibilities. They should consult with the manufacturer if necessary regarding the equipments operation and make certain that all responsible personnel are familiar with its operation. A successful cathodic protection corrosion control system will continuously operate according to established criteria. Annual inspection of the cathodic protection system by the manufacturer or by a qualied corrosion engineer is recommended. At a minimum, this inspection should include an overall examination of the entire cathodic protection system, replacement of all defective parts, a potential prole survey, a physical check of the anode placement, and a written report. Various annual service plans are available from the cathodic protection companies or other service organizations. Cathodic protection systems should be regularly tested and inspected to ensure that they provide the maximum level of corrosion control to the surfaces of the submerged steel tank.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
Controlling Corrosion
91
Components of Paint
Most paints are made up of three primary componentsthe solvent, which is incorporated into the formula to lower viscosity and allow the painter to get the paint out of its container and onto the substrate; the resin or binder, which binds the material together and, more than any other component, determines the physical properties and performance of the cured lm; and the pigment, which can provide color, hiding, or any number of other desirable properties in the lm (e.g., gloss control, sag resistance, or added lm strength). The combination of the solvent and the resin is called the vehicle (Fig. 3-8). The resin binder and the pigments make up the protective dried lm after the solvent evaporates. Most paints also contain additives, which will also be covered in this section.
Resins (binders)
Pigments
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
92
Chapter Three
Organic Solvents
Most paints contain volatile organic compounds (VOCs). These organic solvents are incorporated into paint formulas to lower viscosity and allow the painter to get the paint out of its container and onto the substrate. Water acts as a solvent for some types of paint, but it is not an organic solvent and therefore is not considered a VOC. Organic paint solvents generally fall into one or more of the following classications: Active solvent: An active solvent is a true solvent for the resin (binder) portion of the formula. It dissolves the resin and keeps it in solution. Diluent: Although not a solvent for the resin portion of a particular paint formula, a diluent can still be used in conjunction with a true (active) solvent, without causing precipitation or incompatibility (kick-out). Latent (auxiliary) solvent: This is not a true solvent, but combined with an active solvent, it increases the strength (solvency power) of the active solvent.
Evaporation rate Some solvents are more volatile than others: The greater the volatility, the faster the evaporation rate. Because of its effect on application properties, it is important to consider the evaporation rate when selecting a solvent or solvent blend for a coating formula. For example, the use of a fast solvent may be appropriate if the coating is typically spray applied, but the result may not be a smooth, continuous lm if the coating is applied by brush or roller. Flash point Flash point is dened as the temperature at which the vapor directly above a liquid will ignite when exposed to a spark or an open ame. The faster the evaporation rate of the solvent, the lower the ash point. The U.S. Department of Transportation denes paints with a ash point below 100 F (38 C) as ammable and paints with a ash point above 100 F (38 C) as combustible. A label picturing a red ame must be afxed to containers holding ammable liquids with a ash point below 100 F (38 C).
Controlling Corrosion
Controlling Corrosion
Aromatic hydrocarbons Aromatic hydrocarbons are also derived from distillation of crude oil, but they are considered stronger solvents for a wider range of generic paints than the aliphatic hydrocarbons. All aromatic hydrocarbons contain a benzene-ring molecular structure. In fact, benzene is a solvent and the base molecule for this family of solvents. Aromatic hydrocarbons are active solvents for generic paints including alkyd, oil-based, chlorinated-rubber, certain epoxies, and a few others. They are also used extensively as diluents. Aromatic hydrocarbons most widely used in paint formulations are toluene, xylene, #100 solvent, and #150 solvent. Ketones This family of organic solvents has very high solvency power for most generic paints. Acetone, often used for cleanup in organic chemistry labs, is the base molecule for this family. Ketones most often used in paint formulas are MEK (methyl ethyl ketone), MIBK (methyl isobutyl ketone), MNPK (methyl normal propyl ketone), and MAK (methyl amyl ketone). Esters Esters, like ketones, have high solvency power for most generic paints and are used most often in lacquers and furniture nishes. They have limited use in industrial coatings because of their high cost and reactivity with certain resins. Ester solvents most often used in paints are ethyl acetate, butyl acetate, isobutyl acetate, and amyl acetate. Alcohols Alcohols are not true (active) solvents for most generic paints. Exceptions are found in vinyl wash primers and ethyl silicate inorganic zincrich primers. Certain water-soluble alcohols are also used as co-solvents in water-based paints and in water-emulsion paints. Alcohol solvents found in paints include ethyl alcohol (drinking alcohol), isopropyl alcohol (rubbing alcohol), butyl alcohol, and amyl alcohol. Glycol ethers and glycol-ether acetates Glycol ethers are unusual in that several are water soluble yet also have high solvency power. Because of their water solubility, they are often used as co-solvents in waterbased paints. Glycol-ether acetates are strong solvents that are often used in urethane paint formulations.
93
Controlling Corrosion
94
Chapter Three
Paint manufacturing would be a fast, simple process if it was not for the need to include one or more pigments in most paint formulas. Considerable energy and time are required to disperse pigments into the liquid components of any paint formula. During initial manufacturing, the pigment suppliers grind pigments to a very small particle size. Regrettably, these small pigment particles agglomerate before they are added to protective coatings. When dispersing pigments during paint manufacture, the intent is to break apart the pigment agglomerates into the individual particles originally produced by the pigment manufacturer. The amount of energy and time required to accomplish this depends on the type of pigment. In general, organic pigment agglomerates are much more difcult to disperse than inorganic. Most inorganic pigments can be dispersed using high-speed dispersion equipment, which is generally the fastest and the most economical method of pigmented paint manufacture. More time and energy are required to disperse most organic pigments; other manufacturing methods such as sand milling or ball milling are required. To understand the important functions of pigment in paint, we need to examine the three major classications of pigments: prime pigments, extender pigments, and corrosion-inhibiting pigments.
Prime pigments Prime pigments provide color and hiding power and can be either organic or inorganic. Red iron oxide, yellow iron oxide, titanium dioxide (TiO2 ), lead molybdate (toxic), and lead chromate (toxic) are examples of inorganic prime pigments. Carbon black, phthalocyanine blue, phthalocyanine green, and quinacridone violet are examples of the more expensive organic prime pigments. Extender pigments Most extender pigments provide little, if any, color and hiding. All extender pigments are inorganic minerals that are mined from the earth. These pigments are used in paint formulas to provide a variety of desirable properties including gloss reduction, primer surface roughness for better topcoat adhesion, higher solids, lm reinforcement, lower moisture vapor transmission (MVT), and thixotropy (sag resistance). Magnesium silicate (talc), barium sulfate (barytes), mica, aluminum silicate (clay), calcium silicate (wollastonite), and silica (sand) are examples of extender pigments used in paint. Corrosion-inhibiting pigments Also known as active pigments, corrosion-inhibiting pigments are typically inorganic and have very low solubility in water. They help control corrosion of steel when used in certain generic primers (primarily alkyd or oil based). Their low reactivity with water produces an alkaline condition and/or passivating ions that interfere with the electrochemical process that causes corrosion of steel. Lead tetroxide (red lead), zinc chromate, zinc phosphate,
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
Controlling Corrosion
calcium borosilicate, zinc molybdate, barium metaborate, and cement are examples of corrosion-inhibiting pigments used in paint. Over the years, red lead and zinc chromate have served as excellent corrosioninhibiting pigments for specic primer formulations, but they have been virtually eliminated because of their toxicity.
95
Resins
With only a few exceptions, resins (binders) are organic polymers. Depending on molecular weight and resin type, these paint constituents can be either liquid or solid before they are added to the batch. The physical properties and performance of a cured paint lm are related more to the types of resins used in the paint than to any of the other ingredients. This is why most paints are classied according to the resins (binders) they contain. Single-component paints can sometimes contain more than one type of resin, but these paints are usually classied by the resin that is present in the formula at the higher percentage, with the other resin identied as a modier. For example, a paint that contains 80 percent alkyd resin solids and 20 percent acrylic resin solids would be classied as an acrylic-modied alkyd. Twocomponent paints are generally classied using both types of resins. For example, a two-component paint that consists of epoxy resin in one component and polyamide resin in the second component would be identied as a polyamide epoxy.
Lacquer cure Lacquer curethe drying of a paint lm by solvent evaporation onlyis the simplest curing mechanism. As raw materials, resins that fall into this category are usually high-molecularweight resins. Since no further polymerization takes place when the dried paint lm is formed, the performance properties are already exhibited by the resin as a raw material. In general, the advantages of paints that exhibit this curing mechanism include fast dry, complete cure at low temperatures, and fast recoat times. With the exception of coal tar pitch solutions, the major disadvantage is low solids (high VOC content), which requires application of multiple coats. In addition, use of these paints is limited because of air pollution regulations. Another disadvantage for all of the generic paints that fall into this category is poor solvent resistance.
Vinyls: Organic solvent-based vinyl paints are made from vinylchloride and vinyl-acetate polymers. They are characterized
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
96
Chapter Three
by excellent acid resistance, good alkali resistance, and low MVT. Historically, they have been used on the interior and exterior of steel potable water tanks and in applications where good chemical resistance is desired. Their use today, however, has become almost nonexistent because of air pollution regulations. Chlorinated rubbers: These resins are formed by a reaction of rubber with chlorine. Like the vinyls, they have good chemical resistance and low MVT. In the past, chlorinated-rubber coatings were used on the interiors of potable water tanks. They also have excellent adhesion to concrete and have been used for swimming pools. Coal tar pitch solution: Coal tar pitch is produced from the destructive distillation of bituminous coal. A protective coating can be made by simply dissolving hot pitch in xylene. The cured lm has low MVT and good chemical resistance. Coal tar pitch solutions can be formulated with a higher solids content (lower VOC) than the other lacquer coatings. These coatings have excellent adhesion to steel and concrete and are typically used for sewage and wastewater immersion service. They are only available in black and have poor resistance to direct sunlight. Nitrocellulose: This resin is produced by treating cellulose with a mixture of nitric and sulfuric acids. Nitrocellulose lacquers are widely used as clear and pigmented furniture nishes. Nitrocellulose is also used as a lm-forming material in exographic and gravure inks. Sunlight resistance is poor, so these coatings are most often used for interior applications.
Oxidation and polymerization Generic paints that exhibit the oxidation and polymerization curing mechanism include oil-based paints, alkyds, and epoxy esters. Following application of the wet paint lm and evaporation of the solvent, oxygen from the surrounding atmosphere facilitates the linking together (polymerization) of the resin molecules. Paints that cure by this process have been available for many years. Oil-based paints At the turn of the 20th century, the choice of generic paints was very limited. Most paints were based on vegetable oils such as linseed oil. These oil-based paints exhibited excellent wetting and adhesion to marginally prepared steel substrates and provided long-term weathering and corrosion resistance when exposed to many atmospheric conditions. The biggest disadvantage was very slow dry time. Alkyds Alkyd technology was developed in the late 1920s. It was discovered through laboratory testing that by combining a trifunctional
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
Controlling Corrosion
alcohol with an acid salt and reacting them at high temperature, an ester-type resin could be formed that had very fast dry time. However, the lm was too brittle to be considered as a paint binder. It was then discovered that by incorporating a vegetable oil such as linseed oil in the same reaction, resins could be produced that dried more quickly than straight linseed oil, yet had good enough lm properties to be considered as paint binders. This development revolutionized the paint industry at that time. Further testing revealed that lm properties and dry times could be adjusted depending on the type and amount of oil included in the reaction. Terminology that came out of this discovery included alkyd, which stands for an alcohol/acid reaction, and short-oil, medium-oil, or long-oil alkyd resins. The shortmediumlong terminology designates the amount of oil the alkyd resin contains. Short-oil alkyds dry more quickly than medium- or long-oil alkyds, but are generally less exible and do not produce paints with as good weatherability and corrosion resistance. In general, paints that exhibit this curing mechanism produce paint lms with a wide variety of properties depending on the type and amount of oil in the resin. Overall, alkyd and oil-based paints are less expensive than other generic types and can provide long-term corrosion protection of steel as long as the exposure environment is not too severe. Chemical resistance and color and gloss retention are considered fair to good, depending on the formulation. Alkyd paint formulations can be modied with other resins, such as acrylics and silicones, to upgrade color- and gloss-retention properties.
97
Epoxy esters Epoxy esters are epoxy resins that have been esteried with fatty acids, resin, and so on. Epoxy-ester paints have better chemical resistance than oil-based or alkyd paints, but they chalk more readily when exposed to direct sunlight. The co-reacting curing mechanism Paints that exhibit the co-reacting (chemical cross-linking) curing mechanism usually have two or more components. Examples are two-component epoxies, two-component aliphatic urethanes, two-component uorourethanes, and two-component polyureas. In this mechanism, a chemical reaction between two differing resin types is involved. In general, paints that cure by this mechanism produce cured lms with high cross-linked density, excellent hardness, abrasion resistance, corrosion resistance, low MVT, and excellent chemical and solvent resistance. One disadvantage is limited pot life. Two-component epoxies One component of two-component epoxy contains an epoxy resin with one or more chemically reactive sites known as epoxide rings. The second component (a curing agent)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
98
Chapter Three
contains an amine or amide-functional resin. When the two paint components are combined in the proper ratio and applied to a substrate, they chemically react with each other to form the cured paint lm. Performance properties vary depending primarily on the type of curing agent used. In general, polyamide-cured epoxies have slightly better adhesion characteristics, better exibility, longer pot life, and less acid resistance than the amine-cured epoxies. It is also more difcult to develop protective coatings with ultra-high solids (90 to 100 percent) using polyamide-cured epoxies than it is for those using amine-cured epoxies. With few exceptions, two-component epoxies chalk readily when exposed to direct sunlight. Two-component epoxies can be modied with coal tar pitch, producing coal tar epoxy coatings. The coal tar pitch is usually added to the polyamide or polyamine curing agent. Properly formulated, these coatings can be applied up to 20 mil (508 m) dry lm thickness (DFT) in a single coat. They typically cost less than unmodied twocomponent epoxies and have low MVT and good chemical resistance. They are most often used for protecting steel and concrete substrates from immersion in sewage and wastewater.
Two-component polyurethanes Urethane coatings are generally divided into aromatic and aliphatic types. They are noted for their overall balance of high-performance properties. These include excellent toughness, chemical and solvent resistance, hardness, and abrasion resistance. One component typically contains a hydroxyl-functional polyol resin that cross-links with a second component containing an isocyanate-functional polyisocyanate resin. Aliphatic polyurethanes usually contain an acrylic or polyester polyol portion. When cross-linked with an aliphatic isocyanate, they exhibit excellent color and gloss retention when exposed to direct sunlight. They are expensive and are most often used as thin-lm topcoats over two-component epoxies. Aromatic polyurethanes generally have better adhesion to steel and are less expensive, but they tend to yellow when exposed to direct sunlight. They are often used as direct-to-steel or direct-to-concrete stand-alone coating systems. Some formulations can be used for immersion service. Two-component uorourethanes Fluoropolymer-based coatings are known for their outstanding color and gloss retention when exposed to direct sunlight. Kynar r -based coatings have been around for many years but require baking at high temperature for proper lm formation. Two-component uorourethane coatings are a relatively new technology. These coatings exhibit the co-reacting curing mechanism at ambient conditions. One component typically contains hydroxyl- and
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
Controlling Corrosion
carboxyl-functional uoroethylene vinyl ether (FEVE) resin. Fluorourethane coatings generally exhibit the same performance properties as two-component aliphatic polyurethanes, but they have much better long-term color- and gloss-retention properties.
99
Two-component polyureas These coatings are usually 100 percent solids, cure extremely quickly (sometimes within seconds of application), and have extremely short pot life. Specialized plural-component spray equipment is required. One component contains either aromatic or aliphatic isocyanate-functional polyisocyanate resin; the other component contains an amine-functional resin that cross-links with the polyisocyanate resin when the two components are mixed together in the proper ratio. Because they are 100 percent solids and exhibit an extremely fast cure response, these coatings can be spray applied in one coat at very high lm thickness. Depending on formulation, a wide range of performance properties can be achieved using this technology. Rigid or elastomeric (greater than 100 percent elongation) formulas are possible. Chemical resistance is generally very good, and some formulations are suitable for immersion service. One hundred percent solids, two-component polyurethane coatings are also available. Although their properties are generally similar to those of the polyureas, they are less exible and have better chemical resistance. Baking enamels These are coatings with two co-reacting resins packaged in the same container. One resin is typically a polyester or acrylic containing one or more hydroxyl groups. The other resin is usually a melamine or urea formaldehyde. Cross-linking of the resin molecules only takes place at high temperatures (generally above 250 F [121 C]). Home appliances such as stoves, refrigerators, washers, and dryers have metal substrates that are protected with baking enamels. Components are painted in the shop and then sent through ovens, where the coating cures (usually in 10 to 15 minutes) at high temperature. Pot life is not a concern, since cure (co-reacting) will not take place at ambient temperatures. Moisture cure Polyurethanes Some aromatic and aliphatic urethane resins are designed to react with atmospheric moisture to form a cured lm. These resins are usually based on toluene diisocyanate (TDI) or dephenylmethane diisocyanate (MDI). In the presence of atmospheric moisture (humidity), the resin molecules react with each other to form cured lms. Single-package aromatic urethane primers, intermediate coats, and topcoats containing aluminum or micaceous iron oxide pigments are available that cure by this mechanism. The aromatic urethane types typically have excellent wetting and adhesion
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
100
Chapter Three
characteristics, even to marginally prepared surfaces, and offer excellent barrier-protection properties. For better color and gloss retention, single-package aliphatic urethane topcoats are also available that cure by this mechanism.
Coalescence Emulsion (latex paints) Water-based paints such as acrylic and polyvinyl acetate (PVA) emulsions exhibit the coalescence curing mechanism. Acrylic emulsion resin (acrylic latex), for example, consists of small droplets of acrylic resin emulsied in water. The applied wet paint lm cures through solvent evaporation (mostly water) and coalescence. As the water evaporates, the emulsied acrylic resin droplets get closer together. When most of the water is evaporated, an organic solvent known as a coalescing agent causes the resin droplets to ow together, forming a smooth, continuous paint lm. Waterbased emulsions are often used as interior (PVA) and exterior (acrylic) house paints. They are also used for other architectural applications. Substrates that are coated with emulsion paints include masonry (concrete, concrete block, plaster, and so on.), wood, and drywall. Specially formulated acrylic emulsion paints are also available for direct-tometal applications. Free-radical polymerization Polyesters and vinyl esters have been used extensively for specialty applications since the 1960s. They are based on unsaturated prepolymer resins that are dissolved in an unsaturated monomer such as styrene. By addition of peroxide catalyst, carbonto-carbon double-bond sites react with each other to form the cured lm. Although the monomer (styrene) is volatile in the liquid state, it acts as a cross-linking agent and is incorporated into the lm. The polyesters form hard, dense, chemical- and water-resistant lms. They are used primarily as laminating resins and gel coats for the manufacture of berglass boats, shower stalls, bathtubs, bowling balls, and so on. The vinyl esters have excellent acid resistance and are used primarily as berglass-reinforced and nonreinforced linings for steel and concrete substrates that come in contact with strong acids. Because of their reactive nature, vinyl esters have poor package stability, resulting in short shelf life, especially at high storage temperatures. Hydrolysis The primary use of ethyl silicates and polysilicates, which are among the few resins that are not based on organic polymers, is in the formulation of inorganic zinc-rich primers. The curing mechanism is similar to the curing mechanism for concrete (cement). An inorganic zinc-rich primer contains considerable metallic zinc dust, typically more than 70 percent by weight in the cured lm. When the liquid paint is applied and the solvent evaporates, moisture from the
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
Controlling Corrosion
surrounding air is absorbed into the lm, setting up the hydrolysis process. In the case of ethyl silicates, complex chemical reactions occur, forming a silicon oxide (SiO) matrix in which a small amount of resin binder holds together a large amount of metallic-zinc pigment. Upon complete hydrolysis (curing), the applied lm is very hard, dense, and resistant to abrasion and solvents. Inorganic zinc-rich primers protect steel from corrosion by galvanic action. The zinc becomes the anode in the corrosion battery and the steel becomes the cathode. The zinc sacrices itself to protect the steel in a process that is similar to that exhibited by galvanized-steel substrates. Inorganic zinc-rich primers are resistant to high temperatures (up to 750 F [399 C]), are difcult to topcoat, and have poor acid resistance.
101
Additives In addition to the primary paint ingredients (resin, pigment, and solvent), most paint formulations contain one or more additives. Although they comprise a minor portion of the liquid paint (usually less than 2 percent by weight), additives play an essential role. Most are rheology agents that positively affect the properties of the paint in the can and during application. Following are a few of the additives used to enhance paint properties.
Antisettling agents: There is probably more of this additive used each year than any other paint additive. Since pigment is the heaviest paint ingredient, gravity causes it to settle to the bottom of the container. Antisettling agents do not actually prevent pigment from settling, but they keep it from hard packing in the bottom of the container. This makes it much easier to stir the pigment into a homogeneous mixture with the other ingredients. The most widely used antisettling agent is hydrogenated castor oil (trade name: MPA). Thixotropic agents: These additives are used to incorporate the property known as false body or high viscosity at rest. This property is essential to paints that are to be applied without runs or sags to vertical surfaces at high dry lm thickness. Defoamers: Defoamers are essential additives for water-based paints and certain solvent-based paints to prevent bubbles during manufacture and/or in the applied lm. They are normally silicone based and change the surface tension of water and organic solvents. Driers: For driers, metallic soaps are added to oil-based or alkyd paints to accelerate the oxidation and polymerization process. Mildewcides: Paint lms that contain natural (nonsynthetic) ingredients promote mildew growth when they are exposed to warm, damp conditions. Mildewcides are used as additives in these types of paints to prevent mildew growth. Most alkyd and latex paints contain mildewcides.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
102
Chapter Three
Anti-skinning agents: These are antioxidants used in oil-based or alkyd paints to prevent skinning (drying at the surface) in the can. Pigment wetting agents: These additives are usually silicone based and are incorporated into paint formulas to assist the resin in surrounding and wetting out each of the dispersed pigment particles.
Coating Calculations
The spreading rate (coverage) of any gallon of paint depends on its nonvolatile (solids) content. One gallon occupies a volume of 231 in.3 (0.0038 m3 ) or 0.1337 ft3 (0.0038 m3 ). If a gallon or liter of paint contained no volatile (solvent) and it could be applied without any losses, the spreading rate obtained applied at 1.0 mil (25.4 m) would be 1,604 ft2 (149 m2 ). This gure is expressed as the theoretical spreading rate per gallon or liter. If a gallon or liter of paint contains volatile and its percentage of total volume solids is known, its spreading rate, wet-to-dry lm ratio, and cost per applied mil per square foot (per applied micron per square meter) can be calculated as follows: Theoretical spread rate @ 1.0 mil DFT = Percent of volume solids 1,604 ft2 Spread rate @ DFTs other than 1.0 mil = Percent of volume solids 1,604 ft2 /specied DFT Wet lm thickness = DFT/percent volume solids Cost per mil per sq ft = Cost per gallon/spread rate @ 1.0 mil DFT
Example
Let us assume we have one gallon of paint that is 50 percent volume solids. The specied DFT is 5 mil and the cost per gallon is $22. With this information, we can make the following calculations: Theoretical spread rate @ 1.0 mil DFT = 0.50 1,604 ft2 = 802 ft2 /gal Spread rate at specied 5.0 mil DFT = 0.50 1,604 ft2 /5 = 160 ft2 /gal Wet lm thickness = 5.0/0.50 = 10 mil Cost per mil per sq ft = $22/gal/802 = 2.74 cents/ft2
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
Controlling Corrosion
coatings are a cost-effective way to protect both exterior and interior tank surfaces. A coating applied to the interior wet surfaces of a tank is also called a lining. Both exterior and interior coating systems must be carefully selected to provide the best protection value for the money based on coating life, effectiveness of protection, ease of application, and ease of adding coats in future years. Many protective coating systems have become much more complex than the single-component materials that were prevalent before 1970. D102 is the AWWA standard for painting the interior and exterior of steel water tanks. The objective of this standard is to provide information about various coating systems for coating and recoating the interior and exterior of steel tanks used for potable water storage. Coating systems for new bolted-steel tanks are not covered by this standard. AWWA D102 is not a specication. AWWA standards describe minimum requirements and do not contain all of the engineering and administration information normally contained in specications. Specifying engineers often reference specic interior and exterior coating systems contained in D102 when writing detailed specications for a steel water tank painting project.
103
r Advances in coatings technology r State and federal regulations limiting the amount of organic
solvent contained in protective coatings (VOC regulations); these regulations essentially eliminated the use of chlorinated rubber and vinyl coating systems lead and zinc chromate
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
104
Chapter Three
Outside Coating Systems
Standard
Inside Coating Systems Red lead/aluminum phenolic Vinyl Zinc/phenolic High-solids vinyl Cold-applied wax Hot-applied wax Metallic zinc Hot coal tar enamel Cold-applied coal tar Cold taste-and-odor tar Two-component epoxy Vinyl Chlorinated rubber High-solids vinyl Hot-applied coat tar Cold-applied coal tar Metallic sprayed zinc Two-component epoxy (two coats) Two-component epoxy (three coats) Zinc-rich primer/epoxy/epoxy Vinyl Hot-applied coal tar Cold-applied coal tar Two-component epoxy (two coats) Two-component epoxy (three coats) Inorganic zinc/epoxy/epoxy 100 percent solids polyurethane Organic zinc/epoxy/epoxy
AWWA Alkyd D10264 Vinyl Red lead/linseed oil, alkyd Metallic aluminum
AWWA Alkyd D10278 Vinyl Alkyd/silicone alkyd Alkyd (two primer coats) Chlorinated rubber/alkyd
ANSI/AWWA Alkyd D10297 Alkyd (two primer coats) Alkyd/silicone alkyd Vinyl Epoxy/epoxy/aliphatic urethane Zinc-rich primer/epoxy/ aliphatic urethane ANSI/AWWA Alkyd D10203 Moisture-cured polyurethane Water-based acrylic emulsion Zinc-rich primer/epoxy/ uorourethane Epoxy/epoxy/aliphatic polyurethane Zinc-rich primer/epoxy/ aliphatic urethane
Sources: AWWA standards D10264, D10278, ANSI/AWWA D10297, ANSI/ AWWA D10203. Note: ANSI = American National Standards Institute.
TABLE 3-1 Changes in Inside and Outside Coating Systems Specied in Various Editions of AWWA D102
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
Controlling Corrosion
Inside and outside coating systems contained in future editions of D102 will be further restricted by the continued implementation of more stringent VOC regulations for both shop- and eld-applied protective coatings. Future editions of D102 will most likely only contain inside and outside coating systems that are very high solids based or water based.
105
Surface Preparation
Before a protective coating system can be applied to a steel or concrete water storage tank, appropriate surface preparation must be undertaken. The purpose of surface preparation is twofold: to clean the substrate of contaminants and to roughen or prole smooth surfaces to ensure mechanical adhesion of the rst (primer) coat. Welds may be ground, corners and edges may be smoothed, and voids may be lled so that the applied coating system does not fail prematurely. The Society for Protective Coatings (SSPC), established in 1950 and headquartered in Pittsburgh, Pennsylvania, assesses and advances surface preparation and its understanding by conducting research and developing standards, specications, and guides covering techniques and materials of surface preparation. NACE International is a professional technical society that provides education and communicates information to protect people, assets, and the environment from the effects of corrosion. It, too, develops surface preparation and other standards, provides education and certication, and publishes numerous books and journals. Founded in 1943, NACE is the largest organization in the world committed to the study of corrosion, with a membership consisting of 15,000 engineers, scientists, and researchers in 91 countries. Together, these two organizations have issued joint standards that are commonly referenced by those who need to specify proven surface preparation methods. For example, AWWA D10203 Standard for Coating Steel Water-Storage Tanks cites four SSPC/NACE surface preparation standards (SP10/NACE 2 Near White Blast Cleaning, SP6/NACE 3 Commercial Blast Cleaning, SP7/NACE 4 BrushOff Blast Cleaning, and SP11 Power Tool Cleaning to White Metal). Surface preparation methods vary and may not be appropriate for all materials of construction. Methods may use abrasive blast cleaning (SP10/NACE 2, SP6/NACE 3, and SP7/NACE 4, for example), hand or power tools (SP2, SP3, SP11, and SP15, for example), or water under pressure (SP12/NACE 5, for example). The surface preparation standards listed previously are primarily used for steel surfaces. Methods such as SP13/NACE 6 Surface Preparation of Concrete exist for cementitious substrates. In addition, SP13/NACE 6 further identies surface preparation practices
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
106
Chapter Three
developed by ASTM International, formerly the American Society for Testing and Materials. Organized in 1898, ASTM International is one of the largest voluntary standards development organizations in the world. ASTM International is a not-for-prot organization that provides a forum for the development and publication of voluntary consensus standards for materials, products, systems, and services. Surface preparation is so important to the successful completion of a water tank project that members of AWWA, ASTM, and other organizations donate time to review and update industry standards and methods and to develop new standards and methods as to surface preparation equipment improves and changes.
Surface PreparationSteel
For welded-steel water-storage tanks, surface preparation completed in a fabrication shop before the rst (primer) coats are applied is understandably faster and easier than surface preparation that must be carried out after erection. Shop conditions are controlled, in that operations can be continued regardless of outside weather. Lighting and access to all areas of the structure being fabricated are generally superior to eld lighting and access (Fig. 3-9). After cleaning, steel plate surfaces are abrasive blasted to remove mill scale and/or create a surface prole to which the applied coating will adhere. Abrasive blasting
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
Controlling Corrosion
107
operations may be performed within an enclosed chamber or booth or by an operator using an open nozzle. Speed and efciency are two of the advantages of centrifugal blasting machines; open-nozzle blasting (Fig. 3-10) may allow an operator more time to prepare difcult-toaccess areas. AWWA D10203 Section 1.2, Surface Preparation, paragraph 4.5.2.1 states for outside surfaces of new tanks:
Exterior surfaces shall be cleaned in accordance with SSPC SP6/NACE 3. If specied, tanks located in coastal areas or industrial environments shall be blast cleaned to SSPC SP10/NACE 2. Blast cleaned surfaces shall have a surface prole that is appropriate for the specic primer and coating system as recommended by the manufacturer of the coating.
For outside surfaces of existing tanks, AWWA D10203 Section 1.2, paragraph 4.5.2.2, states:
When the. . . coating system will adhere to the existing coating, all corrosion products and deteriorated coatings shall be removed by spot cleaning to SSPC SP11 or SSPC SP6/NACE 3 and the remainder of the exterior surfaces shall be cleaned by SSPC SP7/NACE 4 or by washing with an alkaline cleaner. . . to remove all dirt, dust, coating/paint chalk, and foreign
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
108
Chapter Three
matter. When the new coating system is not compatible with the existing coating, all existing coatings shall be removed and the surfaces blast cleaned to SSPC SP6/NACE 3 or, if specied, to SSPC SP10/NACE 2.
For interior surfaces of new tanks, AWWA D10203 Section 1.2, paragraph 4.5.3.1, states:
The interior surfaces of new tanks shall be cleaned in accordance with SSPC SP10/NACE 2, excluding interior surfaces of dry risers and dry pedestals. Interior surfaces of dry risers and dry pedestals shall be cleaned in accordance with SSPC-SP6/NACE 3. Blast-cleaned surfaces shall have a surface prole that is appropriate for the specic primer and coating system as recommended by the manufacturer of the coating.
Steel plate for bolted tanks may be prepared by rst cleaning and rinsing in a hot alkaline solution followed immediately by hotair drying. This process removes not only dirt but also hydrocarbon contaminants that will prevent future coating adhesion. Thereafter, these plates are sent through a centrifugal blast machine where an approximately 2-mil-deep (51-m-deep) prole is made on the surface in accordance with SSPC SP10 Near White Blast Cleaning procedures. AWWA D103 Standard for Factory-Coated Bolted Steel Tanks for Water Storage recommends that tank components to be protected with glass coatings receive either Near White Blast Cleaning (SSPC SP10) or, as an alternative, Pickling (SSPC SP8).
Surface PreparationConcrete
Surface preparation for concrete water-storage tanks is different from surface preparation for steel. Most surfaces of concrete tanks are already rough due to the way these vessels are constructed, so there is little need to add a prole. This coarse surface characteristic allows for good adhesion of paints and coatings. That does not mean, however,
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
Controlling Corrosion
that water tanks constructed of concrete are without their own surface preparation requirements. What needs to be accomplished is the removal of areas of poorly adhered concreteake-shaped fragments that detach from the surface of concrete in a process known as spalling. Laitance, a poorly adhered layer of concrete, may also be found on concrete surfaces and must be removed. Although less severe and less damaging than spalling, laitance comprises cement and tiny particles called nes that may be caused by improper vibration of concrete within forms. Left unrepaired, spalling may continue and expose reinforcing bars to corrosion, causing damage to the water tank that is difcult to repair. One way to remove spalling and laitance is by mechanical means, in accordance with ASTM D4259. Roughening of concrete surfaces may be desired on cast-in-place concrete surfaces, such as composite tank columns. These smooth, ascast surfaces may not be of uniform appearance, so abrasive blasting again in accordance with ASTM D4259helps to regulate the appearance of the completed pedestal tower. Bugholes, small irregular cavities uncovered by surface preparation procedures, should be lled with an appropriate material so they will not trap airborne contaminants and mold spores. Occasionally, bolted tanks without bottoms are constructed and placed on concrete slabs. These concrete slabs act as the oor and must be constructed of materials that will not leach out into the potable water supply and thereby contaminate it. NSF International, founded in 1944 as the National Sanitation Foundation, created ANSI/NSF Standard 61, a certication protocol that addresses these concerns. Regarding bottomless tanks resting on a concrete base, NSF may recommend that these concrete surfaces be constructed of ANSI/NSF 61-certied cements and admixtures, for example, or coated with an ANSI/NSF 61-certied coating before being placed in service. These concrete oor surfaces would also require surface preparation prior to the application of ANSI/NSF 61-approved paints and coatings. Once again, preparation routines in accordance with ASTM D4259 may be used. Even though most concrete tank surfaces may need little to no roughening, they do require cleaning. The SSPC SP12 standard for low-pressure water cleaning, WJ4, will accomplish this. This procedure usually removes loose shotcrete clusters and may remove debris left behind by, or concrete escaping through, placement forms. Placement forms are coated with release agents or compounds to prevent adhesion of concrete to these forms and thereby allow placement forms to be removed cleanly. These compounds may act as contaminants, however, and prevent adhesion of paints and coatings. WJ4 may be specied for this purpose. If nonwater soluble or nonwater dispersible form-release compounds are used, low-pressure water
109
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
110
Chapter Three
cleaning will not remove them, and abrasive blast cleaning through the use of ASTM D4259 may be required. Concrete surfaces, because they are porous, also absorb moisture. Whether because of rain or the use of water when cleaning equipment for surface preparation, these surfaces must be allowed to dry before coating. The length of, and need for, time to dry are inuenced both by the temperature and humidity at the tank site and by the type of coating to be applied to the tank.
Coating Selection
To the residents of the community or neighborhood closest to a waterstorage tank, how the tank looksits exterior color and designmay be the most important characteristic. The city name or the name and mascot of the local high school may be emblazoned on the elevated steel tank for all to see. In contrast, residents living near ground concrete storage tanks may not want them visible at all, desiring them to blend into the background landscape. Enhancements are made to both steel and concrete tanks to increase their visual impact. Such enhancements may be from fabrications such as pilasters or simply from the allure of carefully chosen and illustrated paints and coatings. Understandably, residents want the exterior surfaces of water storage tanks to remain colorfast and appealing. But the interior surfaces, which few see, are in fact more important, because it is there where bacteria can grow and corrosion can occur undetected. Coating systems for both interior and exterior surfaces can be selected based on information provided by tank fabricators, by coating manufacturers and their representatives, by the owners or speciers preference, or by reviewing applicable AWWA standards.
Controlling Corrosion
Controlling Corrosion
ICS Number 1 2 3 4 5 Description Two-coat, two-component epoxy Three-coat, two-component epoxy Three-coat, zinc/epoxy/epoxy, interior nonimmersed surfaces above TCL One-coat polyurethane or polyureas Three-coat zinc/epoxy/epoxy, interior surfaces above and below TCL
111
Controlling Corrosion
112
Chapter Three
OCS Number 1 2 3 4 5 6 Description Three-coat (optional four-coat) alkyd Three-coat moisture-cured urethane Three-coat water-based acrylic Three-coat zinc primer/urethane/uorourethane Three-coat epoxy primer/epoxy/urethane Three-coat zinc primer/epoxy/urethane
For exterior surfaces of tanks, ANSI/AWWA D10203 lists six outside coating systems (Table 3-3). According to the standard, [p]roprietary formulations will be acceptable provided the coating is of the same generic type and that the performance of the formulation offered meets or exceeds the performance of the formulation dened in the referenced coating standard and also is suitable for the specied service conditions.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Generic Type Alkyds Adhesion Good Very good Very good to excellent Very good to excellent Excellent Excellent Very good Excellent Excellent Excellent Excellent Very good Good to very good Very good N/A Very good Very good to excellent Excellent Excellent
Acrylics
Very good
Urethanes
Excellent
Fluorourethanes
Outstanding
Polyureas
Epoxies
Controlling Corrosion
Zinc-rich primers
Glass coatings
Excellent
Some generic classications are not used as topcoats. Some generic classications do not include primers. Each generic classication is rated for its adhesion to primer or existing coating. Some generic classications should not be used as topcoats. Polyureas, epoxies, and zinc-rich primers are interior coatings or are topcoated. They do not have color and gloss exterior expectations.
TABLE 3-4
113
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
114
Chapter Three
Many considerations need to be taken into account when selecting the proper interior and exterior protective systems, including governmental regulations, various environmental considerations, the effectiveness of the protection, the ease (or difculty) of application, and the anticipated service life of both the coating and the structure. For instance, an interior lining must be able to withstand constant immersion in water, varying water temperatures, alternate cycles of wet and dry periods, ice abrasion, high humidity and heat, and varying levels of chlorine and mineral contact. The lining materials must not pose a health risk to the general public and must be approved for such use by the appropriate state or federal regulatory agency. Alternately, an exterior coating system should take into consideration the type of atmosphere to which it will be subjected, the expected ambient temperatures, the areas surrounding the tank, and the desired overall appearance and aesthetic value of the coating. In some cases, the entire coating system may be applied in a shop environment; in other cases, the coating system may be applied entirely in the eld. Quite often, though, it is in a combination of these two settings. Each method will be examined individually.
Shop Application
The two major advantages in applying a protective coating in a shop environment are control and accessibility. Often the interior and exterior sections receive just a primer coating in anticipation of eld application of the subsequent coatings specied. This is done to allow fabricators to quickly clean, prepare, and prime the surface in accordance with specications while still allowing them the ability to continue working the plate and shipping it without compromising the surface preparation. When this approach is taken, an area is generally left uncoated around the perimeter of each plate, commonly referred to as the margin. The margin area can vary by specication but is usually between 4 and 6 in. (102 and 152 mm) wide. This allows for eld welding to be performed during the erection in the eld. Of course, these areas will not meet the surface cleanliness requirements of the specication, and they will need to be addressed in the eld prior to the continued application of the coating system. This will be covered in more detail in the following section on eld painting. In some instances, the entire protective coating system is applied in the shopfor example, with bolted tanks. The steel panels are generally coated following roll forming and bolt-hole punching. In this situation, a thermoset liquid coating may be applied and then baked at a prescribed temperature, or a thermoset powder coating may be applied and then baked according to the manufacturers instructions. Depending on the type of interior lining system, the bake temperatures can vary between 425 F (218 C) and (in the case of a glass lining)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
Controlling Corrosion
1,600 F (870 C). Factory-applied lining systems are discussed in more detail in AWWA D103. The factory-applied liquid baked-on exterior coating systems generally combine epoxy primer with an acrylic enamel topcoat or an acrylic polyurethane topcoat. The basic premise of a shop application of the protective coating system, whether it be the primer or the entire system, is that since application is all performed on the ground and under controlled shop conditions, the result will be (and most often is) a very uniformly applied and fully cured protective coating system. However, the coating system is often damaged during loading, transporting, unloading, and erection of the plates. Depending on the extent of the damage, major eld work may be needed for repair. Anticipating this situation, a combination of shop priming and eld painting is often employed.
115
Field Painting
Although coating and/or lining systems applied in the eld share many of the considerations we reviewed under shop-applied coatings, other factors specic to eld painting need to be evaluated. Among these items are the type of lining that is environmentally compliant, tank heating and ventilating, dehumidication requirements, the landscape surrounding the tank, and the type of environment that the tank is subject to during the preparation, application, and cure of the lining and coating systems (e.g., chloride sources in a marine environment). Generally speaking, the interior of the tank requires the highest degree of surface cleanliness and preparation. Many of the protective lining systems require a minimum surface cleanliness equaling an SSPC SP-10/NACE 2 Near White Metal Blast. In an effort to achieve this, painting contractors typically blast the bottom of the tank rst and then begin to blast the wall section by section. Each section (called a drop) is blasted and coated during the work shift unless an environmental control such as dehumidication is needed. The abrasive used in the cleaning process is allowed to fall to the oor of the tank and accumulate there. This abrasive provides an insulation of sorts from the environment so that the initial blast on the oor is held or maintained. If the blast is lost, the contractor reblasts the oor area and coats it as he is nishing the interior of the tank. Special care needs to be taken to ensure that spent blast media is not billowed and deposited into the freshly coated surface. Although this is a common approach to lining the inside of storage tanks, it is not the only correct way to perform this task. When a primer has been applied in the shop and the contractor is only applying nish coats to the tank in the eld, the surface preparation specication is usually a bit different than that just described. Two concerns must be addressed: (1) the condition of the shop primer
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
116
Chapter Three
and its preparation before receiving any topcoats and (2) the weld seam preparation. Typically, the shop primer is swept blast according to SSPC SP7/NACE 4 Brush-Off Blast Cleaning, while the weld seams are prepared according to SP10/NACE 2 Near White Metal Blast. In some cases the primer is reapplied, while in others only the nish coat(s) are applied. Proper ventilation of the tanks interior is critical to ensure a thoroughly cured lining. When coating the outside of the tank, the consequences of overspray, dry spray, and ambient conditions must be considered. Adverse conditions during surface preparation, coating application, and curing can (and most often do) lead to premature catastrophic failure of the coating system. Speciers and contractors should also be aware of the areas surrounding the tank and the environment to which the coating system will be subjected. For example, an elevated water tank in a congested urban area may require coating materials that can only be roller applied or that tend to dryfall if applied by a sprayer. By way of environmental considerations, coastal regions may require a coating system that has a higher lm build and more barrier protection to protect the tank from a chloride-rich environment. Depending on the tank and the contractor, the coating process is completed in different ways, but completing drops is still the most common way to ensure that a properly cleaned surface is maintained. Typically, the specied cleanliness for the exterior of the tank would be an SSPC SP6/NACE 3 Commercial Blast. For a shop-applied primer, the primer is swept blast according to SP7/NACE 4, while the weld seams require SP6/NACE 3. Again, a primer may be reapplied if specied or the nish coats may be applied over the prepared existing primer.
Brushes
Brushes are not as high tech as sprayers, and many consider them an outdated way to apply paint. However, many situations still require their use. A stripe coat, often specied for added protection of edges,
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
Controlling Corrosion
rivets, corners, bolts, and welds, is best applied by a brush, because it improves the wetting capabilities of the coating by forcing the coating into areas that would be problematic if sprayed or roller applied. A worker applying a coating by brush should hold the brush at an angle of approximately 45 degrees and, using the wrist and arm, spread the coating evenly and quickly onto the substrate. Once the coating is evenly spread, it should be smoothed by light brush strokes to eliminate any irregularities. When the next brushload of coating is applied, the nal smoothing strokes should extend from the newly applied coating into the previous brush-applied adjacent area. This spreads the coating over the overlap between the two areas and provides a smooth, uniform coating over the whole surface while maintaining the wet edge (the end of the stroke of the previous applied coating). As the next brushload of coating is applied, the painter should sweep the coating from the substrate back into the wet edge of the previous application to help prevent lap marks. It is also important to brush out over an edge, not against it. Brushing against an edge creates an action that pulls the coating away, causing a thin area on the edge.
117
Rollers
Rollers have earned a bit more respect than brushes, but their production results still pale in comparison with results of spray application. Application by roller is faster than application by brush, but is not quite as fast as application by spraying. Because the roller cover holds considerably more coating than a brush, a much larger area can be covered with one load. Rollers are excellent for large, at areasfor example, the tops or sidewalls of tanks. Rollers can be used wherever the skill of a brush or spray application is not called for. Rollers can also be used if spray applications are prohibited due to overspray concerns. The procedure for using the roller is to immerse it in the coating tray or bucket and roll it back and forth on either a tray ramp or bucket grid on the inside of the bucket. This removes the excess coating from the roller and prevents excessive drip and spatter. Continue spreading the liquid coating onto the surface in the form of a W or an M over an area that one rollers worth of coating will cover. After initially spreading the coating by this method, ll in the area by rolling the roller back and forth over the entire surface being covered. Finish by rolling the coating in one direction. This is called laying off, and it aids in developing a uniform nished appearance. Spraying and backrolling is another example where the roller is used to ensure a uniform application and nish.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
118
Chapter Three
Fluid pressure regulator Regulated air Regulator and moisture separator
Fluid
FIGURE 3-11 Components needed to apply paint by air spray. (Courtesy of Spray-Quip, Inc., Houston, TX.)
atomize the paint as it exits the spray gun. In other words, air is injected into a stream of paint through the air nozzle in front of the gun, creating the mist that is propelled out. The basic components needed to apply paint by air spray are an air compressor, paint pot or cup, oil and moisture separators, air supply hoses, material hose, regulators, and air spray paint gun (Fig. 3-11). The most important element in air spray painting, as in other application methods, is the person operating the gun. Conventional air spray equipment affords the applicator a great level of control and results in a high-quality nish. The applicator is responsible for applying the paint correctly, using the best technique, and keeping the equipment in good working order. Generally, coating manufacturers list the optimum pressures for applying their coatings. They also list the type of gun and the correct sizes of paint nozzle, air cap, and needle to produce the best-quality applied lm. Typically, externalmix air caps are used. The space between the uid nozzle and the air nozzle is called the annular ring. It provides a column of air around the uid stream. As the uid and air leave the air cap, they begin to expand and mix. As this mixed stream leaves the center of the nozzle, it is further atomized with additional force from the holes on the horns of the external-mix air cap. The biggest advantage of a conventional air spray system is the control the applicator has over the nish; relatively easy adjustments to the uid pressure and air pressure give the applicator tremendous exibility and versatility. The biggest drawback is probably low transfer efciency; conventional air spray equipment has a transfer efciency of approximately 25 to 30 percent.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
Controlling Corrosion
119
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
120
Chapter Three
FIGURE 3-13 Standard setup of an air-assisted airless spray system. (Source: Graco)
reaches the airless tip, it is atomized and shaped by the specic size of the tip. The only adjustment to an airless spray gun is to change the tip. Coating manufacturers specify the correct tip size and proper atomizing pressures needed to produce the best-quality applied lm. Although the airless spray applicator does not have the control that a conventional spray system affords, the trade-off is that greater speed and greater transfer efciency value (35 to 50 percent) are possible. Some have found a way to combine the best features of conventional air spray with airless spray equipment and have created a new spray nishing capability. The process has been termed as air-assisted airless spray. This equipment (Fig. 3-13) uses a standard airless pump and an airless spray tip to atomize the coating and shape it into a fan pattern. However, in contrast to normal airless operations, the uid pressure in an air-assisted airless spray system is relatively low. As expected, a low uid pressure (usually below 1,000 psi [6,894 kPa])
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
Controlling Corrosion
fails to produce an acceptable spray pattern, and the resulting pattern has heavy edges called tails. To eliminate the tails and assist in the atomization process, air is added at a low volume, typically 1 to 3 cfm (0.47 to 1.41 L/s), and at a low pressure between 10 and 20 psi (69 and 138 kPa). To this coating stream, assisting air is directed into the airless pattern through horns on a special air cap. This results in a good appearance, very good transfer efciency (50 to 65 percent), reduced overspray, less tip wear, and longer pump life due to the lower pressures. Because of new VOC regulations as well as owners seeking solvent-free coating solutions in order to reduce or eliminate extractables, manufacturers have begun formulating coatings with much higher percentages of solids. Fabrication shops and eld painters have had to comply with tougher emission laws and have begun looking for equipment that provides higher transfer efciency and higher solids protective coating material application capability. These concerns have led to the development and rening of equipment known as electrostatic and plural-component spray equipment. The main advantages of electrostatic spraying are the savings in materials and labor and the high transfer efciencies of material to the surface. In electrostatic spraying, a high-voltage electrical charge is imparted to the atomized paint particles via an electrode on the gun, causing the paint particles to be attracted to the substrate, which is grounded. This virtually eliminates all overspray. Paint particles that would normally be lost because of overspray are instead attracted to the edges and even the back of the substrate. Transfer efciencies obtained with electrostatic spray painting range between 65 and 98 percent. The equipment typically used for electrostatic spraying is the same as that used with conventional air spray equipment and with airless equipment. However, airless and/or conventional electrostatic systems have electric power supplies to give the paint the negative charge needed to draw it to all sides of the substrate being painted. An electrode at the tip of the gun adds a high-voltage electrostatic charge to the atomized paint particles (Fig. 3-14). This technology lends itself to the application of both liquid-applied coatings and powder coatings. In plural-component spray painting, two-component (or more) catalyzed coatings are proportioned, mixed, and applied by the spray equipment. This method is generally for use with coatings that have a very short pot life (from a few seconds to a few minutes) and a very high solids content (typically 100 percent). The base resin and converter are mixed at the spray gun, or at a mixing manifold preceding the spray gun. The two components are then immediately sprayed onto the substrate being coated. There are two basic types of plural-component systems: xed ratio and variable ratio. A xed-ratio
121
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
122
Chapter Three
FIGURE 3-14 Standard setup of an electrostatic spray system. (Source: ITW Ransburg)
system provides only one ratio of volume for the multiple components of the coating. A variable-ratio system can be adjusted for different component ratios (e.g., 1:1, 2:1, 3:1). The equipment consists of two or three airless pumps (feed pumps) attached to an air motor. The pumps move the coating components individually from their containers in separate lines to a proportioning pump. The materials are then normally heated and directed either to the spray gun tip or to a mixing manifold assembly tted with one or more in-line static mixers. From the manifold, the mixed material travels through a whip hose to the spray gun. Heaters play an important role with plural-component systems. They are used to reduce the coating viscosity, improve uid ow, and optimize the reactivity of the materials. Heaters are often installed in-line and are placed on the material containers. The material hoses are often heat traced and insulated, as well help maintain the desired temperature. Plural-component systems also use a solvent-fed purge pump that connects the container of solvent with the back of the mixing manifold. When an applicator shuts down the equipment, the valve for the purge pump is opened, and a solvent ush is delivered to ush out any material that could set up in the mixing manifold (Fig. 3-15). The mixing manifold, when required, is critical for properly blending and mixing the materials before they leave the spray gun. The manifold usually contains a static in-line mixer that works by splitting the coating stream and rotating it to 90 degrees. This is done numerous times so that the components are mixed thoroughly when they exit the spray gun.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
Controlling Corrosion
123
Mixer/manifold
Spray gun
Proportioning pump
FIGURE 3-15 Standard setup of a plural-component spray system. (Source: JPCL, October 1989)
Inspection of Linings
Independent Inspectors Duties
Coating contracts usually involve a signicant investment of both time and money. The owner has a well-written job specication completed and conducts some type of bid process to select the coating contractor. The inspector provides the owner with written assurance that the project has met the specications and that the coating system will perform for its intended full life. The coating inspector is also viewed as providing additional assurance that the risk of catastrophic failure is signicantly decreased or altogether eliminated. The inspector most often becomes the eyes through which the owner observes the nished work and determines whether the contract has been fully satised. Many tests can be performed after the coating has been applied. It is often difcult to nd deciencies in the coating system, however. Once the job is nished, a poor job may look the same as a high-quality job. Therefore, it is important that inspections occur not only at the conclusion of a project, but also during coating operations. This will help determine that the coating specication was met.
During Application
During the application, the inspector may need to conduct a wide array of key tests and observations:
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
124
Chapter Three r Ensure that the proper environmental conditions exist. With
the emergence of new coating technologies, the temperatures and relative humidity constraints change from product to product, and it is always best to refer to the manufacturers data pages. A good rule of thumb is to ensure that the steel surface temperature is at least 5 F (3 C) above the dew point and rising. residue from the blast cleaning operation.
r Ensure that the surface is free of dust, dirt, or any abrasive r Ensure that coatings have been properly thinned ahead of r Ensure that the wet lm is of the proper thickness. This can
time. This includes being certain that the recommended thinner has been used in the recommended amount. be determined by conducting mathematical calculations of the surface area coated and/or by periodically taking direct readings while the coating is being applied. overlapped, and that there are no thin spots, discontinuities, dry spray, and so on.
r Ensure that the coating is applied evenly, that the passes are
The more often problems during application are addressed immediately, the greater the likelihood that runs, sags, and discontinuities can easily be brushed out and corrected.
After Installation
Once the coating installation is complete, the inspector should check that the proper curing and drying conditions are being maintained. The inspector should also make certain that there has been no condensation on the surface or that any type of contamination has been deposited on the coating during the curing process. Overspray, pinholes, runs, or any other imperfections not uncovered at the time of application should be marked now and repaired before another coat is applied. In many cases, other tests may be required once the coating application is complete, including the following points:
r Discontinuity (holiday) testing: low- or high-voltage type r Dry lm thickness measurements: Type I, Type II, or Tooke r Adhesion testing: tape test or tensile adhesion tests r Degree of cure using durometers or the solvent-resistance
method Gage method
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
Controlling Corrosion
125
Inspection Tools
Individuals responsible for quality control should be familiar with basic inspection tools including those listed here. This is not to be construed as an exhaustive list. WFT gauge: The wet lm thickness gauge is used to measure the thickness of paint being applied at the point of application. Two common gauges used are the interchemical gauge and a notch-type gauge. DFT gauge: The dry lm thickness gauge is used to measure the thickness of paint after it has been applied and, preferably, cured. Type 1A magnetic DFT gauge: Commonly called a banana gauge, this is a single-point lift-off gauge (Fig. 3-16). It measures nonmagnetic coatings over a magnetic surface. It operates by magnetic contact and resistance of the magnetic force to the surface by the coating thickness. Calibration assurance in the eld is strongly recommended. Type 1B magnetic DFT gauge: Commonly called a pencil pull-off gauge, this is a single-point lift-off gauge. It measures nonmagnetic coatings over a magnetic surface. It operates by magnetic contact and resistance of the magnetic force to the surface by the coating thickness. Calibration assurance in the eld is strongly recommended. Type 2 electromagnetic DFT gauge: This gauge measures nonconductive coatings over a ferrous metal surface. It operates by electromagnetic contact and resistance of the electromagnetic force to the surface by the coating thickness. Calibration assurance in the eld is strongly recommended. Eddy current gauge: The eddy current gauge (Fig. 3-17) measures nonconductive coatings over a nonferrous surface. It operates by emitting an eddy current and measuring the difference between the emitted signal and the return signal. This difference in time is affected by the coating thickness. Calibration
FIGURE 3-16 Type 1A magnetic DFT gauge (banana gauge). (Source: KTA-Tator)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
126
Chapter Three
FIGURE 3-17 Type 2 electromagnetic DFT gauge. (Source: KTA-Tator)
assurance in the eld according to the gauge manufacturers instructions is strongly recommended. Probing knife: This knife is useful in determining adhesion of coatings. It can be used in conjunction with adhesive tape. Magniers/magnied light scopes: These are useful for closer examination of substrates and evaluation of pits, contamination, pinholes, etc. Mirrors and telescoping mirrors: Mirrors are helpful when the applicator needs to check behind hard-to-reach areas such as nuts and boltswherever direct viewing is impossible. Surface comparators: These are effective in evaluating various surface proles obtained using various abrasive materials. Replica tape and spring micrometers: Replica tape and micrometers are often used to determine surface proles. Sling psychrometer and U.S. Department of Commerce Weather Bureau Psychrometric Tables: These are used in conjunction to determine relative humidity values and dew point temperatures. Surface temperature gauges and infrared noncontact temperature gauges: These gauges aid in determining when the surface is approaching the dew point and when surface temperature is
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
Controlling Corrosion
excessive. Either situation may be problematic and can lead to blistering. NACE/SP0178 Design, Fabrication, and Surface Finish Practices for Tanks and Vessels to Be Lined for Immersion Service (also known as the weld replica standard): This is quite effective in determining if the welds have been prepared properly and are in a condition to receive a protective coating or lining. Holiday detectors: Both wet-sponge low-voltage and high-voltage DC units are effective in examining a lining to ascertain the number of discontinuities (holidays) within it. The low-voltage unit is effective if the lining is less than 20 mil (508 m) DFT. The delimiters on the high-voltage equipment are the coatings thickness and its dielectric strengths; voltages can range from 500 to 200,000 V. Neither unit is recommended for coatings that contain conductive pigments (e.g., aluminum, zinc, and graphite). Adhesion testers: These reveal possible problems with adhesion by dening a numerical adhesion value in pounds per square inch or kilopascals and revealing where the break has occurred. Tooke Gage: Commonly called a paint inspection gauge, the Tooke Gage is known as the referee, so named for its ability to examine individual coatings within a multicoat system as well as the system in its entirety. It is highly accurate in determining lm thicknesses up to coating lms of 50 mil (1,270 m). Testing with the Tooke Gage is destructive, so repairs will be required. Soluble-salt testing (chloride and ferrous): Wide arrays of tests can be performed to obtain information determining the presence of invisible contaminants that will be detrimental to the lining. Two common extraction methods are the swabbing method and the Bresle patch method:
127
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
128
Chapter Three
It is generally accepted by the industry that neither extraction method removes all of the soluble salts, but only up to a maximum of approximately 45 to 50 percent. Once you have obtained your solution, there are several methods for measuring the amount of soluble salts obtained, including the following:
r r r r r
Potassium ferricyanide test Conductivity test Kitagawa tube test Quantab strip test QuantoFix test
Bibliography
Bauer, M. 1988. Changing Regulations on Coatings for Contact with Potable Water. Journal of Protective Coatings and Linings (JPCL) 5(12):2733. Bauer, M. 1996. Organic Zinc Rich Primer for the Interior and Exterior of Potable Water Tanks. In Proc. SSPC Expanding Coatings Knowledge Worldwide, Charlotte, N.C. (Nov.). Pittsburgh, PA.: SSPC. Crist, M. T. 1996. The Cost and Timing of Water Tank Maintenance. In Proc. SSPC Technologies for a Diverse Industry, Charlotte, N.C. (Nov.). Pittsburgh, PA.: SSPC. Dromgool, M. B. 1996. Maximizing the Life of Tank Linings. Journal of Protective Coatings and Linings (JPCL) 13(3):6274. Dubcak, T. O. 1995. Inspecting Water Tank Linings: The Importance of the First Anniversary. Journal of Protective Coatings and Linings (JPCL) 12(9):608. Finch, D. 1996. Protecting Water Storage Tanks in an Era of Environmental Compliance. WATER/Engineering & Management, Nov. Huffman, L. R. 1997. Going with the Flow: A Sampling of Water Tank Maintenance Painting Programs. Journal of Protective Coatings and Linings (JPCL) 14(5):3846. Ippoliti, T. 2000. Waterborne Coatings for Water and Wastewater Treatment Plants. PWC (Nov./Dec.):927. Ippoliti, T. 2002. Polyurea Coatings Win Place in Water, Wastewater Facilities. WaterWorld (Nov.):168. Kapsanis, K. 1990. A Water Tank Update: Issues and Practices in Removing Lead-Based Paint. Journal of Protective Coatings and Linings (JPCL) 7(5): 506. Knoy, E. 1992. When to Repair Pits in Steel Water Tanks. Welding Design and Fabrication (Oct.):512. 1993. Maintaining Aged Steel Water Tanks: What to Look for and Why. Journal of Protective Coatings and Linings (JPCL) 10(5):615. Maronek, A. H. 1988. Evaluating Acceptability of Potable Water Tank Coatings. Journal of Protective Coatings and Linings (JPCL) 5(7):405. Munger, C. G., and D. V. Louis. Corrosion Protection by Protective Coatings. 2nd ed. Houston, TX: NACE International.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
Controlling Corrosion
ODonoghue, M., R. Garrett, and V. J. Datta. 1998. Optimizing Performance of Fast-Cure Epoxies for Pipe and Tank Linings: Chemistry, Selection, and Application. Journal of Protective Coatings and Linings (JPCL) 15(3):3651. OToole, D. 1997. Overcoating: An Effective and Economical Solution for Water Storage Tank Exteriors. In Proc. 1997 SSPC Technologies for a Diverse Industry, San Diego, Calif.; Pittsburgh, PA.: SSPC. Preparation of Protective Coating Specications for Atmospheric Service. 2000. Joint Technology Report SSPC-TR 4/NACE 80200. In Proc. Planning and Specifying Industrial Protective Coating Projects (2004). Pittsburgh, PA.: SSPC. Public Works. January 1995. Specications for Coating Water Storage Tanks are Evolving. Roetter, S. P. 1993. Liability Enormous for Lead-Based Paint Removal. Opow (March). Schubert, R. 1999. Construction and Operation of Water Storage Tanks in Rural Alaska. In Proc. 1999 AWWA Engineering and Construction Conference, Orlando, Fla. Denver, Colo: AWWA. Shannon, G. B. 2003. Selecting Coatings for an Elevated Water Tank in a Densely Populated Business Park. Journal of Protective Coatings and Linings (JPCL) 20(7):857. Smith, L. M., ed. Generic Coating Types: An Introduction to Industrial Maintenance Coating Materials. SSPC 9508. Pittsburgh, PA.: Technology Publishing Company. SSPC Painting Manual Volume 1: Good Painting Practice. 4th ed. 2004. Pittsburgh, PA.: Society for Protective Coatings. SSPC Painting Manual Volume 2: Systems and Specications. 8th ed. 2000. Pittsburgh, PA.: Society for Protective Coatings. Stein, G. R. 1994. Community Acceptance of Lead Paint Removal Projects. Journal of Protective Coatings and Linings (JPCL) 11(5):11925. Zienty, D. 2002. Tanks Pull Double Duty. WATER/Engineering & Management 149(2):913. Zienty, D., and L. Dornbusch. 2002. Painting for Antenna Installations on Water Storage Facilities. Journal of Protective Coatings and Linings (JPCL) 19(9): 739.
129
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Controlling Corrosion
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Source: Steel Water Storage Tanks: Design, Construction, Maintenance, and Repair
CHAPTER
Contractual Considerations
William J. Dixon, P.E.
Dixon Engineering, Inc.
This chapter includes general discussions of the most important topics to be investigated and detailed in preparing the specications for a new steel water-storage tank. Some topics are common to steel water tank repair and/or repaint. Repair and repaint comments are made following the new-tank comment in some cases. This chapter describes the content and purpose of each of the documents involved in bidding, and it notes the duties of owner, engineer, and constructor with respect to specications, bidding, design, construction, and inspection.
Competitive Bidding
The water industry in the United States has been serving municipal clients for more than 200 years. In that time, the industry has developed competitive bidding practices, which are required by law in most states and by governmental subdivisions. Many variations to the standard construction project (designed and bid by the engineer) and some old practices such as maintenance contracts have resurfaced with new twists. Different methods of contract administration have been developed, the most common of which is usually called design/build. Newer practices include computer bidding and what is called a reverse or negative auction. These alternative methods have different benets depending on the project and on whether you are a public owner or a private owner. It is necessary to fully understand the benets of the selected method. The closed competitive bid process was developed to eliminate fraud and political inuence in the awarding of contracts and
131
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Contractual Considerations
132
Chapter Four
generally led to the project being awarded to the lowest responsible and responsive bidder. Responsible refers to the companys ability to successfully complete the project within the required time frame, and responsive refers to the thoroughness of the bid submittalthat is, whether the bidder properly completed the bid, included all bid documents (e.g., noncollusion of contractor with other contractors; minority and/or women and/or disadvantaged participation forms), and submitted the required bonding.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Contractual Considerations
Contractual Considerations
Horizontal privity
133
Engineer
(a)
Constructor
Supplier Subcontractor
Subcontractor supplier
Engineer
Lawsuits Constructor
(c)
Lawsuits
FIGURE 4-1 Roles of owner, constructor, and engineer in the competitive bid process. (a) Privity means a direct relation throughout the contract. (b) In this situation, there is still no privity between the constructor and the engineer. There is vertical privity from the second-tier subcontractor all the way up to the owner. Contract clauses and performance and payment bonds insulate the owners as much as possible from lawsuits by subcontractors and suppliers. (c) Because the engineer and the constructor are not third-party beneciaries of each others contract, neither can sue the other. The owner is under privity both ways, so if he or she is sued by the constructor, the owner can bring the engineer in by ling a claim against the engineer.
and the owner, the engineer is hired to prepare specications and complete project management and inspection services. This is known as horizontal privity of contract between the engineer and the owner. On a repaint or rehabilitation, the engineer is hired to also do a preliminary bid inspection to establish the scope of the project. The owner does not intend the constructor to be a third-party beneciary of this contract. The owner is the sole beneciary of the services performed.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Contractual Considerations
134
Chapter Four
That is why in Fig. 4-1b there is no connection to the constructor in the horizontal privity line. The lack of contractual privity and the owners intention that no third-party beneciaries are to be part of the owner/engineer contract are represented in Fig. 4-1c by the jagged lines between the engineer and the constructor. The arrows indicate that the engineer does not control the constructor and that the constructor cannot rely on (and, in most cases, cannot sue) the engineer. The arrows further indicate that the engineer cannot interfere with the constructors ways and means or means and methods. If the engineer, who might be more experienced, starts giving directions or advice to the constructor, he or she has crossed the line. The engineer assumes the risk for this advice, which has broken down the wall between vertical and horizontal privity. The engineers job is to review, report, and interpret the contract documents. Sometimes the owners staff members provide their own specications and inspection services. In this situation, a denition is needed so that the owners inspections do not substitute for the constructors own quality control responsibilities.
Design/Build
The design/build procedure puts the responsibility of engineering design on the constructor. This procedure works well in new-tank projects but has conicts with rehabilitation projects. The benet of design/build lies primarily in expediting the project. On new-tank or new-tower projects, the owner supplies the bidder with soil investigations, establishes capacity and high water level, and designs standards and a time schedule to follow. The bidder can properly prepare costs and submit the bid. If the procedure is followed properly, there should be no unknowns and no cost increases. Third-party inspection is still necessary. On tank repair/repaints, the extent of repairs and the condition of interior coatings and corrosion may not be known to the tank owner because of the complexities of removing the tank from service for inspection. It is not recommended that the party completing the work be allowed to establish the scope of the work. New construction with no unknowns and larger budgets may be competitively bid as design/build. Design/build is not practical on lower-budget rehabilitation projects, because the unknowns cannot be competitively bid. A pre-bid independent tank inspection can eliminate the unknowns on repair/repaints. But to ensure competent work and competitive bidding, a full set of specications is still necessary, because the constructors idea of what constitutes a proper repair and coating system would be different than what the owner expects. Third-party inspection would be necessary for quality assurance, but without specications and a contract, what would the inspector inspect?
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Contractual Considerations
Contractual Considerations
135
Project Administration
For a further discussion of all of the major methods of project administration, see American Water Works Association Manual M47, Construction Contract Administration.
Contract Documents
The terms contract document and bidding document are often incorrectly thought to be interchangeable. Bidding documents used to solicit project bids traditionally include all the information needed to
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Contractual Considerations
136
Chapter Four
prepare and submit a bid, including the advertisement, information for bidders, general conditions, supplementary general conditions, addendums, technical specications, drawings, and proposal pages. Contract documents include all the bidding documents as well as signed contract or agreement forms, bonds, insurance certicates, notice of award, notice to proceed, and submittals. As the project progresses, change orders and eld orders are added. Most contracts permit the inclusion of minutes from preconstruction and progress meetings.
Design Standards
Incorporation of Standards
Standards prepared by national associations have been incorporated into technical specications for decades. Standards are benecial because the bidder is using the same terminology as used by the owner/ engineer and for the most part knows what is expected. The American Water Works Association (AWWA) standards incorporate other nationally recognized standardsAmerican Welding Society (AWS), Society for Protective Coatings (SSPC), National Association of Corrosion Engineers (NACE), American Petroleum Institute (API), and concrete standards, to name a few. The benets are obvious, but there are pitfalls. Using standards requires the engineers understanding of the included standards. He or she must decide whether to include the entire standard or just portions of it. An example would be the use of AWWA D100 Standard for Welded Carbon-Steel Tanks for Water Storage. D-100 denes how many X-rays are to be taken. If you want more X-rays or a different selection process for X-ray locations, the specications must detail the variance. The potential for a conict may occur more in the incorporation of other standards within the specied standards (i.e., when a second tier of standards is incorporated by reference within the specied standard). Most standards are submitted to the American National Standards Institute (ANSI) for certication. One condition for ANSI certication is that the standard be reviewed and formally updated at least every 5 years. Because of the constant updating and the long bid process, specications must identify which standard is being incorporated, either by date or by clause in the section that outlines general conditions. This also applies to standards incorporated within the standard specied. Industry standards recognize the standard in use when bids are opened. If a standard is updated during a nonbid situation, a negotiated contract, the negotiating parties should dene which standard is to be used.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Contractual Considerations
Contractual Considerations
137
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Contractual Considerations
138
Chapter Four
The old tanks were behemoths and used more steel than the tanks designed today. Water towers were once designed by engineers using slide rules, and steel thicknesses were rounded up to the next one-eighth of an inch (0.125 in. [0.3 cm]). To this, the early engineers added another 0.125 in. (0.3 cm) for corrosion allowance. When welding replaced riveting, welds had to have only 66 percent penetration. Whereas earlier, steel was one size going down the stem until the next fraction was needed, now every stem section could be different, because current steel manufacturing allows steel with differences in size, measured by 10 mil (254 m), to be purchased. Computerassisted design, cutting, and rolling permit the new thinner design methodologies for conical and dished sections. Welding requirements have increased to 100 percent penetration welds. Corrosion allowances are still the option of the design engineer, but they are seldom specied. The excess steelnot maintenance or the coating systemsis the reason some of those older towers are still standing. The interior coating of old towers was two coats of red lead primer protected by a wax (grease) coating. Lead was good from a durability standpoint but obviously now is out of favor because of health effects. The grease coating had a very short life, particularly in cold climates. Pit welding was standard in maintenance projects, whether it was needed or not. The modern epoxy, urethanes, and polyureas, as well as cathodic protection, offer a far superior and cleaner method of protection. Maintenance painting and cathodic protection are more critical now that new designs have no corrosion allowance. There is a safety factor in design calculation, but that is not the same thing as a cushion factor for steel loss.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Contractual Considerations
Contractual Considerations
139
r A copy of an up-to-date inspection report of the structure r A signed document from the present owner stating that the
tank is available for sale. provided by a qualied, registered professional engineer.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Contractual Considerations
140
New-Tank Designs
New-tank designs are another example of industry outpacing the speed at which standards are developed. For example, the composite tank (concrete pedestal/steel tank) was built without an AWWA standard for more than 15 years before a standard was developed. Other smaller associations, including the Steel Plate Fabricators, were able to develop standards more quickly, permitting the compositetank industry to grow until the more comprehensive AWWA standard could be developed. A hybrida glass-lined bolted-steel tank on a pedestalwas developed and applied for inclusion in AWWAs proposed composite-tank standard, but it failed to make the standard because of timing. The caution is not to avoid new products but to understand the standards before you specify something that is not included in them.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Contractual Considerations
Contractual Considerations
The construction process involves design by the constructor and submittal of design to the engineer for review. Sixty days may elapse before the engineer turns it around. After the design drawings are accepted, steel is ordered, cut, rolled, and fabricated in the shop. After shop drawings are approved and before foundation work is even scheduled, the constructor prioritizes the project (based on completion schedule and the schedule of other projects). The foundation is constructed and allowed to cure for 28 days. Steel is usually delivered during this cure time. The start of concrete work is dependent on timely review of submittals. Actual time to erect steel in the eld ranges from 6 to 20 weeks, depending on weather, site conditions, and tank size. The painters need 30 to 60 days, again, depending on tank size, containment requirements, and, particularly, weather. Including a break for winter, it is not hard to see why 540 days and scheduling exibility are needed. On new-tank projects, the existing tank or operating system is not removed until the new tank is operational. On repair and repaint projects, time restrictions are critical as there may be no backup system. Again, the shorter the project time, the more the project may cost, but conditions may justify the cost. Weather, summer demands on the water supply, extra time for containment projects, and even the start of the owners budget year may delay the project start. Money can be saved by specifying a maximum out-of-service time and the latest completion date. This way, the constructor knows that it is a 60-day job and can schedule on the basis of the crews availability. The days can be scheduled anytime, as long as work starts 2 months before the specied latest completion date.
141
Pre-Bid Meeting
A pre-bid meeting is benecial and useful for discussing specic nontechnical portions of the project, the timing of subcontracting requirements, and forms in the bid documents (e.g., noncollusion, minority, afdavits, subcontractor lists, lien waivers, etc.). This meeting can be mandatory or optional. If it is mandatory, interest in the project can be gauged by how many constructors are present, which could affect the contract price. As a minimum, job-site visits should be required. On repaint projects, if the tank is empty, it should be made available to the painter for inspection. If the tank is elevated, prospective bidders should provide proof of insurance before they climb it. To limit time infringements on the owner, limit the days the site is available for inspection.
Prequalication of Bidders
To shorten the time between bidding and awarding of the contract, prequalify the constructors. Tank constructors specialize in the design,
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Contractual Considerations
142
Chapter Four
fabrication, and erection of welded-steel, bolted-steel, or composite concrete/steel tanks. Tank painters are also very specialized. Constructors and painters rely on extensive safety training, specialized equipment (some that they have manufactured themselves), and ways and means procedures developed during years of experience. Tank constructors and tank painters should be prequalied on the basis of their experience, ability to supply bonds, nancial condition, and safety and environmental record. For future discussion, see Chap. 4 of AWWA Manual M47, Construction Contract Administration. Caution: Competitive bidding laws in some states restrict prequalication.
Constructor Assistance
Generally, tank constructors and manufacturers are more than willing to discuss individual tank needs and to assist the owner and the engineer by providing standard design information for a project. For an elevated tank of a given capacity, each manufacturer has different geometric parameters. These dimensions normally do not vary enough to cause difculty if one constructor is selected for a project on the basis of the information supplied by another constructor. To become familiar with current industry standards and practices, the owner is advised to contact prospective bidders and discuss a project before issuing an invitation to bid. Most manufacturers are willing to provide copies of preliminary specications developed for tanks of varying styles and capacities. The owner must be careful to make every effort to write a specication that is open and does not exclude bidding by any qualied manufacturer or supplier. In particular, a given manufacturers proprietary design details should not be included in a projects contract document; this would create an inequitable bidding situation for other qualied suppliers or manufacturers.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Contractual Considerations
Contractual Considerations
Painting projects consist primarily of abrasive blast cleaning, painting, and containment construction, some metal repairs, but not a lot of subcontract work. Also, remember that these constructors and painters have had extensive safety training and that they are responsible for every worker, including subcontractors and forced hires, on that tank. Elements of tank construction, for example, electrical controls, site restoration, and waste disposal, can be separated and bid locally. In fact, it is good practice for the local rm or employees responsible for future maintenance and controls to be familiar with their installation. Telemetry must interface with the owners master system. If the mechanical system requires piping and several valves inside the tank, this work can be bid to local mechanical constructors. On paint projects, it may be possible to tie another project into the paint work to accommodate the subcontracting.
143
Bid Security
Bonds are required on most publicly funded projects over a minimum dollar amount. This dollar amount under the Miller Act is $50,000; many states have a Little Miller Act that may have lower limits. Some municipalities have lower limits yet. The Miller Act requires performance and payment bonds. Bid bonds are generally required by state or local statute. The bidding process is time-consuming and involves signicant expense for both owner and constructor. In a tank-painting contract in the northern states, a bidder failing to honor his or her bid could delay the project into the next season. In that case, the second constructor would still have to honor his or her bid but, thinking the job had been lost, may have taken another project. Painting constructors usually bid and complete all of their contracts within the same weather-restricted season. They traditionally ll their season and do not leave openings for jobs for which they came in second. Fairness may require adjusting the project schedule into the next year if the rst bidder cannot meet the agreement. The bid bond, intended to cover the increased cost of rebidding or awarding to the higher bidder, has been traditionally set at 5 percent of the bid. This amount should be sufcient on a $500,000 newtank contract ($25,000), but it may not be sufcient for a $50,000 paint project ($2,500). If the constructor defaults and the bond is collected, the constructor could lose the ability to purchase bonds. In the coating industry, with its limited number of qualied constructors, limited seasons, and wide range of bids, a painter who has received a more lucrative contract may buy his or her way out of the smaller job. For this reason and others, many engineers require a bid bond higher than 5 percent or for a set amount.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Contractual Considerations
144
Chapter Four
r r r r r r r r r r r r r r r
Bonding Warranties, guarantees Maintenance contracts Insurance Indemnication Prevailing wage and documentation Use of local or union labor Payment application, change order procedures Steel or concrete cost escalation Dispute resolution Safety Meetingspreconstruction, progress, nal punch list Severability Schedule of values Termination
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Contractual Considerations
Contractual Considerations
145
Bonding
Bid bonds, discussed in the previous section, are usually free. The constructor pays roughly 1.5 to 2.5 percent depending on the workload and contract default experience for the actual performance and payment bonds. A combined performance and payment bond for 100 percent of the project bid meets the requirements of the Miller Act, but it may not be sufcient to cover a project gone sour. The performance bond is used to ensure that all aspects of the project are completed. If the original constructor is unable to meet the terms of the contract, the bonding company brings in another constructor to nish the project, at least to the extent of the bond. A payment bond is used to pay all legitimate subcontractors and suppliers if the constructor fails to make payments. Problems generally start with the lowest bid process. If the project is awarded to the lowest bidder, who turns out not to be responsible (is incapable), a 100 percent combined performance payment bond is inadequate. Remember, the bond is for an amount that all of the other bidders thought was too low. Out of that amount, you must pay off all unpaid subcontractors and suppliers and bring in another constructor to nish. Separate performance and payment bonds, each at 100 percent of contract amount, are the current requirements of the EJCDC general conditions. That and control of partial payments should be sufcient to fund completion of the project. Bonding companies have a contract with the constructor, who usually must personally guarantee the bond. The bond names the owner as the intended beneciary. Consider the bond a product supplied as a condition precedent to award of the contract to the constructor. A word of caution: There is no contract between the surety and the owner, but consider the relationship an obligation. The owner is required to control payments to the constructor and to receive waivers from all subcontractors and suppliers; this is called a waiver of surety. If the owner pays the constructor too much and there is insufcient money left to complete the project, the surety has an afrmative defense to avoid payment. Another caution: Verify that the surety company can be served process to force payment. Offshore bonding companies have attractive bonding rates. Offshore companies are offshore for several reasons; they enjoy tax advantages and are untouchable for claim enforcement. The surety should be licensed in the state of the project. Another aspect of the payment bond is the notice requirements of the Miller Act and the Little Miller Act. The prime contractors subcontractors and suppliers do not require notice of hire. Their contract with the prime contractor, or prime, is evidence of notice. If the
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Contractual Considerations
146
Chapter Four
second-tier subcontractors or suppliers and subsequent tiers fail to give notice to the prime at the start and again within so many days of the last workday, the surety does not have to pay the claims under the Miller Acts. The Miller Acts and surety also limit coverage: Third-tier subcontractors and suppliers to second-tier subcontractors are not protected. Although they have to draw a line somewhere, this is unfortunate, because those companies are usually the locals. Although local companies are not protected by surety, the owner can still hold payment until they are paid if the owner has received notice of nonpayment. The fourth type of bond is a maintenance bond. Maintenance bonds are usually free, but a separate maintenance bond is reassurance that any work due under the warranty will be completed. Because a warranty is a contractual requirement, it technically is already covered by the performance bond. However, a separate maintenance bond with the time frame dened is recommended for all warranties exceeding the standard 1-year/13-month warranty. A maintenance bond should also be considered for the full term of a multiyear maintenance contract (extended maintenance bonds would not be free). Performance bonds or maintenance bonds expire unless the owner gives notice to the bonding company that work is needed.
Warranty
The standard construction warranty period is 1 year. The painting warranty is also 1 year, but the D102 standard allows a 13-month period in which to complete the paint warranty. The time extension recognizes the difculty some communities have in isolating their tank. Also, weather may interfere with draining the tank within the specied time. There is also a trend toward specifying longer warranties, a practice that theoretically raises project costs. Constructors prefer to wrap up a project in 1 year. Their bonds are then released; they have less unknown potential liability and can bid other jobs. A multiyear warranty on tank construction has little benet unless full use of the tank must be delayed. Most problems with welded steel are evident within a year. Extended warranties are specied more often on painting of new tanks or repainting contracts. Contractual problems of long maintenance periods can be resolved by the use of a maintenance bond. The problem is that the constructor is giving a warranty on a product that deteriorates with age, weathering, ablation, ultraviolet (UV) degradation, and so on. There is no standard against which to hold a 2- or 5-year paint project warranty condition. Unless specied differently, D102 limits holiday testing (directcurrent voltage testing for coating pinholes) to the high waterline and down on the wet interior surface. If there are coating breaks in that
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Contractual Considerations
Contractual Considerations
area after 1 year, repairs under the warranty are justied. Small coating breaks, rust staining at the lap seams of the wet interior roof or pinhole rusting on the dry interior surface or on the exterior, are not warranty issues. If the specications did not require a holiday-free coating, a warranty cannot require a holiday-free system at 1 year. At 2 years or 5 years, enforcement can only be to whatever expected coating condition at warranty was set in the original specications. Also, a 5-year warranty has to consider normal wear and tear. If you are looking for annual maintenance, bid the maintenance contract into the construction bid as a separate cost; do not try to complete the work under a warranty clause. Trying to have work completed in 5 years for no pay is trickyit is difcult enough just remembering that there is a 5-year warranty. The second concern is whether the constructor is still in business. The owner needs to pay only when scheduled work is completed.
147
Maintenance Contracts
Maintenance contracts are for a set period of time. Generally, the actual painting takes place during the rst year, and touch-up and repairs happen in subsequent years. Some maintenance contracts are attractive because they begin with an enticing nance offer, in which a company nances the initial high cost of the rst painting over the rst couple of years. As always, some good constructors and some bad ones offer these services. To differentiate, follow the moneyor, better yet, control the money. Work including maintenance procedures should be controlled by specications prepared by your engineer. The work should be inspected annually by a third-party inspection rm. The nancial portion should be written or at least reviewed by your attorney. Your attorney should also offer an opinion if competitive bidding of the entire maintenance project is required by local ordinance or state statute. Some of the cost advantage is in the constructor providing nancial and engineering services, but the owner must decide whether the savings are in the owners interest or are in the vested interest of the maintenance constructor. When the dust settles, the good constructors will be there; the ones with prices too good to be true will be the missing parties. Maintenance contracts are not new. In the 1960s and early 1970s, annual maintenance contracts were a major portion of the painting market. Most contracts were for 10 or 12 years and had the same annual payments. Painting on the interior would take place during years 5 and 11, and the exterior would be painted during years 6 and 12. Essentially, the major work was paid in advance. A painter had enough other contracts at varying stages and so could nance the work when it was due. When the gas crunch came in 1973 and gas and paint prices skyrocketed, most constructors merely walked away with the
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Contractual Considerations
148
Chapter Four
up-front money or went bankrupt, and the owners were left with paid but uncompleted projects.
Insurance Requirements
Risk managers or insurance consultants for the owner should establish limits and types of coverages. Sometimes, consultants are nervous because the project requires elevated work or may involve exposure to lead paint. Most tank constructors carry large limits of liability, and some are self-insured. But smaller paint constructors have lower limits. The limits and types of insurance should match the owners exposure to risk. Excess coverage sometimes cannot be purchased by smaller constructors. Purchasing special insurance for one job drives project costs up, particularly if some constructors are eliminated from bidding. Workers Compensation insurance levels are standard and protect the constructors workers. General liability insurance protects site visitors other than employees. Auto insurance is recommended even if all work is on one enclosed site, because the constructor still will run errands. An umbrella policy would be in addition to these policies. The owner and the engineer require the constructor to name them as additional insureds. Any claim against the additional insured other than gross negligence is covered under the constructors policy. Over the years, attorneys have expanded the gray area between the constructors and the owners insurance liability. Some insurance counselors now require the constructor to furnish a separate owners protective policy. Professional liability insurance covers errors and omissions and is associated with the engineer. If the constructor acts as an engineer in a design/build contract, this insurance may still be needed. Some states have strict liability laws for accidents involving gravity, falls, or injuries from dropped objects. Under contract terms, this liability can be covered under an owners protective policy paid by the constructor. But with strict liability laws, responsibility is automatic and liability cannot be avoided. The owner should consider his or her own policy and consider making the constructors policy a primary-pay policy. The EJCDC documents require the owner to supply a builders risk policy. As noted, the EJCDC documents were prepared by professional engineers associations and endorsed by a constructors association; the owners municipal associations were not involved. Owners prefer that the constructor provide a builders risk policy. This policy provides insurance for the project during construction (e.g., if a tornado blows over an unnished tank). The policy covers the cost to replace the tank. Some owners require submittal of the constructors entire policy, but most owners prefer just a certicate. The certicate warrants that
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Contractual Considerations
Contractual Considerations
the constructor will not cancel the policy without giving a specied number of days advance notice. The expiration date, additional insureds, deductibles, and all policy exclusions should be checked.
149
Indemnication
Indemnication clauses are often points of contention and are sometimes contract killers. The owners attorneys want contractual language that protects the owner from all claimssuits that might originate as a result of this project regardless of who is liable. Constructors have attorneys who are as smart as the owners attorneys, and the insurance companies, especially, have their share of attorneys. Although a constructor may agree to any clause to get a contract, it does not mean his or her insurance policy covers the indemnication. A constructor who has no insurance policy does little to offer true indemnication. Rather than proceed under the false assumption of coverage, both the owners and constructors policies should carry comparative liability coverage. Each party pays on the basis of each ones share of liability. Both bonds and insurance are conditions precedent to contract award. We are a litigious society and, as with bonds, insurance is now a requirement before the owner even signs a contract.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Contractual Considerations
150
Chapter Four
Dispute Resolution
The best defense for disputes is to detail in the specications a clear procedure for dispute resolution. The two primary alternatives are the courts and arbitration. Owners, being deep pockets without a face (usually a municipality), prefer the courts. In fact, a future trend by municipalities will be to contractually require the constructor to waive the right to a jury trial. The owner wants a decision based strictly on the law, with no human element, whereas the constructor prefers arbitration by certied arbitrators. The three alternative methods of dispute resolution are negotiation, mediation, and arbitration. There are many variations and hybrid methods of resolution (minitrials, for example). Negotiationdirect talking between the contract partiesis the rst step in all contract disputes. Mediation, generally the second step in the process, brings in a third party. The EJCDCs general conditions make the engineer the mediator. He or she both hears arguments and tries to get the parties to resolve the problem. Because the argument is usually about
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Contractual Considerations
Contractual Considerations
specications that the engineer wrote, he or she, as mediator, is given the nal interpretation of the specications. The engineers decision, while nal, is usually not binding. If either party is still dissatised, it may proceed to court or to arbitration, whichever method is named in the contract documents. Arbitration can be binding or nonbinding. Recent legislation permits contracting away the right of appeals to the court system. The courts are attempting to unload their dockets, and to appeal a bindingarbitration award to a court has very little chance, barring the allegation of fraud, capriciousness, or a signicant procedural error.
151
Safety
Engineering associations have always maintained that the engineer is not responsible for job-site safety. If the engineer and the owner assume such responsibility, they are potentially liable for extensive damages. If the engineer (and ultimately the owner) was responsible and thus liable, the employee can sue through Workers Compensation and collect a much larger settlement. So far, most cases have dismissed the engineer because he or she had horizontal privity with the owner and no contractual relation with the constructor. The exceptions were when the on-site inspector or project manager took on the constructors role by directing some of the work or giving advice on ways and means. No one questions the need for safety, but constructors are contractually responsible for safety. Constructors have developed their own construction procedures and ways and means. Constructors have developed safety programs and trained their personnel accordingly. The engineers personnel should follow the constructors safety program in addition to the engineers safety program.
Meetings
The number and types of meetings required, and who must attend, should be listed as accurately as possible. If home ofce personnel are required to attend, it is a cost issue. Most repaint contracts have a preconstruction meeting and a nal punch list meeting with the job superintendent. Interim progress meetings are usually attended by the on-site superintendent but not by the project manager unless there are problems. On new-tank projects with larger budgets, it is more common to require the project manager to attend.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Contractual Considerations
152
Chapter Four
Contract termination clauses describe the procedure for giving notice to, and terminating the contract by, the owner for convenience or cause and by the constructors for cause.
Schedule of Values
New-tank projects are usually bid as lump-sum contracts. Extras, such as complicated logos, are bid as deductible alternates. On a project that is spread over a year or 18 months, partial payments are in order. To avoid paying too much money up-front or not enough, a schedule of values is submitted early. This schedule can be negotiated until it is acceptable to all parties. The engineer has the nal say. Following is a sample schedule:
Design phase Foundation Fabrication Erection Painting Electrical Site work and punch list 10 percent 10 percent 25 percent 30 percent 15 percent 5 percent 5 percent
Repaint and repair projects can be bid with line items for repair items and unit prices for painting different areaswet interior, dry interior, and exterior. If the project is bid lump sum, a schedule of values should be included on a bid form that assigns costs to wet or dry interior and exterior. Payment is then gured on percentage of work completed (e.g., wet interior abrasive blast cleaning 40 percent, prime coat 20 percent, intermediate coat 20 percent, and topcoat 20 percent).
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Contractual Considerations
Contractual Considerations
Specications should dene responsibilities for this work. AWWA D100 requires that the tank be tested before coating and that the owner furnish the water to ll the tank and provide a means of disposal following testing. D100 permits the coating to be applied before water testing if the tank constructor and the owner have specically agreed to that. Tank testing and disinfection phases of the project could then be concurrent, thus saving the owner the cost of producing and disposing of a large quantity of water. However, water testing the welded tank before applying the coating has the following advantages:
153
r It allows identication and correction of distortions caused r It allows the identication and correction of any leaks that
might have been temporarily covered by the interior coating system. Valves and piping should be tested in accordance with AWWA C600 Standard for Installation of Ductile-Iron Water Mains and Their Appurtenances. The constructor may be required by contract to provide and dispose of the testing and disinfection water. However, the owner will ultimately bear these costs, plus the constructors overhead and prot. by anticipated or unanticipated foundation settlements before coating.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Contractual Considerations
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Source: Steel Water Storage Tanks: Design, Construction, Maintenance, and Repair
CHAPTER
Foundations
Sayed Stoman, Ph.D., P.E., S.E., M.L.S.E., and Kevin Gallagher, P.E.
Caldwell Tanks, Inc.
The proper design and installation of the foundation is essential to all welded-steel tanks for water storage. Before any water tank is erected, it is vital to ascertain the suitability of the site and the feasibility of the project from engineering, construction, cost, and safety perspectives. The site soils must be capable of supporting all loads imparted on or generated by the water tank system with appropriate factors of safety against bearing, uplift, and lateral stability and with reasonable total and differential settlements. (The factor of safety [FS] is a function of the foundation type, the source of loading, and whether the loads are long-term or transient.) Most importantly, conditions at the site must constitute a safe working environment for the construction crew. The ideal sites for erecting water tanks are relatively large and level, dry, and easily accessible. The ideal bearing soils are sandy soils that range in relative density from medium to dense, to very dense, and clayey soils with consistency ranging from stiff to very stiff, to hard. These characteristics are well suited to shallow foundations, with a minimal amount of settlement and full-foundation stability. The ideal site should be large enough to accommodate the construction equipment, provide ample lay-down area, and be free of obstructions, especially high-voltage electric power lines.
155
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
156
Chapter Five
The foundation system should provide for adequate factors of safety for both strength and stability. Since the water-storage system is very sensitive to settlement, care must be exercised to limit the total and differential settlements so that they do not adversely affect the tank and piping system. As a practical rule, it is preferred to limit the total and differential settlements to a maximum of 2 in. (5 cm) and 1 in. (2.5 cm), respectively. If high settlements are expected, special piping or piping joints may be necessary to allow more exibility in the system. While settlement is a major design consideration, each system is unique and must be examined on its own merits. Generally, for economic reasons, shallow foundations are preferred. As long as the bearing soils have reasonable capacity, provide for tolerable settlements, and, when excavated, are properly suited for backll around the footings, shallow foundations are possible. A net allowable bearing capacity of about 3,000 psf (144 kPa) or an ultimate bearing capacity of 9,000 psf (430 kPa) or better would be most appropriate for shallow foundations. Shallow foundations can be built where the allowable bearing capacity is lower, but the resulting footings would be much larger and the settlements possibly higher. Deep foundations are more appropriate where the bearing soils are composed of loose sands or soft clays or where tests have detected the presence of sinkhole cavities, sandy layers that are prone to liquefaction, or silty soils with high moisture content that are likely to consolidate under loading. The type of deep foundation is inuenced by cost, availability of piles, and local practice. Regardless of the foundation type used, grade beams interconnecting the individual footings may be necessary where the horizontal shear resulting from either wind loads or seismic loads is too large for a single footing to resist. These compressive elements are designed as beam-columns on elastic foundations.
Location/Orientation
Aside from accessibility, site location is crucial for several reasons. Specic site location and accurate determination of property lines are vital, as disputes resulting from even minor infringements onto adjacent property can cause major delays in construction and possibly even cancellation of the project. Precise staking of the foundation footprint early in the project can eliminate orientation concerns and facilitate establishing the proper grade elevations and boring locations for geotechnical investigations. Ownership of the site property is essential, as building a storage tank on land owned by others can be costly. Orientation of the tank on the site must also be considered with respect to the piping layout, existing utilities, and other obstacles. To facilitate the connection to the inlet piping as well as to accommodate
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
Foundations
the ow of overow water away from the footing area, situating the tank in the proper orientation, is essential. Tank and piping orientation should be clearly shown on the site plan with reference to reliable existing benchmarks. Sites in low-lying areas and oodplains, areas with sinkholes, and areas with underground shafts, tunnels, or fault lines are not recommended, nor are areas containing substantial lls. Similarly, coastal regions are not recommendedthey are generally subject to signicantly higher wind loading and may require design for tidal waves. The loose sandy soils in these areas could require additional stabilization measures.
157
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
158
Chapter Five
the frost line at a minimum depth of about 4.5 to 5 ft (1.4 to 1.5 m). A minimum projection of 6 in. (15 cm) above the nal grade should be sufcient to protect the column base plates from ground moisture. On sites where standing water or settlement is a concern, higher projections would be appropriate to further protect the base plate and anchor bolts from corrosion.
Excavation Requirements
Before any excavation begins, it is essential that all aspects of jobsite safety are well understood. All excavations, particularly conned excavations, must be performed in strict compliance with the latest federal Occupational Safety and Health Administration (OSHA) standards. It is recommended that excavated slopes, including those for shallow foundations, be laid back at a maximum of 2H:1V (horizontal to vertical) slope. Permanent slopes of 3:1 may be used on ll slopes that have been placed on suitable subgrade. Grass should be planted or other measures taken for erosion control. Vertical cuts for shallow foundations are not recommended unless all the requirements for job-site safety and foundation stability can be assured. Such cuts are not possible in dry, sandy soils, but they can be made to a critical height in an undrained soil where the pore pressures are negative. If vertical cuts are used, however, one must ensure that clear and achievable compaction requirements for the soil wedge alongside shallow foundations are well dened.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
Foundations
159
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
160
Chapter Five
alternatives, the geotechnical report must include all the engineering data necessary for each design option.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
Foundations
Specied Test Classication of soils Cone penetration Consolidation One dimensional Undrained triaxial Direct shear Modied proctor (compaction) One-dimensional swell Seismic refraction method Standard penetration Standard proctor (compaction) Triaxial compression Unconned compression
Note: ASTM = American Society for Testing and Materials.
161
ASTM Designation D2487 D3441 D2435 D4767 D3080 D1557 D4546 D5777 D1586 D698 D2850 D2166
are occasionally left open overnight to permit measurement of groundwater level the next day, preventive measures should be taken to ensure safety during the night. In most states, regulations require that the boreholes be lled with grout or plugged on completion of the investigation. The standard penetration test and cone penetration test are the common tests used to determine properties of soils. The subjective seismic refraction method is also used in subsurface explorations. To obtain an estimate of consolidation settlement in saturated clayey soils, consolidation tests are run in the laboratory. The unconned compression test, direct shear test, and triaxial compression test are alternative test procedures for determining the shear strength of soils. The unconned compression test is primarily suited for cohesive soils. The magnitude of potential swell in clays is determined by the unrestrained swell test or the swelling pressure test. Table 5-1 describes some of the American Society for Testing and Materials (ASTM) standards that can be referred to for further details regarding geotechnical test procedures. Similarly, test procedures are available for checking the design capacity of piles. The axial compression load test (ASTM D1143), the pullout load test (ASTM D3689), the lateral load test (ASTM D3966), and the dynamic pile load test (ASTM D4945) are among some of the common methods used.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
162
Chapter Five
Engineering Properties
Soils that are well suited for foundation design can be cohesive (primarily clayey) or cohesionless. Cohesion, the characteristic that enables the soils to bind or stick together, gives added shear strength to the soil. Shear strength denes the suitability of the soil for the type of foundation work being considered. Cohesionless soils are predominantly sandy soils having particles that lack cohesion. Cohesionless soils draw their shear strength from sliding friction and interlocking of grains. Some soils combine cohesive and cohesionless characteristics and are classied according to which is dominant. Silty soils have been classied as cohesionless by some authors and cohesive by others, depending on the soils clay content. Silty soils, however, are not considered good foundation material due to their compressible nature when wet. Similarly, topsoil and organic soils are unsuited for foundations. Sandy and clayey soils with high bearing capacities and low plasticity are best suited for foundations of water-storage tanks. Engineering properties of soils are dened by the soil grain size distribution. For cohesionless soils, this distribution is determined by sieve analysis, which involves sifting the soil through sieves having openings of different sizes arranged in descending order from coarse to ne. The amount of soil retained in each sieve after sieve agitation serves as the basis of measurements and plots used in dening grain-size distribution. Particle-size distribution in ne-grained cohesive soils is determined by hydrometer analysis based on sedimentation of soil particles in water over a given length of time. Another measure of cohesive soil consistency is called the Atterberg limits. The Atterberg limits refer to the moisture content at which a given volume of a cohesive soil changes consistency from one state to another. These states are dened as solid state, semisolid state, plastic state, and liquid state. The moisture content at which the soil transitions from the solid state to each successive state is referred to as, respectively, the shrinkage limit (SL), the plastic limit (PL), and the liquid limit (LL). The difference between the LL and the PL is dened as the plasticity index (PI). The PI is also a measure of the expansive potential of the soil. Soils with high PI values (PI > 35) have severe shrink/swell characteristics and require additional consideration in design, as is discussed later in the chapter.
Soil Consolidation
All structures are subject to foundation settlement. Given the loading, footing size, and properties of soils, these settlements can be evaluated with reasonable accuracy. Consolidation is time-dependent settlement that can be signicant in saturated soils. It occurs when the soil undergoes compressive deformation under the loading from the structure.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
Foundations
Water is extruded from the voids in the soil as the soil rearranges its grains to accommodate the increased pressure. The process occurs rapidly in granular soils because of their permeability, whereas in cohesive soils or ne-grained silty soils, consolidation can take a long time. Consolidation is also a function of footing size. The larger the footing, the greater the depth of the soil affected by the loads on the footing. The affected depth is also referred to as the effective bearing depth of the foundation. Depending on the thickness of the compressive layer or layers and the depth(s) at which they occur, the resulting settlements can be substantial and could create serious consequences for the structure. Therefore, to ensure structural stability, it is important to include consolidation testing in the work scope where deformationprone soil layers are present within the effective bearing depth of the foundation.
163
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
164
Chapter Five
r r r r r r r r r r r r r r r
Site topography and site preparation Description of the soil and its engineering properties Classication of soil strata Liquefaction potential and its consequences under dynamic loads Presence of rock, rock lenses, and boulders Potential for and consequence of shrink/swell Replacement or remediation of shrink/swell soils Anticipated total and differential settlements Drainage considerations Elevation of groundwater and dewatering requirements Minimum recommended bearing depth of foundation Excavation and backll requirements Suitability of site soils for backll Compaction and compaction testing requirements Seismic design parameters for American Water Works Association (AWWA) and/or other applicable codes
For shallow foundations r Soil ultimate and net allowable (FS = 3.0) bearing capacity resistance
r Soil carrying capacity for lateral load based on soil passive r Extent of overexcavation, if necessary, and backll recommendations
For pile and caisson foundations r Anticipated pile/caisson type, size, and length
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
Foundations r Minimum required reinforcement for caisson (as per local r Pile/caisson allowable lateral load capacity r Pile/caisson bending-moment diagram for appropriate end r Pile or caisson safety factor for long-term and transient loadr Pile testing required and type of test r Special installation considerations r Appropriate uplift connection recommendations
Typically, laboratory analysis of selected samples includes visual classication, cohesive shear strength tests, determination of Atterberg limits, grain-size analysis, determination of eld moisture content, and the following additional parameters:
Soil unit weight Unit cohesion of soil Coefcient of soil active pressure Coefcient of soil passive pressure Standard penetration resistance values Angle of internal friction Coefcient of friction, if different than tan Modulus of subgrade reaction c Ka Kp N f ks
165
practice)
conditions ing
All the required seismic parametersincluding the mapped maximum considered earthquake acceleration at short period Ss and at 1-second period S1 should be specied. Where required, site-specic geotechnical investigation and dynamic site response analysis should be performed to determine the appropriate values.
Problem Soils
Experience indicates that certain types of soils pose special challenges in design and require remedial measures before they can support water tank foundation loads. Among these are expansive soils, which are prevalent in many areas of the United States and elsewhere in the world. The expansive clays with very high plasticity index values are not suited for shallow foundations unless remedial measures are taken that include lime mixing, prewatering, use of water barriers, or soil replacement. All of these measures are costly and require strict quality control.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
166
Chapter Five
Foundation considerations in shrink/swell soils depend on the depth of the active zone and the swell potential of the soil. When a thin layer of these soils is present near the surface, it can be replaced with more suitable low-plasticity soils. When deeper layers are encountered, the expansive soils under the foundation can similarly be replaced and properly compacted. An approach that is often recommended is to place the shallow footing below the depth susceptible to shrink/swell and to replace or remediate the surrounding soils to make them suitable for backll. However, the footing can be placed within the active zone as long as the uplift forces caused by the swelling of the soils are taken into account in design and as long as the structure can tolerate the resulting movements in the foundation. It is important to note, however, that as long as moisture is prevented from entering the soil, the shrink/swell volumetric changes cannot occur. Therefore, pouring a concrete slab over the footing area or placing waterproof barriers around the footing are alternate remedial options. Further detailed options are discussed later in the chapter. When materials such as organic soils, lls, or any other type of loose soil are encountered at the bearing level, they should be undercut and replaced with suitable soils. The replacement soils may be what is commonly known as select structural ll, sand, or crushed stone. Select structural ll consists of uniformly graded sands to silty or slightly clayey sands, free of organics and other deleterious material, with less than 30 percent passing through a no. 200 sieve. Select ll is also recommended for backll around the footings and pile caps when unsuitable soils are present. Structural lls are commonly placed in thin (6- to 8-in. [15- to 20-cm]) lifts and compacted to 95 to 98 percent of the soils modied proctor maximum dry density (ASTM D1557) or other ASTM criteria. They may require some manipulation of the moisture content (wetting or drying) to achieve the required compaction. Flowable ll is another material that can be used for this purpose. Of course, replacing the undercut soils with low-strength concrete is always an option.
Structural Concrete
Water tank foundations are primarily constructed of reinforced structural concrete. Concrete is a mixture of hydraulic cement with ne and coarse aggregates and water in appropriate proportions. Sand, gravel, crushed stone, and, in some cases, iron blast-furnace slag constitute the aggregates. The governing properties of hardened concrete are dened by the quality of the cement paste, ratio of water to cement, and the properties of the aggregates. Structural concrete is concrete mixed to a uniform distribution of materials on the basis of a precise mix/design and satisfactory quality control for required
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
Foundations
durability and compressive strength. The design and construction of water tank concrete foundations follow the Building Code Requirements for Structural Concrete (ACI 318-05) and Commentary (ACI 318R-05) (see Bibliography).
167
r Building Code Requirements for Structural Concrete, ACI r Building Code Requirements for Structural Concrete, Commentary, ACI 318R-05. Concrete is strong in compressive strength, but its tensile strength is limited to a small fraction of its compressive strength. Therefore, in exural design applications such as for foundations, steel reinforcement is provided on the tension side of a member to resist the tensile stresses. Similarly, as shrinkage and temperature reinforcement normal to exural reinforcement, or wherever tensile stresses can develop, steel reinforcement is added to provide tensile resistance. Reinforcement bar sizes and details as well as criteria for determining the amount of reinforcement needed are all outlined in ACI 318-05. 318-05.
Materials
Structural concrete materials include cement, aggregates, water, and admixtures. The reinforcing steel used in water tank foundations comprises deformed bars ranging in diameter from 3/8 in. (9.5 mm) to about 13/8 in. (3.5 cm). Two larger bar diameters of 13/4 in. (4.5 cm) and 21/4 in. (5.5 cm) are also available but are seldom used in water tank foundations. Welded wire fabric is another form of reinforcement often used in oor slabs. Cement is a powdered substance produced from a burned mixture of clay or shale and limestone. Portland cement is the most common type, grayish in color, consisting chiey of calcium and aluminum silicates. Portland cement is manufactured to various designations on the basis of the physical and chemical requirements as dened by ASTM C150. Type I designation represents the general-purpose cement for foundations subject to normal exposure. Where sulfate attack from soil or water is a concern, if high strengths at an early period are required, or if hydration heat needs to be minimized, other ASTM cement types would be better suited and should be specied. Aggregates are generally classied into ne and coarse categories on the basis of their particle size. Fine aggregates consist of sands that pass through a no. 4 sieve, meaning that their maximum particle size is less than 1/4 in. (6.4 mm). Some references include a particle size up to 3/8 in. (9.5 mm) in ne aggregates. Coarse aggregates constitute any material larger than 3/8 in. (9.5 mm). The most common aggregate size is about 3/4 in. (19 mm). However, the maximum coarse
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
168
Chapter Five
aggregate size is governed by the space limitations between the reinforcing bars. As the aggregates constitute up to 75 percent of the total volume of concrete, it is important not only that the proper size be selected carefully, but that the aggregates be properly graded and have the requisite strength, durability, and weather resistance for the exposure environment. Uniformity and workability of concrete are affected by the aggregate gradation or particle size distribution within the aggregate. A properly graded aggregate has a balanced distribution of particle size that remains consistent from batch to batch. Aggregates with smaller gradation minimize the number of air voids and result in more dense, stronger, and better concrete. Water is a necessary ingredient that initiates the hydration process of cement. The mixing water should be clean potable water that is free of oils, acids, alkalis, salts, and other organic materials that are detrimental to concrete or the reinforcement steel. Likewise, the water should be free of high concentrations of dissolved solids. Admixtures should be used only when required by design. They improve the workability of plastic concrete and enhance the properties of hardened concrete. The admixtures include air-entraining to increase resistance to freezing, water-reducing admixtures to reduce the quantity of water needed to maintain a certain slump, retarding agents to slow the setting of concrete, accelerators to hasten strength development at an early age, and y ash and ground, granulated blastfurnace slag to improve the plastic or hardened properties of cement concrete.
Durability
Because water tanks are erected in varied climates and locations, the environmental effects on their concrete foundations can be harsh and must be taken into consideration. Conditions that can profoundly affect the service life of the foundations include extreme temperature uctuations, freeze/thaw cycles when exposed to water, and exposure to chemicals, salts, deicers, etc. Durability, in essence, refers to the capability of concrete to withstand these exposure conditions without damage, distress, or deterioration. ACI 318-05 provides detailed durability requirements for improving the performance of concrete. These requirements include air-entraining recommendations for concrete exposed to freezing/thawing or deicing chemicals, maximum water-to-cement ratios and minimum strength values for concrete exposed to special conditions, maximum percent of total cementitious material by weight for exposure to deicing chemicals, and criteria for resistance to sulfatecontaining solutions and soils. This reference also provides requirements for corrosion protection of the reinforcing steel.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
Foundations
169
Required Strength, fc
Structural concrete can be proportioned to a wide range of design strengths and characteristics. The design of water tank foundations is based on a specied design strength for concrete. The design strength refers to the compressive strength gained by concrete after 28 days of curing and is referred to as f c . For water tank foundations, a minimum design strength of 3,000 psi (20.7 MPa) is recommended. The preferred specied strength, however, is 4,000 psi (27.6 MPa). A common practice in the industry is that when concrete strength in excess of 3,000 psi (20.7 MPa) is required by the specications, a design strength that is
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
170
Chapter Five
500 psi (3.4 MPa) less than the specied strength is used in computations. This allows some exibility in situations where strict quality control measures cannot be maintained due to the long hauls to remote job sites. Evaluation and acceptance of concrete for a given design mix can be made on the basis of actual testing. Adjustments to the mix design can be made to improve the resulting strength as necessary. To ensure that the concrete furnished meets the specied design strength requirements, fresh concrete specimens can be prepared at the job site for testing in the laboratory. ACI 318-05 provides criteria for concrete sampling and testing and for acceptance of concrete compressive strength: Concrete strength is considered acceptable when the average of any three consecutive strength tests equals or exceeds f c and no individual test (average of two cylinders) falls below f c by more than 500 psi (3.45 MPa). For the test results to be meaningful, it is critical that the samples be taken, handled, and cured in strict compliance with the applicable ASTM standard. Testing of cylinders that are mishandled or ignored at the job site may not be truly representative of the concrete furnished. Also, it is important that qualied personnel test all specimens, as the outcome of the tests determines the acceptability of the foundations. If the strength test results fail the acceptability criteria, hardened concrete can be tested by taking core bores in accordance with ASTM C42. Experience indicates that unless the requirements of ASTM C42 are strictly adhered to, the core bore test results will underestimate the true strength of the hardened concrete. ACI 318-05 also provides specic criteria for core drill testing.
Reinforcing Steel
The reinforcement steel used in water tank foundations is generally deformed bars conforming to the ASTM A615 specication and having a minimum yield strength of 60 ksi (414 MPa). Where weldability is a requirement, low-alloy steel deformed bars conforming to ASTM A706 can be used. As noted previously, welded wire fabric reinforcement can be used in oor slabs. These fabrics conform to ASTM A185 for plain wire and ASTM A497 for deformed wire. Epoxy-coated bars or wires are not necessary for water tank foundations. ACI 318-05 provides detailed criteria for determining the amount of reinforcement necessary in design as well as requirements for the spacing, cover, development length, and splice length. Requirements for the development length of bars should be carefully reviewed, especially for the horizontal bars. If horizontal bars are so placed that more than 12 in. (30.5 cm) of concrete is cast in the member below the bar, the required development length is 1.3 times the normal development length.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
Foundations
171
Nonconforming Concrete
On occasion, it is possible that concrete mixed and furnished under a specication fails to meet the minimum design strength requirement. As a result, contractual obligations may require the foundation contractor to remove the nonconforming foundations and reinstall the foundations according to the stated requirements. This can signicantly delay project completion and can be very costly. Therefore, it is important that serious attention be paid to quality control during the mixing, conveying, placing, and curing phases of the concrete foundation construction. Contractual obligations notwithstanding, not every nonconforming condition warrants the removal of the footings. If testing conrms low strength, calculations can be performed to check the adequacy of the furnished concrete with reduced strength and the actual reinforcement provided. The nonconforming condition may be accepted if the calculations conrm that the load-carrying capacity of the foundation is not signicantly reduced and that the design intent has been met.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
172
Chapter Five
Tank diameter Overow elevation Head range High water line
Column (typ.)
Center riser
Elevation
Plan
FIGURE 5-1 Typical leg tank elevation and shallow foundation plan.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
Foundations
173
Shallow Foundations
The shallow foundation is the most cost-effective foundation for water storage tanks. Shallow foundations typically include isolated footings or mat or raft foundations placed just below the columns on the lowest part of the structure, as applicable. Footings can be placed as shallow as possible as long as the bottom of the footing is below the frost line, the resulting bearing pressures are within the allowable limits, the overall settlements are tolerable, and the stability requirements are met. However, for water-storage tanks, shallow foundations can be typically placed as shallow as 4.5 ft (1.4 m) and as deep as 10 ft (3.0 m) below grade. Shallow foundations transfer structural loads to the bearing soil or rock strata occurring below the base of the footing. Shallow foundations for multicolumn elevated storage tanks typically consist of isolated piers with footings (Fig. 5-1). For ground storage tanks and elevated single-pedestal tanks, the foundation may take the form of a ringwall, a ring-tee, or a ring-slab. These ring-type foundations are further discussed later in the chapter. Ground storage tanks may also be founded on a slab or a granular berm. Figures 5-2a, 5-2b, 5-2c, and 5-3 show several common types of shallow foundations. Based on tank geometry, site conditions, and specic environmental loading effects, various foundation alternatives should be evaluated. Typically a shallow foundation is the preferable option. If poor soil conditions, high settlement expectations, or low bearing capacities dictate, deep-foundation alternatives must be considered. Low bearing capacities generally result in large footings, causing the adjacent footings to encroach upon each other. As a result, the overlapping of the pressure bulbs from the individual footings can exacerbate the bearing stresses and magnify settlements. Therefore, when the net allowable bearing pressure falls below 2,000 psf (96 kPA), the deepfoundation alternative should be pursued.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
174
Chapter Five
Radial centerline
Centerline of foundation
Centerline of foundation
Plan
Centerline of foundation
Dowels Hoops
Bars
(a)
Elevation
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
Foundations
175
Radial centerline
Centerline of foundation
Centerline of foundation
Plan
Centerline of foundation
Anchor bolts
Dowels Hoops
Top of grade
Exposure
Bars
(b)
FIGURE 5-2b Flat slab
Elevation
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
176
Chapter Five
Centerline of foundation
Centerline of foundation A
Plan Centerline of foundation Anchor bolts Slab reinforcing U-bars Dowels Dowels Vault for piping U-bars
Bars
Bars
(c)
FIGURE 5-2c Riser.
Elevation
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
Foundations
Centerline of tank and foundation Top of footing elevation Exposure
177
(a)
Extend 35 ft Tank plate (0.91.5 m) beyond tank Top of berm elevation Slope To drain down away Coarse stone or coarse gravel
2 ft (0.6 m) minimum
Centerline of tank and foundation Compacted crushed stone, screenings, fine gravel, clean sand, or similar material
1 1.5 1 1
(b)
FIGURE 5-3 Examples of shallow mat and berm foundations: (a) typical square mat foundation and (b) typical granular berm foundation for at-bottom tanks.
for concrete should be considered in the design of tank structures and foundations. The standard also recommends consideration of a minimum allowance of 25 lb/ft2 (1,205 N/m2 ) for the pressure resulting from the design snow load on the horizontal projection of the tank roof surfaces with slopes not exceeding 30 degrees. A reduction of this allowance is permitted in warmer regions where snow loading is smaller. However, D100-05 limits the minimum roof design load to 15 lb/ft2 (720 N/m2 ). AWWA D100-05 has adopted the American Society of Civil Engineers (ASCE) standard 7-05 for wind loading criteria. However, it retains the minimum design pressures to be 30 Cf lb/ft2 (1,436 Cf N/m2 ), with the force coefcient Cf being 1.0 for at surfaces, 0.60 for cylindrical or conical surfaces with apex angle <15 degrees, and 0.50 for double-curved or conical surfaces with apex angle 15 degrees. For seismic design, the AWWA standard has essentially adopted ASCE 7-05 criteria with some variation in the minimum design acceleration. ASCE 7-05 provides detailed criteria for both wind and seismic loading. Proper determination of the period of oscillation of the water tank system is necessary in all seismic evaluations. The wind or seismic forces can originate from any direction. Structural analysis indicates that the greatest uplift force in a multicolumn elevated water tank occurs in the column that is situated exactly upwind of the lateral force. The maximum uplift force generally occurs
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
178
Chapter Five
when the tank is empty. For taller and shorter towers in areas of high seismic risk, it would not be unusual to nd that the maximum uplift occurs under seismic loading when the tank is full. Similarly, the greatest downward force occurs in the column situated exactly downwind of the lateral force. The downward load will be a maximum when the tank is full. The direction of the lateral force that will cause the greatest uplift may not be the same as the direction of the lateral force that will cause the greatest downward force. Hence, all column foundations are candidates for the worst-case orientation. Typically, structural loading required for the design of the foundations is determined from the analysis of the elevated tank and tower or pedestal. The resulting reactions, shears, and overturning moments due to the gravity loads, wind loads, and seismic loads are all dened. These loads, in addition to the foundation dead loads and other loads emanating from soil pressure or swells, constitute the design loads. Foundations are generally designed according to ACI 318-05 and its commentary, ACI 318R-05. This building code for structural concrete stipulates that the foundations be designed to have design strengths at all sections at least equal to the required strength based on factored loads in dened load combinations. Although ACI 318-05 still retains the classical factored load combinations in its Appendix C as an alternative, in its 2005 edition it has adopted the ASCE 7-05 factored load combinations for design. In the seven load combinations stated for determining the required strength U , loads not present can be eliminated from the load combinations: U = 1.4( D + F) U = 1.2( D + F + T ) + 1.6( L + H ) + 0.5( L r or S or R) U = 1.2 D + 1.6( L r or S or R) + (1.0 L or 0.8W) U = 1.2 D + 1.6W + 1.0 L + 0.5( L r or S or R) U = 1.2 D + 1.0 E + 1.0 L + 0.2 S U = 0.9 D + 1.6W + 1.6 H U = 0.9 D + 1.0 E + 1.6 H where D F Lr L R S E W H = dead loads = load due to weight of uids = roof live load = live load = rain load = snow load = load effects of seismic forces = wind load = loads due to weight and pressure of soil, water in soils, or other materials (5-1) (5-2) (5-3) (5-4) (5-5) (5-6) (5-7)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
Foundations
T = cumulative effect of temperature, creep, shrinkage, differential settlement, and shrinkage-compensating concrete It is the authors view that the load due to the weight of the uids F should be included in the strength design load combinations (Equations [5-4] and [5-5]) with a load factor of 1.2that is, 1.2 F . Otherwise, the case of the full tank under wind or seismic loading may not be appropriately considered. Interestingly, the ASCE 7-05 basic load combinations for allowable stress design correctly include the F loads in load combinations for wind and seismic loading. Likewise, the weight of uids should be included in the seismic load combinations (Equations [57] and [510]), as the seismic uplift can be more signicant in areas of high seismic risk or in the case of tall elevated tanks when the tank is full. The uplift for an empty tank is generally governed by the wind load combinations. Alternatively, the classical ACI 318 Appendix C load combinations may be used: U = 1.4( D + F ) + 1.7 L U = 0.75(1.4 D + 1.4 F + 1.7 L ) + (1.6W or 1.0 E ) U = 0.9 D + (1.6W or 1.0 E ) U = 1.4 D + 1.4 F + 1.7 L + 1.7 H (5-8) (5-9) (5-10) (5-11)
179
Where structural effects (differential settlement, creep, shrinkage, expansion of shrinkage-compensating concrete, or temperature change T ) are signicant, U should not be less than the larger of the following equations: U = 0.75(1.4 D + 1.4 F + 1.4T + 1.7 L ) U = 1.4( D + T ) (5-12) (5-13)
Regardless of the load combination selected for design, the load factor 1.6 on wind load can be reduced to 1.3, where W has not been reduced by a directionality factor. Also, the factor 1.0 on the seismic load should be increased to 1.4, where E is based on service-level seismic forces. Refer to ACI 318-05 for other specics in using these load combinations. It should be noted that in foundations design, AWWA D100-05 Section 12.1.1 requires the water load to be considered as live load, with appropriate factors for live load. Furthermore, the standard does not require the inclusion of snow loading in the load combinations that include wind or seismic loads. An additional AWWA D100-05 requirement that is associated with the ductility of the bracing rods states that foundations should be checked for stability at a lateral seismic force equal to yielding of bracing rods. For A36 rods, the actual yield stress may be as much as 1.33 times the minimum published yield. Hence, the anchor bolts must also be checked to ensure load transfer.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
180
Chapter Five
Bearing Capacity
Bearing capacity refers to the ability of the soil strata below the footing to safely resist the structural loading on the foundation with reasonable safety and tolerable settlements. The loads described earlier must all be transferred to the bearing strata through the foundation system. The pressure resulting from the structural loading at the interface between the foundation and the bearing strata is referred to as the bearing pressure. The bearing pressure must always remain below the ultimate bearing capacity of the bearing soils. The ultimate bearing capacity may correspond to a general shear failure or a punching shear failure in the soils. However, in design, safety factors are applied to further limit the bearing pressures to levels commonly referred to as the allowable bearing capacity. The determination of the ultimate bearing capacity follows Terzaghis equations (Terzaghi and Peck 1967). Based on equilibrium analysis and experimentation, Terzaghi expressed the ultimate bearing capacity in semiempirical forms that can be expressed as q ult = c Nc + qNq + BN where = 1.0 for strip foundation = 1.3 for square and circular foundations = (1+ 0.3 B / L ) for rectangular foundation = 0.5 for strip foundation = 0.4 for square foundation = 0.3 for circular foundation = 0.5 (1 0.2 B / L ) for rectangular foundations = unit weight of soil q = surcharge, or times the bearing depth of the foundation B = width or diameter of the footing L = length of the footing c = cohesion of soil Nc , Nq , N = bearing capacity factors determined on the basis of the angle of internal friction of soil Refer to a soil mechanics textbook for further details (Terzaghi and Peck 1967 or Smith and Pole 1981). Water tank foundations are designed using the net allowable bearing capacity. The net allowable bearing capacity is determined by subtracting the effective surcharge or the overburden pressure from the ultimate bearing capacity and dividing the result by a factor of safety (FS). The FS included in the recommendations of the geotechnical report is critical and should be reviewed carefully. Typically, the FS (5-14)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
Foundations
ranges from 2.5 to 3.0. However, AWWA D100-05 prescribes specic values for various bearing conditions:
181
r A safety factor of 3.0 shall be provided on the basis of calcur A safety factor of 3.0 shall be provided on the basis of calculated ultimate bearing capacity for gravity loads plus wind load, excluding overturning toe pressure caused by shear at the top of the footing, unless specied otherwise. The safety factor may be reduced to 2.25 when specied in the geotechnical report. lated ultimate bearing capacity for gravity loads plus seismic load, excluding overturning toe pressure caused by shear at the top of the footing, unless specied otherwise. lated ultimate bearing capacity for gravity loads plus wind or seismic load, including overturning toe pressure caused by shear at the top of the footing. Therefore, the geotechnical investigation must identify the net allowable bearing capacity using an FS of 3.0 against the ultimate bearing capacity. If a different FS value is specied in the geotechnical report, the bearing pressures must be corrected to an FS of 3.0, as required by AWWA D100-05. lated ultimate bearing capacity for gravity loads.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
182
Chapter Five
The footing thickness is based on the concrete exural and shearstrength requirements of ACI 318-05. The slab bending moment requirements are checked at the faces of the pedestal. Checks are also made on strain compatibility to ensure that the failure mode will be by yielding of the reinforcement, not by the crushing of concrete in the compression zone. Beam or exural shear is checked at the critical distance d from the face of the foundation pier. The punching shear is checked at the critical distance d/2 from the face of the pier. The dimension d represents the distance from the extreme compression ber to the centroid of longitudinal tension reinforcement in the slab, at the face of the pedestal. When checking the punching shear or exural shear capacity of sloping slabs, caution is warranted to use the actual depth at the location under consideration, not the depth at the face of the pier. For the multicolumn tank, the tower typically consists of tubular columns with a base plate at the top of the footing. The column pier or pedestal is sized to accommodate the column and base plate in addition to providing adequate embedment depth and edge distance for the anchor bolts. The pier can be circular, square, orin the case of a battered columnrectangular. The rectangular pier allows the line of action of the column axial force to be centered on the footing, thus avoiding creation of eccentric moments at the base. The depth of the foundation below grade, the pedestal projection above grade, and the thickness of the footing determine the required height of the pier. The designer must ensure that the pier does not become slender. Otherwise, it would have to be designed as a column. ACI 318-05 limits the ratio of the pedestal height to its average least-lateral dimension to a maximum of 3. By this limitation, the ACI building code provides specic reinforcing requirements that are lighter than those typically required for columns. The minimum reinforcement of exural members relevant to the foundation slabs is dened in ACI 318-05 Section 10.5.1. Section 10.5.3 allows this minimum reinforcement requirement to be waived if the calculated area of the reinforcement is increased by one-third. For footings of uniform thickness, Section 10.5.4 species that the minimum area of tensile reinforcement in the direction of the span should be the same as that required for shrinkage and temperature dened in Section 7.12. The upper bound on the exural reinforcement ratio should satisfy the requirements of Section 10.3.5 or Section B.10.3.3. Shear friction should be checked at the pedestal/slab interface according to Section 11.7.4. For cast-in-place pedestals, ACI 318-05 Section 15.8.2.1 species that an area of reinforcement across the interface should not be less than 0.005 times the gross area of the pedestal. For shorter pedestals, this value can be arguably reduced by as much as 50 percent according to industry practice. However, the value should be maintained
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
Foundations
for taller pedestals. The vertical dowels constituting the pedestal reinforcement resist the uplift and lateral forces that exist at the upwind columns when the tank is empty and the design wind load is fully active. They also strengthen the pier in resisting compressive loads. The dowels will require lateral ties as per ACI 318-05 Section 7.10.5. As was noted earlier, once the foundation system is sized based on all other requirements, it is necessary to check for vertical (uplift) and lateral (sliding) stability. When the uplift is severe, it will control the embedment depth and the size of the footing. To ensure stability against uplift, the foundation can be placed deeper or made larger to maximize the dead weight of the soils directly above the footing. This will be especially necessary when the water table is high and when buoyant weights are used in design. Similarly, footing depth or slab dimensions can be adjusted to provide stability against lateral sliding. When such adjustments are made, it will be necessary to revisit nal reinforcement requirements for code compliance. (Typically, for buoyant weights, 60 lb/ft3 [961 kg/m3 ] for soil and 82 lb/ft3 [1,314 kg/m3 ] for concrete are used in design.) AWWA D100-05 requires the weight of the pier (footing) plus the weight of the soils directly above the pier to be sufcient to resist the maximum net uplift occurring when the tank is empty. The lateral stability is provided by the passive resistance, cohesion, and adhesion provided by the soils. It is recommended that a minimum FS of 1.3 be maintained against the working load uplift by including the weight of a 25-degree soil wedge and that a minimum FS of 1.5 be maintained against lateral sliding. In elevated tanks, the riser carries a major portion of the water weight. For torus-bottom tanks, this loading may be equivalent to the weight of water within half the diameter of the tank times the tank head range. The loading and the requirement for pipe entry and exit at the base of the riser footing make the riser foundation unique. The pipe pit design differs considerably from the column pedestal design in that it has a top slab that can support a considerable load. The pipe pit often has an open front so that support for the top slab is provided by just three walls. The slab, treated as a two-way slab, is supported on the front edge by a deepened girder or non-deepened band beam across the open face of the pit and on the other three edges by the walls of the pit. The load transferred to the top slab by the riser consists of two parts: one part comprises the direct loads from the tank transferred by a compressive axial stress in the riser pipe walls, and the other part is due to the water column that bears on the riser oor in wet risers. Another design consideration for the top slab is whether the diameter of the riser pipe is less than or greater than the clear span in the pipe pit below. If the riser diameter is smaller than the clear span, the reinforcement in the slab must be attuned to account for the additional bending moment in the slab.
183
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
184
Chapter Five
The walls of the pit are reinforced in accordance with ACI 318-05 Sections 14.3.2 and 14.3.3, unless required otherwise. The walls are typically 12 in. (30.5 cm) thick. They are checked for compressive stress as well as exural bending stress caused by soil active pressure, and their thickness is adjusted as required. Where the water table is high or when the soils are saturated, soil lateral pressures will be affected, and their effect must also be considered when specifying design lateral pressures.
A
A Plan
3 in. (76 mm) Clean dry at wall sand 6 in. (152 mm) minimum at center
Compacted regular or gravel fill Detail X Centerline of tank and foundation Top of footing elevation Compacted backfill Hoops Sand cushion See Detail X
Expansion material
FIGURE 5-4 Typical ring-wall foundation plan for a at-bottom tank. (Verts. = vertical reinforcement dowels.)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
Foundations
185
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
186
Chapter Five
A Anchor bolts on bolt circle
i Ins de
Ou
dia
O ut side
tsi de
Insid
mete e dia
r rin
gwa
te me r sl
ll
ab
d or Ch
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Ch or
FIGURE 5-5 Typical ring-tee foundation plan for a single-pedestal tank. (Verts. = vertical reinforcement dowels.)
through the no. 200 sieve. Soils with high values of liquid limit and/or plasticity index should be avoided. A liquid limit in the range of 30 to 35 and a plasticity index of less than 15 are commonly preferred. Backll may also be required to replace unsuitable bearing soils. The backll material in this case may consist of well-compacted structural lls as dened above, clean-washed crushed stone (e.g., no. 57 stone), or a lean-concrete mud mat with a compressive strength of
Do not grout pipe. Bend bars around opening B B Bars Pipe sleeve for inletoutlet Section B-B
Verts.
Foundations
Foundations
187
Centerline Ou of tank and tsi Out foundation de side d diam iam eter ring ete wal r s l la b Centerline wall g of inletin r r mete outlet pipe e dia Insid
spCh ac ord in g
ac in
H sp oop ac ing
Plan
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Ch or d sp
Outside diameter
FIGURE 5-6 Typical ring-slab foundation plan for a single-pedestal tank. (Verts. = vertical reinforcement dowels.)
about 2,000 psi (14 MPa). The geotechnical consultant must provide specic recommendations as to the appropriate backll material and required compaction. Resistance to sliding is generally derived from the passive resistance of the soils acting against the foundation. Cohesive soils also
Gravel floor or concrete slab Compacted soil or ground fill Concrete Verts. thrust block Hoops Radial bars
Inlet-outlet pipe
Slab bottom reinforcement bars Slab top reinforcement bars Section A-A
Do not grout pipe. Bend bars around opening Compacted backfill Bars Pipe sleeve B for inletoutlet B Section B-B Bearing elevation Roughened construction joint (or a shear key)
Foundations
188
Chapter Five
draw passive resistance from the soil cohesion. In addition, the shearing resistance at the base of the footing resulting from internal friction in the soil may contribute to the lateral resistance. The coefcient of friction at the base of the footing ranges from about 0.3 for silty soils to 0.5 for coarse-grained cohesionless soils. The backll around the footings is commonly placed in 6- to 8-in. (15- to 20-cm) lifts and is compacted to 95 to 98 percent of the soils standard proctor maximum dry density (ASTM D698) or modied proctor maximum dry density (ASTM D1557) criteria. Manipulation of the moisture content of the backll material may be necessary to achieve the required compaction. Flowable ll is an alternative backll material that is simple to place and does not require elaborate compaction.
Settlement
All structural foundations are subject to settlement. As long as the settlements are reasonably small and uniform, their effect on the structure is relatively small. However, if the settlements become large and the differential settlements excessive, there can be serious consequences that could lead to failure. Therefore, it is absolutely essential that the settlement of all foundations is estimated and that its effect on the structure as a whole is examined before construction proceeds. Geotechnical consultants are expected to provide proper assessment of the total and differential settlements. As was stated earlier, for water tanks it is preferable to limit the total and differential settlements to a maximum of 2 in. and 1 in. (5 cm and 2.5 cm), respectively. If shallow foundations will cause excessive settlement, deep foundations can be used to further limit these settlements. The effect of the settlement on the piping should also be carefully examined. Special piping and pipettings are available that should be used when exibility in the system is required. Settlement of foundations bearing on rock is not a concern as long as all individual footings bear on rock. However, the rock layer must be thick and strong enough to support the loads without being crushed (as might be the case with a rock lens). The designer should be very cautious of situations in which the foundation bears partly on rock and partly on soils, as high differential settlements can result.
Pile Foundations
When the bearing soils are weak or prone to excessive settlements, deep foundationsof which one type is the pile foundationare necessary. Piles transfer the structural loads deep into the stronger
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
Foundations
underlying soil strata or rock formations. They also transfer the lateral loads to the surrounding soils and maintain lateral stability. Given the complex nature of the resisting soils, competent advice from a qualied geotechnical engineer should always be sought on the basis of a thorough subsurface investigation to assess the appropriate pile type, length, and other characteristics necessary for design. Pile foundations consist of long, slender structural members that are either driven into the soil or poured in place after drilling. Whether a pile develops its capacity from end bearing or side friction depends on how deep it is embedded and on the properties of the soils surrounding it. Piles driven to and bearing on hard rock or very dense layers of soil are primarily end bearing, as they axially transmit the loading to the bearing strata. Piles driven to shallower depths and not resting on hard and dense layers transmit the loading mainly by skin friction and, hence, are referred to as friction piles. Generally, piles develop resistance through a combination of both end bearing and skin friction. The resistance varies on the basis of the pile length and the relative density and consistency of the soil layers. The lateral capacity of the pile is a function of the soil characteristics near the surface. A simulation technique called beam on elastic foundation can be used to assess the lateral resistance capacity of the pile. The spring constant necessary for the evaluation can be determined from the elastic or shear modulus of the soil. Pile lateral load is also a function of the exural capacity of the pile itself. Professional advice must be sought in determining pile lateral capacities and load-displacement characteristics.
189
Pile Types
Piles can be driven or cast in place. Available driven pile types include timber, precast, prestressed concrete, steel pipe, and H-piles. All have certain advantages and disadvantages. Where the resulting vibrations from pile driving can be a problem, cast-in-place piles may be more suitable. Auger-cast piles, drilled piers, or caissons are alternatives often preferred over pile driving because of their lightweight equipment. Although pile selection depends on many factorsamong them cost, availability, and load test requirementsthere are advantages to using a particular pile type for a given job. The common pile types are listed in Table 5-2 (ASCE 1993b). The main disadvantage associated with timber piles is the difculty of achieving a high-strength connection between the pile and the pile cap. Similarly, prestressed-concrete piles can pose a challenge in achieving uplift connection. Dowels can be embedded into the pile head for transfer of tensile load, but because of physical space
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
190
Chapter Five
Type of Pile Timber piles Description
Best suited for short-embedment, low-capacity, and low-cost applications. They are also appropriate for application in regions with corrosive groundwater. Timber piles are difcult to splice and very susceptible to decay if untreated. Precast concrete Usually prestressed, these durable and corrosive-resistant piles are well suited for higher capacities. Although precast concrete piles are available in long lengths, splicing them is difcult and can be a problem because water tank foundations resist signicant tensile (uplift) and lateral loads. Steel pipes Open- or closed-ended steel pipes pose some difculties in driving but offer high-resistance capacity, especially when lled with concrete. Steel pipe piles are well suited for splicing, but they do have the potential for corrosion. H-piles Available in a wide variety of sizes and lengths, H-piles can be driven easily and spliced rather conveniently. They offer high axial load carrying capacity and exural bending resistance. Corrosion can be a problem, as with all steel, which can be alleviated with preventive measures.
Source: ASCE 1993b.
constraints, developing a connection for moment transfer can be difcult for smaller piles.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
Foundations
that must be interpreted. (The latter approach is not preferred.) The recommendations may also include options for other pile types and capacities for exibility in design. A piles load-carrying capacity depends on its type, size, and depth of penetration. Geotechnical consulting engineers also provide pile lateral and uplift capacities, a centerto-center spacing recommendation, and anticipated settlement under the governing loads. The minimum center-to-center spacing should be at least three times the diameter or side dimension of the pile for end-bearing piles but larger for friction piles, especially when many piles have been driven in a group. Pile capacity may be limited either by the piles internal structural capacity or by the external capacity offered to it by the resisting soils. For the pile to be able to furnish the full resistance offered by the surrounding soils, the internal capacity must exceed the external capacity. Pile capacity is basically determined on the basis of an approved pile-driving formula, wave equations, or load test methods. IBC-2006 limits the allowable compressive load on any pile to 40 tons (356 kN) when it is determined on the basis of a driving formula alone. For allowable loads above 40 tons (356 kN), it recommends the use of the wave equation method of analysis and verication of this allowable load by a load test in accordance with ASTM D1143 Test Methods for Piles Under Static Axial Compressive Load and ASTM D4945 Test Methods for High-Strain Dynamic Testing of Piles. Similarly, IBC-2006 provides criteria for allowable frictional resistance and uplift capacity. IBC-2006 and/or ASCE 7-05 provide detailed criteria for longitudinal-reinforcement and transverse-connement reinforcing steel for precast, prestressed piles as a function of site class and seismic design category. ACI 318-05, in its Chapter 21, also provides design criteria for piles, pile caps, and foundations that resist earthquakeinduced forces. The ultimate capacity of a pile that derives its resistance from both the side friction and the end bearing is given by QUltimate = QSide Friction + QTip Bearing (5-15)
191
The evaluation of Q depends on whether the pile is driven in sand or clay. Refer to any textbook on pile foundations for appropriate methodologies for determining pile capacity. AWWA D100 requires a minimum FS of 2.0 for gravity loads and an FS of 1.5 for gravity loads plus wind or seismic loads. Other references dene factors of safety on the basis of whether load tests have been performed. Various theoretical pile-driving formulas can be used to estimate pile load-carrying capacity. These formulas do not correlate well with test results and are historically inaccurate. However, they are helpful in establishing when to stop driving a pile to achieve a capacity
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
192
Chapter Five
equivalent to that of the load test. The reader is once again referred to a textbook on pile foundations (Prakash and Sharma 1990). The equation that is often used by the industry is known as the EngineeringNews formula (Liu and Evett 1987): Qa = or Qa = where Qa Wr H S C = allowable pile capacity (lb [kN]) = weight of ram (lb [kN]) = height of fall of ram (ft [m]) = amount of pile penetration per blow (in./blow [mm/blow]) = 1.0 for drop hammer; 0.1 for steam hammer (25 or 2.5) 1000 Wr H 6( S + C ) (in SI units) (5-17) 2Wr H S+C (5-16)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
Foundations
for the job. Also, the pile-driving techniques on test piles must be the same as those that will be used for the production piles. For foundations for elevated water tanks, the most common method of testing piles under static axial compressive loading is that performed under ASTM 1143. But this method is costly and requires a minimum waiting period of 7 days for piles in granular material and 14 days for piles in cohesive soils for dissipation of excess pore water pressure after test pile installation and before load testing begins. More recently, the use of PDA is gaining much acceptance over the static load tests in view of its fast pace and the more quickly available resulting data. PDA is also used to assess pile capacity and pile stresses from measurements of the applied force and acceleration at the head. Refer to ASCE 1993b and ASCE 7-05 for further details.
193
Auger-Cast Piles
Auger-cast piles are piles that are installed by pumping grout under pressure into holes drilled to required depth by continuous-ight, hollow-stem augers. The common diameters of these piles range from 12 to >30 in. (30 to >76 cm), with lengths from 50 to 100 ft (15 to 30 m) and compressive capacities that can exceed 125 tons (1 MN). Augercast piles are reinforced by inserting a single reinforcing bar and/or a reinforcing cage through the unset grout. The cage extends to a dened length based on the structural requirements of the pile in resisting tensile, compressive, and lateral loading. The single reinforcing bar at the center of the pile typically continues to the bottom end of the pile. The grout mostly consists of portland cement, sand, and water.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
194
Chapter Five
Where vibrations due to pile driving can cause damage to other structures or entities in the near vicinity of the job site, auger-cast piles offer a better alternative. As with all other piles, pile axial load tests are performed in accordance with ASTM 1143. Pile installation records are maintained as required. More information on these piles can be found in the Augered Cast-in-Place Piles Manual prepared by the Deep Foundations Institute (DFI 1990).
Foundations
Foundations
S
195
Four piles
Five piles
Six piles
S S
Nine piles
FIGURE 5-7 Typical pile group patterns for single foundations. (S = spacing between piles.)
itself can cause an increase in the number of required piles. Figure 5-7 provides typical pile layouts for four-, ve-, six-, and sevenpile footings. Pile caps must accommodate pile spacing as well as edge distance requirements. The pile cap edge distance, measured from the centerline of the outer piles to the edge of the pile cap, is generally a function of the pile diameter. Typically, for piles with a diameter of about 1 ft (30 cm), a distance of 1 ft. 3 in. (38 cm) is used. The thickness of the pile cap should be checked for punching shear caused by piles exterior to the critical section. The critical section is taken to be at a distance of d/2 from the pedestal, where d is the current depth to centroid of tensile steel in the pile cap. The punching shear should also be checked around the individual piles at a critical section taken a distance d/2 from the face of the pile, and the pile cap thickness should be adjusted, if necessary. The pile cap thickness is also dependent on exural shear both tangentially and radially at a distance d from the face of the pedestal. Flexural reinforcement, in both the tangential and radial directions, should also be checked at the faces of the pedestal. The exural reinforcement determined should then be compared against the minimum exural reinforcement requirements of ACI 318-05 Section 10.5.1 and adjusted, if necessary. IBC-2006 provides specic criteria for pile connection to the pile cap. For prestressed piles, uplift anchorage to pile cap can be achieved
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
S
S
Foundations
196
Chapter Five
by exposing and developing the reinforcing strands at the top of the pile. This approach, however, is not permitted by other model codes in areas of high seismic risk. IBC-2006 permits the option, provided that the reinforcing strand results in a ductile connection. As an alternative, reinforcing dowels can be grouted into the top of the pile. In timber, steel, or pipe piles, a reinforcing bar can be inserted through the member and bent upward into the pile cap. The pile cap must be thick enough to accommodate the anchoring mechanism. Refer to Figures 5-8a and 5-8b for typical pile foundations.
Centerline of foundation
Radial centerline
Centerline of foundation
Dowels Hoops
Aggregate
Radial bars
(a)
FIGURE 5-8a Typical pile foundations: typical pile foundation for a single column
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
Foundations
Prestressed, precast concrete piles
197
or d
Exposure
Hoops Hoops (special Verts. top bars) Typical uplift anchor Radial bars Hoops
Radial bars Reinforced concrete Hoops thrust Prestressed block concrete piles
(b)
Section A-A
FIGURE 5-8b Typical ring-tee pile foundation). (Verts. = vertical reinforcement dowels.)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Ch
Ch
or
Foundations
198
Chapter Five
The pedestals for pile foundations are usually compressive elements with a ratio of unsupported height to least lateral dimension not exceeding 3.0. As noted in the section on shallow foundations, although ACI 318-05 Section 15.8.2.1 recommends a minimum reinforcing ratio across the interface (between the pedestal and footing) of 0.5 percent of the gross area of supported member (i.e., the pedestal), a smaller reinforcement ratio can be justied for the tower column pedestals due to their large size. For taller pedestals, the 0.5 percent reinforcement ratio should be maintained. However, the reinforcement furnished must be sufcient to meet the requirements for uplift as well as exural requirements necessitated by the lateral shears on the pedestal.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
Foundations
There are many advantages to using drilled piers for water tank foundations. Because of its size and capacity, a drilled pier can replace a group of piles and eliminate the need for a pile cap. Installation of drilled piers does not generate much noise or vibration, as pile driving does, and drilled piers can be set up in hard-to-access places. A primary advantage of drilled piers is that they can sustain large axial loads with minimal settlement when bearing on bedrock.
199
Qu = Qbu + Qsu Wp where Qu Qbu Qsu Wp = pier ultimate resistance (kip [kN]) = pier ultimate end-bearing resistance (kip [kN]) = pier ultimate side friction resistance (kip [kN]) = pier dead weight (kip [kN])
(5-18)
An FS of 3.0 is applied for allowable-stress design application. Some references may apply an FS of only 2.0 on the ultimate resistance due to side friction Qsu in service-load design application. Others may also apply a load factor on the shaft dead weight Wp . Refer to Fig. 5-9 for a typical belled, drilled pier conguration. A very useful and relevant reference on drilled piers is a report entitled Drilled Shafts: Construction Procedures and Design Methods, issued by the US Department of Transportation, Federal Highway Administration (Reese and ONeill 1988). This reference provides detailed analysis and design, fabrication, and quality control criteria for drilled-shafts foundations. The Bearing Capacity of Soils, prepared by the American Society of Civil Engineers (ASCE 1993a), is another source for criteria regarding analysis and design of drilled shafts.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
200
Chapter Five
Axial load Lateral load Additional reinforcement, if required Exposure
Hoops
Diameter depends on loading and depth of excavation Depth can vary per design Qsu side resistance
Reinforcing steel WP
Bellmay be used when required. Size variesno larger than three times shaft diameter at base. Underream angle is 45 or 60 typically.
FIGURE 5-9 Typical drilled shaft. (Wp = pier dead weight; Qsu = pier ultimate side friction resistance; Qbu = pier ultimate end-bearing resistance) (Source: Reese and ONeill 1988.)
shear resistance offered by sands or cohesionless silts, however, is a function of the soil angle of internal friction. The resistance capacity offered by side friction can be very signicant. For piers socketed into bedrock, it is possible that the entire resistance capacity is emanating from the side resistance furnished by the socket. It is a recommended practice within the drilled-pier design community to ignore the contributions of side friction and passive resistance in the top 5 ft (1.5 m) or 1.5 diameters of the shaft when
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Base resistance
Q bu base resistance
Foundations
Foundations
evaluating lateral stability. The reason is that lateral movement by the pier causes a wedge of soil to move up and out, resulting in a loss of side friction and passive resistance. Similarly, in clay soils, the side friction in the periphery of the bell or the bottom of the straight pier within 1 diameter of shaft length is ignored in determining the resistance capacity of the pier. The reason is that movement of the base of the pier can result in the development of a tensile crack in the soil, which in turn can cause a lateral stress at the base of the pier and, consequently, a reduced load transfer in side friction (Reese and ONeill 1988).
201
Design of Piers
The diameter of the pier is a function of the soil characteristics within the prole, the location of the water table, and the presence of lateral loads and/or moments. The design of the concrete mix and its strength are also of critical importance. The geotechnical prole of the soil dictates not only how far down to extend the pier, but also the method of construction to be employed, the need for casing and/or dewatering, and the need for under-reaming. Special characteristics of soilsshrinking/swelling of plastic soils, occurrence of boulders, remains of abandoned footings, presence of debris or other unsafe materials, and so onall require that certain measures be taken into full consideration. Aside from the basic structural design, the most important consideration is the amount of the expected settlement of the pier foundation and its effects on the elevated water tank system. Under-reaming, where possible, helps increase the pier bearing surface and consequently the bearing resistance. Under-reaming can also be used interchangeably with socketing where required. The longitudinal reinforcement for drilled shafts depends on the many factors noted previously, but as a minimum, industry practice has been to provide at least 0.5 percent of the cross-sectional area and at least six bars, forming a cage of equally spaced bars. This minimum is actually based on ACI 318 Sections 10.8.4 and 10.9.1. Section 10.9.1 requires a minimum reinforcement of 1 percent. For regions of low-to-moderate seismic risk, Section 10.8.4 states that, for compression members with cross-sectional areas larger than required by consideration of loading, it should be permissible to base the minimum on a reduced effective cross-sectional area not less than half the total area. Additional reinforcement may be required where heavy tensile loading or bending moments are present. The longitudinal reinforcement cage may extend a partial depth or the full length of the pier when required. Hoop or spiral reinforcement is also used for drilled shafts. Hoops are more economical, but from a performance standpoint spirals are preferred. Figure 5-10 illustrates pier reinforcement.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
202
Chapter Five
Tiesspacing as per ACI 318 Sections 7.10 and 7.11. Refer to ACI 318 Chapter 21 for special provisions for seismic design.
Length of cage depends on lateral design requirements and may not require extending to full length. Extend cage to full length in highly plastic (expansive) soils.
In regions of high seismic risk, special reinforcement requirements may also apply, including connement steel near the interface regions with the pedestal or grade beams. Refer to ACI 318-05 Chapter 21 for special provisions in seismic design. Where belled bottoms are needed, the base diameter is generally limited to less than three times the shaft diameter. The under-ream angle is typically in the range of 45 degrees to 60 degrees, with 60 degrees often used for water tank foundations. Also, a toe height of about 1 ft (30 cm) is maintained at the base.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
Foundations
be adequate for uplift stability. But when the loads are severe, belled, or under-reamed, piers are necessary. Detailed criteria on the stability of drilled piers and a discussion on the potential collapse of the bell in loose soils during construction can be found in the study by Reese and ONeill (1988).
203
Load Testing
A clear way of establishing the structural integrity of a drilled pier is by load testing. However, due to the high costs and logistical difculties associated with the arrangement of reaction shafts, such testing is rarely performed. If it is absolutely necessary that a load test be
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
204
Chapter Five
performed, the pier (as with piles) must be able to sustain without excessive settlement a load that is at least twice the working load. The best way to ensure the structural integrity and intended performance of drilled piers is to follow a credible quality control program of inspection and installation procedures. Recent studies have shown that minor construction aws that may not be detectable by common nondestructive evaluation methods can lead to signicant capacity reduction in drilled piers. Such aws include the presence of small voids, soil inclusions, misaligned cage or other reinforcement steel, weak concrete, or corroded reinforcing bars. Refer to Sarhan et al. (2004) for further details.
Settlement
Settlement concerns associated with drilled piers are similar to those dened for piles. Typically, if the drilled pier is bearing on or socketed into the bedrock, settlement caused by direct loading is negligible. Under other installation conditions, it is important that a proper settlement analysis be performed by the geotechnical engineer to ensure that the expected settlements are tolerable from operations and performance perspectives and from the standpoint of structural design.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
Foundations
205
Berm
To drain away
1 1
Slab Foundation
Where the bearing soils are strong or when the water tank capacity is small, at-bottom tanks can be supported by a mat or slab foundation. The slab is uniformly loaded by the pressure head in the tank. The resulting bearing stress under the slab is the pressure due to the weight of the tank and its contents added to the uniform pressure caused by the thickness of the concrete slab. Overturning moment resulting from wind or seismic loading also contributes to the bearing stress. The reinforcement requirements of the mat or slab foundation are based on the loading and deformation characteristics of the footing. Often the minimum reinforcement requirement dened by ACI 318-05 will control. Anchorage and stability requirements should be investigated when the tank is full and when it is empty. Slab exterior edges supporting the tank wall may be thickened, if necessary, to accommodate the additional bearing stress caused by wind or seismic overturning moments. Consideration should also be given to the frost depth in determining slab thickness and bearing elevation.
Ringwall Foundation
As discussed in the section on shallow foundations, ringwall foundations are used when the bearing pressure under the tank shell exceeds the allowable bearing pressure of the soil near grade. The ringwall carries the loads deeper and distributes the pressure over a wider area. When the overturning moments are severe and anchor bolts are required for stability, a ringwall foundation best accommodates these anchorages. The design must consider hoop stresses caused by the internal soil pressure resulting from the weight of the tank and its contents.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
206
Chapter Five
Deep Foundations
Where the bearing soils are weak or the settlements are excessive, at-bottom tanks require deep foundations. Driven piles and augercast piles are typically used under at-bottom tanks. In regions of high seismic risk, special reinforcement requirements also apply, as is discussed subsequently in this chapter.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
Foundations
207
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
208
Chapter Five
forces may also be taken into consideration, in the authors view. Some codes specically disallow this, but for water tanks it is justied since nearly the entire mass is considered effective in the formation of all seismic loads, including the seismic overturning moments. This must be done with attention to signs (load direction), since a column under uplift cannot generate frictional resistance.
Bolt Interaction
Interaction can be checked by means of a simple equation. For the combined effects of tension and shear, the following linear interaction equations may be used in design: T V + 1.33 Tallowable Vallowable T Tseismic-allowable where T = tensile load V = concurrent shear load on bolt The allowable tensile and shear stresses are as dened previously for mild steel. For other types of steel anchors, refer to AWWA D100 or other applicable codes for all allowable stresses. If high-strength or stainless-steel bolts are required, D100 allowable tensile stress for these bolts is based on the lesser of 0.4 times the minimum published yield stress or 0.25 times the published tensile strength. The calculated bolt size may need to be adjusted when corrosion allowance is required in design. AWWA D100 discourages the use of J and L bolts because of their tendency to straighten out, as observed in pull-out tests. Quality control in placement of bolts is essential. Given the size and embedment length required, bolt relocation may not be possible, and remedial measures can be expensive. Therefore, proper bolt placement, including correct embedment and projected length, is critical to proper design. + (wind) (5-19)
V 1. 1.33Vallowable
(seismic)
(5-20)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
Foundations
combinations. Refer to ACI 318-05 for determination of A2 and A1 areas.
209
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
210
Chapter Five
the appropriate seismic use group (I, II, or III). All structures having SDS 0.5g or SD1 0.2g (where g is the acceleration of gravity) are assigned an SDC of D. Also, seismic use group III structures with 0.33g SDS < 0.5g or 0.133g SD1 < 0.2g are assigned an SDC of D. Seismic design category E is assigned to seismic use group I and II structures located on sites with mapped maximum considered earthquake spectral acceleration at 1-second period S1 equal to or greater than 0.75g . Similarly, seismic use group III structures at these accelerations are assigned an SDC of F. Structures assigned to categories C, D, E, or F require special attention to quality assurance during construction. Structures assigned to category E or F are prohibited from being sited where there is a known potential for an active fault. The seismic importance factor IE signicantly affects seismic design. (This factor is dened in ASCE 7-05 Section 11.5.1, Table 11.5-1.) Values of the importance factor range from 1.0 to 1.5, depending on the seismic use group category assigned to the elevated water tank system. AWWA D100-05 assigns a default value of 1.5 to IE unless otherwise specied by the purchaser, but it allows the use of 1.0 for systems not supplying water for re protection.
Reinforcement Criteria
In regions of high seismic risk, ACI 318-05 requires structures to comply with requirements dened in Sections 21.2 through 21.10. These sections dene maximum and minimum exural and transverse reinforcement, maximum spacing for hoops and crossties, bar development length, and other requirements. Section 21.10 provides criteria for the design of foundations. Footings, mats, piles, pile caps, piers, and caissons are all required to be designed under this section. ASCE 7-05 refers to ACI 318-05 for design and construction of concrete foundations assigned to seismic design categories D, E, and F. ASCE 7-05 requires individual pile caps or drilled piers in these categories, as well as in category C, to be interconnected by ties. Likewise, spread footings founded on site class E and F soils are required to be interconnected by ties. The design strength for ties in tension or compression is required to be greater than 10 percent of SDS times the larger pile cap or column factored-dead plus factored-live load, with some exceptions. There are also rigorous requirements for the design of piles in site class E and F soils.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
Foundations
spiral reinforcement, denes the ductile region of the pile as a function of its length, and establishes bounds for the center-to-center spacing of the spirals or hoop reinforcement. Similarly, IBC-2006 also establishes criteria for the design and detailing of cast-in-place pile and pier foundations. The IBC-2006 requirements are very similar to the ASCE 7-05 requirements. Either reference can be used as required, individually or in conjunction with ACI 318, in designing elevated water tank foundations.
211
Foundation Stability
Design for stability is critical in regions of high seismic activity. Foundations must be designed to withstand all design loads with adequate factors of safety. Foundations must also be stable against all forces causing uplift, lateral sliding, and overturning. The safety factors required for stability and strength are dened in various ways by different codes. It is important to appreciate the reasoning and philosophy associated with these factors to ensure structural integrity, safety, and stability. Lateral stability in saturated soils, settlement evaluation in saturated or high-moisture-content silty soils, and potential liquefaction in sandy soils are all conditions that require competent evaluation and assessment before elevated water tanks are built on sites with these characteristics. Piles designed for xity at the pile head must be properly connected to or embedded deep into the pile cap to develop uplift and moment capacity. Backll around spread footing and pile foundations must be consistent with the geotechnical engineers recommendations. Special recommendations made in terms of moisture content, maximum loose lifts, or soil remediation measures must be followed. All nonconforming conditions must be brought to the attention of the engineer of record for evaluation and disposition.
Special Considerations
Design of elevated water tank foundations requires close coordination with the project geotechnical engineer and with the construction team at the job site. All parties must clearly understand the design requirements and must appreciate what is essential to quality design and construction. Structural engineers must not assume that all geotechnical requirements dened in the subsurface evaluation report will be routinely implemented during construction. In todays fast-paced construction, it is not unusual to see the forms removed the following day, or long before the concrete has achieved its specied 28-day compressive strength f c . Backll placement could be started immediately
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
212
Chapter Five
thereafter. Therefore, the engineer of record (EOR) must be specic in dening any special design and construction, including formwork, requirements. Thus, as the concrete strength and backll procedures are critical to the various phases of construction, strict quality control measures must be put in place to ensure that the correct concrete strength is achieved before any backll activities commence. Site inspection and testing will be necessary to ensure proper compaction or soil remediation. It is possible that the site soils are unsuited for backll, and so suitable soils must be imported. It is also possible that topsoils containing organics and other deleterious material could get mixed with other site soils during backlling around the footing. Some states have dened certain soils or soil mixtures as select lls that are recommended for specic structural lls or backll. All of these issues are important in foundation design, and the necessary quality control steps should be taken before starting any construction activity.
Backll Compaction
Geotechnical engineers generally specify compaction in terms of maximum thickness of loose lifts and standard proctor maximum dry density unit weights per ASTM D698 or modied proctor maximum dry density tests per ASTM D1557 (see Annual Book of ASTM Standards). These requirements are usually specied to be 95 to 98 percent of the maximum dry density; even higher percentages are specied for subgrade compaction. Soil compaction is accomplished by the use of hand tampers and sheepsfoot or pneumatic rollers.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
Foundations
Backll compaction not only improves lateral and uplift stability by improving soil shear strength, but it also reduces permeability in cohesive soils. In cohesionless soils, surface drainage must be accomplished by proper grading to avoid basin or boat effects around foundations. A typical compaction note reads:
Backll material should be placed in 6 to 8 in. maximum loose lifts and compacted to at least 95% of the Standard Proctor maximum dry density (ASTM D698).
213
As a rule, for water tank foundations, a minimum unit weight of 100 pcf (15.7 kN/m3 ) should be achieved. Rock fragments and stones larger than 3 in. (7.5 cm) in diameter should not be used in the vicinity of the footings. Any soft or loose material should be removed from the bearing areas before concrete is placed. Thus, it is recommended that a geotechnical representative be present before and during the pouring of the foundations as well as during placement of backll.
Shrink/Swell Soils
Expansive soils and challenges associated with shrink/swell soils were discussed earlier in the chapter in the section on design considerations in plastic soils. Expansive soils are generally plastic clays, also known as fat clays, that swell with increases in moisture content.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
214
Chapter Five
FIGURE 5-12 Typical foundation in shrink/swell soils. (Uw = vertical uplift due to wind; Us/w = vertical uplift due to shrink/swell.)
They are classied as CH clays in the ASTMs Unied Soils Classication Chart. The depth of the expansive soil active zone can vary from a few feet or less than a meter to perhaps more than 15 ft (5 m). Foundations constructed in these soils can potentially be subjected to very large uplift and possibly destabilizing forces if they are not designed properly. Refer to Fig. 5-12 for a typical foundation in plastic zone with an effective active zone of 12 ft (3.7 m).
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
Foundations
The plasticity index (PI) is generally used as a measure of swell potential in plastic soils. Soils with low swell potential are those with PI values below 25; a PI value of 25 to 35 indicates moderate swell potential; PI values exceeding 35 correspond to soils with very high swell potential. Foundations for elevated water tanks sited on soils with low swell potential can be constructed using the standard practices, but foundations sited on soils with PI values exceeding 25 (see ASCE 7-05 or IBC-2006) require precaution, remedial action, and special design considerations (Das 2006). Typically, when placing foundations in plastic soils, geotechnical engineers recommend bearing the footing deep in nonplastic soils or below the active zone. To mitigate the effects of the uplifting forces, the use of select structural ll and backll, soil stabilization with lime, and/or inclusion of clearly dened uplift forces in the design have been recommended. Das (2006) provides recommendations for remedial measures as well as a procedure for estimating the uplift forces caused by the swelling forces. Typical remedial options often recommended for shallow footings include the following: 1. Bear the footing below the active zone and replace the backll with select structural ll. 2. Bear the footing in the active zone, replace 3 to 5 ft (0.9 to 1.5 m) of soil below the footing with select structural ll, and use select structural ll for backll. 3. Use site soils for backll, but ensure that soil moisture content is greater than the plastic limit and that the moisture content is 3 to 5 percent above the optimum moisture. 4. Use a polyethylene or bitumen material on the vertical faces of the footing. 5. Same as point (2), but use site soils for backll with lime mixing. 6. Same as point (1) or (2), but use site soils for backll, and consider the uplifting forces in the design of the footing and in its stability. Use J-voids where necessary to allow room for the soil to swell without imposing any forces on the foundation element. 7. In soils where piers are recommended, geotechnical engineers should recommend belled piers, with emphasis on the reinforcement requirements for resisting the uplift forces at the junction of the shaft and the bell. In summary, when site soils involve clays prone to swelling, specic geotechnical guidance must be sought. The geotechnical report
215
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
216
Chapter Five
must clearly dene the active zone, the potential for swell, uplift, or adhesion forces that need to be considered in design, the bearing depth at which the foundations are to be placed, and suitability of site soils for backll or recommendations for imported soil. If imported soils are to be used for backll, clear criteria must be provided regarding the nature of the soil, its Atterberg limits, compaction requirements, and guidance on local availability of the recommended soils.
Conclusion
Foundations are critical to the design, construction, operation, and performance of welded-steel tanks for water storage. Therefore, foundation design and construction require attention to detail and proper understanding of all criteria and requirements. Sites that are relatively dry, level, and easily accessible and that have good soils properties are ideal locations for erecting elevated water tanks. The suitability of sites must always be established by a qualied geotechnical engineer. Grade elevations and site boundaries must be established carefully to achieve the proper overow and foundation elevations. Geotechnical investigation reports must provide all the necessary information for design. This includes detailed soil properties and other characteristics dened in this chapter. Certain soils exhibit shrink/swell or other characteristics that require extra measures and precautions in design. All of these characteristics must be clearly dened and appropriately addressed in the report. Site classication and settlement evaluation must also be included in the geotechnical report. Generally, isolated spread footings or shallow foundations are the most economical foundation type when suitable to site conditions. Otherwise, deep foundations are necessary. Detailed criteria are provided herein to assist the designer in selecting the most suitable foundation type and to assist the designer with the design, be it shallow footings or deep foundations using piles and drilled piers. In regions of high seismic activity, special design requirements apply that must be incorporated into the foundation design. Both the logic and philosophy for these requirements are explained in this chapter, and further resources are provided in the bibliography at the end of the chapter. Requirements for the quality control, mixing, placing, nishing, and curing of concrete have also been dened here. These requirements are critical, as they govern the strength, durability, and workability of concrete foundations. Also, criteria have been introduced
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
Foundations
for sizing anchor bolts and for allowable bearing capacity under base plates. Requirements for backll compaction and lateral and uplift stability are dened. It is further emphasized that to ensure safety, all excavations must be performed in full compliance with the latest OSHA construction standards.
217
Assume the live load to be zero, and assume that the wind load has been reduced by a directionality factor so that the 1.6 load factor applies. Use a net allowable bearing pressure of 3,000 psf (144 kPA) at a minimum embedment depth of 5.5 ft (1.68 m) below existing grade and a concrete compressive strength f c of 4,000 psi (27.58 MPa). Assume the pedestal to be 4 ft 4 ft (1.2 m 1.2 m) with a 1-ft (0.3-m) projection above grade. Refer to Fig. 5-13.
Footing Design
Step 1: Governing Load Combinations
The load combinations were dened in Equations (5-1) through (5-7). A quick examination of these equations reveals that only load combinations (5-1), (5-4), (5-5), and (5-6) are governing. After simplication, these equations are as follows:
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
218
Chapter Five
U V Grade Footing exposure
Embedment depth
Punching shear
Footing width B
Vertical Loads U 1 = 1.4 ( D + F ) U 4 = 1.2 ( D + F ) + 1.6 W + 0.5 S U 5 = 1.2 ( D + F ) + (1.4 1.0) E + 0.2 S U 6 = 0.9 D + 1.6 W Corresponding Horizontal Loads V1 V 4 = 1.6 W S = 1.6 30 V 5 = (1.4 1.0) E S = (1.4 28) V 6 = 1.6 W S = V 4
= = = =
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
Foundations
Required footing area: AWind = 662 kips = 220 ft2 3000 psf (governs)
219
ASeismic =
AWind governs and a square footing of 15 ft 15 ft (4.6 m 4.6 m) provides the required bearing area. The net bearing pressure at the toe of the footing is f bearing-Wind = 30 kips 6.5 ft + 152 ft2 (15 152 /6) ft3 = 3,290 psf < 4,500 psf (using FS = 2.0) 662 kips 699 kips 152
3
f bearing-Seismic =
ft (15 152 /6) ft3 = 3,430 psf < 4,500 psf (using FS = 2.0)
28 kips 6.5 ft
Although the increase in the net overbearing pressure resulting from the differential weight of concrete is not yet accounted for, the initial size selected is reasonable.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
220
Chapter Five
d 2
(a)
Footing width B
Footing width B
Pedestal width pw
(b)
(B pw) d 2
FIGURE 5-14 Design shear and bending moment evaluations: (a) punching shear, (b) exural shear, and (Continued)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Footing width B
Foundations
Foundations
Footing width B
221
Pedestal width pw
(c)
(B pw) 2
The nominal punching shear capacity as per ACI 318-05 Section 11.12.2.1 is Vc = 4 f c .b 0 .d = 4 3, 500 260 17 = 1,046 kip
Here, f c is reduced by 500 psi (3.45 MPa) for reasons described in the section on structural concrete. Assuming no contribution from slab reinforcement, using a shear reduction factor of 0.75 as per ACI 31805 Section 9.3.2.3, the nominal punching shear capacity is Vn = 0.75 1,046 = 784 kip The punching shear caused by U 5 is Vu = 882 kips 152 ft2 [152 ft2 (4 + 1.42)2 ft2 ) = 767 kip
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Footing width B
Foundations
222
Chapter Five
Since V n is greater than V u kip, a slab depth d of 17 in. (43.2 cm) satises punching shear requirements.
pw
W3 (soil)
W1 (Concretepedestal)
W2 (Concreteslab)
pw
2
d+ pw
2
B/2
FIGURE 5-15 Flexural shear and bending moment evaluation. (psf = pounds per square foot, kPa = kilopascal.)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
Foundations
the factored wind and seismic load combinations are as follows: f bearing-Wind = 48 kips 6.5 ft = 3.79 0.55 152 ft2 (15 152 /6) ft3 = 4,347 (psf) maximum < 9, 000 psf (ultimate bearing) = 3,238 (psf) minimum f bearing-Seismic = = 3.92 0.45 ft (15 152 /6) ft3 = 4,370 (psf) maximum < 9,000 psf (ultimate bearing) = 3,470 (psf) minimum 152
3
223
39 kips 6.5 ft
The bearing stress due to seismic loading governs. From Figs. 5-14b and 5-15, the bearing pressure at a distance d from the face of the pedestal is f bd = 3, 920 + (2 + 17/12) (450) = 4, 125 psf (15/2)
The resulting exural shear at the same location is VFlex = (15 4) 17 1 (4, 125 + 4, 370)(15) = 260 kip 2 2 12
The exural shear capacity of the footing slab as per ACI 318-05 Section 11.3.1.1 is Vcf = 2 3, 500(15 12)(17) = 362 kip Vnf = 0.75 362 = 272 kip Since Vnf > VFlex , the 17-in. (43.2-cm) depth selected is adequate for shear.
(15) +
2 15 4 3 2 Mu = 967 ft kip
(15)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
224
Chapter Five
Determine the reinforcement needed to carry this bending moment. The minimum reinforcement required as per ACI 318-05 Section 10.5.1 is (200)(15 12)(17) A s, min = = 10.20 in.2 (60,000) Try a steel area of 14.0 in.2 (PCA 1999): 14 = 4.58 103 (15 12)(17) fy Mn = A s f y d 1 0.59 fc = Mn = (0.9)(14)(60)(17) 1 0.59(4.58 103 ) Mn = 1,021 ft kip Mn > Mu Therefore, fourteen no. 9 bars each way, 14.5 ft (4.42 m) long, will sufce. 60 3.5
This stress is less than the concrete modulus of rupture f r where, as per ACI 318-05 Section 9.5.2.3, f r = 7.5 3500 = 444 psi As per ACI 318-05 Section 11.5.6.1, assuming a 3-in. (7.62-cm) cover for the pedestal dowels, since 0.5Vc = 0.5(0.75)[2 3500(48)(45)] = 96 kip > U6 = 48 kip,
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
Foundations
no shear reinforcement is needed. However, since the dowels will be in compression due to the other load combinations, No. 4 ties at a spacing of 12 in. (30.5 cm) on center are recommended.
225
Other Steps
The anchor bolts should be designed for tension and shear interaction. Lateral stability should be checked on the basis of the active and passive pressures and the cohesion, if any, of the backll soils. Backll compaction is a function of the stability requirements. A compaction to 95 percent standard proctor maximum dry density, as discussed in this chapter, may be recommended. The embedment depth can be adjusted, if necessary, to achieve additional passive resistance. Refer to Fig. 5-16 for the reinforcing details. Note that, in general, strain compatibility must be checked to ensure that a balanced condition prevails and that the footings are not over-reinforced. Also, note that a nominal top mat reinforcement can be added as required for uplift or shrinkage control.
1 ft (0.3 m)
5.5 ft (1.65 m)
16 #8 dowels No. 5'Snominaleach way (only if required for uplift or shrinkage control) 20 in. (508 mm)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Foundations
226
Chapter Five
Bibliography
American Institute of Steel Construction (AISC). 1989. Manual of Steel Construction, Allowable Stress Design. 9th ed. Chicago: AISC. American Petroleum Institute (API). 2008. Design and Construction of Large, Welded, Low-Pressure Storage Tanks, 11th ed. API Standard 620. Washington, D.C.: API. American Society of Civil Engineers (ASCE). 1993a. Bearing Capacity of Soils. Technical Engineering and Design Guides as Adopted From the U.S. Army Corps of Engineers, No. 7. New York: ASCE Press. American Society of Civil Engineers (ASCE). 1993b. Design of Pile Foundations. Technical Engineering and Design Guides as Adopted From the U.S. Army Corps of Engineers, No. 1. New York: ASCE Press. Bowles, J. E. 1995. Foundation Analysis and Design. 5th ed. New York: McGrawHill. Das, B. M. 2006. Principles of Foundation Engineering. 6th ed. Florence, KY: CL Engineering. Deep Foundations Institute (DFI). 1990. Augered Cast-in-Place Piles Manual. 1st ed. Englewood Cliffs, NJ: DFI. Kosmatka, S. H., and W. C. Panarese. 1990. Design and Control of Concrete Mixtures. 13th ed. Skokie, IL: Portland Cement Association. Liu, C., and J. B. Evett. 1987. Soils and Foundations. 2nd ed. Englewood Cliffs, NJ: Prentice-Hall. National Earthquake Hazards Reduction Program (NEHRP). 2003. NEHRP Recommended Provisions for Seismic Regulations for New Buildings and Other Structures (FEMA 450). Part 1: Provisions. Washington, D.C.: NEHRP. Nilson, A. H., D. Darwin, and C. Dolan. 2004. Design of Concrete Structures. New York: McGraw-Hill. Peck, R. B., W. E. Hanson, and T. H. Thornburn. 1974. Foundation Engineering. 2nd ed. New York: John Wiley & Sons. Portland Cement Association (PCA). 1999. Notes on ACI 31899 Building Code Requirements for Structural Concrete, with Design Application. 7th ed. Skokie, IL: PCA. Prakash, S., and H. D. Sharma. 1990. Pile Foundations in Engineering Practice. New York: John Wiley & Sons. Reese, L. C., and M. W. ONeill. 1988. Drilled Shafts: Construction Procedures and Design Methods. US Department of Transportation, Federal Highway Administration FHWA-HI-88-042, ADSC-TL-4. McLean, VA: US Department of Transportation Federal Highway Administration; and Dallas, TX: ADSC, the International Association of Foundation Drilling. Sarhan, H. A., M. W. ONeill, and S. W. Tabsh. 2004. Structural Capacity Reduction for Drilled Shafts with Minor Flaws. ACI Structural Journal 101(3):291 297, May/June. Smith, G. N., and E. L. Pole. 1981. Elements of Foundation Design. New York: Garland STPM Press. Terzaghi, K., and R. B. Peck. 1967. Soil Mechanics in Engineering Practice. New York: John Wiley & Sons. Woodward, R. J., W. S. Gardner, and D. M. Greer. 1972. Drilled Pier Foundations. New York: McGraw-Hill. Wyllie, D. C. 1992. Foundations on Rock. New York: E. and F. N. Spon, an imprint of Chapman and Hall.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Source: Steel Water Storage Tanks: Design, Construction, Maintenance, and Repair
CHAPTER
Steel Fabrication
Tank constructors have developed specialized equipment, tools, and procedures for the construction of ground storage tanks and elevated water tanks. In the construction of nearly all steel-welded tanks, the steel components are fabricated in a shop environment and shipped to the tank site, where the fabricated components are t and welded into the nished tank by eld construction crews. Steel plate layouts are developed by the constructor, which minimizes welding and maximizes the use of the ordered plate, with consideration to the size and weight restrictions for shipping. For the composite elevated tank, specialized forms and equipment have been developed and are used in the construction of the concrete components.
Material
Plate material may be purchased from a steel warehouse or directly from a steel mill. Steel warehouses stock plate material in most of the
227
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
228
Chapter Six
grades used in welded-steel tanks. Material that is required to conform to supplementary requirements (e.g., silicon-killed, ne-grain practice, normalized, or ultrasonically inspected material) is generally not available from a warehouse.
Cutting
Several methods are available for cutting plates to size in the shop, including thermal cutting by either oxy-fuel gas torches or plasma
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
C o n s t r u c t i o n o f We l d e d - S t e e l Wa t e r - S t o r a g e Ta n k s
229
arc. Thermal cutting methods are commonly used in the shop for irregularly shaped plates (Fig. 6-1). Oxy-fuel gas torches may be automated by either setting up a track burner or by use in a numerically controlled burning bed. Plasma arc cutters are used in a numerically controlled burning bed. Using either method, the plate may be simultaneously cut to size and the edges tapered and beveled for welding by using multiple burning heads. The nished edges should closely follow the detailed plate dimensions to ensure good t-up in the eld. The edges should be uniform and smooth and cleaned of slag accumulation when necessary. Machining and shearing are other methods of cutting plates to size. Rectangular plates that are ordered with minimal trim allowance may be trimmed and squared by machining the edges using an edge planer. Shearing is another option for straight edges that are less than the width of the constructors plate shear. American Water Works Association (AWWA) Standard D100 limits plate thicknesses for shearing to 1/2 in. (12.7 mm) or less if the joint is to be butt welded. Edges that will be lap welded are limited in thickness only by the capacity of the plate shear. Sheared edges should be square and burrs removed before welding.
Forming
Single-curvature plates for welded-steel tanks are typically cold rolled in the shop to the appropriate curvature using a plate roll. Plate widths
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
230
Chapter Six
Plate Thickness Minimum (in.[mm]) >3/8 [>9.5] >1/2 [>12.7] >5/8 [>15.8] Maximum (in.[mm]) 3/8[9.5] 1/2 [12.7] 5/8 [15.8] Minimum Plate Diameter (ft[m]) 40 [12] 60 [18.2] 120 [36.6] Must be rolled for all diameters
TABLE 6-1 Minimum Diameter for Plates Not Rolled
may be limited by the fabricators plate roll capacity. AWWA D100 makes provisions for plates that need not be rolled on the basis of the minimum diameter and plate thickness as outlined in Table 6-1. Singlecurvature plates are frequently used to construct a double-curvature surface if the radius is large enough. One example of this is pie-shaped plates in a dome roof. Double-curvature plates are cold pressed using repeated blows with a mortar-and-pestle-shaped die (Fig. 6-2). Typical examples of a double-curvature plate include the are and ball of a pedestal tank. Press breaks are used to form sharp bends in a platefor example, the uted plate in a uted-column-style tank. Press breaks and presses can also be used to simulate a rolled plate by repeatedly hitting the plate with a straight die, allowing for short spaces between hits (Fig. 6-3). This method can also be used to form cone-shaped plates and is particularly useful for thick plate. Angle rolls are commonly used to roll structural angles for weldedsteel tanks. With all forming operations, it is important to have
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
C o n s t r u c t i o n o f We l d e d - S t e e l Wa t e r - S t o r a g e Ta n k s
231
adequate dimensions on the shop drawings to verify the accuracy of the formed plate.
Shop Subassemblies
Fabricated plate may be subassembled and welded in the shop (Fig. 6-4). This is done to maximize the welding that can be performed
FIGURE 6-4 Shop assembly of cut and formed plates for a dome roof.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
232
Chapter Six
in the controlled environment of the shop using optimal welding processes and congurations. Shipping restrictions dictate the extent of shop subassembly that can be executed. When plate sections are sized such that the shop-welded subassemblies are not an option, complete or partial shop assembly may still be warranted to ensure proper t-up in the eld. This is especially useful for complex geometries with double-curved surfaces.
Shipping
Shipping from the shop to the job site is almost exclusively by truck (Fig. 6-5). The current weight limit is 80,000 lb (36,287 kg) gross for the truck, trailer, and load, resulting in a net load capacity of approximately 45,000 lb (20,412 kg), depending on the weight of the truck
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
C o n s t r u c t i o n o f We l d e d - S t e e l Wa t e r - S t o r a g e Ta n k s
233
and trailer. Rules for oversized loads vary from state to state. Special permitting, routing, and escorts may be an option when oversized loads cannot be avoided or are deemed to be more economical. Plate layouts are often dictated by shipping limitations. Site access should also be considered in planning shipping loads. Material should be sufciently blocked, braced, and tied down to secure the components to the trailer and maintain the fabricated shape during shipping.
Welding
In the 1950s, welding replaced riveting as means of connecting tank joints. Welding can be performed in all climates and in a variety of positions. Over time, the technology has improved, leading to increases in productivity. To convey the correct welding information from the tank designer, weld symbols in accordance with AWS Standard Symbols for Welding, Brazing, and Nondestructive Examination should be used on the fabrication and erection drawings.
Welding Processes
The primary welding processes used in the shop and eld are shielded metal arc welding (SMAW), submerged arc welding (SAW), and ux cored arc welding (FCAW). All are arc welding processes that use an electric arc generated by an electric current between the tip of the electrode and the base metal. Heat from the arc melts the electrode
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
234
Chapter Six
and adjacent base metal which then combines, cools, and solidies to form the weld bead. Welding may be performed manually, semiautomatically, automatically, or by machine welding. Manual welding requires the welder to manually maintain the proper positioning and arc length and replace the electrode as it is consumed. Semiautomatic welding is performed with a handheld gun that continuously feeds the electrode and ux. Automatic welding is accomplished with equipment that is capable of performing the welding operation without a welding operator. This type of welding is more commonly used in assembly line operations. In machine welding, specialized equipment performs the complete welding operation; however, the welding equipment must be monitored by a qualied operator who is responsible for positioning the steel components, starting and stopping the weld, setting the speed, and adjusting the controls.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
C o n s t r u c t i o n o f We l d e d - S t e e l Wa t e r - S t o r a g e Ta n k s
SAW is typically limited to the at position for butt welds and the at and horizontal positions for llet welds. With specialized equipment to contain the ux, SAW may be used for lap and butt joints in the horizontal position. Moving the bulky wire-feeding mechanism for the continuous-feed electrode may make SAW a less desirable option for inaccessible areas. Good joint t-up is also critical for SAW.
235
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
236
Chapter Six
Grinding
Some grinding of welds may be required to ensure that the nished weld contour is suitable for cleaning and painting and will not be detrimental to the life of the coating. Grinding should be used to remove weld slag, weld spatter, burrs, and any sharp surfaces along welds. If the purchaser requires special grinding, it should be noted in the
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
C o n s t r u c t i o n o f We l d e d - S t e e l Wa t e r - S t o r a g e Ta n k s
contract specications, and a recognized standard addressing weld proles should be referenced to clearly dene the extent of grinding required. When lapped plates are joined with llet welds that are less than the full thickness of the plate, the exposed sharp edge of the plate should be removed by grinding. This will minimize the potential for a paint failure at the edge of the plate.
237
Construction
Scheduling Issues
In addition to the production capacity and workload of the tank constructor, construction schedules are affected by the style and size of the tank, the availability of material, the time of year, and daily weather conditions. The purchaser may specify either the number of weeks to completion after award of contract or a set calendar date for completion, or the purchaser may allow the tank builder to propose a scheduled completion. If a specied completion date is critical to the owner, the purchaser may specify liquidated damages to be charged on a daily basis if the work is not completed on time. If the purchaser chooses to set a construction schedule, consideration should be given to mill delivery time to allow the constructor to use material from the mill. In northern climates, a schedule should be specied that allows painting to be performed at an appropriate time of year. Tanks with very short construction schedules are typically purchased at a premium. Weather can signicantly inuence the eld schedule. Wind, extreme temperatures, rain, snow, and sleet can affect what work can be performed and how productive the crew is. Even moderate winds can make it unsafe to pick up and place steel plate. Weather and temperature conditions must also be appropriate for welding. Welding is not permitted when the parts to be welded are wet from rain, snow, or ice, or during periods of high wind, unless the welder and the work are properly protected. No welding is allowed when steel is wet. The protection is typically an enclosure to block the wind. Welding is not allowed if the base metal temperature is lower than 32 F (0 C) unless the base metal is preheated to at least 100 F (38 C) through the thickness and maintained for a distance along the weld of four times the thickness of the parts to be welded. If base metal temperatures fall below 0 F (18 C), welding is not recommended. If welding is performed, low-hydrogen electrodes or low-hydrogen processes must be used, and the base metal must be preheated to 200 F (93 C) in accordance with AWWA D100.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
238
Chapter Six
Unless protection is provided, concrete should not be placed in rain, sleet, snow, or extreme temperatures. American Concrete Institute (ACI) 306.1 and 305.1 provide guidelines for concrete placed in cold and hot weather.
Site Issues
The engineers drawings typically show the site layout superimposed on a topographic drawing. This gives some indication of the relative slope of the site and of potential access problems. If, during the bid stage, questions arise regarding the site, a site visit may be warranted.
Access
The owner should provide a suitable right-of-way for access from the nearest public road to the tank site. The access should be able to handle a semitrailer tractor rig with a trailer that is 53 ft (16 m) long and that weighs 80,000 lb (36,287 kg) under ordinary weather conditions. Side clearance needs to be adequate to accommodate the maximum shipping width for the job. The access road should be free from underground and overhead obstructions that could be damaged by the truck trafc. A minimum vertical clearance of 14 ft (4.2 m) is required.
Site Size
Final property lines should be located sufciently far from the foundation footprint to permit construction operations. During construction, additional clearance is required for steel delivery, storage, staging, and subassembly. If a permanent site of adequate size is not available, the owner should provide an adequate temporary construction easement. As a minimum for the construction operations, a site clearance from the center of an elevated tank to the site limits should be equal to the height of the tank. For a ground tank, it is preferable to have at least 20 ft (6 m) clear around the entire tank so that a crane can be used around the full circumference of the tank. The site should also be big enough to permit abrasive blasting and painting without impacting neighboring property, both after initial construction and during future recoating operations. Clearance requirements between the tank and the neighboring property vary with the prevailing wind conditions, type of paint application, and consequence of damage. Sites should be evaluated on a case-by-case basis, but as a general rule, a clearance of approximately 100 yd (91.5 m) is suggested. If adequate clearance cannot be provided, it may be necessary to shroud the tank during initial and future painting operations. Shrouding the tank is costly and should be avoided if possible.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
C o n s t r u c t i o n o f We l d e d - S t e e l Wa t e r - S t o r a g e Ta n k s
239
Drainage
The tank site should have good drainage during construction. Storage, staging, and subassembly areas should be free from standing water. For sites with poorly draining soils, the bearing surface for a shallow foundation should be protected from becoming saturated prior to concrete placement.
Power Lines
Overhead or buried power lines present a signicant safety risk for tank construction. Sites having power lines within 40 ft (12 m) of the tank or tank foundation are unacceptable.
Security
Access to the tank should be blocked when the tank is left unattended. If the location is remote or subject to frequent vandalism, additional measures to ensure site security may be required. The additional measures may include fencing and full- or part-time security.
Power Requirements
Power requirements in the eld vary depending on the types of tools that will be used on the job. If the purchaser is furnishing power to the site, the power requirements should be coordinated with the tank constructor.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
240
Chapter Six
Tank-Bottom Construction
The bottom of a ground-supported reservoir or standpipe is essentially a nonstressed membrane, the purpose of which is to contain the product inside the tank and transmit the water-bearing load directly to the foundation. The minimum thickness of the bottom plate is 1/4 in. (6.3 mm); it may be thicker if a corrosion allowance is specied. The tank bottom should be crowned up from the shell to the center with a minimum slope of 1 in. (25.4 mm) vertical to 10 ft (3 m) horizontal.
Layout The typical plate layout for bottom plates is a rect-andsketch layout, which refers to rectangular plates with sketch plates at the outside cut to a radius. The outside radius must be a minimum of 2 in. (50 mm) outside of the shell. Additional projection may be provided to compensate for shell out-of-roundness and weld shrinkage in the bottom welds. With a lap-welded bottom, there will be three plate laps at the corners of the rectangular plates. Three plate laps must be at least 1 ft (0.3 m) from the shell. Refer to Fig. 6-7 for an example of a rect-and-sketch bottom layout. Annular ring An annular ring may be required under two possible scenarios. First, if the shell uplift due to seismic overturning is large, a thickened annular ring will increase the uplift resistance of the shell. This strategy is used to eliminate tank anchorage. For this circumstance, butt-welded sketch plates may be substituted for an annular
Cut
ius rad
Inside shell
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
1 ft. (0 .3 m ) minim um
C o n s t r u c t i o n o f We l d e d - S t e e l Wa t e r - S t o r a g e Ta n k s
241
Shell
) m tion 1 m jec 5 ( o n. pr 2 i ide s t ou
Annular plate
ring. Second, if the tank is designed in accordance with AWWA D100 Section 14 and is greater than 150 ft (45.7 m) in diameter, an annular ring is required. If an annular ring is provided, the minimum inside projection shall be 2 ft (0.6 m) or the minimum width required for seismic uplift resistance, whichever is less. The bottom plate is lap welded to the annular ring and has a rect-and-sketch layout. Refer to Fig. 6-8 for an example of a tank bottom with an annular ring.
Welding sequence The welding sequence for the bottom plates shall minimize out-of-plane distortion. A general sequence for bottom welding is described as follows:
r r r r
Weld the sketch plate to sketch plate joints. Weld the rectangular short side joints. Weld the rectangular long side joints. Weld the rectangular plate to sketch plate welds.
Lap welded versus butt welded Bottom plates can be welded by either lap welds or butt welds. For bottom plate thicknesses up to 3/8 in. (9.5 mm), the plates are typically lap welded from the top side only. The weld is a full-thickness llet weld and, for thicknesses equal to or greater than 5/16 in. (8 mm), the llet is typically a two-pass weld. If it is necessary to seal the underside of the bottom or if the bottom
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
242
Chapter Six
FIGURE 6-9 Breakdown of lapped area beneath shell and projected outside of tank.
Shell plate
Bottom plate
plate thickness is greater than 3/8 in. (9.5 mm), butt welding of the bottom plates is appropriate. For lap-welded bottoms, the lapped area that is beneath the shell and projected outside of the tank must be broken down. The purpose of the breakdown is to provide a smooth transition at the lap on the top side so that there will be no gap at the shell-to-bottom connection in the region of the lap. Refer to Fig. 6-9 for an illustration of a breakdown. Annular ring splice welds must be butt welded. The welds may be either single butt welds with backup bars or double butt welds. Commonly, the fabrication shop will subassemble annular ring sections with double butt welds, and the subassemblies will be welded in the eld with single butt welds. Butt-welded bottom plates can be either a one-sided weld with a backup bar or a double butt welded. Single butt welding is the preferred method since the bottom can be laid out and the welding performed from the top side. Double butt welding is difcult for large tanks due to the inaccessibility of the underside of the bottom. For small tanks, however, the initial weld pass can be performed downhand and the bottom can be ipped over so that the welding can be completed down-hand.
Shell-to-bottom junction The connection of the shell to the bottom plate shall be a continuous llet weld on both sides of the shell. Table 18 in AWWA D100-05 gives the minimum size of the llet welds to be used on the basis of the thickness of the shell plate. If the llet weld is 5/16 in. (7.9 mm) or larger, the weld shall be two-pass minimum. The weld should be inspected for watertightness using dye penetrant, penetrating oil, or diesel fuel. The inside llet weld is completed rst, and indicator is sprayed on the weld. If any indicator is visible outside of the shell after a wait period, a leak is indicated and should be repaired. Once there are no indications of leakage, the outside weld can be completed.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
C o n s t r u c t i o n o f We l d e d - S t e e l Wa t e r - S t o r a g e Ta n k s
243
Shell Construction
Crane versus jacking Normally, there are two basic methods for erecting the tank shell. The more common method is to start from the bottom ring and use a crane to place each individual shell plate for each successive ring until the shell is complete. However, for tall tanks a method using hydraulic jacks may be more economical. Using this method, the top two shell rings and roof are erected on temporary jack stands. Once this is complete, the shell is jacked using hydraulics, and the next shell ring is placed. This process is repeated until the shell is complete. This method reduces the crane requirements since there are no high picks. Also, temporary scaffolding for the shell is not required since all shell erection and welding activities are performed at ground level. The shell is the critical component of a storage tank. It is the primary stressed membrane that contains the liquid. Therefore, great care must be exercised in laying out, tting, and welding the shell. Listed here are general steps for layout and t-up of a tank shell. This procedure varies among contractors; however, the general steps are the same.
r Check the elevation of the tank bottom. r Scribe the radius of the inside of the shell on the bottom. This r Mark the chord dimensions for the rst ring. r Install erection nuts or lugs on the bottom that follow the r Set the rst plate starting at the rst chord mark and following r Set the second plate and use t-up gear to align the vertical r r r r
seam for welding. Set the remainder of the rst ring plates and check for level. Weld the vertical seams. Weld the rst ring to the bottom. Hang the second and subsequent rings using t-up gear on the horizontal and vertical seams. the circular scribe mark. outside radius of the rst ring. will be used as a guide for setting the rst ring.
Shimming and the tub ring After the bottom plate is laid, the rst shell ring, or tub ring, is set. Care must be taken in setting the tub ring, since the roundness of the tub ring is the basis of whether the rest of the shell will be round. An essential part of making the shell round is that the tub ring must be level. If the tub ring is not level, tank roundness is difcult to achieve. The tub ring is leveled by using shims between the bottom and the foundation.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
244
Chapter Six
Wind stability During shell erection, the shell is susceptible to wind loads. The shell is designed to be stable and resist buckling due to wind when the tank is complete. However, during construction the shell can buckle easily, even during moderate winds. Therefore, the shell must be braced to prevent a blow-in incident. One method of bracing the shell is with the erection scaffolding. The scaffolding is normally set 3 to 4 ft (0.9 to 1.2 m) below the top of the ring being erected and consists of brackets and scaffold boards or planks spanning between the brackets. If the boards overlap at the brackets and are tied down securely, the scaffolding itself acts as a ring stiffener on the shell. Because of this phenomenon, incomplete scaffolding is normally not allowed to be left overnight. Partial- versus complete-penetration welding The shell vertical welds are always complete-penetration welds. The horizontal welds may be either complete-penetration or partial-penetration welds. When the shell thickness of the thinner of the two plates being joined is greater than 3/8 in. (9.5 mm), the horizontal weld can be a partial penetration. The nished weld must have at least two-thirds the strength of a complete-penetration weld. Partial-penetration welds are not allowed in the shell plates for Section 14 designs. Weld clearances Weld clearances for shell vertical joint offset, permanent attachments, and shell penetrations should meet the requirements of AWWA D100 and good industry practice. Section 14 of AWWA D100 prescribes the requirements for weld clearances. The base code does not describe any weld clearance requirements; however, good practice indicates the following weld clearances:
r Vertical shell plate offset = 12 in. (305 mm) minimum r Permanent attachments = 3 in. (76 mm) (horizontal) and 6 in. r Shell penetrations = 3 in. (76 mm)
Construction openings A construction opening in the shell is normally provided to allow easy access to the interior of the tank. This opening is usually in the form of a short plate that is removed in the rst shell ring. The short plate left out of the shell, called a door sheet, is 6 to 12 ft (1.5 to 3.6 m) wide and has a height equal to the width of the rst shell ring. If a crane must be driven inside of the tank for roof erection, a taller opening is usually required. This is accomplished with a rst and second ring door sheet, which may or may not include the full height of the second ring. Temporary stiffening must be provided around the door sheet to bridge the vertical loads during tank erection.
(152 mm) (vertical)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
C o n s t r u c t i o n o f We l d e d - S t e e l Wa t e r - S t o r a g e Ta n k s
Shell penetrations Shell penetrations are required for access to the interior of the tank and for an overow to prevent overlling. The inlet and outlet piping may go through a shell penetration but more commonly goes through the tank bottom. A minimum of two manholes are required for access. The penetrations have a neck plate that is welded to the shell, and additional reinforcing in the form of a circular reinforcement plate may be required. Post-weld heat treatment Post-weld heat treatment is only required for shell penetrations that are 12 in. (305 mm) in diameter or greater in shell plate that is thicker than 1 in. (25.4 mm). The penetrations should be prefabricated in the shell and stress relieved before shipment. This requirement applies only to Section 14 designs.
245
Roof Construction
Roof conguration can be either supported on structural framing or self-supporting. The self-supporting roofs can be unstiffened, or stiffeners can be welded to the roof plate.
Method of roof erectioncrane versus air raised For tanks with structurally supported roofs, the typical method of construction is to use a crane to lift the various components into place. The roof framing is erected after the bottom and shell are in place, and the roof plate is placed after the framing is complete. For tanks with self-supporting roofs, there are more options. The roof can be built in place using a crane and temporary support for the roof or the roof can be built on temporary supports outside of the tank and the entire roof can be lifted into place. The latter method is advantageous for tall tanks, roofs requiring seal welding, and in situations where a crane with enough capacity can be used economically. Another option is to have the roof erected on the oor of the tank and to lift it into place after the shell erection is complete. This is accomplished by sealing the outside edge of the roof to the shell and pressurizing the underside of the roof to lift it to its nal position. This method is economical for large-diameter tanks that are relatively tall. Surprisingly, the pressure required to air-raise a roof is on the order of a water column of 3 to 6 in. (76 to 152 mm). The roof can be raised using high-velocity fans bolted to the shell manholes. Subassembly For self-supported roofs, to minimize the number of crane picks and reduce the need for welding in place, the eld crew may elect to subassemble some of the roof sections. This may also decrease the amount of time the crane needs to be on-site, therefore reducing costs. Roof-to-shell junction The roof-to-shell junction can be congured in several ways. For cone- and dome-type roofs, an angle can be either
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
246
Chapter Six
butt or lap welded to the top of the shell. The roof plate laps onto the top of the angle. This arrangement can be advantageous since fabrication and erection variances can be tolerated. The top angle is used to aid in keeping the tank shell round. As an alternative to using an angle, a bar may be used. A double-curved transition may be used for either a supported or unsupported roof. This type of transition can be more visually pleasing for taller tanks and any tank for which aesthetics are important.
Seal welding Seal welding may be specied to reduce rust bleeding from the inaccessible plate lap areas. If seal welding is required, the type of roof must be considered. If the roof plate is supported on structural members, the surfaces mating the tops of the structural members to the underside of the roof plate will also be inaccessible. Seal welding the roof plate lap welds will solve only part of the problem. However, if the roof framing is to be seal welded to the roof plate, the tank designer must consider the effects of thermal expansion and contraction caused by temperature differentials on the roof framing. Also, the amount of welding required to seal all of the roof framing might induce additional weld distortion in the roof plate. If the roof is self-supported, any framing will be welded to the roof plates by design. Ponding For supported cone roofs, the minimum roof slope is a 3/4in. (19-mm) rise in a 12-in. (305-mm) run. This is a very shallow roof slope and it may therefore produce ponding if the roof plate is built with excessive distortion. In many local jurisdictions, ponding is not allowed by law. The easiest solution to potential ponding is to increase the roof slope.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
C o n s t r u c t i o n o f We l d e d - S t e e l Wa t e r - S t o r a g e Ta n k s
with a short eld-construction schedule. Use of a mobile crane requires more site clearance around the tank. Whether using a derrick, tower crane, or mobile crane, adequate support is critical. For either a derrick or stationary tower crane, supplemental groundwork or a support pad should be provided if required before setting the crane. A mobile crane requires a reasonably level surface around the tank and site conditions capable of supporting the loaded crane.
247
General Requirements
Field subassemblies Shipped plates are frequently subassembled on the ground in the eld. The subassemblies are planned on the basis of the maximum weight and size feasible to lift and t into place. This erection practice allows the welding to be performed close to the ground in more favorable positions. Construction aids Specialized erection equipment developed by the tank constructor is used to aid in lifting, tting, aligning, and spacing plates with the appropriate weld gaps. Maintaining the proper gaps, alignment, and overall dimensional accuracy is critical for subsequent plate placement. Some construction aids may be permanently left in place, while others are temporary and are removed after the plate is secured. Temporary attachments need to be removed without damaging the plates, and the remaining weld should be chipped or ground smooth before painting. Dimensional accuracy is maintained by consistently checking dimensions. Levels and transit levels may be used to verify elevations, check angles, and to verify that a component is plumb. Access to the tank Safe access to the tank and tower is required for welders, inspectors, and painters. Temporary scaffolding is commonly used in conjunction with permanent and temporary ladders for access. Aerial lifts such as a boom lift or scissor lift may also be used. A work basket or chair hung from a spider line is another frequently used option. This option requires a secure anchor point above the area to be accessed. Regardless of the method of access, fall protection needs to be considered and special measures taken to ensure the safety of the workers.
Fluted-Column-Style Tank
The uted tower rests on butt-welded base plates that are seated on shims and xed to the foundation by the anchor bolts. It is critical that the base plate is level before erecting the uted plates. After the tank has been erected, but before it is lled with water, the space between the base plate and foundation is grouted.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
248
Chapter Six
FIGURE 6-10 Erection of tower, uted-column-style tank.
The vertical joints in the uted tower are lap welded, and the horizontal joints are butt welded. Water-bearing plates in the tank are welded with full-penetration butt welds. The roof is typically lap welded on the top side only. When specied by the purchaser, the overhead laps in the roof are also seal welded (Figs. 6-10 to 6-12). Access to the inside of the uted tower is required at all times and is typically provided at the opening for the overhead door. A bottom manhole provides access to the inside of the tank. Tank constructors have developed specialized equipment to enable safe access to difcult areas such as the outside of the cone or the underside of the roof. The constructor must be cognizant of the stability of the structure at all times, but especially when the structure is left overnight. Regardless of what component the crew is erecting, the crew should not leave the tank unattended until all the plates in a given ring are in place and adequately secured. Provisions should be taken to stiffen unnished sections of the tank in case of high winds. This may include providing stiffening or continuous scaffolding at the upper limits of construction or guying the structure to the ground.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
249
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
250
Chapter Six
Pedestal-Style Tank
Complete-penetration butt-welded construction is used for all the components of the pedestal tank and tower except the roof. The roof is usually lap welded on the top side. At the request of the purchaser, the underside may also be seal welded or, alternately, the roof may be butt welded (Figs. 6-13 and 6-14). The base cone of the tower of a pedestal-style tank sits on a thick base plate that is welded with complete-penetration butt welds, set on shims, and xed to the foundation by the anchor bolts. As with the uted-column-style tank, it is critical that the base plate be level before erecting and welding the base cone. The base cone is llet welded to the base plate. As with the uted-column-style tank, grout is placed under the base plate after the tank is completely erected but before it is lled with water.
Multicolumn-Style Tank
Erection for a multicolumn-style tank typically begins with one bent in the rst panel, consisting of a pair of columns, one bolted strut, and loosely connected cross-bracing that will either be welded or
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
C o n s t r u c t i o n o f We l d e d - S t e e l Wa t e r - S t o r a g e Ta n k s
251
bolted to the columns. Base plates are welded to the bottoms of the columns in the rst panel. The base plates of the rst bent are set on shims placed on the foundation pedestals and are xed using the anchor bolts. Additional bents are erected by sequentially adding a column, strut, and cross bracing around the tower. After all the bents are in place in the rst panel, the cross braces are adjusted to length, as required, to ensure that the panel is square and true before proceeding to the next panel. Subsequent panels are erected in a similar manner with the columns of the upper panel welded to the lower columns. Typically, the portion of the tank that is welded to the upper column is welded to the column before the tank is erected. After the tower is complete, the intermediate plates are t-up and welded with complete-penetration butt welds. It is critical to maintain dimensional accuracy of the tower for proper t-up of these plates. The tank joints between water-bearing plates are joined with complete-penetration butt welds. The roof plates may be lap welded with or without seal welding, or they may be butt welded. An alternate construction sequence is to construct the upper bents and tank without the lower columns in place. The advantage of this construction method is that the tank and upper tower can be constructed and painted when closer to the ground. After this portion of the tank is complete, it is lifted by cranes and the lower columns are
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
252
Chapter Six
FIGURE 6-15 Multicolumn-style tank.
set underneath (Fig. 6-15). The structure is then lowered to its proper height and seated on the columns. After the tank is complete, but before it is lled, the nal tightening or welding of the cross-braces is done. At this stage, the grout is also placed under the base plates.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
C o n s t r u c t i o n o f We l d e d - S t e e l Wa t e r - S t o r a g e Ta n k s
FIGURE 6-16 Tower construction, composite elevated tank.
253
either by pumping or by bucket. Hand compaction and power vibration are performed in accordance with ACI 309 to ensure proper compaction, minimize segregation, eliminate air voids, and to ensure close contact with the reinforcement and forms. After the rst ring is poured and has had time to cure, the forms are removed. The sequence of placing reinforcement, jumping the forms, and pouring the concrete is repeated until the support tower is complete. Forms are set for the dome and ringbeam or the at slab. Similar to the tower forms, the tank constructor will have developed specialized forms for their geometry and construction practice. Reinforcement is placed and tied and embedments secured before the concrete is poured.
Concrete Mix
The concrete mix should be suitable for the method of placement and the weather conditions. The proportions of the mix should be adjusted to provide adequate workability and the proper consistency for placement. For each tank, the material should be from a consistent source and the mix design number veried upon delivery. The arrival of trucks should be sequenced to sustain a pour without long delays. Retempering of the concrete should be controlled to maintain the mix
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
254
Chapter Six
FIGURE 6-17 Roof erection, composite elevated tank.
parameters. Concrete testing should be in conformance with ACI 318, Building Code Requirements for Structural Concrete.
Liner Plate
An interior liner plate is placed over the dome or at slab. The liner is lap welded on the top side only. For tanks with a dome, formed liner plates may be used and constructed so that the liner lies directly on
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
(a)
(b)
FIGURE 6-18 (a) CET hoisted tank erection as the tank is being raised. (b) CET hoisted tank erection with the tank in the nal position.
255
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
256
Chapter Six
FIGURE 6-19 CET liner plate formed to t dome with derrick-erected cone and shell plates.
the dome. Alternately, unformed steel liner plates that do not match the shape of the dome may be used if the space between the plate and the dome is completely lled with owable grout after welding (Fig. 6-19).
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
C o n s t r u c t i o n o f We l d e d - S t e e l Wa t e r - S t o r a g e Ta n k s
Foundations and anchors that are not within tolerances should be identied and addressed before the tank is erected. A design professional representing the tank constructor should evaluate whether the structural capacity of the foundation has been compromised and should provide details for remedial action when required.
257
Support wall variation from plumb r In any 5 ft (1.5 m) of height: 3/8 in. (9.5 mm)
r In any 50 ft (15 m) of height: 1.5 in. (38 mm) r Maximum for total height: 3.0 in. (76 mm)
Support wall diameter variation r 0.4 percent (not to exceed 3.0 in. [76 mm]) Dome tank oor radius variation r 1.0 percent Level alignment variation r From specied elevation: 1.0 in. (25.4 mm)
The offset between adjacent pieces for formwork facing material should not exceed the following:
r Exterior exposed surfaces: 1/8 in. (3 mm) r Interior exposed surfaces: 1/4 in. (6.3 mm) r Unexposed surfaces: 1/4 in. (6.3 mm)
The nish tolerance of troweled surfaces should not exceed the following when measured with a 10-ft (3-m) straightedge or sweep board:
r Exposed oor slab: 3/8 in. (9.5 mm) r Tank oors: 3/4 in. (19 mm) r Concrete support for suspended steel oor tank: 1/4 in.
(6.3 mm)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
258
Chapter Six
Maximum Diameter (ft[m]) 40 [12] 150 [45.7] <250 [<76.2] 250 [76.2]
TABLE 6-2 RoundnessCylindrical Shells
Radius Tolerance (in. [mm]) 0.5 [12.7] 0.75 [19] 1.0 [25.4] 1.25 [32]
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
C o n s t r u c t i o n o f We l d e d - S t e e l Wa t e r - S t o r a g e Ta n k s
Subject to Primary Stress (in. [mm]) 1/16 [1.6] Lesser of 0.10t or 1/4 [6.3] Subject to Secondary Stress (in. [mm]) 1/8 [3.1] Lesser of 0.20t or 3/8 [9.5]
259
TABLE 6-3 Maximum Allowed Offset for Butt-Welded Plates Subject to Primary or Secondary Stress
Alternately, if a plate thickness is based on a buckling analysis performed by the tank constructor, measurements must be taken to verify that the deviations assumed in the analysis have not been exceeded. AWWA D100 also provides tolerances for plate alignment for lapwelded joints and butt-welded joints. Lap joints should be held in as close contact as possible, with no plate separation exceeding 1/16 in. (1.6 mm). When plate separation is present, the weld size should be increased by the amount of separation. The maximum allowed offset for butt-welded plates subject to primary or secondary stress is dened in AWWA D100 and repeated in Table 6-3.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
260
Chapter Six
The most common method of evaluating complete-penetration butt-welded joints for weld quality is by radiography. Radiographic inspection is to be performed in accordance with ASME Section V, Article 2 by Level II radiographers. Section 11 of AWWA D100 prescribes the number and location of radiographs for tank shells, risers, and single-pedestal columns. The radiographic inspection should be performed as the work progresses. The purchaser may participate in the selection of the specic radiograph locations. AWWA D100 has radiograph inspection standards that must be used for evaluating discontinuities and defects present in the radiograph lm. A weld shall be repaired or replaced if cracks, incomplete fusion, or inadequate penetration are noted. In addition, welds with inclusions or rounded indications that exceed the limits specied in AWWA D100 need to be repaired or replaced. The welds in bottom plates of a ground storage tank are required to be tested for watertightness by magnetic-particle testing or by airpressure or vacuum testing. There are additional inspection requirements for ground storage tanks built to AWWA D100 Section 14. The weld between the shell and the bottom should be inspected for watertightness using dye penetrant, penetrating oil, or diesel fuel. The inside llet weld is completed rst and indicator sprayed on the weld. If any indicator is visible outside of the shell after a wait period, a leak is indicated and it should be repaired. Once there are no indications of leakage, the outside weld can be completed. Section 14 requires more extensive radiographic examination of butt welds in the shell and annular plate. It also requires that all welds attaching manholes, nozzles, and other penetration be inspected for cracks by either the magnetic-particle or the dye-penetrant method by a qualied inspector.
Hydrotest
Water testing is typically performed on the completed tank after it is painted and disinfected. The purchaser is responsible for furnishing the water to the site with sufcient pressure to ll the tank. Water should be lled to the top capacity level, and weld seams should be inspected for any signs of leakage. If leaks are found, the water must be lowered at least 2 ft (0.6 m) below the point of repair, and the defect must be repaired and rewelded. If no leaks are found, the tank can be put directly into service, which eliminates the need to dispose of the test water.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Source: Steel Water Storage Tanks: Design, Construction, Maintenance, and Repair
CHAPTER
Bolted-steel tanks are factory coated and conform to American Water Works Association (AWWA) D103, Factory-Coated Bolted Carbon Steel Tanks for Water Storage.
261
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
262
Chapter Seven
Various lengths and strengths of structure bolts, washers, and nuts are used to assemble the tank and appurtenances. Each manufacturer species the degree to which bolts must be tightened to properly assemble the tank and its components. Typical instructions indicate a specied torque or a visual observation of gasket deformation that must be achieved. Coated areas that are damaged in the erection process must be repaired in accordance with the tank manufacturers written procedures. In addition to wrenches and drift pins, proprietary equipment may be used to ensure that the sheets are properly joined and aligned.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
C o n s t r u c t i o n o f B o l t e d - S t e e l Wa t e r - S t o r a g e Ta n k s
263
Floor
If the tank will have a concrete oor, specially sized sheets and panels will be embedded into the oor, forming a ring of foundation sheets on which the remainder of the tank will be erected. If the tank will have a steel oor, factory-coated oor segments/panels will be used.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
264
Chapter Seven
the top of the footing pour. These assemblies are used to position the embedded tank foundation sheet (Fig. 7-3). The foundation ring is set on the leveling plate assemblies, then leveled and rounded to specied tolerances (Fig. 7-4). Floor sumps are then installed, and other piping is stubbed off above the oor line (Fig. 7-5).
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
C o n s t r u c t i o n o f B o l t e d - S t e e l Wa t e r - S t o r a g e Ta n k s
265
FIGURE 7-5 After oor sumps are installed, other piping is stubbed off.
Reinforcement is placed in the oor area and around the curb to the outside of the foundation ring in accordance with the engineering drawings (Fig. 7-6). Forms are usually used for creation of the foundation oor curb around the entire perimeter of the foundation
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
266
Chapter Seven
assembly. Forms may be installed during or after placement of the oor and curb reinforcement steel. A water-stop seal strip is installed onto the foundation sheet prior to concrete placement. The oor and curb concrete is placed, nished, and allowed to cure before further tank construction takes place (Figs. 7-7 and 7-8).
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
C o n s t r u c t i o n o f B o l t e d - S t e e l Wa t e r - S t o r a g e Ta n k s
267
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
268
Chapter Seven
Tank Construction
Jacking Method
Specially designed jacks are used to build the remainder of the tank. The jack assemblies are anchored to the tank oor, one at each sheet
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
C o n s t r u c t i o n o f B o l t e d - S t e e l Wa t e r - S t o r a g e Ta n k s
269
location around the tank perimeter (Fig. 7-12). After all jacks are installed, the faceplates to which the wall sheets will attach are leveled with each other. As the rst ring of sheets is placed on the jacks, sealer is placed in the overlapping vertical joints, and the sheets are bolted together. Before tightening the bolts, a special tool is used to spread the joint apart, simulating the loading that will be placed on the vertical joint from the stored liquid load. As the joint is held in its spread condition, the bolts are tightened to their specied torque. At this point, the roof segments are bolted and attached to the top of the rst ring of sheets (Fig. 7-13). The center of the roof is temporarily supported while the roof segments are bolted into place. When the roof is complete, the temporary support is removed and the entire structure is jacked up to the next level. After the rst ring of sheets is completed and tightened, the jacks are energized and the structure is raised to a height that allows the next ring of sheets to be installed in the same manner as the rst ring (Fig. 7-14). The second ring of sheets rests in supports attached to the foundation sheet while being bolted to the ring above it. On completion of the second ring of sheets, the jacks are disconnected from the rst ring, lowered to a specied location in the ring just completed, and connected to that ring. The jacks are energized, and the structure is raised to the next level. Tank erection continues in this manner until the last ring of sheets is installed and tied into the foundation sheets. Tanks taller than 120 ft (36.5 m) have successfully been erected in this manner. The last sheet of the bottom ring is typically left out to provide an easy means of access for other work inside the tank and for the removal of the jacks.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
270
Chapter Seven
Wind stiffeners, ladders, ladder cages, and platforms, as applicable, are attached to the side of the tank as successive rings are assembled and jacked to the next level (Fig. 7-15).
Scaffold Method
Exterior scaffolding similar to that shown in Fig. 7-16 is required. The quantity and length of scaffold planks required are determined by
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
C o n s t r u c t i o n o f B o l t e d - S t e e l Wa t e r - S t o r a g e Ta n k s
271
FIGURE 7-15 Wind stiffeners, ladders, ladder cages, and platforms are attached.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
272
Chapter Seven
the size of the tank and the width of the tank panels. Scaffolding is moved from ring to ring as work progresses, meaning that the minimum quantity of planks is enough to encircle the tank at one level, plus a few extra. Some crews prefer to leave all scaffolding in place until the shell and roof are complete, thus requiring two planks for every shell segment in the tank. Scaffold planks are supported by scaffolding brackets (Fig. 7-17). Normally, the brackets consist of steel angles 2.5 in. 2.5 in. 0.25 in. (63.5 mm 63.5 mm 6.35 mm). Accommodation for safety line uprights must be provided. The bracket shown in Fig. 7-17 will receive a tubular upright that ts over the 6-in.(152-mm)-long plank-retaining rod at its end. Any plank-retaining device should have a minimum height of twice the scaffold plank thickness. The safety line upright must be 42 in. (1 m) in height, measured from the top of the scaffolding board. Common practice is to leave all scaffolding brackets in place until the shell and the deck are complete. This requires one bracket for each shell segment in the tank. All boards must be secured. If interior scaffolding is not used, a hooked drive-out ladder similar to the one shown in Fig. 7-18 is required during erection. Points that bear on the shell should be padded to protect the interior nish of the tank. Hoisting equipment capable of lifting components weighing as much as 1,000 lb (453.6 kg) is required. A variety of devices can be used, but gin poles similar to the one shown in Fig. 7-18 are the
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
C o n s t r u c t i o n o f B o l t e d - S t e e l Wa t e r - S t o r a g e Ta n k s
273
most common. Made of steel pipe or tubing, they are supported from scaffolding brackets and extend well above the top of the ring under construction. The tank shell must be protected from gin-pole bearing points.
Roof Installation
At least three types of roofs are commonly installed on factory-coated bolted-steel tanks. These types are self-supported (Fig. 7-19), centersupported (Fig. 7-20), and self-supported aluminum domes (Fig. 7-21).
Self-Supported Roofs
Self-supported roofs consist of one-piece pie-shaped panels that are temporarily supported in the center while the panels are lapped onto each other and bolted together. The roof slope is typically 20 degrees, and the outer end of the panel is formed in a rounded shape, creating a knuckle, which adds stiffness to the panel. This outer edge bolts to the top of the tank wall (Fig. 7-13). After all roof panels are assembled and attached to the tank wall, the temporary center support is removed, allowing the roof to support itself. Low-prole self-supported roofs are typically sloped at a 1:12 pitch to allow for rain runoff. One or two horizontal support members span the tank diameter, and an elevated collar is located at the mid-span to set the roof pitch and accept the radial rafters or stiffened roof sheets.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
274
Chapter Seven
Center-Supported Roofs
Center-supported roofs are supported by a center pole that extends from the tank oor. A common system consists of a center support column of prefabricated pipe with a base plate at the bottom, a rafterbearing plate at the top, and radial rafters (see Fig. 7-22 for proper arrangement of parts).
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
C o n s t r u c t i o n o f B o l t e d - S t e e l Wa t e r - S t o r a g e Ta n k s
275
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
276
Chapter Seven
tank shell sheets (Fig. 7-23) or constructed on the ground and lifted onto the top ring of shell sheets as a completed assembly. In either case, the mounting shoes of the dome attach to a formed angle that has been attached to the upper horizontal bolt line of the rst ring of shell sheets. The dome consists of an aluminum I-beam structure, lightweight aluminum roof panels, and ashing. Although the dome is attached to the tank shell at the perimeter roof angle, the attachment allows necessary movement between the roof and the tank.
Roof Accessories
A hinged, lockable roof access door is normally provided near the outside ladder to allow liquid samples to be withdrawn from the top
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
C o n s t r u c t i o n o f B o l t e d - S t e e l Wa t e r - S t o r a g e Ta n k s
277
FIGURE 7-24 Roof ventilator usually located in center of roof at roof cap.
of the stored liquid (Fig. 7-25). The door is bolted onto an opening provided in the roof panels for this purpose. A roof railing assembly is installed after the roof installation is complete. Depending on the pitch and the type of roof, a walkway may be provided (Fig. 7-26). The assemblies are bolted together
FIGURE 7-25 Hinged, lockable roof access door near outside ladder.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
278
Chapter Seven
using appropriate fasteners; sealer and neoprene pads are used where support brackets attach directly to the roof panels. A caged ladder with a roof manway landing platform that meets requirements of the Occupational Safety and Health Administration (OSHA) is supplied with most tanks (Fig. 7-27). Depending on tank height, some ladder/cage assemblies also include one or more stepoff platforms. Individual sections of the ladder/cage assemblies are constructed on the ground. The sections are then attached to the rings of shell sheets during the tank erection process.
Shell Penetrations
Tank manufacturers policies vary concerning penetrations through the tank sidewall for piping and other instrumentation. Some manufacturers supply the openings in the panels shipped from the factory; others provide detailed instructions for locating and cutting the openings in the eld during or after tank erection. Depending on the opening size, the tank manufacturer may require and provide the means to reinforce the area around the opening. Depending on the tank coating, the reinforcement can be a plate welded around the opening in the factory or bolted on in the eld (Fig. 7-28).
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
C o n s t r u c t i o n o f B o l t e d - S t e e l Wa t e r - S t o r a g e Ta n k s
FIGURE 7-27 Caged ladder is supplied with most tanks.
279
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
280
Chapter Seven
FIGURE 7-29 Brackets holding overow pipe should be correctly located.
After the tank sidewall has been tied into the foundation sheet, one or more access door assemblies (manways) are mounted to the tank sidewall within the lowermost full-height ring of shell sheets (refer to Fig. 7-26). A variety of overow piping designs can be installed. Care should be taken to ensure the brackets holding the overow pipe are correctly located and cushioned against the tank to prevent damage to the coating (Fig. 7-29). When level indicators and other control devices are being installed, workers need to heed the tank manufacturers instructions regarding penetrations of the sidewall and prevention of coating damage.
Completion
After all tank sections have been erected, all appurtenances have been installed, and piping is complete, the interior is cleaned of all construction equipment and debris. Any damaged coating areas on the tank interior or exterior are repaired in accordance with the coating manufacturers instructions. The tank exterior is examined to ensure that all safety decals are in place, if applicable.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
C o n s t r u c t i o n o f B o l t e d - S t e e l Wa t e r - S t o r a g e Ta n k s
281
The tank is tested for leaks by lling it to the overow level. Any leaks found are repaired in accordance with the tank manufacturers recommendations. The test liquid is usually disposed of using the tanks drain system.
FIGURE 7-31 Completed standpipe.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
282
Chapter Seven
Once testing is complete, the tank should be disinfected. AWWA Standard C652 and the tank manufacturers recommendations should be followed to achieve proper tank disinfection. All construction equipment is removed and the tank site is cleaned in accordance with the project specications. Figures 7-30 and 7-31 show the completed tanks.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Source: Steel Water Storage Tanks: Design, Construction, Maintenance, and Repair
CHAPTER
The purchaser should inspect the tank as construction proceeds to ensure that the structure complies with specications, both in form and in quality. This chapter discusses the specic items to be checked by the purchaser and those that are the responsibility of the constructor. On the job, the purchaser and the constructor should keep in mind that a quality structure is the result of the cooperation and afrmative efforts of all parties. If the relationship between the purchaser and the constructor is combative or antagonistic, the project is likely to be completed late and quality will probably be adequate at best. On the other hand, a purchaser with a sound knowledge of specications, standards, and trade practices can work with the constructor to complete a high-quality project on schedule.
283
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
284
Chapter Eight
specialized equipment and knowledge are required to conduct a total quality control program. Nonetheless, the owner or the owners engineer, as well as third-party consultants where needed, should monitor the work for inevitable human errors and misunderstandings. Even before construction begins, the owner or engineer should check shop drawings to ensure that the special requirements of the job are met. The constructor is usually responsible for the structural design of the tank, but the interplay of the legally dened responsibilities of the engineering and construction phases is not rmly established. The engineer reviewing the drawings should clearly specify the purpose and the extent of the review to avoid being held legally liable for a more detailed examination than was actually performed. A quality assurance program for the tank project should take into account each of the functions involved in building a tank. In general, these functions fall under the following categories: foundation, fabrication, steel delivery, tank erection, eld-applied coatings, shopapplied coatings, and appurtenances.
Soil Investigation
The purchaser should be at the site when the borings are being taken as part of the soil investigation. This gives the purchaser better insight into problems that might be encountered during construction of the foundation.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
I n s p e c t i n g N e w - Ta n k C o n s t r u c t i o n
285
being driven, the purchaser must determine if the piles are driving as predicted. The purchaser should be on the job to verify that the pile-driving log is properly completed. Site and nal concrete elevations should be conrmed. Placement of forms, reinforcing steel, and anchor bolts should be veried, and photographs should be taken to document these steps before the constructor allows the concrete to be placed.
Concrete
If the owner, constructor, or engineer does not have extensive previous experience with the materials supplied by the concrete ready-mix plant, a design mix should be developed and tested. The consistency of the concrete should be evaluated as it comes out of the chute, and concrete test cylinders should be taken. The storage location for the test cylinders should provide satisfactory moisture conditions and controlled temperature. The cylinders should not be transported during initial cure. Test cylinders that are taken after approximately oneeighth of the trucks load has been discharged give a more representative sample of the concrete than the initial material that is placed. Slump tests should also be performed. For large pours, it is necessary to sequence the pouring operations so that the concrete does not set up before placing fresh concrete next to it, creating cold joints. The concrete should not be dropped into the forms from excessive heights. After the concrete is placed, it should be vibrated with a mechanical
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
286
Chapter Eight
vibrator to ensure proper distribution of the material. Mechanical vibrators should not be used to move the concrete from one location to another. Proper removal of the forms and of all form ties should be veried. Tolerances on concrete foundations are given in AWWA D100 and AWWA D103. The purchasers representative should be familiar with American Concrete Institute (ACI) Standards 301 (Specications for Structural Concrete for Buildings) and 318 (Building Code Requirements for Structural Concrete). With a good cure, quality concrete develops the necessary compressive strength and is less likely to experience surface deterioration. If the surface of the foundation is not cured properly to protect it from the elements, chipping or spalling failure of the concrete can occur long before the steel tank deteriorates.
Backlling
If backlling is done improperly, the concrete is overstressed. Proper backlling techniques are necessary to provide a structurally stable foundation, to prevent water from ponding on moisture-weakened soils, and to make the site more solid for the tank-erection crew. Proper backlling operations require the specialized services of a qualied soil-testing laboratory to determine the optimal moisture content and maximum density of the backll material, check the moisture content of the material being placed, and conduct relative density tests in the eld after the backll material has been placed and compacted. This last test ensures that the specied degree of soil compaction has been obtained. Adequate soil compaction is particularly important for the foundations of ground storage tanks. Although the bottoms of these tanks are usually quite exible, particular care is necessary for backlling pipe trenches beneath the tank and the soil or ll material adjacent to concrete ringwalls. Severe differential settlement in these places can rupture the underlying pipes and cause possible failure of the tank bottom. The contract documents may assign the responsibility for providing necessary soil-testing services to either the tank constructor or the owner. In either case, copies of all soil test reports should be furnished promptly to all interested parties.
Fabrication
It is recommended that the owner and the engineer visit the constructors facility while the tank is being fabricated. Fabricators approach the process differently in terms of ow of materials and the sequence of operations, which eventually inuences how the structure is evaluated. The owner should inspect the quality of shop fabrication, welding, and t-up; the type of surface preparation; and the shop coating
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
I n s p e c t i n g N e w - Ta n k C o n s t r u c t i o n
if applied. The owner should compare the mill test certications to the heat numbers stamped on the steel plates. These mill test certications should be led for future reference. The material should also be examined for excessive corrosion or pitting, signs that the material has been stored outdoors for too long. The amount of fabrication performed in the shop varies depending on the contractor. One function that will be performed in the shop is rolling of the plates. Table 19 in the D100 standard outlines the conditions under which the shell plates must be rolled. If D100 requires that the shell plates be rolled, the owner should verify that they are rolled to the correct radius. The conditions for welding and the available equipment make welding in the shop much easier than welding in the eld. The welds should be visually evaluated in the shop to determine if they meet the requirements of D100 and can be adequately painted. Welding repairs can be more effectively performed in the shop than in the eld. This visit also serves to open communications for the balance of the project.
287
Steel Delivery
The owner should be on hand when the steel is delivered to the job site. The owner can help resolve conicts with neighboring property owners, document any damage occurring in the unloading process, and protect underground utilities on the site or under the access road.
Tank Erection
Erecting and welding or bolting the steel are tasks for which the expertise of the constructor is vital to the success of the project. Erecting steel is a dangerous operation, requiring skills acquired only through experience. During this phase, the purchasers representative may need assistance. Independent testing laboratories are usually equipped to take radiographs of welded seams, but they know little about steel erection and t-up and are not willing to climb to the heights usually associated with water-storage facilities. Using someone from another tank constructors organization as the purchasers representative can lead to conicts of interest and other problems. It is very difcult for a competitor to be unbiased in the evaluation of another constructors work. Even if this competitor is fair, it is difcult for the tank constructor to accept the opinion as an unbiased one. Therefore, it is usually best to secure the services of a consultant who specializes in this type of inspection work and has the expertise and climbing ability to accomplish the job.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
288
Chapter Eight
Fit-Up Quality
Tank Bottom
The levelness of the tanks base plate(s) is critical if the rest of the tank is to be erected properly. The constructors steel-erection supervisor should check the foundation(s) for differences in elevation. Any such differences should be compensated for by shims underneath the base plate(s). If this task is not done properly, or if there were fabrication problems with the steel, the purchaser may see slivers of steel that need to be cut from seams, frequent use of a large hammer to form the steel variations in the seam gaps, or plates not aligned in accordance with the tolerances required in AWWA D100 Section 10.6.3. These problems usually produce a tank of unacceptable aesthetic or structural quality.
Tank Shell
AWWA D100 has several t-up requirements. Most are related to appearance of the structure, but improper t-ups can be structurally signicant if bad enough. AWWA D100 addresses plumbness of the shells of ground storage tanks. The shells deviation from vertical should be measured as the shell is erected, and variations from vertical should be corrected when they approach the limits set in AWWA D100. The standard also establishes the roundness of the shell. The tank diameter should be measured in several locations 1 ft (0.3048 m) above the tank bottom corner weld. The measurements should not exceed the tolerances established in AWWA D100. AWWA D100 also establishes tolerances for peaking and banding of the shell of ground storage tanks. Peaking is the out-of-plane distortion across a vertical weld seam, and banding is the out-of-plane distortion across a horizontal weld seam. To measure peaking and banding, a sweep board is useful. A sweep board can be constructed from a piece of plywood 36 in. (0.9144 m) long. One side of the plywood board should be curved to the radius of the tank, and the other side should be at. The curved side should be used to measure peaking, and the at side should be used to measure banding. The offset of aligned shell courses is governed by AWWA D100. During t-up, it should be veried that the plates are aligned within the tolerances established in D100, and these tolerances should be maintained throughout the welding process.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
I n s p e c t i n g N e w - Ta n k C o n s t r u c t i o n
289
Welding Quality
According to AWWA D100, the constructor is required to check the quality of the welding. It is the job of the owner to monitor the constructors quality control program. First, the owner should collect the certication papers of all welders on the site. These papers detail the types of welding and the steel thicknesses for which the welder is certied. The most common method of evaluating weld quality is by means of radiography. The purchaser should participate in the selection of radiograph locations, watch for documentation of the radiographs, and review the radiographs with the constructors quality assurance expert. The areas selected should be in strict accordance with the AWWA D100 standard, which requires that the radiographs reect the general quality of welding on the tank. Equal proportions of shop, ground, and air welds should be reected in the radiographs. The contractor should document these radiograph locations on a rollout. AWWA D100 has radiograph inspection standards that must be used for evaluating discontinuities and defects present in radiograph lm. The penetrameter, which ensures the reviewer that the radiograph was sensitive enough to identify the smallest defect addressed by the standard, must be visible in each radiograph. It is vital that the radiographs be evaluated in accordance with this criterion and that any repairs and follow-up radiographs be conducted in accordance with D100. It is also important for the tank constructor and purchaser to visually inspect all welds to ensure the removal of all weld splatter, sharp surfaces, overlaps, and unacceptable undercuts that will be detrimental to the coating life. Welds do not need to be perfectly smooth, but sharp edges must be removed. Ground storage tanks erected under AWWA D100 Section 14 Alternative Design Basis require many more radiographs than standard tanks.
Bolting Assembly
Bolted-steel tanks require the proper placing of steel sheets, gaskets, and sealants. Some erection methods may also require pre-tensioning the sheets and tightening the bolts to a prescribed torque. These details are covered by the manufacturers erection instructions and drawings. The engineer or purchaser may require that a set of these instructions be included with the shop drawing package that is submitted.
Tank Appearance
Tank appearance is of great importance to many owners. The nal appearance is known only after the tank is coated, when dents and buckles become apparent. It is then that the owner expresses dissatisfaction. Determining how well the tank complies with the specications and applicable codes and negotiating a settlement for poor appearance are time-consuming and stressful. Usually these problems
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
290
Chapter Eight
can be avoided if the constructor checks to see that the tank is level, round, and plumb as it is being built. Incorporating dimensional tolerances into the contract will also minimize disputes. AWWA D100 species some of these tolerances.
Surface Regularity
A smooth, regular surface provides a good base for the application of a protective coating system, thus helping reduce maintenance costs. To this end, the constructor and the purchaser should ensure that the weld contour is smooth, that unacceptable weld undercutting is eliminated, that weld spatter is ground off, that remains of welds used to attach erection and t-up equipment are chipped and ground smooth, and that unacceptable gouged-out places in the steel are lled in. Representatives of the tank constructor and the purchaser should be alert for sharp edges or areas that would cause premature coating failure so that corrective action may be taken as the work progresses.
Water Testing
When welded tanks are water tested before they are coated, any leaks that are found can be repaired without requiring any coating to be redone. If the tank is not lled until after it has been coated, small pinholes in the welds may be plugged temporarily with coating; these will cause leaks later if the coating breaks loose. The owner should ensure that water for the test is available at the time and pressure necessary to coincide with the constructors schedule. The owner should also ensure that provisions are made for draining and disposing of the test water. If leaks are found in factory-coated bolted tanks, the constructor should make repairs according to the manufacturers recommendations.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
I n s p e c t i n g N e w - Ta n k C o n s t r u c t i o n
291
Steel Cleanliness
The rst requirement for a good coating is a clean surface. The steel should be free from dirt and oil, both of which may accumulate during construction. All weld seams, abraded areas, scratches, shop or eld markings, or poorly adhering shop primer should be removed by abrasive blast cleaning. The areas cleaned by abrasive blasting should blend well into the adjoining undisturbed shop primer. Some shopapplied primers must be scaried or otherwise prepared before ensuing coats are applied. The purchaser should also be aware that welding or cutting activity on one side of a plate is likely to damage the coating bonding on the opposite side of the plate. This is especially important if shop priming is used. The areas opposite welding or cutting operations should be examined for coating damage resulting from the heat induced by the cutting or welding process. The manuals Good Painting Practice and Systems and Specications visual standards and an inspection manual available from the Society for Protective Coatings give good guidelines for inspecting coatings.
Inspection Instruments
Instruments needed to inspect coating include at a minimum a wetlm thickness gauge, a calibrated dry-lm thickness gauge, equipment for measuring air temperature and humidity, a steel-temperature thermometer, a surface-prole measuring device, and a wet-spongetype holiday detector. The holiday detector is used to inspect the coating for voids that will cause premature coating failure. If full-time inspection is not conducted, destructive testing involving the use of a Tooke Gage and/or other instruments will be necessary to evaluate the thickness of each coat and to obtain an indication of the cleanliness of the substrate.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
292
Chapter Eight
Inspection Planning
The purchaser should plan work to aid in the timely completion of the tank eld coating. This will require open lines of communication with the coating company and an understanding of the effects of weather on coating progress. The constructor will also need to work efciently in good weather. The purchaser should state requirements for the number of locations to be tested according to the total surface area of the plate. Minimizing testing is unwise, but an excessive number of testing locations places an unreasonable burden on the constructor and can substantially delay the progress of the tank coating. SSPC PA2 delineates procedures for measuring coating dry-lm thicknesses. To avoid excessively delaying the coating progress, large tanks may require more than one purchasers representative to conduct the required eld tests.
Shop-Applied Coatings
Bolted tank panels are coated at the factory under controlled conditions. AWWA D103 requires that the panels be grit-blasted to nearwhite metal (SSPC SP10) and coated within 15 minutes of cleaning to prevent rust from starting. The coating is then either baked on or fused on. If desired, the purchaser may observe these operations during shop inspection. If specied, a preconstruction primer may be shop applied to new welded-steel tanks. Observation of the shop painting and fabrication of the steel components of welded-steel tanks is necessary to evaluate proper fabrication techniques, shop surface preparation, and shop primer application.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
I n s p e c t i n g N e w - Ta n k C o n s t r u c t i o n
293
r Electrical wiring should meet applicable codes. r Conduits, xtures, pipes, valves, or other items should not r Cathodic protection anodes and hand-hole covers should be
properly placed, and the purchasers representative should witness the energizing of the cathodic protection system and the initial potential prole being conducted as per the project specications. interfere with the safety of the ladders or platforms.
r All hatches should be locked. r Safety belts and sleeves should be furnished for the ladder
safety devices. Safety sleeves should be checked for proper operation along the full height of the rails or cables. Any coating, deviations, or obstructions that prevent the free operation of the sleeve should be removed.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Source: Steel Water Storage Tanks: Design, Construction, Maintenance, and Repair
CHAPTER
Operation
Jos e N. Hern andez, P.E.
City of Cleveland
There are an estimated 400,000 potable water storage tanks in the United States. Worldwide, the total number of tanks is undoubtedly staggering. Water-storage facilities have played and continue to play a pivotal role in the growth and success of water distribution systems. Existing and new tanks come in a variety of styles, construction materials, congurations, and functions, and they have a wide range of capacities. Tanks have been constructed from materials as diverse as steel, wood, and concrete; they can be at ground level, elevated, or buried. They can have many different inlet and outlet congurations and can hold as little as 10,000 gal (37,854 L) or as much as 140 mil gal (529,957.6 kL) or more (Fig. 9-1). These and other factors inuence tank performance and capabilities. Such characteristics also play a role in how utility personnel operate the tanks, and how they affect the important tank functions such as emergency storage capacity and the preservation of water quality. Concerns about the effects of tank characteristics and operation on water quality present new challenges for both operators and tank design engineers. It is the intent of this chapter to provide the reader with practical information, in addition to technical and scientic data, regarding the design and operation of potable water storage tanks. Although tanks are often the most visible part of a water distribution system, they are just one among several major components in a system designed to bring potable water to utility customers. Potable or drinking water can be dened as the water delivered to the consumer that can be safely used for drinking, cooking, and washing (De Zuane 1997).
295
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
296
Chapter Nine
FIGURE 9-1 Masonry and concrete reservoir, capacity 23 mil gal (87,064 kL), in Parma Heights, Ohio.
A utilitys water may begin its journey to its customers from a nonpotable (raw) source or from another utility acting as a wholesaler. Raw water can be groundwater, such as in the case of wells. It can also be surface water from lakes, rivers, or dams (Fig. 9-2). It may also be desalinated brine or seawater. The raw water is treated according to rules and regulations established by government regulatory agencies. Myriad treatment strategies are available. The applicability of each treatment strategy depends on the characteristics of the source water and the technology
FIGURE 9-2 Water intake crib in Lake Erie; Cleveland, Ohio, is in the foreground.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
Ground tank
297
Surge tank
required to make it potable. There is an extensive list of references on potable water treatment. AWWAs Water Quality and Treatment, A Handbook on Drinking Water, published by McGraw-Hill (AWWA 2010), is an excellent general reference on this subject. Once treated, water is usually stored in a large tank or reservoir at or near the treatment plant. Finished water is then pumped into a water distribution system serving a community or service area, as demand requires. Water distribution systems comprise several major components (Fig. 9-3). Pipes and piping systems include trunk and distribution mains, valves, and hydrants. Trunk mains are large-diameter pipes that carry water away from treatment plants. Trunk mains branch off into distribution mains. Distribution mains are smaller pipes that carry the water through individual streets or zones. Each water customer has at least one service tap into a distribution main. In a well-designed distribution system, trunk and distribution mains act as a network, or web, with many connecting nodes. The web connections are redundant. If a section of pipe inside the web should break, valves could be closed to isolate a small affected area and conduct repairs while maintaining service to the remaining customers in the system. The pipe networks design serves another function. A completely closed pipe network has no dead ends, thus eliminating the possibility of water stagnation. When a distribution systems area is very large or encompasses substantial differences in elevation, it is often necessary to divide the system into two or more pressure zones, or highs. Booster pumping stations are used to raise the pressure of the water as it is pumped from a low-pressure zone to a high-pressure zone. Storage tanks are connected to the trunk-main web. Under optimal conditions, a distribution system is designed so that one or more storage tanks are located at the opposite end of the systems grid from the pumping station. The main function of a water distribution system is to deliver sufcient quantity of potable water at a minimum established pressure
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
298
Chapter Nine
to utility customers. This role has been expanded in recent years to that of preserving the quality of the water in the system. More detailed information regarding the design and operation of potable water distribution systems is available from many sources, including the Water Distribution Systems Handbook (Mays 2000).
Tank 1
Treatment plant
Tank 2
Tank 3
FIGURE 9-4 Node representation of a distribution system network; arrows indicate average pipe segment ow.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
Hydraulic grade line Energy grade line
299
V 2/2g Total dynamic head H static Elevated tank Trunk and distribution water mains Pump
Ground tank
FIGURE 9-5 Distribution system energy lines. (Note: V 2/2g = velocity head.)
The energy head at any point in the distribution system is calculated using the Bernoulli equation: H= V2 P + +Z 2gc
Each point in the system has an energy level, H . The energy grade line (EGL) is a graph of the total energy versus position in a pipeline from a reference line or datum. Friction losses in the pipe cause the EGL to slope downward in the direction of ow. Since friction in the pipe is a function of uid velocity, the faster the ow, the steeper the EGL. The hydraulic grade line (HGL) is a graph of the sum of the pressure and potential energies versus position in a distribution system from the reference line or datum. The HGL level at any point in the distribution system is equal to the height a water column would rise inside a vertical conduit open to the atmosphere. It can also represent the height of the water in a tank connected to the system at that point. The kinetic energy component is the difference between the EGL and the HGL. Figure 9-5 shows distribution system energy lines. In most water distribution applications, the elevation and pressure head terms are much greater than the velocity head term. For this reason, velocity head is often ignored, and modelers work in terms of hydraulic grades rather than energy grades. Therefore, given a datum elevation and an HGL, the pressure can be determined as (Walski, Chase, and Savic 2001): P = (HGL Z) Both the EGL and the HGL increase at the location of a pump within the pipeline by an amount equal to the head added by pumping. The head added by pumping (h A ) may be calculated if the ow
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
300
Chapter Nine
velocity and gauge pressure are known for the suction and discharge pump nozzles. hA = P V2 + +Z 2gc
discharge
P V2 + +Z 2gc
suction
The head added by the pump is a function of the ow rate through the pump. A graph of pump head versus ow rate is called the pump curve. The plotted head is the head difference across the pump and is given the name total dynamic head (TDH). Traditional hydraulic modeling provided an insight into how the water level in tanks changed under simulated demand conditions. However, the water in the tank was considered of invariable quality. Hence, there was no difference in quality whether the water was entering the tank, inside it, or leaving it. In the past decade, increased emphasis on water quality in storage facilities prompted more detailed investigations of water dynamics in tanks. Modeling of water ow regimes and water quality in tanks has been done using multiple methods:
r r r r
Scaled laboratory models Tracer studies Semiempirical mathematical models Computational uid mechanics using nite-element or nitevolume models
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
Weber number We = U 2 L
301
where U is the free stream velocity of the system; L is the characteristic length, diameters, or depths; g is the gravitational acceleration; is water density; is the viscosity of water; and is the surface tension of water. A tank and a geometrically similar model are in similitude if Re , Fr , and We are the same. The scaling of the model, however, is based on the predominant parameter for each particular application. The Froude number is generally used in the scaling of water-storage facilities. A scale model should be as large as possible to minimize scaling errors on tank performance. Many sources quote typical scale ratios for tank models in the range of 1:30 to 1:50. Chemical tracers or dyes are used to visualize streamlines in the model. However, most sophisticated technology, such as optical technology and lasers, has been used to quantitatively measure scalar values. The objective of these tests is to trace water streamlines from the inlet as they mix with ambient water in the vessel and exit the tank. The tracer is monitored at the outlet and compared with a constant inuent concentration over time to determine how much time water spends in the tank (residence time). The effects of temperature on the buoyancy of inuent water are of particular interest for tank modeling. Temperature distribution in tanks can be measured at different locations and depths in the model with temperature probes.
Tracer Studies
Tracer studies are conducted in water storage tanks to determine residence time and/or water quality distribution (Fig. 9-6). Tracers may be chemicals or dyes that can be tracked or measured by ion-specic electrodes, conductivity probes, colorimeters, or visual/camera observation. A tracer can be introduced at a known concentration by a dosing pump at the tanks inlet piping. Typical tracers include chloride ions (such as sodium chloride, calcium chloride, and lithium chloride), uoride ions, and the uorescent dye Rhodamine WT. Local regulatory agencies must approve the use of a particular tracing chemical for studies of actual potable water tanks. The tracer should not be consumed or removed during treatment. Fluoride ions are not typically present naturally in water. Therefore, uoride can be used in lower concentrations than chloride tracers. Rhodamine WT must be used following certain guidelines found in Appendix D of the August 1999 US Environmental Protection Agency (USEPA) Disinfection Proling and Benchmarking Guidance Manual (USEPA 1999). Selection of a
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
302
24
Chapter Nine
22
20
18
16
14
12
10 0 1 2 3 Time (h) 4 5
FIGURE 9-6 Tracer study results of live pass-through distribution system tank with plug ow to determine contact time.
particular chemical tracer may depend on the salt concentrations present in the water. Specic instructions on chemical tracers and the conditions under which they are most effective are found in Appendix D of the Guidance Manual. If a tracer study is needed to nd the contact time (CT), a water system should consult the latest tracer study guidance from its regulatory agency. The tracer chemical should be added at the same injection points as the disinfectant to be used in the CT calculations. Tracers are commonly added in two ways: the step-dose method and the slug-dose method. In the step-dose method, the tracer is injected at a constant dosage, and the endpoint concentration is monitored. To acquire 90 percent recovery for the tracer, endpoint sampling should continue until the tracer concentration reaches steady-state level. In the slugdose method, however, a large dose of tracer chemical is instantaneously injected. The tracer concentration is then monitored at the endpoint until the entire dose (slug) has passed through the tank. Figure 9-7 shows apparatus to measure CaCl tracer concentration. A mass balance is required for this method to determine whether the entire tracer dose was recovered. Contact time is then determined mathematically from the concentration versus time prole. A tracer study is generally done as follows:
r Determine the ow rate or rates to be used in the study. r Select the tracer chemical and determine the raw water background concentration of the tracer chemical. This is needed
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
303
FIGURE 9-7 Apparatus to measure CaCl tracer concentration at tank inlet and outlet. Ion-specic probes can be seen at left. Data were recorded on a PC.
r Determine the appropriate tracer dosage. r Determine tracer addition locations, sample collection logistics, and sampling frequency. Sampling frequency depends on the size of the tankthe larger the tank, the less frequent sampling is needed, but the longer the duration of the sampling event. method.
r Conduct the tracer test using either the step-dose or slug-dose r Compile and analyze the data. r Calculate CT.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
304
Chapter Nine
geometric parameters. Some of these models have an extensive database of experimental data so that they can produce highly accurate results if the operational conditions are within the datas range. These models have been adopted by the USEPA for outfall modeling of discharges into bodies of water.
FIGURE 9-8 Computational uid dynamics model of reservoir with two inlets and two outlets showing velocity contours. Light gray is highest velocity and dark gray is stagnant.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
reattachment, vortices, and swirl are not accurately predicted by current mathematical procedures. Specialized application software packages are available to predict such phenomena, but they are limited in application and cannot easily be generalized due to their reliance on numerous empirical and semiempirical equations. These limitations allow general-purpose CFD modeling to be more useful for bafing and plug ow optimization than mixing, for example. Some packages include dispersion models or the ability to incorporate transport equations programmed by the modeler. Nevertheless, the capability of the packages to produce accurate predictions is limited by the mathematical constraints of modeling curvilinear ow patterns and uctuating or time-dependent phenomena. Their capability is also limited by the modelers grasp of advanced uid mechanics principles and his or her ability to detect an improbable or inaccurate result. Otherwise, the phrase garbage in, garbage out may apply. Many CFD users have learned that validating models against real-world testing or experimental data is needed to prevent faulty or inaccurate solutions. CFD is a step in the design process that minimizes trial and error, but it is not in itself a validation of design.
305
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
306
Chapter Nine
FIGURE 9-9 Chlorine residual analyzers monitor inlet and outlet disinfectant residual at ground storage tank.
mandated to mail the CCR directly to their customers. The report discloses contaminant levels in a communitys drinking water supply alongside MCLs and maximum contaminant level goals (MCLGs). It also tells what type and concentration of disinfectant, such as chlorine or chloramines, is used by the utility. Whenever a disinfectant molecule reacts with organic or inorganic molecules in the water, it forms what are commonly known as disinfection by-products (DBPs). DBPs are a collection of chemicals, including trihalomethanes (THMs) and haloacetic acids (HAA5), that are highly soluble in water. Animal testing has demonstrated that some of these compounds have carcinogenic properties. Other disinfectants, such as chloramines, chlorine dioxide, and ozone, may yield DBPs upon reacting with organic or inorganic molecules. The reaction products from such interactions are similar to those produced by chlorine, but they tend to occur in smaller concentrations. Figure 9-9 illustrates a chlorine residual analyzer. The USEPA announced in December 1998 the Disinfectant/Disinfection By-Product Rule, Stage 1 (D/DBP). This rule created the following MCLs: total THMs, 80 g/L; HAAs, 60 g/L; and bromate, 10 g/L. The rule also established MCLs for disinfectants: chlorine, 4 mg/L; chloramines, 4 mg/L; and chlorine dioxide, 0.8 mg/L (AWWA 2003 Principles and Practices). The USEPA published the Stage 2 Disinfectant/Disinfection ByProduct Rule (Stage 2 DBPR) on January 4, 2006. The Stage 2 DBPR
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
builds on existing regulations by requiring water systems to meet DBP MCLs at each monitoring site in the distribution system to better protect public health. The Stage 2 DBPR includes a provision requiring all community water systems (CWSs) and only nontransient noncommunity water systems (NTNCWS) serving more than 10,000 people to conduct an initial distribution system evaluation (IDSE). NTNCWSs serving fewer than 10,000 are exempted from IDSE requirements, but will need to comply with the Stage 2 DBPR compliance monitoring requirements. The goal of the IDSE is to characterize the distribution system and identify monitoring sites where customers may be exposed to high levels of total trihalomethanes (TTHM) and haloacetic acids. Compliance with the IDSE requirements includes the modeling or monitoring of distribution system site on the basis of criteria outlined by the EPA that include all water-storage facilities. Utilities are required to report trended averages per site and address MCL violations. The Total Coliform Rule mandates monthly monitoring of distribution system samples for coliform bacteria. A fecal or Escherichia coli bacteria test must be performed on any positive sample. Additional samples and analyses are required at the positive-sample point as well as in its vicinity within 24 hours. Utilities must submit a sampling plan, and samples must be taken at the customers taps or from taps that are representative of the distribution system. The Total Coliform Rule does not require the testing of water from storage facilities or their outlet pipes. The Lead and Copper Rule (LCR) mandated desktop studies to determine the need for corrective action regarding lead and copper concentrations. Many utilities discovered that they required the addition of corrosion-inhibiting agents to arrest the release of copper or lead ions from piping materials into the water. Action levels for copper and lead were set at 1.3 mg/L and 0.015 mg/L, respectively. Pilot studies were conducted by utilities to identify the most suitable inhibitor for their system. Orthophosphate and phosphoric acid are popular choices. Stagnant areas of distribution systems, such as dead ends or poorly mixed tanks, readily lose their residual concentration over time. Residual phosphate compounds used as inhibitors do not readily dissipate like disinfectants do. In the absence of sufcient disinfectant, these compounds can foster the development of biological agents such as algae and bacteria. Regular ushing of dead ends in distribution systems and appropriate tank design and operation are needed to eliminate this potential problem. The water quality in distribution systems water storage tanks and reservoirs is affected by several other factors. Some likely issues, their cause, and suggested solution are listed in Table 9-1.
307
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
308
Suggested Solution(s) r Investigate low ow or demand for size of mains r Boost disinfectant in large/multizoned distribution systems r Find valve issues in trunk mains r Biolms on interior pipe surface are difcult to eliminate, r r r r r prevention is best choice: adequate pipe velocity, disinfection, and ushing Improve disinfection and ushing after main repair or installation Eliminate dead ends in distribution system Find and repair main breaks, leaks, and backow issues Solve issues at upstream tanks, if any Boost disinfectant
Operation
Possible Cause(s) r Excessive water transport time to tank r High biological or chemical demand in distribution system r Distribution system backow or pipe integrity issues r Number and size of tanks in series upstream of facility and their water quality issues
Nitrication
r Chloramines
r Ensure adequate chloramines residual throughout the system (2.0 to 2.5 mg/L) r Reduce water age by avoiding excessive storage residence time r Use chlorine:ammonia:nitrogen ratio of 4.5:1 r Hydraulic analysis to investigate proper distribution piping, pumping, or storage requirements r Revisit tank location and elevation r Excessive pump operation
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
r Low inow and/or outow r Low tank volume change over time r Low normal demand versus tank size r Improper tank location, elevation, or size
Stratication
r Tank geometry and location of inlets and outlets r Buoyancy caused by temperature difference between tank ambient and inuent water r Accumulation of sediments:
r Increase tank turnover r Improve tank mixing r Properly locate inlets and outlets
chemical and biological demand r Exposure to ultraviolet (UV) light (open tanks) r Diffusion due to ambient air temperature r Corrosion of tank metals r Excessive water tank residence time
Operation
Biolms r r r r
r Availability of nutrients in water or tank surfaces r Low disinfectant residuals r Nitrication r Warm temperatures r Corrosion inhibitors r Tank coatings
r Periodic cleaning of tank sediments r Eliminate tank elements that allow sediments to accumulate or provide habitat for biolms r Install appropriate tank cover r At tank design, decrease ratio between water surface area and tank volume r Design venting to prevent excessive air drafts above water surface r Conduct periodic tank maintenance and rehabilitation r See Stratication r Perform periodic tank cleanings r Monitor condition of vents and hatches to prevent biological pollutants from entering tank See Loss of Disinfectant Residual See Nitrication Improve tank turnover and mixing Replace with NSF61-approved coatings that do not promote biogrowth; minimize crevices, gaps, and substrate imperfections before applying coatings to minimize biolm habitat
309
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
TABLE 9-1
310
Suggested Solution(s) r Provide tank mixing r Provide bafing for pass-through tanks (if inlet and outlet are connected to different pressure zones with little or no backow) r At design, optimize ratios of tank surface area to volume and of height to diameter r Locate inlets and outlets such that the largest volume of water in the tank is contained between them r See Short-Circuiting r See Stratication r Follow manufacturers recommendations for cure time versus substrate surface temperature r Follow manufacturers recommendations for component mixing and use factory-measured quantities r Use NSF61-approved coatings r Consult coating specialist for proper coating selection and surface preparation r See Effects of Ice r Ensure proper surface preparation during maintenance or rehab r Follow periodic and comprehensive tank inspection and maintenance program
Operation
Issue Short-circuiting
Coating leachates
r Insufcient coating cure r Improper coating component mixing or mixing ratios r Not NSF61-approved coatings
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Effects of metal corrosion in contact with the water, such as red water, iron-reducing bacteria, and high turbidity
r Improper coating or coating application r Ice damage r Presence of sharp edges, cavities, or gaps that prevent proper coating or cause coating failure r Inadequate tank inspection and maintenance program
Contamination, intentional or unintentional, through tank openings such as vents and hatches r Periodically clean tank sediments
r Improper vent and overow screening r Improper hatches r Tank cover r Improper tank overow and drain
r Provide and maintain vent and overow screening r Provide secure hatches and proper tank covers to prevent animals, insects, vandals, or rain from entering tank r Provide proper air gaps
Chemical composition of precipitates in the storage facility, such as iron and manganese r r r r
r Metals come out of solution and settle inside tanks, affecting water quality in high concentrations
Operation
Effects of ice including tank damage; encapsulation and later release of contaminants, debris, and coating particles upon meltdown
Provide insulation and heating of a tank for surge tanks Provide tank cover At design, bury or partly bury tanks See Stratication
TABLE 9-1
311
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
312
Chapter Nine
Security Concerns
The events of September 11, 2001, raised questions about the safety of the nations water supply. In general, water tanks are accessible through access hatches, air vents, overows, and access ladders. These entry points can be tempting targets for vandals or criminals attempting to contaminate the water supply. They are also potential sources of accidental contamination from rainwater, birds, insects, and other natural sources. Continuous online monitoring of water quality parameters can provide an indication or alarm should contamination occur. The affected tank can be isolated from the system, and authorities and the public can be notied. Figure 9-10 illustrates protective measures for water tanks.
Tank-Monitoring Program
The tanks themselves can be a source of concern. Leaching from coatings, red water and bacteriological concerns from rusting wet surfaces or overhead structural elements, accumulation of sediments that may contain biolms, settled metal particles, or other detriments to water quality may be present in storage. Some may engender complaints about the waters taste, odor, or appearance. A tank-monitoring program provides a utility with background data of tank parameters for different seasons and weather conditions; it helps establish schedules for tank inspection and maintenance; and it can serve as a guide to water quality managers for planning treatment strategies for changing distribution system conditions. Although no regulatory requirements in the United States mandate tank monitoring, there are regulations that require periodic water
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
313
FIGURE 9-10 Tank overow and catch basin are protected from insects or vandals by combination of stainless-steel cage and insect screen; ow switch (not shown) triggers overow alarm.
testing in distribution systems. The National Primary Drinking Water Regulations (CFR 141.23), the Surface Water Treatment Rule (SWTR), the Lead and Copper Rule (LCR), the Total Coliform Rule, and Stage 1 of the D/DBP all establish contaminant restrictions and monitoring requirements for distribution systems. Table 9-2 provides water quality parameters and related regulatory information. Regulations cover such important contaminants as total and fecal coliform bacteria and heterotrophic bacteria, disinfection by-products such as trihalomethanes (THMs) and haloacetic acids (HAAs), nitrite, nitrate, lead, and copper. They also limit the concentration in the system of residual disinfectants such as chlorine or chloramines. The USEPA has identied several secondary contaminants (nonenforceable) under the National Secondary Drinking Water Regulations (NSDWR). The enforceability of this rule is up to the individual states regulatory agencies. Table 9-3 lists the secondary nonenforceable contaminants. At a minimum, utilities should attempt to monitor disinfectant residual, heterotrophic plate count (HPC), and coliform bacteria in water-storage facilities. Suspected biolms on tank surfaces should be sampled and speciated to determine source or cause. An ideal way to test a tank for biolms is to prepare a metal or concrete coupon with a coating and nish similar to those of the tank. The coupon can be
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Parameter
Surface Water Treatment Rule D/DBP Rule, Stage 1 Surface-water systems serving more than 10,000 people Only applies to systems using surface-water supplies
Sample Location
Regulatory Limit
Reference
Comments
Disinfectant residual
314
Surface Water Treatment Rule National Primary Drinking Water Regulations (NPDWR), Code of Federal Regulations (CFR) 141.23 NPDWR, CFR 141.23 D/DBP Rule, Stage 1 D/DBP Rule, Stage 1 Total Coliform Rule Lead and Copper Rule Lead and Copper Rule Lead and Copper Rule Maximum contaminant level Maximum contaminant level Systems serving more than 10,000 people Systems serving more than 10,000 people Action level at 90th percentile Action level at 90th percentile Unless state determines otherwise
Disinfectant residual
Distribution system
Maximum residual disinfectant levels (MRDLs): chlorine, 4.0 mg/L; chloramines, 4.0 mg/L; running annual average
Detectable levels of disinfectant residual or HPC bacteria count of 500 or fewer colony-forming units (cfu) per milliliter in 95 percent of samples collected each month for any 2 consecutive months
Only applies to systems using surface-water supplies; in the United States, Legionella is also regulated by a treatment technique
Nitrite
1.0 mg/L as N
Operation
Nitrate
10.0 mg/L as N
Total trihalomethanes
Lead
Customers tap
0.015 mg/L
Copper
Customers tap
1.3 mg/L
pH
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
TABLE 9-2
Operation
Operation
Secondary Maximum Contaminant Level 0.050.2 mg/L 250 mg/L 15 color units 1.0 mg/L Noncorrosive 2 mg/L 0.5 mg/L 0.3 mg/L
315
Parameter Aluminum Chloride Color Copper Corrosivity Fluoride Foaming agents Iron
Conditions Colored water Salty taste Visible tint Metallic taste, blue-green stain Metallic taste, corrosion, xture staining Tooth discoloration Frothy, cloudy, bitter taste, odor Rusty color, sediment, metallic taste, reddish or orange staining Black to brown color, black staining, bitter metallic taste Rotten-egg, musty, or chemical smell Low pH: bitter metallic taste, corrosion High pH: slippery feel, soda taste, deposits Skin discoloration, graying of the white part of the eye Salty taste Hardness, deposits, colored water, staining, salty taste Metallic taste
Manganese
0.05 mg/L
Odor pH
Silver
0.10 mg/L
5 mg/L
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
316
Chapter Nine
Parameter Iron oxide Aluminum hydroxides Calcium carbonates Manganese Heterotrophic plate count (HPC) Depth of sediment Gross microbial examination Indication Parameter Is Present Distribution system corrosion Excess aluminum after occulation Supersaturation of minerals in hard waters Source-water problem Taste and odor problems; recurring bacterial counts Rate of accumulation; disinfectant residual loss due to resuspension System cross-connection, poor hydraulic circulation, or failed facility vent screening
fastened to a wet tank surface so that its conditions mimic those of the tank walls. In this manner, the coupon can be retrieved from the tank for analysis without interfering with tank function. Samples from tank bottom sediment may be collected to determine chemical composition or biological activity. Kirmeyer et al. (1999) recommend the sediment monitoring parameters outlined in Table 9-4. The need to monitor other bulk water parameters varies depending on the type of tank, source water, environmental conditions, and so on. Monitoring the amount of sediment accumulated in the tank bottom can give a utility an indication when the next cleaning cycle should take place. Table 9-5 lists water quality monitoring parameters recommended for storage facilities. Several nitrication tests should be performed where chloramines are used for secondary disinfection. As a minimum, tests for heterotrophic plate counts (HPC), nitrite, nitrate, ammonia, and chlorine species can help to ensure that optimal conditions are maintained in storage facilities when chloramination is used.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
Sampling Procedure Used
317
Parameter Alkalinity
Purpose
Indicates potential buffering On-line ion-selective capacity (pH stability) electrode or grab sample and laboratory analysis Indicates potential coagulant overfeeding On-line ion-selective electrode or grab sample and laboratory analysis On-line ion-selective electrode or grab sample and laboratory analysis On-line chlorine residual analyzer or grab sample and amperometric titration laboratory analysis
Aluminum
Indicates protection from bacterial growth and provides early warning sign of water quality deterioration; monitored at inlet and outlet to control rechlorination when practiced Indicates the presence of indicator bacteria
Can quickly indicate relative On-line ion-selective electrode or grab changes in total sample and dissolved solids (e.g., laboratory analysis alkalinity) Represents potential for ongoing chemical reactions and DBP formation Indicates conformance to MCL; provides early warning sign of water quality deterioration Indicates potential corrosion reactions Grab sample and laboratory analysis
Disinfection by-products
Heterotrophic bacteria
Iron
TABLE 9-5 Water Quality Monitoring Parameters for Storage Facilities (Continued)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
318
Chapter Nine
Sampling Procedure Used On-line ion-selective electrode or grab sample and laboratory analysis On-line ion-selective electrode or grab sample and laboratory analysis On-line ion-selective electrode or grab sample and laboratory analysis Grab sample and laboratory analysis On-line sensor
Parameter Nitrate
Nitrite
pH
Indicates changes from the water source; indication of corrosion of concrete or an unlined new facility Evidence of water quality problem in progress Differences in storage facility indicate possible stratication and stagnant zonesearly warning sign of potential microbial problems Provides early warning sign of water quality deterioration
Turbidity
TABLE 9-5 Water Quality Monitoring Parameters for Storage Facilities (Continued)
Sampling is divided into two categories: grab samples and continuous sampling. Grab samples are small volumes of tank water manually collected by a technician to be analyzed either in the eld or under laboratory conditions. Continuous sampling is accomplished by means of electronic equipment such as ion-specic probes, temperature probes, or on-line colorimetric chemical analyzers. The sensors are in the tank water, or tank water is continuously or periodically piped to the sensor. The data are recorded locally either on paper or electronically, or they are transmitted via telemetry to the utilitys data storage and monitoring facility. Kirmeyer et al. state that
a [monitoring] program that takes all necessary parameters into account and schedules sampling when needed to provide adequate information is a conceptual starting point. A recommended approach. . .is to further
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
break down sampling needs into two categories of routine sampling and diagnostic sampling. Routine sampling is dened as monitoring of parameters on a regular (continuous, weekly, monthly) basis and may include regulatory and operating parameters. Diagnostic sampling is dened as special purpose monitoring to document condition or to determine the cause of a problem. Routine monitoring is used to document general water quality conditions, whereas diagnostic monitoring is often more facility specic. Diagnostic monitoring can rst provide a baseline for a storage facility and identify problems. After the problems are corrected, routine monitoring can then be used to track tank conditions to detect or prevent the recurrence of the problems or the beginning of new ones.
319
The types of data being collected or the purpose for the data collection dictates whether grab or continuous sampling is required for a particular parameter.
Grab Samples
In theory, technicians using grab sampling techniques can collect every type of parameter. Certain types of tank-water tests such as heterotrophic plate count, total coliform bacteria, chemical composition of tank sediments, biolm analysis, and disinfection by-products can only be performed on manually collected tank water, as they require analysis under laboratory conditions. A rare exception is when a tank is located next to the utilitys laboratory and sampling lines exist directly between the tank and the laboratory. The laboratory technician or chemist is then able to ll the test vial directly from the sampling tap. In most cases, technicians must travel to several tanks in remote locations as often as the monitoring program dictates the taking of grab samples. Under the best of circumstances, the sampling program includes the installation of permanently and properly located sampling taps on the tanks. The taps can be connected through small-diameter piping to several sampling locations inside the tank. This scheme can provide a more or less three-dimensional view of the tanks water quality parameters. The more sampling taps are installed, the more complete the water quality picture will be. The ideal locations for sample points are the inlet(s) and outlet(s), if any; locations that may be subject to short-circuiting or stagnation, such as regions not in the general path between the tanks inlet and the outlet; and at several depths to test for the effects or the presence of stratication. The sampling lines can be designed such that the water will ow out of the tank by gravity or be pumped out with the use of a jet (vacuum) or metering pump. Technicians must ush the sampling lines for sufcient time to provide a proper sample from the tank water at the sampling point. Twenty minutes of ushing is usually sufcient. Some systems allow for continuous ow through the sampling lines, which facilitates this step. Others are designed so that the sampling lines can be periodically disinfected and ushed. Permanently
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
320
Chapter Nine
installed sampling lines are a security concern, as they may provide easy access for intentional contamination of the tank water. Sanitation of the sampling collection area and frost proong are also concerns. Sampling lines create an environment in which a relatively small volume of tank water is enclosed by a relatively large surface area. This condition is favorable to the formation of biolms inside the sampling line. Technicians should monitor test results such as elevated bacterial counts or turbidity that may show such a problem exists. In general, sampling taps should be enclosed and protected from the elements. Pump station buildings, insulated enclosures, and heated underground vaults are all potential locations for sampling taps. (The vaults are not so convenient if conned space is a concern.) Most tanks, however, are not tted with sampling taps, and technicians must use roof hatches to gain access to the tank. This implies that the technician must be t, trained, and equipped to safely climb the tank and open the hatch and that the tank meets all Occupational Safety and Health Administration (OSHA) requirements for climbing safety. Several depth sample collection probes and tubes, such as weighted collection bottles with string-operated trap doors or rods with check valves, can be used to collect samples at different depths (Fig. 9-11). Although samples can be taken at various water depths using these devices, the number of sampling locations is limited by the location and number of roof hatches. The sampling equipment, including tethers, must be adequately disinfected before it is introduced into the tank. Care must be observed
FIGURE 9-11 Grab sample retrieved from ground tank using calibrated depth sampling tube with check valves.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
so that the equipment disinfection process is compatible with the parameter being tested. For instance, disinfecting a sample bottle and tether with 200 ppm of chlorine and then lowering the bottle into the tank to retrieve a chlorine residual sample may not yield a satisfactory result. The water must be collected in a properly prepared and labeled bottle suitable for the type of sample being prepared, and it must be transported to the laboratory in a timely and sanitary manner to preserve the validity of the test results. Some tests, such as colorimetric chlorine residual, may be performed by the technician on site, as there is a chance that the residual concentration may decrease in transit. More than one technician may perform grab samples. Proper training in sample collection and the use of calibrated tethers or rods helps maintain consistency among technicians and samples. Both on-site and laboratory analyses should be performed by a certied water quality laboratory using the methods specied in Standard Methods for the Examination of Water and Wastewater and the USEPAs Manual of Methods for Chemical Analysis of Water and Wastes.
321
Continuous Sampling
Climbing tanks to take grab samples can be dangerous or impossible, especially during rainy or cold weather. Continuous online sampling, which relies on technology rather than technicians to collect, analyze, record, and communicate the data, does not require that operators climb the tank to retrieve water or that they even be present during sampling, and its performance is independent from weather conditions. Online sensing probes may be located at various locations inside the tank, or water from various locations in the tank may be brought to an analyzer through sampling lines. The analyzer, data recorders, telemetry, and other equipment should be located in a secure, heated, and sanitary location to preserve the integrity of the readings. Figure 9-12 shows a pressure transmitter, analyzer, and corrater. Online sampling technology offers the advantage of a continuous data stream or data collected at relatively brief time intervals, depending on the type of test, type of instrument, and the utilitys desired sampling rate for particular parameters. Grab samples reect only a momentary condition of the water in the tank, often with no accurate time reference. The analyzed data can be stored on site using a personal computer, data logger, printout, or pen-chart. Operators can retrieve the data in either electronic or paper form at scheduled intervals that can vary from daily to yearly, depending on the purpose of the testing. Data can also be sent to a central data collection and monitoring facility using a telephone modem connection, remote terminal unit (RTU) with radio frequency communication capability, cellular technology, broadband (T lines), satellite, and so on. These methods of communication are
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
322
Chapter Nine
FIGURE 9-12 Left to right: tank water elevation (pressure transmitter), disinfectant residual (analyzer), and water corrosivity (corrater) are monitored for ground water storage tank.
discussed in the section Telemetry of this chapter. The amount of monitoring data storage is limited by several factors:
r r r r r
Number of parameters Total sampling rate for all the parameters Capacity of the data storage device Frequency of data retrieval by the utility Size of the data packages being stored for each parameter
Online monitoring can also serve a local control function. This is particularly useful in cases where rechlorination is desirable (Fig. 9-13). Online chlorine residual analyzers can serve both as monitoring devices for chlorine residual and as controllers for chlorineboosting feed systems. For example, when an analyzer at the inlet of a tank detects that the chlorine residual is below a level accepted by the utilitys water quality manager for the tank or is in violation of minimum disinfectant concentration regulations, it can start or adjust the on-site chlorine feed to match a target concentration. It is ideal for this process to take place at the inlet of the tank to provide some contact time for the disinfectant and as a backup safety mechanism for potential malfunctions of unmanned chlorine-feed systems. Ideally, a controller for such system should be able to determine whether the
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
323
FIGURE 9-13 Hypochlorite generation system makes disinfectant from brine for rechlorination at this water-storage facility.
water is inowing or outowing from a single inlet/outlet tank; and the boosting should only take place into the inow. A second chlorine residual analyzer monitoring the outow from a tank with an inlet and an outlet can be integrated as part of a feedback loop control for the boosting system and/or can serve as an alarm trigger in case of overfeeding. It is important to note that the effectiveness and accuracy of an online monitoring system is only as good as the maintenance it receives. A calibration schedule must be established for each type of analysis equipment being used. Most ion-specic probes have a life-span and must be replaced as recommended by the manufacturer. Some analyzers have moving parts that require cleaning and maintenance. Chemical solutions used by analyzers should be checked and replenished as needed. Sampling hoses must be kept clean and should be replaced when fouling is suspected or on a regular schedule. Maintenance technicians rst introduced to a monitoring program should be made aware of these issues and should be appropriately trained.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
324
Chapter Nine
Clearwells
Treatment plants require tanks in which to store treated water before it is pumped into the distribution system. These tanks are commonly known as clearwells. Clearwell sizing is critical to reducing or eliminating uctuations in use of ltered water. These tanks also provide the utility with disinfectant contact time (CT) credit. The SWTR requires that all surface water treatment facilities provide ltration and disinfection that achieves at least a 99.9 percent (3-log) removal-inactivation of Giardia lamblia cysts and a 99.99 percent (4log) removal-inactivation of enteric viruses. The SWTR assumes that for effective ltration, a conventional treatment plant achieves 2.5log removal of Giardia and a 2-log removal of viruses. Disinfection is required for the remainder of the removal-deactivation. The amount of disinfection credit to be awarded is determined with the CT concept, CT being dened as the residual disinfectant concentration (C , in mg/L) multiplied by the contact time (T10 , in minutes) between the point of disinfectant application and the point of residual measurement. The SWTR Guidance Manual (USEPA 1991) provides tables of CT values for several disinfectants that indicate the specic disinfection or CT credit awarded for a calculated value of CT (AWWA 1990). Clearwell design must take into account CT requirements for the particular treatment process served by the tank. It is a recommendation of the Ten States Standards (1992) that intermittently operated ltration plants with automatic high-service pumping from the clearwell during nontreatment hours provide enough extra clearwell volume to compensate for depletion of storage during nighttime hours to ensure adequate disinfectant CT. It is commonplace to design clearwells with two or more compartments. One compartment may be removed from service for maintenance or during times of low demand. Methods for optimizing CT in clearwells will be discussed in the section on plug ow in this chapter. Figure 9-14 is an aerial view of a bafed tank optimized for contact time. Clearwell operation must follow preset parameters for ow and elevation. It is desired that a clearwell should operate in a condition as close to steady state as possible. The hydraulic control of raw water pumping, lter efuent ow, and pumping out into the distribution system should be coordinated and interlocked, if possible, to prevent pulsating ows and other transients. Interlocks should also maintain elevations and should properly shut down during power failure. This allows for fast recovery when power is restored. To further prevent ow uctuations, since most raw water pumps are vertical pumps, caution should be exercised so that pumps are not operated in unstable regions of their curves.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
325
FIGURE 9-14 Aerial view of bafed tank optimized for contact time.
r Reduce the need for pumping during high water demand r Act as pressure relief should a pressure transient occur in a r Provide extra water storage for emergencies such as res or r Help optimize water treatment by allowing treatment plants r Help reduce the size of trunk and distribution mains r Act as a sediment trap to settle solids from distribution system r Serve as a landmark, even a source of identity and pride, for
a community The most important parameters in the design of distribution system water storage tanks are location and size. A tank serves a specic area of a distribution system. Hydraulic engineers, designers, and modelers must determine how much water must be stored in the tank water to maintain relatively constant treatment rates power outages distribution system periods (peak shaving)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
326
Chapter Nine
to serve both typical and emergency capacity demand. The water must be stored at sufcient elevation to meet the pressure requirements of the service area. It is important to keep in mind the preservation of water quality when sizing the tank and determining its operating characteristics. Distribution system tank operation is inherently intertwined with the pumping facilities that feed it, other parallel tanks and their elevations and capacities, the size of upstream piping, and valve operation. Each of these is discussed hereafter. Isolation valves in a distribution system may be inadvertently closed after repair of a water main break or after a new installation, for example. This may cause a lower-than-expected pressure at the end of a system, where tanks are likely located. Such a condition may prevent adequate lling of a tank, increase water transport time between the pump station and the tank (system residence time), and create customer dissatisfaction from low pressures. Periodic isolation valve surveys and valve exercising should be carried out to ensure proper valve operation and position to prevent isolation valve mishaps. Hydraulic modeling is a tool that can be used to assist in the location of improperly positioned isolation valves, pressure zone boundary valves, and faulty pressure regulators. All of these may reduce supply pressure to tanks. Altitude valves (Fig. 9-15) are installed at the system connection to tanks. There are two types of altitude valves: single acting and
FIGURE 9-15 Piston-style altitude valves shown here control ow and water elevation for two adjoining storage tanks.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
double acting. Single-acting altitude valves allow water to enter the tank when it is less than full. They do not reopen if the system pressure drops; they remain closed until some other connection or a check valve bypass causes the tank to draft, dropping the water level below the valves set point. Double-acting altitude valves are used for single-inlet/outlet tanks, since they eliminate the need for a check valve bypass. This reduces installation cost and possible transients caused by check valve slam. Double-acting valves close when the water elevation in the tank reaches a set point, and they open when the system pressure drops below another set point. Altitude valves can have hydraulic or electric solenoid pilot controls that allow for throttling inow and outow, further controlling ll and draft cycle times. Altitude valves, in general, have a considerable pressure drop. This is why many are installed with a bypass containing a remotely controlled valve, such as a motor-operated buttery valve. Some utility operators opt to lock the altitude valve in the full open position and use a motor-operated valve to isolate the tank if the water level gets too high. Some operators attempt to control the tank level by turning pumps on and off, throttling pump discharge check valves, or reducing a variable-speed pumps revolutions per minute (rpm), essentially negating the reason for having an altitude valve. In most water distribution systems, a tank experiences two cycles of ll and draft in a 24-hour period. The ll cycles usually take place at noon or midnight, 3 hours. To optimize power consumption, the ll and draft periods should be long enough that the fewest number and the smallest sizes of pumps are needed to satisfy demand. This also ensures that tank turnover is optimal. The number and size of pumps operating upstream of a tank can affect the available pressure at the base of the tank. In most cases, a pump is run continuously, and a second pump is added to help satisfy demand during peak hours if the tank cannot supply enough peak shaving. This number of pumps varies seasonally. Hydraulic modeling is useful not only during system design, but it can also be valuable for system operation because it can predict the amount of pumping required under various system conditions. If enough pumps are in operation, the tank will be lled with leftover water after system demand is satised. If upstream pumping is reduced before the tank is full, several things may occur; for instance:
327
r The tank may not ll at a rate fast enough to provide sufcient r If the ll rate is low enough, the tank may not ll high enough r If pumping is reduced excessively, the tank may begin drafting
even though it has not been lled. to help peak shave pumping demand during the next highdemand period. turnover and/or mixing.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
328
Chapter Nine
If the upstream pumping is larger than demand so that the tank lls at a fast rate, it may cause a different set of events:
r The high inow into the tank may uidize sediments at the
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
for tanks to cycle in unison, water tank residence time will vary, and water quality may become inconsistent between facilities in the same system. However, the effect of differing tank shutoff times in the same system may render transient travel times not constant. Hence, pump check valves at pump stations may require a much longer closing or opening time to prevent pressure surges. Distribution system water storage tanks should be periodically taken out of service for cleaning and inspection. Most of the water in the tank should be allowed to ow back into the distribution system. A few feet or meters of water, typically between 3 and 5 ft (0.9 and 1.5 m), are left in the tank to prevent collected sediments from reentering the system. Debris and sediments are brought to the tank from the systems piping and are collected at the bottom of tanks. This is a desirable means of removing contaminants and particulates from the water. However, as discussed in the water quality section of this chapter, several potential biological and chemical water quality issues are associated with tank sediment. Removal of this sediment is the only way to eliminate these potential problems. NSF International approved chemicals are available that remove persistent, troublesome stains , such as those caused by manganese and iron deposits. Tanks inlets and outlets should be designed such that settled solids are not uidized by the inow and do not return to the distribution system through the outlet. In the authors experience, a good practice is to allow the water main supplying the tank to ush through the tank, using it as a sediment trap. This can be achieved by emptying the tank and then opening the tank shutoff valve while the drain is open. This creates high-velocity scouring of the mains in the vicinity of the tank. A considerable amount of sediment has been removed from tank supply mains using this scheme. The ushing can be accomplished in as little as a couple of hours. The drained water must be treated according to local regulations (dechlorination and solids removal, for example) prior to disposal. The tank should be isolated with at least two valves in series with the tank. All hatches should be open, and the tank drain should be kept open. After all water and sediment are drained from the tank, the tank is typically powerwashed prior to inspection. Regulations require that the tank be disinfected before it is returned to service. The tank should be disinfected according to the latest version of AWWA C652, Standard for Disinfection of Water-Storage Facilities. The standard describes the materials needed, facility preparation, application of disinfectant to interior surfaces of the tank, and sampling and testing procedures for the detection of coliform bacteria. It also contains instructions for disinfecting equipment used in on-line underwater inspections.
329
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
330
Chapter Nine
Three methods of tank disinfection are discussed in the standard. Only one method is required to be used, although it is possible to combine two or all three methods, if necessary. The three methods are
r Full tank chlorination so that, at the end of the retention per Spraying the interior tank surfaces with a solution of 200 r Chlorinating the bottom portion of the tank with 50 mg/L
of available chlorine, then lling the tank to overow and maintaining a free chlorine residual of at least 2 mg/L for 24 hours. The standard should be consulted for more detailed instructions. According to the Ten States Standards, two or more sets of samples taken from the tank at 24-hour intervals shall indicate that water is microbiologically satisfactory before the facility is placed in operation. One of the main functions a tank serves is to dissipate pressure transients that may take place in the distribution system. When a tank is taken ofine, a distribution system may become vulnerable to water hammer or other damage stemming from a potential pressure surge. It is a good practice to plan the installation of temporary pressure relief valves at critical locations in the distribution system for the duration of the tank work. Insulated enclosures should be provided along with the surge relief valves in locations subject to freezing conditions. Large customers in the tanks service area should be notied and encouraged, if at all possible, not to run processes that demand a great amount of water while the tank is ofine. This is important because emergency water storage is lost when a tank is taken out of service. The risk of losing water pressure during a re is reduced when large customers temporarily abstain from using large volumes of water during tank work. The Federal Aviation Administration (FAA) determines and regulates structures that may pose an obstruction hazard to air trafc. Elevated tanks, tanks located at high elevations, and those within an FAA-designated three-dimensional controlled volume of airspace at the end of airport runways are required to carry aviation obstruction markings and/or equipment. The equipment may be an air trafc obstruction light at the highest point on the tank. Utility operators and maintenance crews must monitor the lights operation and replace the light when it burns out. Failure to comply with FAA requirements may lead to nes in the best of cases, or an airplanes collision with the tank in the worst case. mg/L of available chlorine. riod, a free chlorine residual equal to or greater than 10 mg/L is achieved.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
331
r Elevated tanks with small-diameter (less than 36 in. [0.9 mm]) r Tanks with uninsulated and unheated appendages that exper Tanks experiencing overow problems because of frozen or r Tanks with abnormally static water conditions r Tanks with inadequate vents or overows
otherwise malfunctioning controls for valves or pumps rience no ow (e.g., a drain valve at the end of a nipple) uninsulated risers
The National Bureau of Fire Underwriters publishes tables giving the heat loss per hour from various types of tanks. A 250,000-gal (1-ML) elevated tank located in a 10 F (23 C) area losses 1 million Btu/h (292 kJ/s) in a 12-mph (19-km/h) wind. Move the tank to a 40 F (40 C) location, such as International Falls, Minnesota, and the heat loss almost doubles (Knoy 1991a, 1991b). See the isothermal map in Fig. 9-16. Although it is possible to replace most of the water in a tank with warmer water, that is seldom the way the tank is operated. Water storage tanks (particularly elevated tanks and standpipes), because they are connected to the main only by the riser pipe, usually oat on the system. As a result, it is possible that a tank can serve a system that uses several times more water per day than the tank capacity yet still receive only a small percentage of fresh water daily. The operating procedures discussed in the following paragraphs allow a tank to make optimal use of the heat available in incoming water and highlight limitations and effects of water quality. Most utilities in cold-weather regions experience a drop in demand during the winter months. If the upstream pump station to a tank that is part of such a utilitys distribution system does not allow for adequate reduction in pumping so that the tank is allowed to cycle, tank turnover may be jeopardized, water quality may suffer, and, in extreme weather, ice may form. Drafting the tank and lling it may slow the formation of ice caps inside tanks. This is the only operational tool available to slow icing. The more a utility is able to cycle a tank, the less ice buildup will occur. However, tanks should not be kept at low levels for long periods, because the amount of heat energy contained in the tank is a function of the volume of tanks water. The
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
332
50 (0.048) 144 (0.138) 255 (0.245) 380 (10.365) 519 (0.499) 670 (0.644) 820 (0.788) 982 (0.944) 1,152 (1.11) 69 (0.066) 192 (0.184) 340 (0.327) 506 (0.486) 692 (0.665) 893 (0.859) 1,092 (1.05) 1,309 (1.26) 1,536 (1.47)
Add Btu Tank CapacitiesThousands of US Gallons (Thousands of Liters) Heat per Lineal (Btu) 25 30 40 50 75 100 150 200 250 Ft (kW-hr/m) Loss (94.6) (113.6) (151.4) (189.3) (283.9) (378.5) (567.8) (757.1) (946.4) Uninsulated 2 per Ft Steel Riser Square Feet (Square Meters) of Tank Surface 2 (kW-hr/m ) Atmospheric Tank 1,210 1,325 1,550 1,800 2,370 2,845 3,705 4,470 5,240 3 ft 4 ft Temperature Radiating (112.4) (123.1) (144.0) (167.2) (220.2) (264.3) (344.2) (415.3) (486.8) (0.914 m) (1.220 m) ( F[ C]) Dia. Dia. Surface Btu Lost per Hour, Thousands (kW)
35 [1.7]
30 [1.1]
40 43 51 59 77 92 120 145 168 (0.012) (0.013) (0.015) (0.017) (0.023) (0.027) (0.035) (0.042) (0.049) 56 62 72 83 110 132 171 207 242 (0.016) (0.018) (0.021) (0.024) (0.032) (0.039) (0.050) (0.061) (0.071)
Operation
25 [3.9]
61.5 (0.183)
75 82 96 111 146 175 223 275 323 (0.022) (0.024) (0.028) (0.033) (0.043) (0.051) (0.065) (0.081) (0.095)
20 [6.7]
77.2 (0.243)
94 103 120 139 183 220 287 346 405 (0.028) (0.030) (0.035) (0.041) (0.053) (0.064) (0.084) (0.101) (0.119)
15 [9.4]
93.6 (0.295)
114 125 146 169 222 267 347 419 491 (0.033) (0.037) (0.043) (0.049) (0.065) (0.078) (0.102) (0.123) (0.144)
10 [12.2]
110.9 (0.349)
135 147 172 200 263 316 411 496 582 (0.039) (0.043) (0.050) (0.059) (0.077) (0.093) (0.120) (0.145) (0.171)
5 [15.0]
128.9 (0.406)
156 171 200 233 306 367 478 577 676 (0.046) (0.050) (0.059) (0.068) (0.089) (0.108) (0.140) (0.169) (0.198)
0 [17.8]
148.5 (0.468)
180 197 231 268 352 423 551 664 779 (0.053) (0.058) (0.068) (0.079) (0.103) (0.124) (0.161) (0.195) (0.228)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
5 [20.6]
168.7 (0.532)
205 224 262 304 400 480 626 755 884 (0.060) (0.065) (0.077) (0.089) (0.177) (0.141) (0.183) (0.221) (0.259)
10 [23.3] 296 (0.087) 331 (0.097) 368 (0.108) 407 (0.119) 447 (0.131) 490 (0.143) 534 (0.156) 629 (0.184) 730 (0.214) 848 (0.248) 1.116 (0.327) 1,340 (0.392) 731 (0.214) 962 (0.282) 1,154 (0.338) 1,503 (0.440) 1,745 (0.511) 620 (0.182) 816 (0.239) 979 (0.287) 1,275 (0.373) 569 (0.067) 749 (0.219) 900 (0.264) 1,171 (0.343) 1,413 (0.413) 1,538 (0.450) 1,814 (0.531) 2,105 (0.616) 519 (0.152) 683 (0.199) 820 (0.240) 1,068 (0.313) 1,288 (0.377) 473 (0.138) 622 (0.182) 747 (0.219) 972 (0.285) 1,173 (0.343) 1,375 (0.403) 1,510 (0.442) 1,656 (0.485) 1,805 (0.529) 2,126 (1.623) 2,467 (1.722) 427 (0.125) 562 (0.165) 674 (0.197) 878 (0.257) 1,059 (0.310) 1,241 (0.363) 1,718 (1.65) 1,926 (1.85) 2,145 (2.06) 2,381 (2.29) 2,620 (252) 3,139 (3.02) 3,702 (3.56) 384 (0.112) 506 (0.148) 607 (0.178) 790 (0.231) 954 (0.279) 1,118 (0.327) 1,515 (1.46) 2,020 (1.94) 2,291 (2.20) 2,563 (2.46) 2,860 (2.75) 3,174 (3.05) 3,494 (3.36) 4,186 (4.02) 4,936 (4.75) 344 (0.101) 452 (0.132) 543 (0.159) 707 (0.207) 853 (0.250) 1,000 (0.293) 1,329 (1.28) 1,771 (1.70)
190.7 (0.601)
231 (0.068)
253 (0.074)
15 [26.1]
213.2 (0.672)
258 (0.076)
283 (0.083)
20 [28.9]
236.8 (0.747)
287 (0.084)
314 (0.092)
25 [31.7]
262.3 (0.827)
318 (0.093)
348 (0.101)
30 [34.4]
288.1 (0.909)
349 (0.102)
382 (0.112)
35 [37.2]
316.0 (29.3)
383 (0.112)
419 (0.122)
Operation
40 [40.0]
344.0 (0.997)
417 (0.122)
456 (0.134)
50 [45.5]
405.6 (1.28)
491 (0.144)
538 (0.158)
60 [51.1]
470.8 (1.48)
570 (0.167)
624 (0.183)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Notes: To determine heat loss per hour, nd the minimum mean atmospheric temperature for 1 day from the isothermal map (Fig. 9-16) and note the corresponding heat loss. Heat loss for a given capacity with a different tank radiating surface than shown here shall be obtained by multiplying the radiating surface by the tabulated heat loss per square foot (square meter) for the atmospheric temperature involved. The minimum radiation surface area shall be the wetted tank steel surface area plus the top water surface area. For tanks with large steel plate risers, the heat loss from the riser shall be added to that from the tank. The riser loss per linear foot (linear meter) shall be as tabulated above. These numbers are square feet (square meters) of tank radiating surfaces used for each capacity to compute the tabulated heat loss values and are typical for tanks with D/4 ellipsoidal roofs and bottoms. Source: AWWA Manual M42.
333
TABLE 9-6 Thousands of British Thermal Units (Btu) Lost per Hour from Elevated Steel Tanks Based on Minimum Water Temperature of 42 F (5 C) and Wind Velocity of 12 mph (5 m/s)
Operation
334
Chapter Nine
FIGURE 9-16 Isothermal lines for lowest one-day mean temperatures and normal daily minimum 30 F (1 C) temperature line for January, United States and Southern Canada.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
335
lower the volume of water in a tank, the less heat energy is present in the tank. It is this heat energy that minimizes ice formation. For example, it takes longer for a pitcher of water than a glass of water to freeze. The authors have been successful in eliminating icing by using tank mixing systems in combination with normal tank operation.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
336
Chapter Nine
FIGURE 9-17 More than 100 tons (90.72 metric tons) of dirty ice was discovered inside this 3-mil-gal (11.35-ML) elevated tank in the spring of 2004. It took weeks for repair crews to remove the ice before work on the tank could begin.
Elevated tanks are more susceptible than ground tanks to icing conditions (Fig. 9-17). Ground tanks are more likely to experience icing than partly or fully buried reservoirs. Insulating the tanks is not a viable option; insulation only slows heat loss but does not stop it. Hence, prolonged extreme weather eventually causes icing despite the insulation. The reason partly or fully buried tanks have less propensity to freeze is that the ground temperature is much higher than the air temperature below freeze depth. Freeze depth is the depth of ground from surface (grade) below 32 F (0 C). Ice formation on the interior surfaces of the tank acts as insulation and retards further icing of the water. However, formation of an ice cap on the surface of the water is the most damaging result of cold weather. Ice can have several detrimental effects on tank longevity and water quality. The physical effects of ice have been well documented. Floating and falling ice can scrape coatings and damage or destroy structural elements of the tank such as tie rods, ladders, overow weirs and piping, painters rings, and so on. The effect is cumulative and progressive; more and more damage is done in each cold season if the ice problem is not addressed. Although it is often desirable to take tanks down for inspection or rehabilitation work during low-demand winter months, caution must be taken to ensure that the tank is drained before ice forms. Otherwise, substantial amounts of ice may remain in the tank after it is drained. In some cases, so much ice may be present that it would need
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
to be physically removed before work can proceed. This can cause considerable unexpected delay and added expense to tank inspection or rehabilitation. Thawing a frozen tank is a difcult task. There are, however, some alternatives for dealing with such situations. A common technique is to lift a heavy-duty hose 3/4 in. (19 mm) in diameter from the ground up over the top of the tank. The end of the hose terminates with a 1/2-in.- (12-mm)-diameter pipe about 10 ft (3 m) long. This pipe is dropped through the tank vent or manhole located directly over the inlet or riser pipe. It must be kept slightly off the ice to keep it from sticking to it. Warm water from a re department tank truck is pumped through the hose, parting the ice as the probe drops down. The water must be used judiciously. Stopping in the middle of this process could allow the thawing pipe to freeze in the tank, which may mean the equipment must be left in the tank for the rest of the winter. When the tank truck is empty, it must be relled from utility mains. However, the rell water will not be as warm as the original water in the truck, which was taken from the heated re station. Steam generators have been attached to this type of probe, but the warm-water method seems to work best, is cheaper, and creates fewer safety hazards. The same equipment can be used to thaw a frozen riser. However, it may be difcult to thread the probe into the riser pipe. The tank drawings or a recent tank inspection report should be reviewed before this type of riser thawing is attempted, unless the positioning of the piping arrangement is known from experience. Articially thawing tanks is expensive and dangerous. In addition, a warm front may move through the day after the crew has thawed the tank, which makes a high thawing bill hard to justify. Rust, coating debris, and damaged structural elements are normally encapsulated in tank ice. Because the damage occurs as the ice develops, the substanceswhich may include biolms, metals, debris, and assorted particulates such as coating chipsbecome trapped in the ice for the duration of the cold season. Most of the accumulation is in the tanks ice cap. These substances are released when the ice thaws. Since they are released near the surface, they may be suspended long enough to be drafted out of the tank with the outow. Another way ice formation can affect water quality in tanks is that if the ice cap becomes thick enough (as it often does), the water level underneath the ice may drop while the ice cap remains stationary. This creates a small vacuum above the surface of the water that can cause air and chlorine (if used as a secondary disinfectant) to leave the water. This wet chlorine gas and air can cause accelerated corrosion in the areas damaged by the ice. Several devices on the market claim to prevent ice formation inside tanks. Some involve the use of mechanical mixers such as pumps
337
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
338
Chapter Nine
or propellers, some use air bubblers (bubbles remove heat from the water, and there must be an inux of warmer water for the system to operate properly), and others use turbulent jets. They are all essentially mixing devices with varying degrees of mixing efciency and energy consumption. A small tank may be tted with a recirculation pump and a water heater. This energy-intensive option is limited by tank size and equipment expense. There are reasons beyond tank operation that may make a tank susceptible to freezing problems. Isolation or altitude valves may be improperly applied or malfunctioning, which creates conditions of overow, low ow, or no ow that may cause a tank to freeze. Valves hydraulic control piping should be protected against freezing by providing heated enclosures, insulation, or electric heat tracing. Some traditionally designed air vents for tanks can collect condensation, freezing rain, or snow that freezes on vent parts and hinders operation. A common problem in such cases is the insect screen serving as a substrate for ice formation. Water outow from a tank with a frozen vent creates a vacuum condition that may result in progressive collapse of the tank shell until structural failure allows venting or the water outow stops. Several manufacturers supply frostproof tank vents designed either to prevent the formation of ice on their parts or to dislodge any ice formed by using a tank vacuum condition. Utility crews should inspect tank vents periodically to ensure their proper functioning. A common cause of tank freezing is inadequate cover over the pipe leading to the tank. Sometimes soil conditions preclude installing the tank foundation deep enough to provide adequate frost cover; in such cases, ll should be brought in for cover, or other means should be devised to insulate the pipe.
Site grade In some tower-type elevated tanks, the riser foundation is built higher than the column foundations. The site should be graded higher in the center to prevent the inlet/outlet piping from being exposed to the atmosphere between the concrete riser foundation tunnel and the earth. Compacting ll If the earth over the connecting piping is not compacted properly, it will settle during the rst few years of operation. The ensuing lack of adequate cover, combined with moisture saturation of the depression, creates a potential trouble area that may freeze. Supervising the covering The base of the tank is usually the location of the interface between constructors, and it may become a no-mansland. Unless the construction work is properly supervised and inspected, the piping may not even get backlled before the rst winter operation (AWWA 2003).
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
Tank overows are subject to icing when the tank overows at a slower rate than the freezing rate. This may occur for any of several reasons: a utility may want to misguidedly trickle-overow a tank to prevent it from freezing; the hydraulic controls for the altitude valve may be set above the overow elevation or may be damaged by ice or frozen; an altitude or isolation valve may be leaking; telemetry may be faulty due to weather conditions or damage; or the altitude valve may have been locked in the open position so that the tank can oat on the system, and the system pressure may have increased beyond the tank capacity. When tanks overow in freezing weather, several problems can develop. An overow-to-grade may freeze solid, especially where there is a trickling overow, where screens are plugged, or where ap or rubber valves are stuck on the discharge. If water continues to be pumped into the tank after the overow pipe is frozen solid, the tank may overow through the roof hatch for a while and then through the vent. The tank will then freeze solid, build up pressure, and burst. When water overows through the hatch and vent, it invariably forms a large icicle, weighing tons, on the tank exterior. The same problem can be caused by normal overow through a stub overow (one extending only a few feet or meters from the shell of the tank). Either situation places a large eccentric load on the structure which, in the case of water towers, can exceed the structures design stress. The icicle usually forms on the side of the tower that is away from the prevailing wind, and the wind and icicle together create additive loadings. Even if the structure is not damaged by the ice load, it may be damaged when the ice thaws or breaks off and falls. Eccentric ice loadings or tower members damaged by falling ice have caused water towers to fall (AWWA 2003). Proper tank design and operation will prevent many of the freezing problems discussed previously and will allow operators to deal with the problems that do occur. Special consideration should be given to tank inside appurtenances. Tanks located in areas where the LODMT is 5 F (15 C) or colder should not be equipped with inside ladders or overow pipes. As ice forms and moves up and down, it can exert tons of force on ladders and pipes, tearing them loose from their supports and possibly ripping or punching holes in the container. The resulting leak will occur at a very inopportune time. If an inside overow pipe is broken, the tank will rapidly lose all water down to the break, creating a large icy area on the ground below. If the vent is plugged with ice or snow, the tank roof may collapse when water evacuates the tank rapidly. It is acceptable to equip a tank with inside ladders and overow pipes if the tank is known to have a high turnover rate of warm water. A ladder and overow can also be installed at the center of the tank
339
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
340
Chapter Nine
and supported by the access tube, as in single-pedestal tanks and extremely large column-type tanks. The use of interior girders, roof bracing, painters rails, or virtually any other protrusion below the high water line or within an area affected by oating or suspended ice is a poor design practice for areas with an LODMT of 20 F (29 C) or colder. Certain local conditions or tank use patterns such as those discussed earlier may cause equally severe icing problems in warmer areas.
FIGURE 9-18 Insulated surge tank in metropolitan area provides protection from water column separation to large pump station located approximately 200 ft (60.961 m) lower than tank.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
Since these tanks do not oat on the distribution system, special attention must be given to the quality of water, disinfection residual, and turnover in the tanks. In colder climates, special consideration has to be given to eliminate freezing, which can affect the available volume and speed of delivery at the desired head. A circulation pump changes the water in the tank at a sufcient rate to maintain water quality. Tank water is returned to the system, and fresh water is supplied from the system upstream of the return location. In cold climates, surge tanks are typically insulated, and a recirculation pump may be used to cycle the water in the tank through heaters. The chlorine residual should be monitored in tanks whose recirculation systems do not exchange water with the main. If needed, chlorine should be boosted using a rechlorination system.
341
Hydropneumatic Tanks
Hydropneumatic pressure tanks are used in very small systems to reduce the amount of pumping required to provide water at pressure. They can also serve as temporary replacements to elevated storage in small systems during prolonged rehabilitation work. Hydropneumatic tanks are pressure vessels typically made of steel. A portion of the tank is kept lled with compressed air. Once full of water, the tank provides water in excess of the pump capacity as required. This keeps the pump from short-cycling and provides pressured water for short periods during power outages. These vessels can also act as pressure surge relief tanks.
Plug Flow
Short-circuiting, in general, occurs when inuent water bypasses most of the tank volume, having only minimal interaction with ambient water, and ows directly to the outlet. Clariers, clearwells, or tanks where contact time is needed should not be designed to have any form of short-circuiting. It is ideal if the water enters the tank and leaves the tank in an orderly fashion like a train, with the oldest water in the tank leaving rst. This is referred to as the rst-in, rst-out ow mode or the regime generally known as plug ow. In such a ow mode, a decrease in tank elevation decreases the ow area. This increases the speed by which the inuent water reaches
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
342
Chapter Nine
the outlet. Hence, the detention time of water in the tank decreases. Also, depending on geometry, some areas inside the tank may experience a change in the nature of the ow. For example, a separation area near where water changes direction may trap more water and increase velocities in the rest of the cross-sectional area, which may cause some mixing and/or short-circuiting. The Disinfection Proling and Benchmarking Guidance Manual of the USEPA (1999) has procedures for CT calculations that list bafing factors for various bafing conditions. These are approximate, and the regulatory agency usually approves the bafing factor during design reviews. Computational uid dynamic analysis can accurately predict bafing factors by modeling a tracer ow through the tank. However, the use of CFD is limited to design validation and should not be a tool for determining bafing factors because drastic difference in results are possible depending on the model and modelers limitations. Tracer studies are the most accurate means of determining bafing factors. A tanks theoretical detention time (TDT) is computed by dividing the volume (V ) of the tank by the peak hourly ow rate ( Q): (TDT = V/ Q). The bafing factor, T10 / T , is multiplied by the TDT to yield an estimate of the contact time (also known as the effective detention time), T10 , as follows: T10 = Contact Time = V/ Q T10 / T Bafing factors are a function of tank design. T10 / T equal to 1.0 represents pure plug ow characteristics where TDT is equal to the contact time, T10 . Figure 9-19 illustrates a CFD model of a bafed clearwell showing velocity contours.
FIGURE 9-19 Computational uid dynamics model of bafed clearwell showing velocity contours.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
Bafing Condition Unbafed (mixed ow) Poor Average Superior T10 /T 0.1 Bafing Description None, agitated basin, very low length-to-width ratio, high inlet and outlet ow velocities Single or multiple unbafed inlets and outlets, no intrabasin bafes Bafed inlet or outlet with some intrabasin bafes Perforated inlet bafe, serpentine or perforated intrabasin bafes, outlet weir or perforated launders Very high length-to-width ratio (pipeline ow), perforated inlet, outlet, and intrabasin bafes
343
1.0
Bafing classications and factors as given in the USEPA Guidance Manual are shown in Table 9-7. A discussion of CT calculations is outside the scope of this text. However, we shall discuss the effect of bafing geometries on detention times. Bafes are obstructions in a tank that can be made from a variety of materials. These obstructions contain and direct the ow in tanks to create plug ow conditions. Ideally, the objective is to transform the tank into a wound pipe, creating a rst-in, rst-out condition. Bafe congurations can be numerous; however, some bafe arrangements produce better plug ow than others. Design modications that can increase T10 may allow the same inactivation (CT) with a decreased disinfectant residual or a decrease in tank size. The following summarizes some of the design features that optimize clearwell plug ow design and operation.
Inlet Treatment
The inlet to a tank can be modiedfor example, by adding a perforated wallso that the ow entering the tank does not create an uneven stream but is distributed evenly along the ows cross-sectional area. In addition, the ow should not be directed such that it impinges on and attaches itself to a boundary; this creates a skewed velocity prole.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
344
Chapter Nine
area should be long and narrow, eliminating secondary ows and allowing a pressure gradient along the length of the ow channel only. Ideally, the entire volume of water should be in motion in one direction with no recirculation, stagnation, or mixing.
r Avoid any dead zone by eliminating (lling in) corners ber Add perforated walls at each change of ux direction. To obtain good water distribution on the whole cross section, a certain head loss must be created through holes, given by the following formula: P = k (V 2 /2g ) where k = 0.62 v = velocity through hole, in feet or meters per second g = acceleration of gravity = 32.2 ft/s2 (9.80665 m/s2 ) A velocity of 2 ft/s (0.6 m/s) creates sufcient head loss to ensure good distribution. tween horizontal and vertical surfaces.
Outlet Treatment
To maintain water level, an outow weir may be provided at the tanks outlet. Water drop should be minimal to prevent aeration of water and disinfectant loss. However, a bypass through the weir should be added to allow drafting of the clearwell in an emergency. A perforated wall in the vicinity of the outlet may help in eliminating preferential currents and help ensure an even distribution into the outow from all parts of the bafed channels cross-sectional area.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
FIGURE 9-20 Computational uid dynamics model of 0.8 bafing factor tank.
345
Mixed Flow
Mixed ow occurs when the inuent water impinges on the ambient water, resulting in a diluted volume representative of their proportions. The water leaving the tank is no longer the oldest water in the tank but is of an averaged age based on the tanks turnover ratio and mixing efciency. Just as the bafing factor represents the scale of plug ow present in a pass-through tank, mixing efciency or effectiveness represents the amount of mixing achieved. Just as bafing schemes are not equal in performance, performances of mixing schemes differ. Mixing in tanks can be achieved in many ways; we shall attempt to discuss most of them, concentrating on turbulent jet mixing due to its applicability in water storage tanks as discussed hereafter.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
346
Chapter Nine
where j = parameters pertaining to the discharge jet A = cross-sectional area u = velocity along main ow axis gj = reduced gravitational acceleration of the discharge jet due to the density difference between the efuent and ambient environment (AWWA 2003) The momentum ux affects the relatively near-eld mixing region and has minimal affect on the far eld region. Momentum ux is directly proportional to the micromixing; however, it is not an indication of mixing in the entire tank. Available research specically dictates that macromixing or large-scale folding of the interfaces is what affects mixing efciency, not micromixing or small-scale wrinkling. There is ample research on turbulent mixing, and the more appropriate measures to use would be the coefcient of variance, decay function, and/or mixing efciency calculations based on uid interfaces (Hjertager et al. 2008; Nathman, Aguirre, and Catrakis 2004).
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
347
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
348
Chapter Nine
implies the solution is heterogeneous. High levels of homogeneity are not needed in tanks to maintain water quality. In addition, it may be very expensive to achieve CoV levels less than 0.1 (10 percent). A CoV of 0.15 (15 percent) is considered good for industrial applications if mixing time is increased by approximately 25 percent. A higher CoV may then be acceptable if we are able to increase mixing time, slightly boost incoming disinfectant residual, or make other less expensive tank modications that can slow disinfectant deteriorationor if it is determined that the higher variations effect on water quality is acceptable. Hence, adequate mixing is subject to many interpretations from many perspectives. It should be based on achieving water quality objectives with an efcient use of resources. Nevertheless, one cannot go wrong by targeting a CoV lower than or equal to 10 percent if the ability to do tank analysis is hindered. The coefcient of variance is dened as CoV = /xave where n x ave = number of samples = standard deviation of the measured readings corrected to the true value of the population by using n1 in the denominator = average of the measured readings
Determination of CoV is the most denitive method of establishing tank mixing performance. Several samples are collected at various elevations and areas within a tank. A good rule of thumb is to collect at least six samples; more samples should be collected for tanks larger than 1 mil gal (3.78 ML). Any number of parameters can be studieddisinfectant residual, disinfection by-products, turbidity, temperature, and so on. A CoV of 0.2 or less is an indication that the tank is sufciently mixed and does not require mixing enhancements. Another widely used parameter for quantifying mixing effectiveness is the range mixing effectiveness ( ERange ). The ERange is dened as E Range = 1 RangeOut /RangeIn. where RangeOut = range of concentration readings leaving the tank RangeIn = range of concentration readings entering the tank An E Range value of 1.0 implies excellent or homogeneous mixing, whereas a value of zero implies a heterogeneous solution or poor mixing. This measure may yield misleading effectiveness values if short-circuiting is present in a tank. However, this anomaly will be revealed when the tank is drafted and stagnant water leaves the tank. Stagnant water may cause an E Range value below 1.0.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
The advantage of this method of mixing evaluation is that it lends itself easily to online monitoring, since only the inlet and outlet require continuous sampling and testing for water quality parameters (disinfectant residual, for example). Mixing time calculations involving inow and outow rates should be compared with tank ambient volume to determine whether or not a mixing system would work. If tank turnover rate is insufcientthat is, if the volume of water entering and leaving does not change a certain volume in the tankturbulent jet mixing systems may not result in a homogenous tank, regardless of the mixing efciency. The required percentage of tank volume to be exchanged is a function of the scalar concentrations of the ambient water and the incoming water. These scalars include disinfectant residual, contaminants, disinfection by-products, and so on. Other inuential parameters may be the temperatures of the incoming and ambient water, chemical compositions and biological contents, atmospheric conditions, and the tanks physical condition.
349
Mixing Theory
Of the many mixing technologies, no single one can be used for all mixing duties. This makes choosing mixers a complex task that requires adequate understanding of mixing processestheir application and limitations. Many texts have been written on this subject. Hereafter we shall attempt to discuss the subject in general and then focus on its applications in tanks. The mixing of one or more components or materials in a uid system can be described in terms of two separate but interlinked processes, macromixing and micromixing:
r In macromixing, there is no mixing on the molecular scale, but r Micromixing is complete mixing of species on the molecular
level. Droplet or particle size reduction (dispersion) of one or more components of the mixture produces increased homogeneity of the system. Most uid-mixing problems may be analyzed in terms of the miscibility or ease of mixing of the components. The ease of distribution affects the mixing approach to be adopted. For instance, where the rate of reaction between the components is to be improved (such as combining water with a high disinfectant concentration with water that contains bio-matter water or with low-residual water), the mixing approach is focused on maximizing distribution (macromixing). uid elements or different components are well distributed or blended to create uniformity throughout the mixture.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
350
Chapter Nine
For mixing immiscible uids such as chlorine gas or solids with water, the mixing approach is focused on reducing droplet or particle size to maximize the area of contact (micromixing). Hence, micromixing has a higher tendency to resuspend settled solids or diffuse gases. Another point of consideration is the mode of operation involved, of which the uid mixing is normally only a part. The most important distinction that affects the mixing operation is whether the tank operation is a batch process (distinct ll or draft cycles) or a continuous process (pass-through where ll and draft occur simultaneously). In a batch process, a discrete volume of material is mixed in the tank, whereas in a continuous process, a stream of material is mixed.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
taking place over time also contribute to the increase in the coefcient of variance. In addition, the higher velocities reduce the total amount of tank inuent water because of the effect of the resulting higher head loss on pump performance. Reducing the amount of water with high disinfectant residual entering the tank results in a lower overall increase in tank disinfectant residual over time. Therefore, creating high-velocity jets in an effort to increase micromixing is not an optimum way of mixing tanks.
351
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
352
Chapter Nine
Mixer Types
The many types of mixers applicable to water mixing in tanks may be categorized as follows:
Impellers
These have specially shaped blades on a rotating shaft driven by a gear motor and/or variable-speed drive. They are used almost exclusively for batch processes. Applying them in water tanks or towers may be prohibitive because of structural support requirements and energy consumption issues. Also, these systems may not work in changing water levels.
Static Mixers
These devices require continuous uid motion to work, so they are used in continuous processes. They comprise a set of nonmoving obstructions or orices in a pipeline. The obstructions or orices are shaped and positioned in such a way as to create cutting and folding effects and/or turbulence for mixing of piped uid streams. Static mixers are a reliable and low-cost alternative. Nevertheless, any highpressure drop across the mixer may require larger and more expensive pumps, increase energy consumption, or alter pump operating points.
Dispersers
Dispersers comprise a range of complex machines and systems that deliver relatively uniform dispersions in particular uid applications. A valve homogenizer comprises a very high-pressure pump and a controlled valve nozzle through which the uid is forced at very high velocity to rupture the droplets through extensional stressing. The jetimpinging mixer, another type of disperser, uses high-velocity uid streamsexcept that in this case, the uid is jetted against a plate or contra-jet to rupture the droplets or particles using impact stressing. The high level of mixing that these systems provide is localized; use of this technology in water tanks would require many nozzles or jets, making it high in installed cost and energy consumption.
Pump Mixers
Available in both batch and continuous forms, pump mixers use internally generated energy to force uid through small nozzles at very high velocities while extending and shearing it. The uid owing through the nozzles at high velocity then impinges on an internal wall of the mixer. A dynamic cutting and folding action added to vigorous turbulent ow provides distributive mixing. Pump mixers are suited to a wide variety of applications because they can handle a wide range of materials and viscosities with high mixing performance. In addition to energy consumption and availability issues, these systems may not be as effective in large tanks. Tests conducted for the US
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
Department of Energy have shown that a considerable volume of water in large tanks remains unmixed (Lee and Dimenna 2001).
353
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
354
Chapter Nine
only in ve possible asymptotic regimes in which they have an invariant internal force balance, invariant turbulence, and entrainment properties. In between these regimes, the buoyant jet properties are variable and cannot be scaled uniquely by local jet parameters (Jirka 1999). The local Reynolds number (Re) in the case of a turbulent jet in a quiescent reservoir is approximately equal to the jet exit Reynolds number Rej = d j U j / (d j is the jet diameter, U j is the jet velocity, and is the kinematic viscosity of water). If the jet momentum ux Mj U j = j (d j /2)2 U j 2 ( j is water density and Mj is the mass of water in the jet) is held constant as the jet diameter decreases and its velocity increases, the jet approaches a point source of normal momentum, which generates a counterrotating vortex pair (Shan and Dimotakis 2001). At low Reynolds numbers, in particular, tertiary and sometimes quaternary vortices are formed such that the vortices no longer have equal circulation, and each vortex could have a different induced velocity. In that case, the induced vertical velocities would be substantially smaller, and the overall mean trajectory would be shallower. At high-Re transverse jets, the counterrotating vortex pair is the dominant structure and the primary mechanism for entrainment of free stream uid. The vortex circulation is a decreasing function of downstream distance decaying through viscous diffusion (Shan and Dimotakis 2001). In other words, high-Re (more turbulent) inlet sources would result in a ow with higher vertical velocities and a vortex pair as the main source of water entrainment. As will be explained later, entrainment is the major mixing mechanism. The higher vertical velocity means that the inuent would reach the water surface faster, resulting in even less entrainment of the ambient water in the tank. Hence, the high level
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
of micromixing caused by the high Reynolds number results in more homogenous mixing in the vicinity of the inlet, but less water is mixed. Experimental data indicate that the scalar gradients are steeper in the horizontal directions than in the vertical directions. Anisotropy of the transverse jets scalar eld is in contrast to the far eld isotropy for axisymmetric jets discharging into a tank (Shan and Dimotakis 2001). Scalar mixing in the transverse jet is enhanced by increasing the Reynolds number. In the case of turbulent jets discharging into a tank, the concentrations probability distribution functions lose their peak at the highest Reynolds number (Shan and Dimotakis 2001). This means that when discharging into a reservoir or tank in which there isnt a crossow, mixing is decreased in the far eld at high Reynolds numbers (or inuent velocities). The minimum Reynolds number for which turbulent mixing can be considered as fully developed is approximately 10,000 (Nathman et al. 2004). On the basis of the previous analysis, tank mixing systems need to reduce the Reynolds number to slightly above 10,000 by reducing the velocity through each inlet. An efcient way to accomplish this is to have more inlets to spread the ow. Having more inlets results in a larger volume of water involved in near-eld micromixing, and it introduces the inuent at various locations in the tank, further enhancing the distribution of the micromixing effect. Flow-dependent mixing is explained by noting that turbulent mixing is essentially a three-stage process (Shan and Dimotakis 2001): Entrainment: Engulfment of irrotational (ambient) ow into the turbulent ow region, or macromixing. Stirring: Kinematic motion responsible for creating interfacial area between species. Molecular mixing: Diffusive mixing on the molecular scale, or micromixing. The balance among these three stages determines the probability distribution function of the mixed water. Nevertheless, the mean concentrations are a measure of entrainment rather than of molecular mixing. Hence, the transverse jet entrains less ambient uid than the ordinary turbulent jet. Transverse jets homogenize the entrained uid more thoroughly. This indicates that for transverse jets, there is more stirring and molecular mixing; for ordinary jets, there is more entrainment (Shan and Dimotakis 2001). Increases in water elevation in tanks with mixing systems result in little transverse motion. Transverse motion is especially negligible in a large tank unless it is a pass-through tank with considerable and independent inow and outow rates. Therefore, the inuent jets need to entrain larger volumes to mix the whole tank. To maximize entrainment, the inlets should be located such that the inow engulfs
355
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
356
Chapter Nine
the maximum amount of volume possible. This is done by creating sheet ows at different elevations that intersect and or interact in the far eld. This is further enhanced if the inuent is buoyant, as will be shown later, whether positively or negatively due to temperature difference between inuent and ambient water.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
requires less throttling at each inlet and multiple inlets at the proper elevations. The locations of the inlets should be such that boundary-layer attachments occur only as part of the entrainment scheme and do not disrupt it.
357
Mixing Regions
The hydrodynamics of an inuent continuously discharging can be conceptualized as a mixing process occurring in two separate areas. In the rst area, the initial jet characteristics of momentum ux, buoyancy ux, and outfall geometry inuence the jet trajectory and mixing. This area, called the near eld, encompasses the jet subsurface ow and any surface or bottom interaction (or, in the case of a stratied ambient, terminallayer interaction). The mixing zone is the part of the near-eld area in which the initial dilution of a discharge occurs. Many hydrodynamic denitions of mixing zones include both neareld mixing and boundary-interaction processes (MixZone 2005). In this area, mixing system design can usually affect the initial mixing characteristics through appropriate manipulation of design variables. In particular, designs with dynamic bottom attachments should be avoided (MixZone 2005). Dynamic plume attachments occur when the discharge ow interacts strongly with a boundary in the near eld. Such near-eld boundary interactions present the possibility of high inuent concentrations near the discharge (MixZone 2005). Often, near-eld attachments are avoidable with proper design of the mixing system. This ow also exhibits a subsequent buoyant liftoff and an unstable near eld (MixZone 2005). Two types of attachment are typically found: wake attachment forced by the crossow and Coanda attachment forced by the entrainment demand of the inuent jet itself. A physical description of these processes is given below (MixZone 2005). In wake attachment, the presence of the discharge structure and the jet inux interrupts the ambient velocity eld and causes a recirculation area in the wake downstream from the discharge (MixZone 2005). A Coanda attachment is a rapid dynamic attachment that occurs when a jet discharges close to a nearby parallel boundary. This process is referred to as a Coanda effect. It occurs because of the entrainment demand of the jet ow at its periphery. If a boundary limits the approach ow of ambient water, then low-pressure effects cause the jet to be deected toward that boundary, thereby forming a wall jet. Thus, the mixing process of Coanda-attached ow is governed by the dynamics of the wall jet (MixZone 2005). Figure 9-22 shows a negatively buoyant turbulent jet ow with wall attachment. This implies that a tank mixing system discharging very close to the bottom or surface may cause ow attachment to the bottom or a buoyant lm at the top with reduced mixing.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
358
Chapter Nine
FIGURE 9-22 Negatively buoyant turbulent jet ow showing wall attachment. (Source: MixZone.)
Boundary interactions occur when the ow contacts the surface, bottom, or sides or forms a terminal layer in a density-stratied ambient environment (Fig. 9-23). Boundary interactions also determine whether mixing is controlled by stable or unstable conditions at the discharge source (MixZone 2005). Boundary interaction generally
FIGURE 9-23 Turbulent jet ow into density-stratied tank model. (Source: MixZone.)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
provides the transition from near-eld (discharge sourcecontrolled, or micromixing region) to far-eld (ambient environmentcontrolled, or macromixing region) mixing processes. However, boundary interactions in the form of dynamic plume attachments to the bottom are considered near-eld mixing processes (MixZone 2005). As the turbulent buoyant jet travels farther away from the source, the source characteristics become less important. Conditions existing in the ambient environment control trajectory and dilution of the ow through the spreading of buoyant density-current motions and passive diffusion due to ambient turbulence. This region is referred to as the far eld (MixZone 2005). A counterrotating vortex pair has been noted in the far eld of a transverse jet; however, the mean ow state is not necessarily a symmetric vortex pair but can be unsteady and asymmetric under certain conditions (Shan and Dimotakis 2001). The rotational ow created by the vortex is what helps to make the ow regime more homogenous. Hence, a properly designed tank mixing system would attempt to encourage or extend the creation of lateral vortices that do not reach the surface so that it enhances the mixing of the largest volume of water. The assessment of near-eld stability (i.e., distinguishing stable from unstable conditions) is a key aspect of analyzing inuent dilution and modeling the mixing zone. It is especially important for understanding the behavior of the two-dimensional plumes resulting from multiport diffusers (MixZone 2005). Discharge plumes may be classied as having the following characteristics:
359
r Stable discharge conditions usually occur for a combination r Unstable discharge conditions occur when a recirculation phenomenon appears in the discharge vicinity. This local recirculation leads to re-entrainment of already mixed water back into the buoyant jet region (MixZone 2005). The previous discussion of stability emphasizes the importance of eliminating recirculation at the discharge vicinity. Recirculation at the inlets can be minimized by (1) reducing inuent velocity to minimize the recirculation region size or (2) having a boundary surface very close to the point of discharge to prevent or minimize rotational ow in the direction opposite that of the discharge. In the second case, this means not using discharge nozzles. of strong buoyancy and weak momentum (MixZone 2005).
Buoyant Discharges
Information about the density distribution in the ambient water body is very important for correctly predicting inuent discharge plume behavior. Density currents are buoyancy driven far-eld ows that are dened by transverse horizontal spreading while being advected
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
360
Chapter Nine
downstream by an ambient current. These spreading processes can intrude into the ambient ow, forming a buoyant upstream wedge and stagnation point. These ows are caused by the density difference of the mixed ow relative to the ambient density. Density currents are preceded by turbulent jet mixing in the near eld and are followed by passive diffusion in the far eld. Density currents may or may not form upstream intrusions, depending on the crossow magnitude and internal buoyancy at boundary interaction (MixZone 2005). Buoyant jets discharged horizontally along the water surface from a laterally entering channel or pipe bear some similarities to the more classical submerged buoyant jet. For a relatively short initial distance, the efuent behaves like a momentum jet, spreading both laterally and vertically due to turbulent mixing (MixZone 2005). After this stage, vertical entrainment becomes inhibited due to buoyant damping of the turbulent motions, and the jet experiences strong lateral spreading. During stagnant ambient conditions, ultimately a reasonably thin layer may be formed at the surface of the receiving (ambient) water; that layer can undergo transient density-current buoyant spreading motions (MixZone 2005). In the presence of ambient crossow, buoyant surface jets may exhibit any one of following three types of ow features (MixZone 2005):
r They may form a weakly deected jet that does not interact r When the crossow is strong, they may attach to the downr When a high discharge buoyancy ux combines with a weak
crossow, the buoyant spreading effects can be so strong that an upstream intruding plume is formed that also stays close to the surface near the inlet. Density currents are effective transport mechanisms that can quickly spread a mixed efuent laterally over large distances in the transverse direction, particularly in cases of strong ambient stratication. In this case, inuent of considerable vertical thickness at the terminal level can collapse into a thin but very wide layer, unless this is prevented by lateral boundaries (MixZone 2005). If the inuent water is nonbuoyant or weakly buoyant, there is no buoyant spreading area in the far eldonly a passive diffusion area. Depending on the type of near-eld ow, ambient density stratication, and boundary interaction process, several types of density current buoyant spreading may occur: stream boundary, forming a bottom-hugging plume. with the bottom or surface.
r Spreading at the water surface r Spreading at the bottom r Spreading at a sharp internal interface with a density jump
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
361
FIGURE 9-24 Buoyant discharge from single port inlet at 45-degree angle into stagnant tank.
Turbulence in the ambient environment becomes the dominating mixing mechanism in the far eld at sufciently large distances from the discharge point. In general, the passively diffusing ow grows wider and thicker until it interacts with the vessel bottom and/or sides (MixZone 2005). The strength of the ambient diffusion mechanism depends on several factors that relate mainly to the geometry of the ambient shear ow and the amount of ambient stratication. From classical diffusion theory, gradient diffusion processes in the bounded ows can be described by constant diffusivities in the vertical and horizontal direction that depend on turbulent intensity and on channel depth or width. In the presence of a stable ambient stratication, the vertical diffusive mixing is generally strongly damped (MixZone 2005). In the surface approach condition, the weakly bent ow impinges on the surface at a near-vertical angle (>45 degrees) (Fig. 9-24). After impingement, the ow spreads more or less radially along the water surface as a density current. In particular, the ow spreads some distance upstream against the ambient ow and laterally across the ambient ow. The strong buoyancy of the discharge dominates this spreading. The lateral spreading of the ow in the surface impingement area is driven by both the ow momentum and the buoyancy force (MixZone 2005).
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
362
Chapter Nine
Since inuent water is rarely at the same temperature as ambient water in the tank, buoyant ow can be used as a free source of mixing energy. Substantial additional mixing can be created and further optimized if the tank mixing system is designed to use density streams as part of the entrainment scheme. This would further negate the use of inlets at the bottom or near the surface in a tank mixing apparatus. Such inlets prevent the density streams interfaces from folding due to stratication and prevent the engulfment or entrainment of large volumes of water needed for mixing efciency.
Flow Diffusers
Inuent
A multiport diffuser is a linear structure consisting of many more or less closely spaced ports or nozzles that inject a series of turbulent jets into the ambient receiving water body. These ports or nozzles may be connected to vertical risers attached to an underground pipe or tunnel or they may simply be openings in a pipe lying on the bottom (MixZone 2005). Flow diffusers in water tanks mixing systems should be designed to use and accommodate all the physical phenomena associated with turbulent jet mixing. Such systems should optimize mixing efciency using as little energy as possible, as follows:
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
363
FIGURE 9-25 Sheet ow from multiport diffuser into tank model showing formation of vortices and folding of interfaces in far eld. Note: better mixing distribution in far eld.
Efuent
The ow diffuser discussed so far is an inuent structure. However, it may also be a tank efuent structure. The lling cycle typically uses a fraction of the total time of a tanks operating cycle. The tank may remain idle for some time or may draft for a long time, feeding back into the system. Reliance on inuent mixing alone is not optimum, because throughout the longest part of the operational cycle, no mixing is taking place. To optimize mixing, it is ideal to also mix during the draft cycle. After the ll cycle, ambient water in the tank will stratify, lose disinfectant, or be rendered otherwise nonhomogeneous because of some physical or biochemical activity. As a result, water quality may progressively decrease. More importantly, impurities or disinfection by-products may settle, stratify, or accumulate unevenly because of temperature gradients and removal of uid solely at one or two locations on the tank bottom. To prevent the possibility of high concentrations of accumulated impurities (such as some disinfection by-products or solids being fed back into the distribution system by excessive drafting), it is prudent to mix or blend the efuent water from various areas and elevations of the tank as it is drafted. At a minimum, efuent mixing will accomplish the following:
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
364
Chapter Nine r Minimize the number of dead spots due to drafting from the r Decrease reliance on passive diffusion which may be disr Decrease the possibility of icing in colder climates due to disr Remove water close to the top, where biological activity is
higher and disinfectant residual is lower tributed motion of the uid and removal of uids near the top rupted by many environmental factors regions close to the outlet
r Make efuent more uniform and provide a more homor Because of uniformity of mixing, achieve better and more r Eliminate mixing cost, since water from the tank or reservoir is
mixed by gravity and forced back into the distribution system. When water is combined from different areas and elevations through the diffusers, it creates large interface areas internally which are then stirred by the turbulence in the diffusers and tanks piping, valves, and ttings. This further mixes the ow to create a more homogeneous efuent and consistent water quality. meaningful tracking of water age geneous starting point for the next ll cycle, making turbulent jet mixing more effective
Tank Venting
Most water storage tanks are nonpressurized tanks that require adequate venting. By allowing the removal or replenishment of air as water enters or exits the tank, venting prevents both pressurized and vacuum conditions. Atmospheric tanks are not designed to handle pressurization; the absence of sufcient venting to handle the air outow generated as water enters the tank would cause the air in the tank to compress and exert pressure on the tank walls that may exceed design stress limits. Likewise, tanks are not designed to handle the vacuum conditions created when water is drafted from a tank without adequate venting. Buckling of tank walls takes place even when differential pressure is small. The styles of air vents most commonly found in water tanks are the mushroom, pan, and 180-degree types. AWWA D100, Standard for Welded Steel Tanks for Water Storage, requires that one tank vent, even if more than one is required, always be located near the center of the roof. A reasonable offset is allowed for tanks designed with center dry-access tubes. Vent designs, examples of which are given in Figs. 9-26 to 9-28, should meet the following requirements:
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
365
Screen
FIGURE 9-26 Double 90-degree elbow roof vent detail. (Source: AWWA Manual M42, Steel Water Storage Tanks.)
r Prevent insects and animals from entering the tank (a nonr Prevent rainwater or surface water from entering the tank r Prevent air drafts from entering the tank
(Outside diameter)
3/16
C er ov
Ve nt
di am .
Tank ro of
(Inside diameter)
di am et er
(Outside diameter) (Hole in roof) Plan view Section A-A
FIGURE 9-27 Pan deck vent detail. (Source: AWWA Manual M42, Steel Water Storage Tanks.)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
366
Chapter Nine
p Air
PTFE gaskets (typical)
re su res
Pres sure
Vacuum
palle
pallet
Screen (brass material is normal) Support bars Air vacuum Carbon-steel body
Roof
FIGURE 9-28 Typical clog-resistant vent detail. (Note: PTFE = polytetrauoroethylene. Pallets should be removed during coating to prevent clogging of the screens. Periodic inspection and maintenance are required to keep in proper working condition.) (Source: AWWA Manual M42, Steel Water Storage Tanks.)
r Exclude dust and debris, as much as possible, from entering r Provide some level of security against accidental or intenr Prevent direct sunlight from entering the tank r Be frostproof in cold-weather areas r Be tall enough, or installed high enough, not to be blocked by
drifting snow or debris tional contamination the tank
It is a requirement of the Ten States Standards that overows not be considered as vents. Obviously, a tank using its overow as a vent would be left without venting during overow conditions. It also points out that vents on ground-level tanks should terminate in an inverted U shape with its opening 24 to 36 in. (609.6 to 914 mm) above the tanks roof or ground. The U-shaped overow should be covered with 24-mesh noncorrodible screen installed within the pipe at the location least susceptible to vandalism. AWWA manual M42, Steel Water Storage Tanks, recommends clog-resistant vents with pressureand vacuum-releasing pallets. Large tanks should be provided with more than one vent. One should be installed near the center of the roof, and the other(s) closer
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
to the tanks walls. This facilitates crossow ventilation through the tank. Vent sizing is of special concern in the case of tanks in systems that have experienced demand growth. Increased tank inow and outow rates must be handled by tank venting. Undersized vents must be replaced with properly sized ones to prevent problems related to increased maximum ow rates.
367
Telemetry
Most storage facilities for potable water are located in unmanned sites. Some tanks are located in sites manned by a handful of operators whose main responsibilities are to monitor a water treatment process. In either case, it is desirable to have automated systems that monitor hydraulic and water quality parameters of tanks. These devices can store data in electronic form or on paper. They can also transmit information collected to a central location or manned facility where an operator can keep track of and control multiple facilities throughout a plant and/or a distribution system. Telemetry is the science and technology of automatic measurement and transmission of data by wire, radio, or other means from remote sources, pumping stations, distribution system tanks, or other facilities or processes to receiving stations for recording and analysis. Most telemetry systems used by water utilities are commonly known as SCADA (for supervisory control and data acquisition) systems.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
368
Chapter Nine
elevation data if the tank geometry is known, and changes in tank volume can be calculated over time. This trended ow and volume data can help water quality personnel monitor mixing patterns in tanks over the course of the year and provide operators with strategies to enhance tank mixing for each tanks operating characteristics. A balance must be maintained between the need for optimum water quality and emergency storage. Allowable low levels in tanks should leave sufcient water in storage to satisfy potential emergency demands from res, power outages, water main breaks, and so on. Excessively high water elevation can trigger an overow alarm to alert the SCADA operator that an altitude valve may be malfunctioning and that tank overow is probable. The operator can respond by turning pumps off at upstream pumping stations and/or closing a remotely controlled motor-operated isolation valve, if one is present at the tank. Depending on the particular circumstances, the operator can dispatch a road crew to the tank. Skillful operation and knowledge of the distribution system are required to appropriately address high-pressure conditions. Isolating a tank from the distribution system without taking other measures, such as shutting pumps off, may create abnormally high pressure and leave a system vulnerable to water main breaks and other catastrophic failures. Tanks that are left open to a distribution system provide surge relief should pressure transients be generated. Such systems are deemed soft systems. A system operated at high pressures with its tank(s) ofine loses this surge protection and is said to be a hard system. It should be noted that some utilities have chosen to forego altitude valves and rely entirely on telemetry and motor-operated isolation valves to control water level in the tank. Many strategies are available for sensing water level. A few of the most common technologies are listed here, divided into two categories: contact sensors and noncontact sensors.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
used to monitor each switch in the tank and transmit digital outputs corresponding to tank level. Icing is a concern with this technology.
369
Street Pressure
Street pressure is measured on the street side of the altitude or tank isolation valve. The most common technology used is the pressure transmitter. A continuous-voltage or current-analog signal corresponding to the pipe pressure at the sensor elevation can be continuously sent to the SCADA operator. (The pressure transmitter need not be at the same elevation as the pipe centerline, but this discrepancy must be accounted for in the determination of street pressure.) If the altitude valve is not locally controlled, a decrease in street pressure signals the operator that the altitude valve or tank isolation valve should be opened and the tank drafted to meet demand. Data on street pressure enable the operator to monitor distribution system pressures even if
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
370
Chapter Nine
the tank has been isolated. For instance, a sharp decrease in street pressure may be an indication of system failure such as a water main break.
Disinfectant Residual
Water quality managers are installing monitors for disinfectant residuals at representative distribution system locations. Some installations are made because of regulatory requirements, others as a voluntary measure. Tanks are ideal for such systems since they are usually in secured locations, electrical power is available, and utility personnel periodically visit the tank site. Various technologies are commercially available to measure and transmit concentrations of disinfectant residual. The most common secondary disinfection chemical in the United States is chlorine. The following methods are described for measuring concentrations of chlorine residual at water storage facilities.
Iodometric Method
Potassium iodide reacts with free chlorine in the sample water to produce iodide. The iodide concentration is measured by the instrument to yield total chlorine. Free chlorine is not measurable by this method.
Amperometric Electrodes
Combinations of probes consisting of a silver anode and a platinum cathode measure free chlorine concentration, pH, and temperature. A current proportional to the free chlorine concentration is produced within the electrodes. The amperometric electrodes require replacement after a manufacturer-specied lifetime (Pollack et al. 1999). Although automated, these systems may require chemical replenishment and periodic maintenance and calibration to sustain accuracy.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
Disinfectant-residual sensors can also act as feedback for booster disinfection at storage facilities. The SCADA operator can remotely control the feeding system. System parameters such as start, stop, feed rate, remaining disinfectant, and set point may be controlled and/or monitored.
371
Temperature
Temperature transmitters and thermocouples can be used to measure and transmit temperatures. Low air temperature inside equipment enclosures can alert the SCADA operator to potential freezing conditions that are detrimental to tank-monitoring devices. A water temperature probe inserted either in the tank or in the pipeline leading to the tank, or in both, can provide the utility with information regarding tank stratication conditions. A complete temperature prole of a tank can be obtained by using a weighted line of thermocouples designed to measure temperature at various water depths. The information may be transmitted to SCADA or stored locally and downloaded manually. Trending of such temperature proles over time can help water quality managers and operators to determine operational parameters for seasonal or changing conditions.
Flow
Many different types of meters can be used to measure water ow. SCADA monitoring of ow into and out of a tank can indicate problems in the distribution system, assist water quality managers in determining optimum tank operation, determine water depletion time during emergencies, and so on. Some of the systems used to measure ow at tanks are differential-type owmeters such as venturis, insertion meters (V-Cone, Annubar, etc.), and orice plates and electronic-type meters such as ultrasonic, temperature, and magnetic owmeters. Detection of ow direction is inherent to the operation of some of the meters, such as magmeters. Other meters, such as venturis, require additional devices to determine ow direction. Each meter named, whether as a primary or a secondary device, makes use of a transmitter to calculate and convert the ow into an analog current or voltage signal.
Security
As discussed earlier in this chapter, security at water storage facilities is a concern to utility ofcials and law enforcement. SCADA systems can also transmit data from security sensors and video from cameras either to the SCADA operator or directly to a separate security SCADA monitoring center or to law enforcement monitoring ofcials. A variety of sensors are available to detect intrusion to a tank site or
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
372
Chapter Nine
tampering with tank appurtenances such as hatches and vents. Each of these sensors is capable of sending a digital signal to SCADA that indicates the appropriate security-related reaction. Pan/tilt/zoom cameras can be operated remotely to track an intruders activities. Available camera technology is able to register images even at very low light levels. Video recording devices at each site may be accessed remotely through SCADA to download video images of the intrusion.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
of information. Available services range from basic telephone modem communication (2,400 bits per second [bps]) to leased duplex lines with high broadband capability (>2 million bits per second [Mbps]). Because telephone lines are already available near most water storage facilities and the needed equipment is relative inexpensive and commonly available, telephone communication is the most popular technology used for SCADA systems. Telephone lines are susceptible to weather such as lightning or windstorms, which may disable SCADA access to the facility. Careful consideration should be given during design of any SCADA system to default operation of controlled devices if there is a communication failure. Cellular communication technology can be used if the water storage facility and the SCADA center lie within the coverage range of a cellular communication company. A cellular modem is installed at the tank and at the SCADA center, but no hard wire exists. Instead, data are transmitted via a wireless cellular network of communication towers and cellular antennas between the site and the control center. Cellular communication is a good choice for locations where hard phone lines do not reach, as the cost is relatively higher than for a hard telephone line and fewer broadband options are available. Many electronic devices, such as pressure transmitters, small process controllers, security sensors, and so on are now available with integrated cellular modems capable of sending a small number of monitoring and/or control signals to a cellular modem at the SCADA center. Radio-frequency communication systems use a radio modem and a low-powered transceiver at the tank location, and a transceiver is connected to an RF base station at the SCADA center. Several tank sites or other remote facilities can be polled over a single ultrahighfrequency (UHF) or very-high-frequency (VHF) system. Any station can serve as a repeater to extend the line-of-sight transmission of the SCADA center (Pollack et al. 1999). In a typical application, the SCADA base requests data from a remote location, such as a tank, by transmitting a wake-up signal to send data. When the remote begins transmitting, the base reverts to the receive mode and collects the data package. After transmitting the data, the remote goes back to the receive mode and awaits instructions from the base. The output of the sensors at the remote site has usually been converted to digital data by the RTU or PLC. This signal (typically in the range of 300 to 3,000 Hz) is delivered to a modem that converts it to an analog form that can be frequency-modulated to the RF carrier. When the base receives the analog data, the base modem converts it back to digital data. The Federal Communications Commission (FCC) has allocated certain frequencies that can be used for xed operation. Certain frequencies are available for RF transmission in the low band (25 to 50 MHz), midband (72 to 76 MHz), VHF band (150 to 174 MHz), UHF band (450 to 512 MHz), and 900 MHz (928 to 960 MHz). The low band provides the
373
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
374
Chapter Nine
best communication range because the path loss is less than at higher frequencies. However, it is susceptible to interference from electrical noise. The UHF band is the most frequently used because of the large number of available channels and its relative freedom from electrical noise. Line-of-sight studies are always required to test the feasibility for RF systems. Obtaining a license from the FCC for the exclusive use of a frequency can be expensive and time-consuming. Start-up cost is high, and although maintenance cost is low, the utility becomes the sole owner and operator of the RF communication system and is responsible for its maintenance and upgrades (Pollack et al. 1999). Fiber SCADA communication systems require the installation of expensive ber-optic cable (often several miles or kilometers) to a ber utility cable. Fiber provides the best broadband of any communication method, often surpassing 100 Mbps. This expensive option should only be considered when a utility requires the fast transmission of very large volumes of data, including real-time video. The ber lines can be leased or owned, depending on availability and agreement with the provider. When the water utility owns the line, it becomes responsible for its maintenance and upgrades. When a tank is located where telephone lines, cellular communications, or RF systems are impractical, satellite communications is an option if a satellite covering the distribution system area is in space. In this case, the satellite acts as a relay station between the tank and the SCADA center. Transmitters and receivers are required at both ends to communicate through the satellite. This option is more expensive than hard phone lines or cellular technology, but it may be well worth the cost when no other communication alternative is viable.
SCADA Systems
The sophistication of the SCADA system depends on the utilitys budget, the equipment supplier, and the programmer/system integrator. Often a single operator is in charge of remotely controlling and monitoring thousands of data points throughout the distribution system. A master station at the SCADA center is usually a single device (centralized system), a master with submasters (hierarchical system), or a parallel group of processors (distributed system). For the purpose of this discussion, each will be referred to as the master station. The functions of the master station include scanning PLCs and RTUs throughout the distribution system. This is accomplished by monitoring the proper operation of remote control devices, ensuring that messages from these devices are error free, retrying when messages are incorrect, and reporting PLC or RTU failures. A master station also processes data received from RTUs and PLCs. The
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
master station does this by checking for alarm conditions, averaging and trending data, storing event changes, and entering data into a database. The transmittal of operator commands is another important function of the master station. The transmittal of commands involves several steps: interrupting the scan and arming the proper remote, encoding and transmitting the command, verifying that the proper command has been received, permitting execution of the command, and verifying command execution. Master stations must also maintain a database for historical data. To accomplish this, data received from the remote location are typically condensed into hourly and daily averages, peak values are delineated, and various data-compression techniques are used to minimize storage. Additionally, the historical data might include status information such as valve positions, water level elevations, and similar items to allow later correlation with ows and pressures. The historical database must also provide very exible data retrieval capabilities. The master station is also responsible for driving the human/ machine interface. This is done by presenting data on video display screens, map boards, printers, or similar mediums; providing the ability to dene screen formats, including graphics; and providing the ability to dene report formats. Master stations provide the important function of providing failover to a backup when necessary. This involves maintenance of duplicate data les in a backup processor and monitoring of the primary processor (by the backup) and switch to the backup (i.e., failover) on detection of a stall or error. Master stations may also perform advanced functions such as supply prediction, demand prediction, optimal pumping, and leak detection. The human/machine interface is the point at which the operator interacts with the SCADA system. Current SCADA systems offer interactive HMI modules. These allow building of display screens by those with no programming knowledge. This permits operations personnel who will be using the system to design and build graphic and tabular displays that precisely meet their needs. These displays may be interactivethat is, the symbol for a pump may change color depending on pump status, or a reservoir icon may ll as the reservoir level increases. Inputs to a SCADA system occur either as real-time events automatically sensed and reported by the remote control device or as manual inputs through an HMI. Inputs from RTUs or PLCs include status, ow, pressure, and level. Inputs from HMIs include commands for open/close, run/stop, and set point. SCADA outputs are either for driving the HMI or for executing the commands at the remote location. HMI outputs include periodic reports, alarms, alarm summary reports, graphic pictures, displays of
375
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
376
Chapter Nine
real-time data, displays of averaged or trended data, and historical reports. Control outputs include set point and on/off or start/stop. SCADA technology should permit building of reports by persons with no programming skills. An operator or engineer, for instance, can readily dene a report format. The resulting report can then be produced for a special study or scheduled to be automated output as a routine operational report (Gotoh et al. 1993). HMI screens should be organized and labeled in a way that they are easily identied and uploaded to the screen. The interface with the operator should be clear and simple (feedback, on-screen help, and option menus are useful tools). A sufcient number of control and monitoring screens should be provided to keep screen cluttering to a minimum. Alarms should be in a scroll window that does not overtake the main window. Symbols, colors, and terms should be consistent and self-descriptive. The overall screen environment should be intuitively simple and allow operation with minimal computer programming skills.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
(energy loss) due to friction. Maintaining water elevation in tanks within a specic range can help set limits on the minimum and maximum system curves. Coordinating that with the pump curves forces pumps to operate at or close to their highest possible efciencies. The size and number of pumps installed must be optimized in keeping with the demand conditions and storage available. Pumps operating efciently can reduce electric consumption drastically. In many cases, pumps with best efciency points (the combination of ow and pressure at which a pump operates most efciently) that are greater than 90 percent provided wire-to-water efciencies of less than 25 percent due to inappropriate operation. Pump wire-to-water efciencies during operation are commonly less than 50 percent. To improve pump efciency, elevated tanks should be used to satisfy the marginal demand, and pumps should be used only when there is enough demand in the system for them to operate near their optimum efciency. In addition, allowing tanks to oat on the system eliminates the need to start pumps to meet marginal demand increases, which eliminates maximum electric demand surcharges. Most water utility power rates are based on demand or capacity surcharge. That is, the water utility pays based on its peak power consumption during the billing period, for the entire billing period. Rates are also higher for power consumed during peak hours. Therefore, water administrators and operators should look for ways to decrease overall and peak-hour power consumption. The action of starting pumps, in particular, draws large and instantaneous amounts of inrush current from power grids. Electrical distribution systems may experience serious problems if a power company does not have enough standby power to meet this instantaneous demand. In fact, utilities that require large pumps for distribution pumping often must get clearance from the power company before starting a pump. Power companies may also require water utilities to install soft-starter technology to reduce starting motor current. Some small utilities with sufcient storage are able to shift pumping to periods of low electrical demand and pay a reduced rate for power. This strategy, however, is difcult to implement in large systems because of the excessive volume of storage that would be required. Many utilities have resorted to variable-speed pumping to meet variable demand. Variable-speed drives allow pumps to operate below normal speeds to reduce ow and pressure output. Although wire-to-water efciencies may be low at lower speeds, the amount of energy used is less, reducing energy consumption. Hence, peak power consumption is reduced, because only a fraction of the total potential pump power is used. The efciencies achieved by variablespeed pumping can be exceeded by properly designed and operated constant-speed pumping systems and tanks.
377
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
378
Chapter Nine
Ideally, the most efcient means of conveying water is to have no more than two pumps operating continuously at constant speed near or at optimum efciency. The number of pumps may increase or decrease on a seasonal basis if demand patterns change, but it remains constant otherwise. Tanks are lled when daily demand drops and drafted when it increases; the draft and ll limits are set by the boundaries of the pumps high-efciency region. Of course, not all systems have pump stations or tanks that are set up to do that. In addition to the peak-shaving volume for energy considerations, tank size should provide sufcient reserve storage for re ow and emergencies while maintaining tank turnover for water quality. It is not easy to optimize the tanks diameter versus height for the required storage volume to satisfy all or most of these considerations.
Bibliography
American Water Works Association (AWWA). 2003. Principles and Practices of Water Supply OperationsWater Treatment. 3rd ed., p. 210. Denver, CO: AWWA. AWWA. 1986. Maintaining Distribution-System Water Quality. Denver, CO: AWWA. AWWA. 1990. Water Quality and Treatment, A Handbook of Community Water Supplies. 4th ed., p. 14.4. New York: McGraw-Hill. AWWA. 2010. Water Quality and Treatment, A Handbook on Drinking Water. 6th ed. New York: McGraw-Hill. Clark, R. M., and W. M. Grayman. 1998. Modeling Water Quality in Drinking Water Distribution Systems. Denver, CO: AWWA. Clesceri, L. S. (ed.), A. E. Greenberg, and A. D. Eaton. 1998. Standard Methods for the Examination of Water and Wastewater. 20th ed. Washington, D.C.: American Public Health Association, AWWA, and Water Environment Federation. Code of Federal Regulations. 2004. Title 14Aeronautics and Space, Chapter 1, Subchapter E Airspace, Part 77. Objects Affecting Navigable Airspace. Washington, D.C.: Federal Aviation Administration, Department of Transportation. Code of Federal Regulations. 2004. Title 40Protection of Environment, Chapter 1, Part 141. National Primary Drinking Water Regulations. Washington, D.C.: US Environmental Protection Agency. Connell, G. F. 1996. The Chlorination/Chloramination Handbook. Denver, CO: AWWA. Crozes, G. F., et al. 1999. Improving Clearwell Design for CT Compliance. Denver, CO: American Water Works Association Research Foundation (Awwarf). De Zuane, J. 1997. Handbook of Drinking Water Quality. 2nd ed. New York: John Wiley & Sons. Gotoh, K. (ed.), J. K. Jacobs, S. Hosoda, and R. L. Gerstberger. 1993. Instrumentation and Computer Integration of Water Utility Operations, pp. 1134. Denver, CO: Awwarf and Japan Water Works Association.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
Operation
Grayman, W. M., L. A. Rossman, C. Arnold, R. A. Deininger, C. Smith, J. F. Smith, and R. Schnipke. 1999. Water Quality Modeling of Distribution System Storage Facilities. Denver, CO: Awwarf and AWWA. Guidance Manual for Maintaining Distribution System Water Quality. 2002. Denver, CO: Awwarf and AWWA. Hjertager L. K., B. H. Hjertager, N. G. Deen, and T. Solberg. 2008. Experimental and Computational Studies of Turbulent Mass Transfer in a Mixing Channel. International Journal of Chemical Reactor Engineering 6:A105. Jirka, G. H. 1999. Five Asymptotic Regimes of a Round Buoyant Jet in Stratied Crossow. 28th International Association of Hydraulic Engineering and Research (IAHR) Biennial Congress, Graz (Austria). Kirmeyer, G. J., L. Kirby, B. M. Murphy, P. F. Noran, K. Martel, T. W. Lund, J. L. Anderson, and R. Medhurst. 1999. Maintaining Water Quality in Finished Water Storage Facilities. Denver, CO: Awwarf and AWWA. Knoy, E. C. 1991a. Good Design Eliminates Frozen Storage Tanks. Opow 17(2):1. Knoy, E. C. 1991b. Solving Cold Weather Problems for Storage Tanks. Opow 17(1):2. Lee, S. Y., and R. A. Dimenna. 2001. Performance Analysis for Mixing Pumps in Tank 18. Report WSRC-TR-2001-00391 prepared for US Department of Energy, contract DE-AC09-96SR18500. Aiken, SC: Westinghouse Savannah River Co. Lindeburg, M. R. 2001. Mechanical Engineering Reference Manual. Belmont, CA: Professional Publications. Mays, L. W., ed. 1999. Hydraulic Design Handbook. American Water Works Association. New York: McGraw-Hill. Mays, L. W., ed. 2000. Water Distribution Systems Handbook. American Water Works Association. New York: McGraw-Hill. MixZone, Inc. 2005. www.cormix.com. Moegling, S. D. 1992. Modeling the Effects of Reservoir Mixing on Water Quality in Water Distribution Systems. Graduate thesis, University of Akron, Akron, OH. Nathman, J. C., R. C. Aguirre, and H. J. Catrakis. 2004. Far-Field Turbulent Mixing Efciency and Large-Scale Outer-Fluid-Interface Dynamics. 42nd American Institute of Aeronautics and Astronautics (AIAA) Conference, Sacramento, CA. Pollack, A., A. S. C. Chen, R. C. Haught, and J. A. Goodrich. 1999. Options for Remote Monitoring and Control of Small Drinking Water Facilities, pp. 52120. Columbus, OH: Battelle Press. Recommended Standards for Water Works [Ten States Standards]. 1992. Great LakesUpper Mississippi River Board of State Public Health and Environmental Managers. Albany, NY: Health Research. Roberts, P. J. W., X. Tian, S. Lee, F. Sotirepoulos, and M. Duer. 2004. Physical and Numerical Modeling of Mixing in Water Storage Tanks: Progress Report. Denver, CO: Georgia Institute of Technology and Awwarf. Sanks, R. L., ed. 1989. Pumping Station Design. Stoneham, MA: ButterworthHeinemann. Schlichting, H. 1968. Boundary Layer Theory. 6th ed. New York: McGraw-Hill.
379
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Operation
380
Chapter Nine
Shan, J. W., and P. E. Dimotakis. 2001. Turbulent Mixing in Transverse Jets. Report CaltechGalcitFM:2001.006. Pasadena, CA: Graduate Aeronautical Laboratories, California Institute of Technology. Ten States Standards. 1992. See Recommended Standards for Water Works. Great LakesUpper Mississippi River Board of State Public Health and Environmental Managers. Albany, NY: Health Research. US Environmental Protection Agency (USEPA). 1974. Manual of Methods for Chemical Analysis of Water and Wastes. Washington, D.C.: USEPA. US Environmental Protection Agency (USEPA). 1991. Guidance Manual for Compliance with the Filtration and Disinfection Requirements for Public Water Systems Using Surface Water Sources [Surface Water Treatment Rule Guidance Manual]. EPA 570391001. Washington, D.C.: USEPA. US Environmental Protection Agency (USEPA). 1999. Disinfection Proling and Benchmarking Guidance Manual. Appendix D, Determination of Contact Time. EPA-815-R-99-013. Washington, D.C.: USEPA. US Environmental Protection Agency (USEPA). 2006. Stage 2 Disinfectant and Disinfection Byproducts Rule (Stage 2 DBP rule). EPA 815-F-05-003. Washington, D.C.: USEPA. Compliance Help: http:/ /www.epa.gov/safewater/ disinfection/stage2/compliance.html#quickguides. Accessed February 2008. von Huben, H. 1999. Water Distribution Operator Training Handbook. 2nd ed., p. 16. Denver, CO: AWWA. Walski, T. M., D. V. Chase, and D. A. Savic. 2001. Water Distribution Modeling, p. 31. Waterbury, CT: Haestad Press. Walski, T. M., J. Gessler, and J. W. Sjostrom. 1990. Water Distribution Systems: Simulation and Sizing. Chelsea, MI: Lewis Publishers.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Source: Steel Water Storage Tanks: Design, Construction, Maintenance, and Repair
CHAPTER
10
Why have a maintenance program? The answer is simple: Preventive maintenance has been, and always will be, less expensive than crisis maintenance. Preventive maintenance allows owners to identify potential problems and develop solutions before the problems reach crisis proportion. For example, it can be much cheaper to identify and arrest coating failure and corrosion before they turn into metal loss requiring more extensive repair. Additionally, tank painting, if done properly, is typically required at intervals of 15 to 20 years. If the coating adhesion is monitored regularly during inspections, topcoats can be applied to the exterior to restore the aesthetics and extend life of the original or underlying coating system beyond the anticipated 15 to 20 years. Topcoating can cost only a fraction of the cost of full repainting.
381
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
382
C h a p t e r Te n
Initial Evaluation
An initial evaluation is a thorough evaluation performed to determine the tanks structural, sanitary, safety, and coating condition. The AWWA manual M42, Steel Water Storage Tanks, recommends that a professional engineer familiar with the design and maintenance of water storage tanks perform this type of evaluation. The initial evaluation is the most detailed and intensive evaluation.
Update Evaluation
An update evaluation should be performed approximately every 3 to 5 years following the initial evaluation. The update evaluation is performed to monitor changes in the coating condition and rate of corrosion and to verify that tank conditions have not changed signicantly since the previous evaluation or rehabilitation. The same person or rm that performed the original initial evaluation should perform the update evaluation. The update evaluation is not as time-consuming and detailed as the initial evaluation. The advantages of having an initial evaluation and subsequent update evaluations performed by a professional are that these evaluations will identify the optimum time for tank repainting and repairs, and the owner can better plan for and budget for proper tank maintenance or rehabilitation. The evaluations will identify all of the work that is required to properly maintain the tank. This eliminates surprises and change orders during a repair or repainting project.
Operator Evaluation
Tank owners should perform a cursory evaluation of the tanks condition at least annually. The purpose of this evaluation is to identify items that can be easily remedied by maintenance personnel and to indicate if any issues exist that require professional evaluation. If any signicant deterioration is found, or if the tank has been damaged in some way, a professional should be called in to evaluate the problem. Items requiring basic maintenance can be remedied by operating personnel at this time. If the owners personnel are not properly equipped or qualied to climb the tank, the professional person or rm that performs the initial and update evaluations could perform this function. The advantages of operator evaluations are that any signicant or serious changes that may require further evaluation by a professional, such as a potential leak or metal loss on the anchor bolts, can be identied by the operator. Also, routine maintenance can be performed by water department personnel, thus saving the costs of replacing items or repairing items at the next rehabilitation.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
383
r The AWWA Standard D100 for steel water storage tanks was r The National Fire Protection Association (NFPA) initially
originally published in 1935 and has undergone continual upgrading and modication. adopted NFPA 22 Standard for Water Tanks for Private Fire Protection in 1914.
r AWWA D100-05AWWA Standard for Welded Carbon Steel r AWWA D102-06AWWA Standard for Coating Steel Waterr AWWA D103-97AWWA Standard for Factory-Coated r AWWA D104-04AWWA Standard for Automatically Conr API Standard, ANSI/API 65-1992Welded Steel Tanks for r API Standard, ANSI/API 653-1995Tank Inspection, Repair, r API Standard, ANSI/API 620-1992Design and Construcr NFPA 22Standard for Water Tanks for Private Fire Protection tion of Large, Welded, Low-Pressure Storage Tanks Alteration, and Reconstruction Oil Storage trolled, Impressed-Current Cathodic Protection for the Interior of Steel Water Tanks Bolted Steel Tanks for Water Storage
Composite-Tank References
r ACI 371R-98Guide for the Analysis, Design, and Construcr AWWA D107AWWA Standard for Composite Elevated
Tanks for Water Storage tion of Concrete-Pedestal Water Towers
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
384
C h a p t e r Te n
should be inspected periodically by the operator and instructions regarding repair.
Site Access
Inspection
The tank and the site should be monitored for signs of unauthorized access and vandalism, which are a potential liability for the tank owner. Signs of unauthorized access include damage to the tank or site, grafti on the tank or site appurtenances, paint chipping caused by rocks being thrown at the tank, and bullet holes or indentions in the steel caused by from guns being shot at the tank. Personnel should look for damage or loose wiring in the site fence and barbed-wire strands as well as gaps between the fence and the ground. The proper operation of the gate locking mechanism, site motion detectors, site lighting, and surveillance cameras should also be veried. If the tank is equipped with an exterior ladder, the proper operation of its vandal deterrent and locking mechanism should also be conrmed.
Repair
If the site is not already enclosed by a fence, a fence at least 6 ft (1.8 m) tall and topped with barbed wire should be installed around the entire tank site. Barbed-wire strands should be added to the top of the fence if they are not already present. Personnel should then regularly maintain the fence and barbed wire so that they are in good condition. Any holes, broken wire, or bent sections should be repaired. The fence should be close enough to grade to prevent intruder passage under it. All barbed-wire strands should be taut. The fence should be equipped with a gate or gates that can be locked whenever the site is unattended. Vegetation should be regularly trimmed back from the fence so that it does not damage or restrict view of the fence. All light xtures, motion detectors, and surveillance cameras should be regularly maintained. If the tank has an exterior ladder, it should be equipped with a locked vandal deterrent.
Site Maintenance
Inspection
The operators personnel should evaluate the condition of the tank site not just for appearance purposes, but also to help protect the tank from damage and corrosion. The presence of any trees, bushes, or other vegetation touching the foundation, bottom plate, or tank should be noted. Foliage traps moisture against the steel and creates a damp atmosphere that can accelerate corrosion. These areas should also be checked to see if grass clippings or other debris have accumulated there. If saturated or eroded soil not caused by precipitation or
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
385
Repair
Trees and bushes should be trimmed back to prevent the limbs and foliage from touching the tank. Vegetation should be trimmed so it does not grow up on the foundation, base plate(s), and tank. Personnel should remove any debris found on the foundation and base plate(s). When the tank site is mowed or other maintenance operations are performed with similar equipment, the discharge should be directed away from the base of the tank to prevent any rocks discharged from hitting the tank and damaging its coating. This will also prevent grass clippings from accumulating on the foundations and base plates and accelerating corrosion. Care should be taken that maintenance equipment, trucks, and so on do not come into contact with the tank or foundation. If necessary, personnel should regrade the site so that the foundation projects 6 to 12 in. (152 to 304 mm) above grade and adequate drainage away from the foundation occurs. Rainwater runoff and overow discharge should be directed away from the foundation.
Foundation(s)
Inspection
The foundation should be checked to verify that it projects between 6 and 12 in. (152 and 304 mm) above grade and that there is proper drainage away from the foundation. The foundation(s) should be examined for signs of settlement and the concrete inspected for evidence of cracking, spalling, or exposed reinforcing steel. Deep cracks or extensive crumbling of the foundation signal, a potentially serious issue, and a professional evaluation should be conducted. Also, if the foundation tops are not approximately level with each other, this may be evidence of differential settlement of the tank foundation, and a professional evaluation should be conducted.
Repair
Personnel can apply a bonding agent and vinyl emollient concretepatching mortar to any deteriorated areas or voids found in the concrete foundation to build up the surface to its original contour. The condition of this repair should then be monitored.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
386
C h a p t e r Te n
for any cracks, voids, or deterioration. These can allow moisture to build up between the tank foundation and bottom plate and cause underbottom corrosion.
Repair
A exible sealant can be applied to any deteriorated areas or voids found in these materials to restrict the ingress of moisture through the voids and under the tank bottom plate. The condition of these repairs should then be monitored.
Repair
Personnel should keep the chairs free of debris, vegetation, and grass clippings.
Repair
Personnel should install locks on manholes and access doors. They should also replace any manhole gaskets that do not create a positive seal. If any of the bolts have corroded, they should be replaced with stainless-steel bolts to prevent rust staining from streaking onto the tank surfaces.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
387
Repair
If gaps are noted, personnel should reposition the ap gate or elastomeric check valve on the overow pipe to eliminate them. Any damaged screening on the overow pipe discharge should be replaced to prevent the ingress of insects and small animals.
Venting
Inspection
The proper operation of the clog-resistant vent and its pallets needs to be checked before and after freezing weather. The condition of the vent screening needs to be assessed to verify it is adequate to prevent the ingress of insects into the tank. Shielding over any vertically oriented screening also needs to be assessed so that wind-driven dust and debris do not enter the tank.
Repair
Personnel should replace any damaged vent screens to prevent the ingress of insects into the tank. Any damaged shielding over the screening should also be replaced so wind-driven dust and debris do not enter the tank.
Ladders
Inspection
All ladders should be carefully checked for deteriorated members that might pose a danger to climbers. The ladder brackets and their attachments to the tank and the ladder itself should be checked for missing or deteriorated bolts and/or cracked welds. The rungs should be inspected for metal loss, especially where they join the side rails.
Repair
If deteriorated members are noted on a ladder or its associated brackets, repairs should be made. If the ladder is equipped with a safeclimbing device, the device should be shielded from any paint or solvent being used to ensure its continued proper operation.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
388
C h a p t e r Te n
Repair
Personnel should replace any missing covers from oor openings and/or protective chains from safety railing.
Interior Lighting
Inspection
Personnel should check to make sure all interior lighting xtures operate properly. The condition and presence of the protective cages and globes on the xtures should be veried. The conduits associated with the lighting should be assessed to conrm that they enclose all wiring and are adequately supported. If they do not appear to be adequately supported, a professional engineer should be contacted.
Repair
Personnel should maintain any interior light xtures so that they operate properly. Burned-out bulbs should be replaced, as should damaged protective cages and globes. If the xtures or associated conduits expose wiring, it should be covered in accordance with National Electric Code (NEC) guidelines.
Obstruction Lighting
Inspection
If obstruction lighting is required on a tank, personnel should make sure it is operational and lit. The condition of any globes and bulbs should be veried. The lighting should be evaluated to conrm that it is adequately braced and that it and the associated conduits do not have exposed wiring. The condition of the photoelectric cell should be checked. The proper operation of the lighting should be veried both at night and during the day to ensure that the lights are on when required and off during daylight hours (unless otherwise required by the Federal Aviation Administration) to reduce electricity use and the frequency of replacing bulbs. If the xture and its conduits do not appear to be adequately supported, a professional engineer should be contacted.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
389
Repair
Personnel should replace damaged bulbs or globes. If wiring is exposed, it should be covered in accordance with NEC guidelines.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
390
C h a p t e r Te n
may not be visible. Additionally, the gaskets or sealants between the bolted joints should be evaluated to conrm they create a watertight seal. Glass-lined coatings should also be checked for damage around the bolts from over-tightening. If a leak or excessive corrosion is noted, a professional engineer should be consulted regarding repair, as the leak may indicate a more serious issue.
Professional Evaluation
AWWA recommends that water storage tanks be professionally evaluated at least every 5 years and otherwise whenever conditions warrant evaluation. A thorough professional evaluation will enable the tank owner to accurately schedule required maintenance, prolonging the structures useful life. A professional evaluation should consist of a careful study of the tanks interior, exterior, foundation, and accessories. All necessary surfaces on the tank should be accessed by rigging and rappelling the interior and exterior as required by the condition and design of each tank.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
391
Float-Down Evaluation
The interior of the tank is full of water as a oat-down evaluation begins. A eld technician in a small raft evaluates the interior surfaces as the owner drains the tank. The interior wet riser of elevated tanks is typically evaluated by rigging after the oat-down evaluation has concluded. The duration of this evaluation is determined by the rate at which the tank is drained.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
392
C h a p t e r Te n
the tank to access the bottom plates. Technicians get to the necessary surfaces of the tank by rigging and rappelling the interior (including the interior of riser pipes 36 in. [0.9 mm] in diameter and larger) as required by the condition and design of each tank. Both dry and wet evaluations have limitations. First, with a diving evaluation, the diver is able to access all of the steel surfaces. During a dry evaluation, the tank evaluation crew can only access, via simple rigging from roof manholes and vents, surfaces that are adjacent to ladders. However, the diver must evaluate the steel surfaces up close, as the limited light does not allow him or her to move away from the tank shell and evaluate the overall corrosion patterns inside the tank. Also, because there is usually silt in the bottom of the tank, the tank bottom cannot be as thoroughly evaluated by diving. When a diver stirs up this sediment, visibility is impaired, diminishing the quality of the evaluation of the tank bottom and the lower portion of the tank shell. In addition, the diver is working with a limited supply of air, which typically causes him or her to accelerate the evaluation. Some of the physical tests that are normally performed, including adhesion tests and dry lm thickness readings, cannot be accomplished on the submerged surfaces. Perhaps most importantly, only one diver sees the tank interior, whereas it is ideal for several members of the tank evaluation crew to visually assess the tank interior and evaluate the problems found. This provides for greater accuracy in the evaluation.
Structural Evaluation
Structural evaluations are normally only performed if the owner or the engineer believes a tank does not meet current structural standards or if the structural integrity of the tank is suspect. Structural evaluations should evaluate metal loss compared to the apparent or observed original metal loss obtained by ultrasonic testing. A structural analysis is not commonly required for properly maintained existing tanks unless the tank has been modied (if, for example, equipment or antennas have been added to the structure) or has experienced an extreme event such as high winds or an earthquake. The rst step of a structural analysis is an engineering evaluation of the tank to determine its condition. A structural engineer should review deterioration of the foundation to determine its effects on the tanks structural integrity. A level should be used to determine if differential settlement has occurred since construction of the tank. The original design drawings should be reviewed for compliance. Measurements should be taken in the eld to analyze the tank and anchorage for compliance with current structural codes and requirements that may have changed or come into effect since the tank was originally designed and constructed. The latest AWWA standards and local building codes should be used. Careful attention should be given
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
393
Specialized Inspections
Ultrasonic Thickness Measurements
Ultrasonic thickness measurements of the steel should be taken, and areas of metal loss and deterioration should be analyzed for structural deciencies.
Coating Evaluation
The coating survey should include laboratory analysis of coating samples to determine the total lead content by weight. Similar tests should be conducted for other regulated heavy metals such as arsenic, barium, cadmium, chromium, mercury, selenium, and silver. Additionally, the coating type, thickness, condition, and adhesion should be tested to assess the ease of applying a topcoat to the existing coating. If such tests indicate that topcoating is an option, recoating costs could be signicantly reduced.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
394
C h a p t e r Te n
inspections can identify problems that potentially could arise during freezing weather. Many of these problems could be easily repaired and maintained before they cause hazardous conditions or before the tank fails during freezing weather.
Owner-Performed Inspection
Immediately following a tornado, hurricane, major windstorm, or earthquake, or during freezing weather, tanks should be evaluated for any possible damage. If damage is evident, a professional structural engineer familiar with water tank design and maintenance should be contacted as quickly as possible to evaluate the structural condition of the tank.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
395
r Tanks where the foundation is extremely sensitive to the inr Sites believed to have a potential or known soil problems, or r Sites where the potential properties suggest that the default
building code soil factors used in determining the seismic load are not credible. For example, when tanks are located in areas subject to soil liquefaction or gross slip failures, additional site investigation and remediation may be required. The size, location, and type of tank inuence the relative value of a soil investigation. A tank of low height with an unanchored at bottom typically imposes less load on the soil and may not be susceptible to soil and foundation problems during an earthquake. Conversely, a large standpipe or elevated tank with substantial anchorage requirements may be signicantly affected by the soil behavior. The existing building codes and national tank design standards all specify factors to adjust the seismic design load for the site soil classication. All of these documents also have a default value when tegrity of the tank
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
396
C h a p t e r Te n
sufcient detail is not available. For many sites, the default site classications are conservative for determining the design load. Another important factor in assessing the need for a site-specic soil investigation is the history of tank failures during seismic events. The types of tank failures most often encountered are related to piping exibility, damage to the shell anchorage, shell buckling, or sloshing damage to the roof and roof support structure. Few foundation problems resulting from earthquakes are reported. When foundation problems are reported, they are often related to gross soil failures (e.g., a tank sliding down the hill) that may not be addressed by the typical soil report or may be a consequence of inadequate anchorage design.
Tank Cleaning/Washouts
As water is held in the tank, suspended solids begin to settle out of the water and onto the tank bottom. Without regular washouts, large amounts of sediment may accumulate in the tanks. In addition, proper evaluation of the interior surfaces of the tank cannot be conducted with sediment covering the bottom of the tank.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
397
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
398
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Source: Steel Water Storage Tanks: Design, Construction, Maintenance, and Repair
CHAPTER
11
The use of water as a leveraging tool in conict is not new, or is the concept of water security. Besides the air we breathe, water is the single most critical element to human survival. In Water Conict Chronology (Gleick 2008), more than 100 incidents are documented in which water was the cause of, or was integral to, a major conict or event. These events or types of conicts are grouped into one or more of the following categories: control of water resources, water as a political or military tool, terrorism, water as a military target, and disputes related to development of water resources. As early as 2,500 bc, water was used as a military tool to help defeat an enemy. With humans reliance on safe and sustainable potable water, its use as a tool of war and conict should be no surprise.
399
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
400
Chapter Eleven
December 31, 2004. The actual schedule for completion of the VAs was the following:
r March 31, 2003, for systems serving a population of 100,000 r December 31, 2003, for systems serving a population of 50,000 r June 30, 2004, for systems serving a population greater than
3,300 but less than 50,000 In each case, the system was to complete an ERP as soon as possible, but no later than 6 months after completion of the VA. The ERP was to incorporate the results of the VA. Water systems were not fundamentally insecure before September 11; most had fences, locks, and other systems to detect and delay intruders. Larger water systems sometimes had guards and more intricate electronic security systems. What fundamentally shifted was the focusaway from protecting water systems against natural disruption and contamination and toward reducing the risk from an intentional malevolent human attack (and not necessarily from an international terrorist organization). Some of the most prevalent, best documented, and least appreciated threats to water systems come from disgruntled current or former employees, a lone vandal or a group of vandals, and common criminals. Almost monthly since September 11, news stories have documented break-ins at water facilities. These types of events almost certainly occurred as often before 9/11, but they received little publicity or attention. The main difference between the pre- and post9/11 incidents is that the Federal Bureau of Investigation (FBI) and other law enforcement agencies paid the formerusually unorganized attempts at vandalismlittle attention. Nevertheless, the incidents directly pointed to the need for better risk reduction at water systems, which quickly began to improve formerly minimal security practices. or more but less than 100,000 or more
Denitions
People tend to think of providing security at water systems, and this chapter uses that terminology, but the real goal is to reduce risk by eliminating vulnerabilities. This process of risk reduction ultimately leads to the security that water system operators and the public seek. In that connection, the following denitions are provided (Sandia 2002).
r RiskMeasure of the potential damage to or loss of an asset r Risk assessmentProcess of analyzing threats to and vulnerability of a facility, determining the potential for losses, based on the probability of an undesirable occurrence.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
401
r Physical protection systemIntegration of people, procedures, and equipment for the protection of assets or facilities against theft, sabotage, or other malevolent human attacks. The goal of any security system is to prevent an attack if possible. It is generally not cost-effective, though, to stop any and all attacks. Can a water system afford the level of physical protection used at a nuclear facility or strategic military facility (armed and trained guards; kill zones, clear areas outside the perimeter where deadly force is authorized; and so on)? The answer to this question is almost always no, and so water system management must be willing to develop strategies to mitigate the consequences of an attack. This ensures that even though a water system may not be able to stop the attack from happening, it can still cost-effectively reduce the overall level of risk. Consequence mitigation, in addition to reducing the risk from an intentional malevolent human act, also helps reduce the risk to a system from a natural disaster. By providing a double benet, consequence mitigation measures may be the most cost-effective risk reduction measures of all. Certain aspects of risk reduction at a potable water storage system also benet the system during natural disasters. The focus of this chapter, however, is still on reducing risk from an intentional, malevolent human act.
Types of Threats
A water-storage facility can be intentionally attacked in three basic ways: physical disruption, contamination (radiological, chemical, or biological), and interference with supervisory control and data acquisition (SCADA), computer, and information technology (IT) systems.
Physical Disruption
Much has been written about contamination being the worst-case scenario for a water-storage facility. This is valid and worthy of discussion, but perhaps the simplest and the most effective way of having an impact on potable water storage is through physical disruption. The amount of water that humans actually consume is only a fraction of a percentage of the total potable water produced. In Milwaukee, Wisconsin, and Albuquerque, New Mexico, for example, the percentage of potable water actually consumed is one-half to one-quarter of 1 percent of the total produced (Danneels 2001). Having storage, and
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
402
Chapter Eleven
therefore supply, of nonpotable water still allows res to be fought, industry to operate, contamination to be contained, and basic sanitation to continue. In cases where potable water storage is compromised, potable water can be temporarily provided using bottled water, mobile treatment systems, and bulk water that has been hauled in. The purpose of this chapter is not to identify specic vulnerabilities of a water-storage facility or to provide direction for adversaries; therefore, the discussion will remain general. Physical disruption of storage facilities generally requires some knowledge of the specic water system to be truly effective. However, almost every water system relies on critical storage facilities that, if eliminated, would critically disrupt its ability to supply water to the distribution system or to critically important customers. It is easy to disable or eliminate a storage facility without sophisticated chemical or biological knowledge and equipment. Imagine the damage that can be done to electrical systems with basic tools. Sugar in the fuel tanks of emergency generators can create substantial damage. Valves can be broken and extensively damaged without explosives. Any simple Internet search reveals recipes for various homemade explosives capable of doing substantial damage.
Contamination
Three types of contaminants are of concern in water systems. These are, in order of concern, biological, chemical, and radiological. Traditional water treatment has focused on removal or inactivation of naturally occurring contaminants and contaminants unintentionally introduced by humans. Each case of intentional or malevolent contamination can cause unique problems. Besides the obviouscustomers getting sick or dyingone of the most likely overall problems is the widespread public perception and panic that water is not safe to drink (Burrows, Valcik, and Seitzinger 1997). Additionally, there is the problem of timely determination of what agent (or agents) has been introduced. Charlotte-Mecklenburg Utilities (in North Carolina) has dealt with this issue twice. The rst event was unintentional and involved Foamgate (Krouse 2001); the other occurred after 9/11 and was intentional. In each case, even with rapid detection of the contamination, the testing necessary to determine its exact nature and potential harmful effects was one of the most difcult parts of the entire response effort. A chemical agent might be easily detected through the taste, odor, or appearance of the water, especially if enough of the agent is present to do physical harm to a person. The problem with radiological or biological agents is that they are much more difcult to detect and deal with. The rst means of detecting these agents in water, even large quantities of agents, might be through symptoms that do not appear in an affected population until days or weeks later. Moreover,
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
403
SCADA/IT Interference
A third method of disabling a water-storage facility is through cyber attacks against a SCADA system. Fortunately, many water systems still practice manual operation and allow their SCADA systems to perform very little, if any, control. Those that do not practice manual operation or that allow maximum control by their SCADA systems run the very real risk of losing control through hackers entering their system. These hackers can be current insiders or employees, disgruntled former employees, lone thrill-seeking hackers, or a group of organized and highly capable hackers bent on signicant and coordinated destruction.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
404
Chapter Eleven
Remote Location
When a storage facility is remotely located, its primary vulnerability is that few people are around to detect an intrusion. Unless it is a manned facility, such as a clearwell at a water treatment plant, the only reliable means of detecting an intrusion would be through an accurate, automated detection system, which many remote facilities do not have. Even when a system has the capability of accurately detecting an intrusion attempt at a remote site, response would normally take too long because of the distance from a regular patrol area.
Urban Location
An urban or heavily populated location does not have the same vulnerabilities as a remote location, but several inherent vulnerabilities still exist. Location in a congested area means that many more people have close access to the site and are potentially aware of the facilitys importance. In general, in many urban areas, a lot of criminal activity goes unnoticed and unreported. One thing common to virtually all water system facilities is the presence of grafti, especially on tanks. Most water systems have not worried about this in the past, but the presence of grafti points to the ease of access by and the poor detection of intruders. In addition, because these storage facilities are so close to large population centers and because they tend to serve more critical customers, they are usually much more vital assets. In both remote and urban settings, the key is good detection. Obviously, until a system accurately detects an intrusion attempt in the rst place, delay of the intruder will not be possible. A response force, no matter how close or aware, will have not have any impact, and no facility location will be safer than any other.
Accessibility
Accessibility, as discussed here, has to do with the number of people allowed to access the facility. Almost all potable water storage systems allow nonutility personnel to have unmonitored access to storage tanks. These are most often employees of telecommunication companies, electrical utilities, and other city departments. An unscientic survey of results of many vulnerability assessments shows that almost all facilities allow this access without maintaining any direct control over who accessed the facility or when. An equally critical vulnerability is the common practice by many water systems of allowing too many of their own personnel to have keys to facilities. Maintaining access control over the water departments own personnel is a more difcult problem to solve than
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
405
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
406
Chapter Eleven
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
407
FIGURE 11-3 Tank-specic piping for enclosed-base and pedestal spheroid elevated tanks.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
408
Chapter Eleven
discharge piping, sampling ports, overow piping, shutoff valve(s), and an altitude control valve (if used). An integral pumping system is commonly provided in the base of a uted-column tank, but usually not in a pedestal/spheroid tank. In one sense, the large size of the enclosed base is one of the pluses of a uted-column tank, because more assets can be stored in the space. The other side of the coin is that storing all critical assets in one place creates potential vulnerabilities, because only a single door serves to delay an intruder. Within the base of each style are usually found SCADA components such as tank pressure gauges, residual chlorine analyzers, remote terminal units (RTUs), and radio/dialer equipment (Fig. 11-4). Internal ladders providing access to the top of the tank bowl are almost always located in the base of both styles of tanks. These ladders allow direct access to the water storage portion of the tank by way of direct hatch access or through the water-storage vent.
Multicolumn Tanks
Multicolumn tanks have many of the same features as an enclosedbase tank, but without the same level of protection. Figure 11-5 shows the base of a typical multicolumn elevated tank with a ladder guard. Usually, multicolumn tanks have detached underground vaults to
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
409
FIGURE 11-5 Typical base of multicolumn style tank with ladder guard.
house critical piping and shutoff and altitude control valves (see Fig. 11-6 for an example of this arrangement). SCADA components and other related instrumentation are sometimes housed in the same vault, but more often they are located in the open on the tank leg or possibly in an unprotected shed detached from the tank.
FIGURE 11-6 Detached underground vault for piping and valves, multicolumn tank.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
410
Chapter Eleven
In the past, ladder access was available at ground level in many systems, but that practice began to change even before September 11. The practice of cutting off ladders 20 ft (6 m) or so above ground level and adding locked access gates began as a way of controlling vandalism, and it has now become an even more accepted means of limiting access.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
411
Construction Materials
Materials of construction play only a minor part in the security of a tank. Almost all tanks are constructed of concrete, steel, or a steel/concrete composite. A study of explosives, tank characteristics, and materials of construction would be needed to determine which of the three would be most susceptible to destruction. Sufce it to say that a steel, concrete, or composite tank of proper structural design will withstand about the same level of explosive force, all other factors being equal.
Water-Storage Vulnerabilities
This section is general and avoids describing specic methods and means of contaminating or disrupting a water system through intentional acts at a potable waterstorage facility. Most key elements of water system vulnerability have been covered previously. Specic locations exist on most storage facilities that are the most vulnerable points. These include vents, sampling ports, berglass hatches, and local chemical feed stations. Many utilities have hatches that are lightly screened or not screened at all because of wear and tear. Fiberglass hatches are common on ground storage tanks and present a minimal barrier to a determined adversary. The locks usually provided for metal hatch covers are of the type found at the hardware store and are easily cut with large bolt cutters. Readily accessible sampling ports, re-hose connections, or local chemical feed systems (for maintaining residual chlorine levels, for example) are simple points of access for possible contamination. Disruption of a water system through physical destruction at a water-storage facility is a bit more difcult, but it is possible just the same. It would take a large amount of explosive placed strategically close to a storage facility to ensure complete destruction. Because of this, we tend to focus on the possibility that an adversary would attempt the same level of disruption through focused destruction of critical piping, valves, booster pumping, or other on-site components. As with a tanks access hatches and vents, most enclosed tank base doors or exterior vaults are only secured with a minimal hasp-andlock system. SCADA/IT vulnerabilities are not currently severe or common, because not many water systems rely on SCADA/IT to control functions. Many utilities use SCADA only to monitor a few key parameters and are alerted either when the signal is lost or when values are out
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
412
Chapter Eleven
of range. This does not mean, though, that these vulnerabilities can be ignored. Reliance on SCADA signals without verication can be dangerous, and often SCADA systems alarm over many minor occurrences, leaving operators to lter these alarms and potentially miss something of real importance. SCADA-related vulnerabilities will probably increase as security systems (closed-circuit television [CCTV], perimeter alarms, and so on) begin running signals through the same SCADA system used for operational data. This also opens up a new avenue to be concerned about: A disgruntled employee who controls not only the operation of a system but the security system as well is known as a super insider.
Physical Security
Physical protection systems are security measures such as CCTV (camera) systems, motion sensors, alarms, fences, locks, and guards. The basic concept of PPS is to detect an adversary as early as possible. Detection means not just having a camera system record an intruder, but having a person assess the alarm or image and react quickly and effectively to alert whatever response mechanism is planned. Delay is the combination of measures that will slow an adversary who is on the
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
413
Detection Practices
Digital CCTV
Many utilities installed CCTV capability before September 11. Some of these provided digital image storage. The majority used tape and relied on an operator to see an event in real time or to forensically view what happened. After 9/11, digital CCTV systems became more prevalent. These systems store images in digital format and provide an alarm if the viewed image deviates from a stored baseline image. In such a case, in addition to providing the alarm, they pull up the correct segment of video image, including the moments immediately preceding and following the event. With any camera system, lighting conditions and clear lines of sight are critical. An uninterrupted fence line and clear areas at least 15 ft (4.5 m) outside the fence line are essential to successful early detection. Adequate lighting, properly designed with the camera system to provide optimum contrast, is also essential. Lights should be the quick-strike type so that after a power outage has been resolved, it does not take several minutes for the lights to warm up. (Quick-strike lights come up to full candlepower almost instantly after power is restored. They do not operate without power. The best means of powering lights and other critical functions during a power outage is to provide a generator.)
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
414
Chapter Eleven
Hand in hand with these systems is the ongoing maintenance of each part of the tank and the tank site. Areas inside and outside of fences must be kept clear, lights that burn out must be immediately replaced, and any camera system must be designed to work with the light level available. These practices fall somewhat into the operation systems category because they are policy-level practices that humans take care of operationally. They are listed here, though, because they are also integral to physical security, and they clearly demonstrate the need for all protection systems to be just thatsystems. Table 11-1 shows some basic comparisons of CCTV technologies, with pros and cons for each.
Access Control
Controlling access is another key component of both detection and delay. Access control can be as simple as basic door and window locks or it can comprise state-of-the-art biometrics. Basic lock-and-key systems can be effective against many adversaries, but they require strict key-control policies that are practiced and enforced. If everyone has a key to all facilities and assets, locks cease to be effective. Good key control can detect and delay both insider and outsider adversaries. If padlocks are used at remote storage facilities to which other
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
415
Comments r Good for day and night viewing r Will not have to redo or add lights r Expensive r r r r r Good for day and lower-light vision Inexpensive Not good for dark conditions Not as easy to distinguish during the day Will have to redo site lighting to have effective monitoring
Day/night (color/B&W)
r Good for day viewing r Not good for low-light or dark conditions r Will have to redo site lighting to have effective monitoring r Expensive r Color is good for day viewing r B&W is better for night viewing r More expensive than B&W or color r Will have to redo site lighting to have effective monitoring
Recording Technology No recording r Must monitor at all times to be functional r Nothing is available that can be used for prosecution r Used for backup validation of alarms r Hard to nd previously recorded moments r Cannot record while viewing a previously recorded moment r Used for backup validation of alarms r Begins recording based on motion in the eld of view r All recordings are date/time stamped for ease in nding a particular moment when viewing r Accessible from a remote location r Images are in PC-friendly format and can be stored electronically indenitely
Tape recording
Digital recording
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
416
Cons r Must have properly installed and maintained fence lines r Prone to all types of vibrations, which can be minimized
Potable Water Security
Types of Detection
Fence sensors
Technology r Vibration
Pros r Most economical and easiest to install of the fence sensors r High probability of detection
r Taut wire
with enhancements: r Weather sensor stationfeeds weather information to eld processor, which then adjusts its vibration alarm sensitivity r Pulse count accumulatorsensitivity is determined by choosing number of pulses needed to create an alarm r Nuisance alarms can be caused by shrubbery, trees, animals, and severe weather that causes fence to vibrate r Regular tensioning maintenance is required r One of the most expensive fence sensor systems because of laborious installation and maintenance time r The more activity there is at fence, the lower the sensitivity setting r Sensitive to extreme temperature changes and blowing debris r Could be sensitive to large-animal activity r The fence must be stable, free of vibration, and in good condition
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
r Fiber optic
r Not overly sensitive to wind r Very reliable r Low false-alarm rate and low nuisance-alarm rate r Immune to electrical or electromagnetic interference (EMI) disruption r Intrinsically safe and uses very stable equipment, resulting in high reliability r Adjustable sensitivity.
r Strain-sensitive r Capable of hearing what may be causing an alarm (similar to cables pressing ear against the wall) r E-eld r Self-adjusting circuit rejects wind and ambient noise r Extremely low nuisance-alarm rate r Capacitance r Weather and EMI/radio frequency interference (RFI) have no effect on sensors ability.
In-ground sensors
r Very sensitive to high-EMI sources (for example, substations) and radio frequency interference r Sensitive to poor fence construction or maintenance r Adverse weather such as rain, snow, and lightning can create problems r Vegetation and animal movement can cause sensors to react r Generally mounted on top of fence, so use in conjunction with another type of sensor on lower part of fence fabric r Anything making physical contact that changes fence characteristics may cause an alarm r Should use additional surveillance/detection when
working with large expanses of concrete r Tree roots may cause problems when tree blows in wind r Sensitive when in close proximity to roads/rails due to machinery. r Avoid installing under chain-link fences; install at least 3 ft (0.9 m) above buried metallic pipes r Susceptible to buried metal r Affected by high-EMI sources such as large electrical equipment or substations (should not be used in close proximity to these areas)
TABLE 11-2
417
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
418
Potable Water Security
Types of Detection
optic
Pros r Mostly immune to weather and environmental noise r Immune to electrical or EMI disruption r Adjustable sensitivity
r Buried geophone
Volumetric sensors
r Active infrared
Cons r Must be installed away from poles and trees at a distance equal to at least the height of the pole or tree) r Should not be installed in or under concrete or asphalt r Susceptible to erosion where either more exposure or deeper burial affects the sensitivities r Sensitive to tree roots as the tree blows in wind r Sensitive to medium in which geophones are buried r Sensitive to trees, fences, light poles, and telephone poles, which can trigger the alarms when blowing in wind r Precise alignment of sensors is critical r Not good with hilly terrain r Sensitive to snow and grass around the sensors r Sensitive to fog, heavy rain, and dust r Sensitive to vegetation overgrowth r Sensitive to high-frequency spectrum r Sensitive to areas that contain strong emitters of electric elds (radio transmitters) or magnetic elds (large electric motors or generators) r Can interpret ionization cycle created by uorescent bulbs as motion r Potential health hazards
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
r Microwave
r Send multiple-beam pattern, increasing coverage r Good probability of detection r Available in portable versions r Narrow detection zone good for monitoring perimeter sectors r Can be used to monitor an area or a denitive perimeter line r Use monostatic sensors where well-dened area of coverage is needed (400 ft [122 m] coverage) r Bistatic sensors can be used up to 1,500 ft (457 m)
r Passive infrared
r As ambient temperature approaches temperature of intruder, sensor is less likely to respond r Sensitive to all heat sources (heaters, animals, and so on) r Precise alignment of sensors is critical r Not good with hilly terrain r Sensitive to snow and grass around the sensors r Sensitive to fog, heavy rain, and dust r Sensitive to vegetation overgrowth r Reduces probability of detection since both sensors must positively detect before sending an alarm r Has all the cons of each technology r Potential microwave health hazards r Susceptible to uneven terrain r High maintenance r Potential radio-frequency health hazards r Needs lighting r Needs unobstructed viewing
r Radar
r Greatly reduces false-alarm rate if used in predictable and/or controlled environment r Cost effective (cheaper than purchasing two individual sensors) r Good for detecting helicopter or plane intrusions
r Can help to limit false alarms r Provides record of events during an intrusion r Monitoring eld can be manipulated r Typically used in conjunction with other monitoring technologies
419
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
TABLE 11-2
420
Chapter Eleven
utilities and/ or agencies may need access, the tank owner should avoid daisy-chain systems (several interlocking padlocks); all that is necessary for an intruder to do is to break the weakest lock. Swipe cards and/or personal identication number (PIN) access control can be more secure and allow easier key control. The person must remember his or her code and remember to carry his or her key. An advantage of these systems is that they allow logging of who enters the facilityor at least of whose card and PIN were used to enter. This may not stop the adversary (the wrong person with the right key or access code can enter), but it will dissuade those who want to escape undetected. Biometric systems control access by using characteristics and traits that are unique to an individual. Among the most common are ngerprint and retina/eye scanners. These systems are virtually impossible to trick, and they do not involve having to carry a key. Their cost may prevent widespread use, but they can be especially effective against an insider or as a second layer to a perimeter detection system for an especially critical facility. See Table 11-3 for a further breakdown of various access control systems.
Glass-Break Sensors
Delay and response are most effective when there is early detection. If an adversary gets through a fence or other outer perimeter undetected, the time available to a response force for intervention is greatly diminished. However, using glass-break sensors on building windows may be necessary if perimeter detection at a fence line is not available or practical. Certainly, it is preferable to have the extra distance and delay, but short of moving entire facilities, that may not be possible. This type of sensor may also be considered a layer in a detection system for a highly critical storage facility or where threat by an insider is the main concern.
Door Alarms
Door alarms, too, are more appropriate when the adversary is an insider or as an extra layer in a detection system. The use of alarms for storage facilities within the propertys perimeter can detect an insider who, although legitimately within the perimeter of the facility as a whole, may need to be restricted from entering key buildings that house specic assets.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Technology r Proceduralrelies on identication of person by guard r Relies on guard for all access control r Proceduralrelies on identication of person by guard r Relies on guard for all access control r PIN entry can be coded per entry point, but not per person r Automated process
Comments
Photo ID
Stored-image badge
Entry Method r Verication of a personal picture on a badge to actual person wearing badge r Verication of picture on badge to
r Correct combination of numbers entered on keypad for entry into restricted area r Automated verication of card
r Key cards can be coded per entry point and per card r Access can be denied to some cardholders and allowed to others, or access can be only during certain times of day r Access privileges can be modied r Automated process r Must have both the card and PIN for access r Access can be denied to some cardholders and allowed to
Biometrics
others, or access can be only during certain times of day r Access privileges can be modied r Automated process r Characteristics include ngerprints, retina or voice recognition, or face scanning r Each characteristic is unique to the individual r Access can be denied to some individuals and allowed to others, or access can be only during certain times of day r Access privileges can be modied r Automated process
421
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
TABLE 11-3
422
Chapter Eleven
indicatorsamong the most common residual chlorine and oxidationreduction potential (ORP). The theory behind residual chlorine analysis is that a biological contaminant exerts a chlorine demand and therefore creates a drop in the residual. This unusual or unexpected drop would raise an alarm, but there would be no specic information about what caused the drop and whether it was intentional or natural. The same is true for ORP detection. This indicator may react to more contaminants, including chemical and biological contaminants, but there is no way of identifying a specic agent or of determining whether contamination occurred naturally or intentionally. Several criteria should be considered when deciding whether to implement an early warning system for water system contamination. In no particular order, they are:
Any decision to choose an early warning system must be made locally, and the relative costs (monetary, physical, social, and organizational) must be weighed against the relative benets. It is also important to keep in mind the relative infancy of this technology. Little is known about which contaminants the technology might most accurately detect, and any early warning system currently considered would not likely be able to score high on all the criteria just listed. The following sections detail types of systems and tools that will likely be used when early warning systems become more effective and prevalent. For much more specic information on planning, designing, implementing, and operating an early warning system, please refer to Early Warning Monitoring to Detect Hazardous Events in Water Supplies, from which much of this contaminant monitoring information is taken (Brosnan 1999).
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
423
Contaminant Analyzers
Current technologies for detecting a contaminant look at its effect on certain key indicators. Among the most common are residual chlorine and ORP, described previously. The very nature of these types of detection means the contaminant is already present in the system and its consequences must be mitigated. Another technique is to use biological analyzersorganisms that react in certain ways to any of several toxic agents. Their reaction is tied to an electronic signal that creates the alarm. The problems here are the lack of any specicity as to the cause of the alarm and the potential for false positives or negatives. A few examples follow:
r In the dynamic sh test, golden ides are exposed to an articial water ow/current, which they normally swim against. If they detect an upset condition, they turn to avoid it, and this action would be detected and registered. Similar techniques have been used in Europe since the 1970s. trolled column of raw water and exposed to several infrared light beams, which they regularly interrupt and which indicates a regular level of activity. If a contaminant is introduced into the water, the activity level initially increases and then sharply declines because of the death or incapacitation of the daphnia. indicator. The theory is that when mussels are subjected to a contaminant, their shells close at low contaminant levels and then open wide at severe levels. The monitor takes several mussels and glues one half of the shell to a wall. The other half of the shell has a magnet attached that contacts a reed switch to indicate an open or closed position. Electromagnetic sensing between the two shell halves can indicate their interim positions between fully opened and fully closed. use the principle that the presence of a contaminant diminishes the luminescent/uorescent level of either the algae or the bacteria. While these methods may not be desired for use at this stage, they give an indication of the body of knowledge available to enhance security at all your facilities. Technology to monitor and analyze contaminants is constantly being developed and perfected with a goal of providing accurate, real-time capability. Already the Sandia National Laboratories staff
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
424
Chapter Eleven
have developed the ChemLab (microChemLab), a palm-sized analytical laboratory that can virtually instantly detect any number of chemical or biological contaminants (Sandia 2002). This type of technology, which can accurately detect and identify an agent in real time, appears to represent the future of contaminant monitoring.
Delay Practices
Delay measures generally are the most cost-effective part of a risk reduction system that comprises detection, delay, response, and consequence mitigation. There is a multitude of number and types of measures; the only limits are the constraints of the particular site. Whether it is an operator-staffed facility such as a water treatment plant clearwell or a remote, unmanned facility such as an elevated water storage tank, the most common delay features are fencing and gates. As with any protection system, fencing and gates are useless without proper maintenance and training of the staff on how to maximize their effectiveness. A simple way of making a regular chain-link fence more secure is to use razor wire at the top of the fence instead of three strands of barbed wire. Traditional fences consist of 6-ft to 8-ft (1.8-m to 2.4-m) chain link with three strands of barbed wire on outward-facing outriggers. Where necessary and practical, the fence can be made more secure by replacing the three-strand barbed wire with at least one coil of concertina or razor wire (Fig. 11-8). Even more delay can be built in by using two layers of fencing. This system is prevalent at critical
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
425
military or nuclear sites and may be appropriate for certain waterstorage facilities. If the facility is highly visible and is located in a neighborhood, ornamental or architectural-type security fences may be necessary. Figure 11-9 shows an example of an ornamental fence that can also provide security benets. There are numerous varieties of this type of fence (the example in Fig. 11-9 is from Delgard) that can help with both security and public acceptance. Regardless of the type of fencing used, both fence and clear areas must be properly maintained. This can be assured by establishing and complying with a policy to regularly check the entire fence linethat is, to perform a touch test on the entire perimeter. Finally, tamperproof nuts and bolts for gates and fences should always be used. When reviewing the effectiveness of a perimeter fence, one of the rst checks is to see if the nuts and bolts can be loosened by nger pressure only. This is frequently the case, and it negates the effectiveness of hardened locks, razor wire, and the like. At perimeter entrance points for personnel, gates with effective locks, swipe card, or biometric access control are effective. Because vehicle access is commonly needed at water-storage facilities, the same locking systems as used for personnel access should be used. Figures 11-10 and 11-11 show examples of vehicle gate entrances at remote sites. Usually, the gates are only of the vehicle-access type; because
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
426
Chapter Eleven
the sites are unmanned, they are almost always accessed by vehicle. If gates exist but vehicle access is no longer allowed, Jersey-type barriers are very effective. These come in various forms, including plastic barriers that can be lled with liquid to add weight. If they are to be effective, they must remain lled with liquid.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
427
A special caution needs to be sounded against using daisy-chain locks if at all possible. These systems are allowed to exist because of the normal practice of permitting those other than the tank owner and personnel (e.g., people from the phone company, emergency services, police, and so on) to have unrestricted access to a site because they have equipment there. As noted elsewhere in this chapter, this practice should be stopped or at least severely restricted. In addition to preventing unknown personnel from having unrestricted access to a site, it is important to have an effective lock. Figure 11-12 illustrates the concept of the weak link in the chain, in which a simple lock of the type available at a hardware store is all that stands in the way of an adversary.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
428
Chapter Eleven
used for all windows (if applicable). Figure 11-13 shows a typical entrance conguration for a uted-column enclosed-base elevated tank. If this conguration is not practical, bars, cages, fence, or mesh can be installed on the inside of the window frame. Of course, these measures are worth nothing if doors are not kept locked and if there is no key control. Presuming the adversary gets to the asset before a response arrives, further delay measures can still be used. The most common and simplest is to build a steel cage around the actual asset. The design of this barrier must allow for adequate normal maintenance, but it can be very cost-effective.
Response Practices
The response component of physical security should focus on providing the water tank owner and staff with backup communications systems for all possibilities. This should include landline phones, cellularphone backup, and even radio systems tied into emergency frequencies. Local law enforcement should be made fully aware of all facility locations and should train on these sites. Water system staff should also be familiar with local law enforcement agencies and should have all of their emergency phone numbers up-to-date and readily available at all times.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
429
In conjunction with good detection system practice, nuisance alarms must be minimized to prevent the cry wolf problem, in which alarms are ignored because there are too many false alarms. If private guards are to be used, many issues must be addressed. Will they be employed 24/ 7/365? Will they be armed? What level of authority will they have? Will they be used at all facilities? Do they regularly train with local law enforcement? Generally, the cost of hiring private guards is prohibitive. An adequate response can be made by local law enforcement if you have worked to improve relationships with those agencies.
Operational Security
Operational security (OS) can also provide security, detect and delay an adversary, and enhance response capabilities.
r From an operational perspective, one of the best ways to improve detection is to have a well-trained and aware staff. Preparing and fully implementing a set of security policies
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
430
Chapter Eleven
and procedures along with emergency operations and response plans is absolutely the most important element of any risk reduction program. and should be well trained.
r Complete background checks should be conducted for all emr Limit access and key availability to only those employees who
need them. ployees. Focus more thorough and more frequent checks on employees who have critical access.
r Strengthen existing backow prevention policy or establish a r As already stated, probably the most effective way to delay
an adversary is by establishing and implementing securityand emergency-related policies and procedures. These should specically address such areas as key control for all facility locks. If biometrics or other types of access control are used, proper policies and procedures still must be followed. The same type of key control policy should apply to vehicles and at all other points where access needs to be restricted. All employees should be subject to strict sign-in/sign-out procedures around all critical facilities and when using any water system vehicle.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
new policy. Begin requiring backow prevention on all connections and change-outs.
431
Consequence Mitigation
If detection, delay, and response have failed and a successful attack has occurred, you are left to mitigate the consequences of that attack. For water systems, conducting mitigation may be one of the most costeffective means of reducing the risk of future attacks and ultimately improving the level of security for the system. Consequence mitigation provides benets after an intentional human act and after natural disasters. As with some high-level adversaries (e.g., international or domestic terrorists, organized criminal enterprises, and saboteurs), a natural disaster cannot be prevented from attacking a water system; in either case you must be able to mitigate the consequences. These general mitigation techniques are applicable to all sites:
r Provide and maintain an inventory of replacement equipment, focused on the most critical assets as determined from a Sandia-based RAM-WTM (Sandia 2002) or other vulnerability assessment. same location or structure as the primary item.
r Do not store replacement or redundant components in the r Provide generators or other backup power at all critical facil-
r For utilities that use gaseous chlorine, store less total chlorine r If you must store large quantities of gaseous chlorine on site,
store it in two or more geographically distant locations to lessen the amount available at any single place.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
ities. They should be capable of powering the critical assets, at a minimum. on site, assuming delivery is on time and reliable.
432
Chapter Eleven r Provide additional gas venting and storage locations for all r In lieu of gaseous chlorine, switch to safer means of disinfecr Provide tamperproof, lockable re hydrants. Schedule regular r Work toward establishing system interconnects with neightraining and communication with re department personnel. boring utilities whenever possible. Modeling and testing of the feasibility of an interconnect must happen before any physical connection is made. tion such as hypochlorite delivered in bulk form or created through on-site generation. gaseous chlorine, and regularly provide emergency training.
Bibliography
Brosnan, T. M., ed. 1999. Early Warning Monitoring to Detect Hazardous Events in Water Supplies. International Life Sciences Institute (ILSI) Risk Science Institute Workshop Report. Washington, D.C.: ILSI. Burrows, W. D., J. A. Valcik, and A. Seitzinger. 1997. Natural and Terrorist Threats to Drinking Water Supplies. US Army Center for Health Promotion and Preventive Medicine. In Proc. 23rd Environmental Symposium and Exhibition, American Defense Preparedness Association, Arlington, VA. Danneels, J. J. 2001. Department Manager, Sandia National Laboratories. Statement to US House of Representatives Committee on Science, hearing on H.R. 3178 and the Development of Anti-Terrorism Tools for Water Infrastructure, Nov. 14, 2001. Deininger, R. 2000. The Threat of Chemical and Biological Agents to Public Water Supply Systems. Water Pipeline Database, Science Application International Corporation (SAIC), Hazard Assessment and Simulation Division. McLean, VA.: SAIC. Gleick, P. H. 2008. Water Conict Chronology (revised). Oakland, Calif.: Pacic Institute for Studies in Development, Environment, and Security. Krouse, M. 2001. Backow Incident Sparks Improvements. Opow 27:2. Public Health Security and Bioterrorism Preparedness and Response Act of 2002. Public Law 107-188, 42 U.S.C. Washington, D.C.: 2002. Security Systems and Technology Center, Systems Analysis and Development Department, Sandia National Laboratories. May 2002. Risk Assessment Methodology for Water (RAM-WSM ). Notebook Volume I. Copyright 2002 Sandia Corporation. Contract DE-AC04-94AL85000. Export Control Classication Number (ECCN) EAR99. US Environmental Protection Agency. 2006. Guidelines for the Physical Security of Water Utilities. ASCE/AWWA Draft American National Standard for Trial Use. American Society of Civil Engineers (ASCE), American Water Works Association (AWWA), and Water Environment Federation (WEF). Washington, D.C.: USEPA.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Source: Steel Water Storage Tanks: Design, Construction, Maintenance, and Repair
CHAPTER
12
Tank Rehabilitation
Gregory R. Chip Stein, P.E.
Tank Industry Consultants
Maintaining water-storage facilities is becoming increasingly important because of rising replacement costs and the difculty of obtaining rate increases and funding for large-scale construction operations. Although the cost of maintenance is also increasing, these smaller outlays can substantially delay or even eliminate the need to replace a utilitys large capital investment in tanks. This chapter is a guide to the proactive rehabilitation of existing water tanks as well as a guide to planning short- and long-range maintenance operations on a new tank. When renovation of an existing tank is being considered, an evaluation must be made to determine the scope of work to be included. The costs of renovation versus replacement must be compared and amortized over the life of a new tank to determine if repair is economically justiable.
Developing Specications
If an evaluation of the tanks condition, components, and appurtenances has determined that repair is requiredand if repair is economically feasibleit is necessary to generate a set of detailed technical specications and bonding requirements. The scope of work must be determined by evaluating the recommendations and cost estimates from the inspection report and comparing these to the availability of funds and to the tank owners long- and short-term plans for the tank. Often, there are multiple potential solutions to an observed deciency. To determine the repair that best ts the utilitys needs, these solutions and their associated costs should be evaluated in terms of the level of risk the utility is willing to accept.
433
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Tank Rehabilitation
434
C h a p t e r Tw e l v e
Standards Referenced
For the specication writer to be effective, he or she must have a working knowledge of and have access to the following material:
r Applicable American Water Works Association (AWWA) r National Sanitation Foundation (NSF) standards r SSPC Painting Manual Volume 2: Systems and Specications. r Local regulations regarding volatile organic compounds r National Fire Protection Association regulations r All pertinent regulations from the Occupational Safety and
Health Administration (OSHA) and American National Standards Institute (ANSI) In addition to these, the specication writer must have a working knowledge of any state or local regulations that apply to water tank rehabilitation. The writer should also be familiar with the capabilities and availability of qualied contractors to perform work of the nature and magnitude required. (VOCs) Society for Protective Coatings standards
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Tank Rehabilitation
Ta n k R e h a b i l i t a t i o n
Open communication among the specication writer, the tank owner, and local ofcials is imperative when preparing specications.
435
Environmental/Worker Safety
Lead Regulations
Regulations regarding removal of paint that contains lead and other regulated heavy metals were changed in the early 1990s. Methods of compliance and the interpretation and enforcement of these regulations to protect the environment and workers have changed dramatically. Many areas of the United States now enforce a policy of no emissions into the atmosphere or past the property line. Add to this the concern for the safety of workers while they are removing the coatings, and it is obvious why the cost of water tank rehabilitation has doubled. The largest problem has been collection of the dust and debris generated by the removal of the tanks coating while keeping workers exposure levels to heavy metals within the permissible range prescribed by OSHA in its regulation 1926.62. One solution is to shroud the entire structure with impervious tarps and conduct open blasting within this containment system. Dust collectors are then used to negate the pressurization effect of the compressed-air abrasive blasting, producing a negative air pressure in the containment enclosure. Workers must be adequately equipped with respiratory protection while they are in this hazardous environment. This relatively expensive method of containment has been very successful and widely used. Other methods of surface preparation include the use of vacuum shrouding around blast nozzles and power tools and the use of ultra-high-pressure (35,000+ psi [241.32 MPa]) water jetting. The most promising technology currently in use and undergoing further development is the robotic blasting system. This system includes a self-contained centrifugal blasting apparatus that seals against the tank surface. The unit is raised and lowered by a winch and cable. There is no compressed air, so there is no pressure to disperse the debris that is generated. The abrasive media is typically recyclable, so the amount of debris is minimized. Additionally, because workers are outside the blasting assembly, they are not exposed to the concentrated dust.
VOC Regulations
Volatile organic compounds, the solvents that traditionally have given coatings their liquidity and workability, are being heavily regulated nationwide. To complicate matters, different areas of the country are
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Tank Rehabilitation
436
C h a p t e r Tw e l v e
adapting different acceptable levels of VOCs in industrial coatings. As the solvents in the coatings are released, the coating dries. To reduce VOCs in their products, coating manufacturers are producing more high-solids coatings and more water-based coatings. These new coatings will greatly affect coating selection for topcoating operations, recoating, and construction of new tanks.
Water Circulation
Short-circuiting and stagnation of water in tanks is a concern for tank owners, who have installed bafe walls and piping systems to force circulation and water turnover. Bafe walls should be carefully designed to account for their effect on the tank structure. Additionally, these walls present challenges to future tank maintenance. Piping systems should be evaluated for use of dissimilar metals, increased cost of interior repainting, and degree of head range loss required to run the system.
Surface Preparation
A successful coating application depends largely on the quality of surface preparation. Regardless of the substrate (be it steel, concrete, or a coated surface), the area to be coated must be clean, relatively free of contaminants, and properly abraded to receive a coating. Surface preparation should be specied to conform to the applicable SSPC standards for cleanliness and the coating manufacturers surface prole requirements. Depending on the location of the water tank (in coastal or heavy-industry areas, for example), specic requirements regarding the degree of cleanliness and additional testing requirements may be required for surface contaminants.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Tank Rehabilitation
Ta n k R e h a b i l i t a t i o n
437
Coating Systems
There is no longer any such thing as a standard coating system. Technology in the painting industry, especially in the water storage tank industry, is in a period of rapid change. There is no longer a standard specnot if you want a coating system that will truly protect your tank. Gone are the days when conventional paints were applied over minimally cleaned surfaces by everyday laborers. Now, in a period of increasingly stringent environmental regulations, highly skilled technicians apply sophisticated coatings onto surfaces cleaned by everevolving surface preparation methods. We must now design a coating system for each tank, taking into consideration all the specic conditions that may affect the systems performance.
r r r r r r r r
What are the constraints of the tank site? What is the design of this tank? What is the current condition of its coating? What are the types of coating failures observed on this tank? Why did these coating failures occur? What can be done to correct these coating failures? Where are the existing corrosion problems on this tank? What time of year and for how long can the tank be taken out of service for painting?
r What is the level of community acceptance of this tank? r What are the owners short- and long-term plans for this tank?
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Tank Rehabilitation
438
C h a p t e r Tw e l v e
After these questions have been answered, review possible coating alternatives. Weigh the advantages and disadvantages of each system so that the best system can be provided for a specic tank and owner. Research of coating alternatives should begin with a thorough review of applicable standards. This review should include AWWA D102 Standard for Painting Steel Water-Storage Tanks and the applicable standards of the SSPC. The coatings must comply with and be tested in accordance with the requirements of the NSF for coatings in contact with drinking water. Finally, the coating manufacturers performance test data and real-life case histories should be investigated, as well as any independent laboratory testing or documented service history.
r Reduce initial cost. r Provide the optimum coating life for the tank environment. r Minimize release of VOCs or other harmful materials into the r Provide a coating system that will be easily maintained by
touch-up and maintenance topcoating, thus minimizing the need for abrasive blasting to bare steel until the tank has been topcoated several times. atmosphere.
r Eliminate unsealed or uncoated interfaces of steel surfaces. r Provide excellent resistance to abrasion and be self-healing r Provide excellent resistance to ultraviolet (UV) light, moisture, r Provide a recoat window varying from a few days to as long r Meet all NSF standards and US Environmental Protection r Describe the system in generic or performance terms that do
not rule out qualied coating manufacturers yet that uphold the standards of quality and performance necessary to provide the tank owner with the best possible system. Agency (USEPA) regulations. as years for new tank projects. oil, soil, and chemicals. when subjected to minor abrasions and scratching.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Tank Rehabilitation
Ta n k R e h a b i l i t a t i o n
Prior to the effective date of NSF Standard 61, Drinking Water System ComponentsHealth Effects addressing direct and indirect water additives, there were many types of coatings: r Vinyls
439
Phenolic aluminum In the past, these coatings have worked with varying degrees of success. However, because strict environmental guidelines for toxins, heavy metals, VOC emissions, and other health threats have since been established, signicantly fewer of these coatings are likely to meet new criteria set forth for use on tank interiors. The success of the two-component catalyzed epoxy appears to make it the frontrunner at this time. Epoxies can be and have been formulated with very high solids (low VOCs) and with many chemical varieties available. Two-component catalyzed epoxy is a highly versatile tank lining and coating. Another product for consideration is the solventless 100 percent solids polyurethanes. These products are not mixed, as conventional epoxies and urethanes are; they are sprayed with a dual pump arrangement that mixes the polyurethane at the spray gun tip. The advantage is less waste and a coating that cures for immersion within 48 hours. Manufacturers claim that these coatings offer from 20 percent to 38 percent longer life than epoxies, but in this authors opinion, extensive eld testing and evaluation are required to substantiate this claim. One last coating for consideration for water immersion is not really a coating at all. Spray metalizing using zinc, aluminum, or a combination of both has been used successfully for many years. Only recently has technology made this a viable option when considering costs. Zinc coatings can also be used for direct application to the water tank. While there is a lack of extensive service history in our industry, inorganic zinc coatings could be used on surfaces intended for immersion in potable water if NSF certied. However, these coatings should not be topcoated unless they are fully cured and hydrolyzed.
r r r r r r r
Zinc dust/ zinc oxide Chlorinated rubber Bituminous Coal tar Red lead Wax grease
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Tank Rehabilitation
440
C h a p t e r Tw e l v e
contaminants. Because of potential community resistance, coatings requiring minimal to no abrasive blasting are attractive alternatives for future repainting needs. With ever-tightening regulations to control VOC emissions, the alternatives for exterior systems have been reduced signicantly. Solvent-based aluminums, acrylics, vinyls, and chlorinated-rubber paints do not meet most VOC restrictions and have lately been used very little. Although we are never quite sure what direction the regulatory bodies will take when it comes to environmental issues, the trend appears to be to reduce emissions even further, resulting in lowering the VOCs of all coatings. Generic coating systems that currently meet most areas restrictions are high-solids alkyds, water-based acrylics, epoxies, polyurethanes, and inorganic and organic zinc-rich coatings. More stringent regulations will probably eliminate alkyds and all but the high-solids epoxies and polyurethanes in the future. The most widely used exterior system today is the epoxyurethane system, sometimes with a zinc-rich primer and sometimes with an additional clear urethane topcoat. Water-based acrylics are becoming more popularespecially for overcoating, due to the minimal stress they have on existing coatings during cure and for congested sites where their dry fall characteristics are important. (Dry fall coating overspray releases all of its solvents as it falls through the air. The overspray is dry when it contacts the surface below.) A more recent technology is the use of solvent or new water-based uorourethanes. Previously, these coatings were only available as a baked-coil coating material from which more than 25 years of color and gloss retention was normally expected. Time will tell if the newer air-dried versions will perform as well. Another category of exterior coatings comprises inorganic-based siloxane hybrids that claim to weather as well as, if not better than, conventional polyurethanes, but apply like high-build epoxies. Finally, there are varieties of coatings of several generic types that are formulated so that they can be applied over very minimally cleaned surfaces. They can be applied over rust, rust stain, old chalked and cracked paint, and other existing coating defects. Environmental issues, especially for lead paint removal and abrasive dust generation, have caused speciers to strongly consider alternatives to conventional cleaning methods. To avoid open-air blasting, the coating industry has developed various methods to achieve the same degree of cleaning. Among these methods are containment of the structure with tarp material and the use of dust collectors to produce negative air pressure inside this containment.
Risks Cost 0 Low Low Moderate High High Low Low Low High High Low Moderate Low High Low Low Low Low High Low Early Coating Failure N/A Environmental Release N/A Worker Contamination N/A Adverse Publicity High High Moderate Low High Low
Alternative Do nothing
Benet None/negative
Very low
Zone painting
Low
Spot repair/overcoat
Moderate
Tank Rehabilitation
Complete removal/recoat
High
Replace tank
High
TABLE 12-1
441
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Tank Rehabilitation
442
C h a p t e r Tw e l v e
information. Costs may be inserted using an engineering estimate or even from the actual bids. Another consideration is when the tank can be drained and available for painting. If this cannot be done in normal warm-weather conditions, the coating system design must specify either coatings that can be applied and cured at colder temperatures or coatings that are applied while using heaters and dehumidication to control the environment. If the schedule is tight and downtime must be limited, multiple shifts using environmental control might overcome schedule constraints. Also, the coating system must meet the owners aesthetic requirements. Color availability and color and gloss retention are important aspects of aesthetic appeal. To the public, aesthetic appeal is often the most important aspect of the coating system. One nal consideration when designing coating systemsthe specier must keep in mind the knowledge and abilities of the potential low bidder. The specier must realize that if no independent eld inspection of the work will occur, there is greater risk in specifying a coating system that is very sensitive to the quality of workmanship as are nearly all of the new long-life systems. So, if little or no inspection is to be performed or if prequalication of the bidders is impossible, it is not recommended to specify coatings that are difcult to properly apply. Likewise, the specier must be prepared to address problems that will undoubtedly occur in the eld. This may even include demonstrating to the contractor how the specied coatings are to be mixed, applied, and cured. As new systems are developed, adequate product knowledge and practical eld experience with these new coatings are lacking. Beware of being the guinea pig for new coating systems. Know what you are specifying! If you lack previous experience with the new product, observe application procedures and gain information from knowledgeable colleagues. It is important that speciers continually learn about new coatings, equipment, procedures, regulations, and other important aspects of the coating industry through pertinent professional organizations and societies so they can provide the best service possible.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Tank Rehabilitation
Ta n k R e h a b i l i t a t i o n
443
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Tank Rehabilitation
444
C h a p t e r Tw e l v e
information, and interpret and dene the owners decisions. The utilitys representative should also be responsible for arranging for access onto both public and private properties as necessary and for reviewing and providing input on all documentation submitted by the contractor and the engineer.
r Temperature of steel r Weather conditions (temperature, wind velocity and direcr Paint batch numbers used on the day of the observation r Location of work performed r Quality of work being performed and compliance with the r r r r r r r r r
project documents Wet and dry lm thickness readings Calibration record of dry mil thickness gauge Measure of the paint cure Number of workers on the job Equipment on the job Recommendations made Estimated completion date Photographs of signicant details Other pertinent data as required or requested tion, relative humidity, and dew point)
It is necessary that the on-site project representative, in addition to having the previously discussed qualications, be trained and qualied to competently use the equipment necessary to verify the quality of the work. The project representative generally uses the following equipment and resources to observe the work when required to do so:
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Tank Rehabilitation
Ta n k R e h a b i l i t a t i o n r r r r r r r r r r r
AWWA standards D100-96 and D102-97 Testex Press-O-Film Prole Measurement System Surface contamination detection device (soluble salts) Wet lm thickness gauge Dry lm thickness gauge Certied thickness calibration standards Steel temperature gauges Sling psychrometer and psychrometric tables Wet sponge holiday detector (low voltage) Tooke Gage (if required) Adhesive force measurement device (if required)
445
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Tank Rehabilitation
446
C h a p t e r Tw e l v e
bonding, length of contract time, and bidding information. Sometimes a utility has a complete set of contract documents; sometimes it just provides certain documents and/or input on minimum requirement levels. If the utility lacks a complete set of contract documents, there are organizations that provide boilerplate documents (e.g., the Engineering Joint Contract Documents Committee) that can easily be modied for tank rehabilitation. Regardless of how the contract documents are assembled, the utility must provide precisely exact input in numerous areas, including minimum insurance level requirements, liquidated damages amounts, on-site availability of water and electricity, and bid opening dates.
Contract Administration
The specier and the tank owner should collaborate to administer the project to make sure that the owners needs are being satised. The owner may prefer that some activities be performed on-site during a rehabilitation project; some activities are best overseen by either the specifying engineer or the on-site project representative. The project engineer should verify compliance with the project specications and contract documents to ensure that both the letter and the intent of the documents are being followed. The go-ahead for work to proceed should not be given until all submittals have been reviewed and accepted. After all of the submittals have been reviewed and accepted, numerous other administration activities need to be done, including these:
r Pre-job conference attendance r Consultation on adequacy of and compliance with the project r Specication interpretation r Attendance at the preconstruction meeting and all subsequent r r r r
meetings, and provision of meeting notes Review of all contractors submittals and shop drawings Review of construction schedule Review and approval of materials Preparation for negotiations of change orders and assistance with supplemental agreements specications
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Tank Rehabilitation
Ta n k R e h a b i l i t a t i o n
447
r Have an experienced foreman present. r Be prepared to perform minor touch-up work. r Bring all rigging necessary to performance of the touch-up r Bring at least 1 gal (3.79 L) each of the exterior primer, interr Bring at least 1 gal (3.79 L) each of an interior coating that can r Bring Scotch-BriteTM abrasive disks with power tools and r Supply equipment with which to apply coating repairs. r Supply equipment with which to wash out the tank and chlorine to disinfect it following the evaluation and any required touch-up work. The project representative should prepare and submit to the water tank owner a brief report with color photographs of the conditions found during the rst anniversary evaluation and of the touch-up work. sandpaper to clean the steel surface. be placed in immersion service immediately for minor spot repairs. mediate coating, and nish coating. work.
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.
Tank Rehabilitation
Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com) Copyright 2010 The McGraw-Hill Companies. All rights reserved. Any use is subject to the Terms of Use as given at the website.