ASSIGNMENT 3 (CRITICAL PATH METHOD)

No 1 2 3 4 5 6 7 8 9 10 Item/Activities A B C D E F G H I J Duration (month) 1 1 3 6 3 0 5 6 6 9 Succeeding activities. B C, D, E F, J F, H H, J G, H I I J -

Based on the above table: i. ii. iii. Construct the activities network using Critical Path Method. Determine the duration for the whole project. Determine the activities that are in the critical path.

ASSIGNMENT 4 (PRECEDENCE DIAGRAM METHOD)


No 1 2 3 4 5 6 7 8 9 10 11 Item/Activities A B C D E F G H I J K Duration (month) 2 2 2.5 1 0.5 2 1.5 2 2 5 1 Preceding activities. A B C D D&E H F F&H F, G, H, I J

Based on the above table: i. ii. iii. iv. Construct the activities network using PDM. Determine the duration for the whole project. Determine the activities that are in the critical path. Determine total float (TF), free float (FF) and independent float (FF)