POWER SYSTEM OPERATION CORPORATION LIMITED.

SOUTHERN REGIONAL LOAD DESPATCH CENTRE

DAILY OPERATION REPORT


POWER SUPPLY POSITION IN SOUTHERN REGION FOR 06-SEP-2013

DATE OF REPORTING : 07-SEP-2013 AT 06:00HRS

1. REGIONAL AVAILABILITY
EVENING PEAK (19:00HRS)
AVAILABILITY
(MW)*

SHORTAGE
(MW)#

32555

1081

NIGHT OFF-PEAK (03:00HRS)*

DAY ENERGY (MU)

FREQUENCY (Hz)

AVAILABILITY
(MW)*

SHORTAGE
(MW)#

FREQUENCY (Hz)

MET

SHORTAGE #

50.10

26412

300

50.17

724.73

21.55

* MW Availabilty indicated above includes SR ISTS Loss.


2 A. STATE DEMAND (ENERGY - MU)

#Shortage is calculated at 50 Hz which is the sum of Load Shedding and Frequency Correction at 50 Hz.

STATE

THERMAL

HYDRO

GAS/NAPTH
A/ DIESEL

WIND

OTHERS

NET SCH
(FROM GRID)

DRAWAL
(FROM GRID)

AVAILABILITY

DEMAND
MET

AP

110.15

38.14

11.70

2.02

17.20

81.20

83.69

260.41

262.90

7.29

KAR

58.91

29.75

21.15

9.35

14.40

18.64

17.47

152.20

151.03

10.82

KERALA

0.00

27.94

0.10

0.22

0.22

27.27

27.95

55.75

56.43

1.17

TN

89.48

21.74

20.52

24.74

28.74

63.22

63.36

248.44

248.58

2.24

PONDY

0.00

0.00

0.00

0.00

0.00

6.97

5.79

6.97

5.79

0.03

TOTAL

258.54

117.57

53.47

36.33

60.56

197.30

198.26

723.77

724.73

21.55

SHORTAGE #

# The accuracy of shortage computation depends on timely load shedding details furnished in the web directly by constitutents
2 B. STATE DEMAND (MW) & ENERGY FORECAST (MU)
19:00 HRS PEAK

03:00 HRS OFF-PEAK

STATE

DEMAND
MET

SHORTAGE #

DEMAND
MET

AP

10910

275

KAR

7399

450

KER

3011

TN

10732

PONDY

DAY PEAK

DAY ENERGY (MU)


DEVIATION
FROM
FORECAST
(ACTUAL +
LS FORECAST)

SHORTAGE #

DEMAND
MET

TIME

SHORTAGE#

FORECAST

9612

11664

19:00

275

263.00

6.03

4945

300

7338

19:00

450

170.00

-8.97

150

1878

3058

19:00

156

58.16

-0.85

206

9415

11224

19:30

219

255.65

-5.89

153

212

292

18.22

7.03

-1.24

SR ISTS LOSS

350

--

350

--

--

--

--

--

--

SR

32555

1081

26412

300

33392

18:56

1081

753.84

-10.92

DAY ENERGY
(MU)

AVG MW

3. GENERATION :
STATION

INSTALLED
CAPACITY(MW)

19:00HRS
PEAK MW

03:00HRS
OFF-PEAK MW

DAY PEAK
MW

HRS

ANDHRA PRADESH
Vijayawada TPS

1760

1551

1465

1599

19:06

37.22

1551

Kothagudam TPS

1720

1269

902

1269

19:00

26.15

1090

Rayalaseema TPS

1050

546

486

546

19:00

13.22

551

Simhadri (IPP)

1000

914

942

979

06:38

22.73

947

Kakatiya TPP

500

501

408

510

20:33

9.57

399

Other Thermal*

63

157

146

157

19:00

1.26

53

Total Thermal

6093

4938

4349

--

--

110.15

4591

N'Sagar

816

719

29

829

18:50

8.57

357

Srisailam LB (Gen)

900

822

--

824

19:02

8.48

353

Srisailam RB

770

545

--

632

05:57

6.79

283

Srisailam LB (Pump)

900

--

--

--

--

--

--

Lower Sileru

460

116

125

137

21:34

4.40

183

Upper Sileru

240

100

51

161

18:51

1.92

80

Other Hydro

751

365

358

--

--

7.98

333

Total Hydro

3937

2667

563

--

--

38.14

1589

Vijjeswaram Gas

272

130

155

163

04:15

3.16

132

Reliance Energy Ltd.

220

--

--

--

--

1.36

57

Jegrupadu

217

63

64

65

04:04

1.49

62

Spectrum

208

128

66

131

22:36

2.00

83

LANCO

351

158

157

162

07:18

3.69

154

Vemegiri (GMR)

370

--

--

--

--

--

--

Jegrupadu Ext.

220

--

--

--

--

--

--

Konaseema

445

--

--

--

--

--

--

Gauthami

464

--

--

--

--

--

--

GMR(BRG)

237

--

--

12:47

--

--

Other Gas/Naptha/Diesel

27

--

--

--

--

--

--

Total Gas/Naptha/Diesel

3031

479

442

--

--

11.70

488

Wind

430

15

133

133

03:00

2.02

84

Others

707

35

15

35

19:00

17.20

717

Total AP

14198

8134

5502

--

--

179.21

7469

* The genaration includes the injection of CPPs for which installed capacity not considerd due to variable nature.

Page 1 of 16

STATION

INSTALLED
CAPACITY(MW)

19:00HRS
PEAK MW

03:00HRS
OFF-PEAK MW

Raichur TPS

1720

840

Bellary TPS

1000

841

UPCL(IPP)

1200

Total Thermal

DAY PEAK

DAY ENERGY
(MU)

AVG MW

10:00

20.79

866

22:13

19.52

813

791

19:00

18.60

775

2522

--

--

58.91

2454

723

349

981

09:41

16.36

682

300

--

368

06:41

3.42

143

460

128

46

295

11:36

2.15

90

Other Hydro

1992

810

355

--

--

7.82

326
1241

MW

HRS

937

974

858

913

791

727

3920

2472

Sharavathi

1035

Nagjher

885

Varahi

KARNATAKA

Total Hydro

4372

1961

750

--

--

29.75

Yelehanka Diesel

128

--

--

--

--

--

--

Jindal

1460

1025

664

1121

07:21

21.15

881

Other Gas/Naptha/Diesel

118

--

--

--

--

--

--

Total Gas/Naptha/Diesel

1706

1025

664

--

--

21.15

881
390

Wind

2163

654

547

700

19:29

9.35

Others

1055

320

311

320

19:00

14.40

600

Total KAR

13216

6432

4794

--

--

133.56

5566

KERALA
Iddukki

780

554

178

629

19:07

8.54

356

Sabarigiri

280

222

219

282

20:44

5.41

226

Lower Periyar

180

158

88

159

19:10

2.62

109

Other Hydro

751

548

366

--

--

11.37

474

Total Hydro

1991

1482

851

--

--

27.94

1165

Kayamkulam

360

--

--

00:01

--

--

Reliance Energy Ltd

157

--

--

--

--

--

--

Brahmapuram DPP

107

--

--

--

--

--

--

Kozhikode DPP

128

42

--

56

19:28

0.10

Other Gas/Naptha/Diesel

22

--

--

--

--

--

--

Total Gas/Naptha/Diesel

774

42

--

--

--

0.10

Wind

35

--

--

--

--

0.22

Others

20

--

--

--

--

0.22

Total KER

2820

1524

851

--

--

28.48

1187

TAMILNADU
Ennore TPS

450

89

102

102

00:00

2.13

89

North Chennai TPS

630

903

838

984

10:40

13.60

567

Tutucorin TPS

1050

858

949

971

16:20

23.52

980

Mettur TPS

1440

1095

913

1135

17:58

26.53

1105

Neyveli-I (IPP)

600

391

323

391

19:00

7.65

319

ST-CMS

250

219

221

223

11:49

6.01

250

NCTPS STAGE-II

600

--

--

--

--

10.04

418

Other Thermal

--

--

--

--

--

--

--

Total TN Thermal

5020

3555

3346

--

--

89.48

3728

Kadamparai (G)

400

--

--

199

06:22

1.16

48

Kadamparai (P)

400

--

--

--

--

1.71

71

Other Hydro

1824

1043

570

--

--

20.58

858

Total TN Hydro

2224

1043

570

--

--

21.74

906

Basin Bridge

120

--

--

--

--

--

--

Kovilkalappal

108

61

59

71

21:42

1.55

64

Kuttalam

101

80

80

80

00:00

2.05

85

Valattur(Stg 1&2)

187

89

89

89

00:00

4.04

168

Samalpatty

106

--

--

28

09:57

0.09

P P Nallur

331

274

275

324

06:16

6.86

286

Madurai Power CL

106

12

--

88

10:03

0.18

GMR Vasavi

196

120

40

160

08:10

2.29

95
144

Other Gas/Naptha/Diesel

1477

1448

1446

1448

19:00

3.46

Total Gas/Naptha/Diesel

2732

2084

1989

--

--

20.52

854

Wind

7149

1348

921

1629

00:00

24.74

1031

Others

806

54

54

54

19:00

28.74

1197

Total TN

17931

8084

6880

--

--

185.22

7716

Page 2 of 16

STATION

INSTALLED
CAPACITY(MW)

19:00HRS
PEAK MW

03:00HRS
OFF-PEAK MW

Ramagundam,NTPC

2600

2226

Neyveli TPS II

1470

840

Neyveli TPS I (EXP)

420

Madras APS

DAY PEAK

DAY ENERGY
(MU)

AVG MW

20:36

52.58

2191

10:53

20.77

865

398

18:46

9.16

382

145

152

19:06

3.27

136

372

363

374

00:15

9.36

390

440

387

388

393

00:07

9.43

393

Neyveli TPS II (EXP)

--

--

--

--

--

--

--

Talcher II, NTPC

2000

1713

1920

1920

00:00

44.84

1868

Simhadri II, NTPC

1000

482

475

499

13:56

11.30

471

Total ISGS

8810

6560

6553

--

--

160.71

6696

Vallur

1000

--

--

--

--

--

--

Total JV

1000

--

--

--

--

--

--

MW

HRS

2108

2265

831

901

391

323

440

149

Kaiga STGI

440

Kaiga Unit 3 & 4

CENTRAL SECTOR (ISGS)

JOINT VENTURE

IPP UNDER OPEN ACCESS


LKPPL

366

--

--

10:12

--

--

SIMHAPURI

300

128

131

133

06:55

3.12

130

MEENAKSHI

300

221

214

225

18:48

5.15

215

Total IPP

966

349

345

--

--

8.27

345

Total State Thermal

15633

11314

10562

--

--

266.81

11118

Total ISGS Thermal

7490

5652

5657

--

--

138.65

5777

Total Thermal

23123

16966

16219

--

--

405.46

16895

Total Hydro

12524

7153

2734

--

--

117.57

4901

*Total Gas/Naptha/Diesel

8609

3630

3095

--

--

53.47

2227

Total Nuclear

1320

908

896

--

--

22.06

919

Total Wind

9777

2017

1601

--

--

36.33

1514
2523

Total Others

2588

409

380

--

--

60.56

Inter-regional (Except Talcher II)

--

1310

1355

--

--

37.77

1574

Grand Total

57941

32393

26280

--

--

724.73

30197

* Total Gas/ naptha/Diesel includes pondy Karaikal Power Plant of 32.5 MW

4 A. INTER-REGIONAL EXCHANGES & HVDC - PHYSICAL FLOWS [IMPORT(+)/EXPORT(-)]


MAX INTER-CHANGE (MW)

ELEMENT

19:00 HRS PEAK


MW

03:00 HRS OFFPEAK MW

IMPORT

TIME

EXPORT

TIME

Bhadrawati B2B

840

840

980

1915

--

--

21.228

Gazuwaka B2B

513

598

612

0600

--

--

12.550

Talcher-Kolar

1670

1837

2150

0500

--

--

46.781

Talcher Stage II I/C

-43

-83

--

--

--

--

1.938

ENERGY (MU)

4 B. INTER-REGIONAL EXCHANGES - SCHEDULES, WHEELING, UI & TALCHER AC I/C


ISGS Schedule
Talcher
Stage II
to SR

Bilaterals of SR
constituents

Power Exchange

Wheeling through
SR

Through Through Through ER to SR


ER ISGS Through
ER
WR
ER
WR

40.482

0.894

8.255

0.000

6.872

0.000

0.000

Diversion of SR
power

WR to
SR

IR Schedule

Through Through ER to SR
ER
WR

0.000

0.000

0.000

13.971

Net UI

Inter-Regional

WR to
SR

ER to SR

WR to
SR

Schedule
(Total)

Flow
(Total)

21.430

0.517

-0.202

35.402

35.717

5. FREQUENCY PROFILE
% OF TIME
RANGE

<48.8 Hz

<49.0 Hz

<49.2 Hz

<49.5 Hz

<49.7 Hz

<49.8 Hz

49.7 To 50.2Hz

>50 Hz

>50.2 Hz

0.0

0.0

0.0

0.0

3.4

20.1

92.8

31.5

3.8

Instantenous Maximum

Instantenous Minimum

Block Maximum

Block Minimum

Day Avg

Hz

TIME

Hz

TIME

Hz

TIME

Hz

TIME

Hz

Frequency
Variation
Index

50.47

4:04

49.57

21:17

50.31

4:15

49.71

6:45

49.93

0.25

Std. Var.
0.14

Page 3 of 16

6. SHORT TERM OPEN ACCESS TRANSACTION


WHEELING
NAME OF THE TRANSACTION

BILATERAL
ER END

WR END

NAME OF THE TRANSACTION

MU

PEAK
(MW)

OFF-PEAK
(MW)

APTRANSCO TOTAL EXPORT

0.000

EMCO-APPCC(EMCO)(11.19MW)(ER-SR)

0.183

11.190

11.190

STERENERGY-APCPDCL(KISPL)(5.93MW)(ER-SR)

0.097

5.930

5.930

STERENERGY-APCPDCL(PTC)(22.39MW)(ER-SR)

0.365

22.390

22.390

STERENERGY-APCPDCL(PTC)(22.39MW)(ER-SR)

0.365

22.390

22.390

STERENERGY-APPCC(SCL)(11.19MW)(ER-SR)

0.183

11.190

11.190

JSWRGIRI-APCPDCL(JSWPTC)(22.39MW)(ER-SR)

0.365

22.390

22.390

SIKKIM-APPCC(MITTAL)(5.59MW)(ER-SR)

0.091

5.590

5.590

JINDALPOW-APCPDCL(JPL)(28MW)(ER-SR)

0.256

28.000

28.000

JINDALPOW-APCPDCL(JPL)(28MW)(ER-SR)

0.256

28.000

28.000

SIL-APCPDCL(PTC)(30MW)(SR-SR)

0.720

30.000

30.000

SIMHAPURI-APCPDCL(PTC)(85MW)(SR-SR)

2.040

85.000

85.000

SIMHAPURI-APCPDCL(PTC)(43MW)(SR-SR)

1.032

43.000

43.000

JSWEL-APCPDCL(JSWPTC)(300MW)(SR-SR)

7.200

300.000

300.000

MEENAKSHI-APCPDCL(PTC)(100MW)(SR-SR)

2.400

100.000

100.000

MEENAKSHI-APCPDCL(PTC)(140MW)(SR-SR)

3.360

140.000

140.000

JSWEL-APCPDCL(JSWPTC)(127.61MW)(SR-SR)

3.063

127.610

127.610

JSWEL-APCPDCL(JSWPTC)(13.03MW)(SR-SR)

0.172

13.030

13.030

APTRANSCO TOTAL IMPORT

22.148

SIL-APCPDCL(PTC)(30MW)(SR-SR)

0.720

30.000

30.000

JSWEL-APCPDCL(JSWPTC)(300MW)(SR-SR)

7.200

300.000

300.000

JSWEL-APCPDCL(JSWPTC)(127.61MW)(SR-SR)

3.063

127.610

127.610

JSWEL-APCPDCL(JSWPTC)(13.03MW)(SR-SR)

0.172

13.030

13.030

KPTCL TOTAL EXPORT

11.155

SRPOWERMP-BESCOM(ESSARPOWER)(23.51MW)(ER-SR)

0.384

23.510

23.510

GUVNL-BESCOM(GUVNL)(76.68MW)(ER-SR)

1.251

76.680

76.680

VIDARBHIPL-BESCOM(RETL)(14.72MW)(ER-SR)

0.240

14.720

14.720

KPTCL TOTAL IMPORT

1.875

KSEB TOTAL EXPORT

0.000

SHRECEMTPS-KSEB(SCL)(11.19MW)(ER-SR)

0.183

11.190

11.190

GRIDCO-KSEB(PTC)(22.1MW)(ER-SR)

0.361

22.100

22.100

GRIDCO-KSEB(PTC)(43MW)(ER-SR)

0.133

43.000

18.000

KSEB TOTAL IMPORT

0.677

TNEB TOTAL EXPORT

0.000

PRAKASHIND-TANGEDCO(INSTINCT)(6.77MW)(ER-SR)

0.110

6.770

6.770

JINDALPOW-TANGEDCO(INSTINCT)(4.7MW)(ER-SR)

0.060

4.700

4.700

SHRECEMTPS-TANGEDCO(SCL)(13.99MW)(ER-SR)

0.228

13.990

13.990

GRIDCO-TANGEDCO(NVVN)(22.39MW)(ER-SR)

0.365

22.390

22.390

STERENERGY-TANGEDCO(STERLITE)(22.61MW)(ER-SR)

0.369

22.610

22.610

WBSEDCL-TANGEDCO(NVVN)(11.19MW)(ER-SR)

0.183

11.190

11.190

TRIPURA-TANGEDCO(NVVN)(5.59MW)(ER-SR)

0.091

5.590

5.590

STERENERGY-TANGEDCO(NVVN)(11.19MW)(ER-SR)

0.183

11.190

11.190

WBSEDCL-TANGEDCO(NVVN)(5.59MW)(ER-SR)

0.091

5.590

5.590

WBSEDCL-TANGEDCO(NVVN)(5.04MW)(ER-SR)

0.082

5.040

5.040

JINDALPOW-TANGEDCO(INSTINCT)(3.67MW)(ER-SR)

0.047

3.670

3.670

JINDALPOW-TANGEDCO(JPL)(44.78MW)(ER-SR)

0.416

44.780

44.780

GRIDCO-TANGEDCO(NVVN)(93MW)(ER-SR)

1.317

93.000

93.000

TNEB TOTAL IMPORT

3.542

GOA TOTAL EXPORT

0.000

GOA TOTAL IMPORT

0.000

LKPPL TOTAL EXPORT

0.000

Page 4 of 16

7. VOLTAGE LEVEL AT CRITICAL SUB STATION


% OF TIME
SUBSTATION

400 KV

<380 KV

<390 KV

>420 KV

>430 KV

HYDERABAD

0.00

0.00

22.15

GOOTY

0.00

0.00

VIJAYWADA

0.00

KOLAR

MAXIMUM

220 KV / 230 KV
MINIMUM

MAXIMUM

MINIMUM

KV

TIME

KV

TIME

KV

TIME

KV

TIME

0.00

425

0100

409

1200

231

0400

219

1900

40.14

7.08

432

0400

412

1900

244

0400

233

1900

0.00

96.04

8.54

431

0400

419

1900

234

0400

213

1900

0.00

0.00

1.67

0.00

423

0400

398

0700

225

0100

207

1000

BANGALORE

0.00

16.53

0.00

0.00

418

0400

388

1000

218

1800

205

0900

HIRIYUR

0.00

0.00

33.47

0.00

426

0400

409

0900

235

0000

220

0900

CHENNAI

0.00

0.00

0.35

0.00

419

0400

394

1000

230

0000

216

1600

TRICHY

0.00

0.00

0.00

0.00

413

0400

397

1200

231

0100

222

1900

TRIVENDRAM

0.00

0.00

0.00

0.00

426

0100

402

1100

226

0100

218

1100

KAIGA

0.00

0.00

0.35

0.00

421

0200

411

0900

233

0100

228

0900

8. MAJOR RESERVOIR PARTICULARS


DESIGNED
RESERVOIR

MDDL
(Mts)

FRL (Mts)

PRESENT

LAST YEAR

LAST DAY

MONTH

Energy
(MU)

Level (Mts)

Energy
(MU)

Level (Mts)

Energy
(MU)

Inflow
(Mus)

Usage
(Mus)

Prog. Inflow
(Mus)

Prog. Usage
(Mus)

JALAPUT

818.39

838.40

534

836.52

454

834.69

380

1.90

1.90

15.74

9.53

SRISAILAM

243.84

270.70

1392

268.71

922

258.29

0.00

6.96

0.00

47.51

N.SAGAR

149.30

179.90

1398

179.19

959

155.57

0.00

10.16

0.00

47.31

LINGANAMAKKI

522.73

554.50

4557

554.42

4552

550.59

3387

14.99

14.68

72.73

69.25

SUPA

495.00

564.00

3159

560.43

2834

546.35

1736

2.43

1.86

17.54

18.29

IDUKKI

694.94

732.43

2148

730.32

2014

709.61

631

10.31

9.07

60.58

49.66

KAKKI

908.30

981.45

916

980.11

849

959.96

355

5.54

5.52

23.30

26.80

NILAGIRIS

--

--

1504

--

1366

--

683

6.95

2.20

41.94

11.92

TOTAL

--

--

15608

--

13950

--

7172

42.12

52.35

231.83

280.27

Note: The Reservoirs data are of previous day and Cumulative figures for the month is upto previous day

9. DETAILS OF OVER DRAWAL WHEN EXCESS OF 3% OF SCHEDULE OVER A DAY WHEN FREQUENCY < 49.8 HZ
CONSTITUENTS

AP

KARNATAKA

KERALA

TAMILNADU

PONDY

AVERAGE MW ( F<49.8)

0.00

0.00

0.00

66.38

0.00

OD MU'S ( F<49.8)

0.00

0.00

0.00

0.18

0.00

OD NO OF BLOCK( F<49.8)

11

GENERATOR

NLCII

NLCEXPI

RSTP

SEPL

LANCO

MEPL

AVERAGE MW ( F<49.8)

0.00

0.00

0.00

0.00

0.00

0.00

Under Injection MU'S ( F<49.8)

0.00

0.00

0.00

0.00

0.00

0.00

Under Injection NO OF BLOCK( F<49.8)

Note: Over drawal/Under Injection computed above for the day is the average MW value of all the time blocks during which the BENEFICIARY/BUYER was over drawing at freq. below 49.8Hz AND the total
over drawal/Under Injection of the day while freq.was below 49.8Hz was exceeding 3% of the respective schedule.

10. SIGNIFICANT EVENTS (IF ANY) :


11. SYSTEM CONSTRAINTS (IF ANY) :
12. WEATHER CONDITIONS:

Page 5 of 16