IMPORTANT NOTES:

1- Dawn sand piping not important in case of cutting and filling on


backfilling for preparation of level layer.
2- Photos
3- Checking in 3 areas middle, right and lift in any layer.
4- Daily Program from Contractor important.
5- Inspection Request from Contractor.
6- Concrete Program should be before one day before active.

Concrete Active Notes:


1- On White paper : (Max design ) write
*Temp. : (Degree)

* Site: (No.)

*Slump : (result )

* Active: (type of active)

* Cubes No.:
2- On Yellow Paper

Inspector Sign

Site Engineer Sign

3- On Cubes: write

Site No.

Data

Concrete strength/AGG size ( for example : 25/20)

Max Desig

:
-1 :
:
- - )\(-
)\(.