You are on page 1of 5

Annual Testing of 132KV J.P.

H-1 E14Q1
Report Time: 4/22/2013 11:00:31 AM

Zone Verification
Test objects

Test Time:2013-04-22 10:59:06

Test Object: Line Protection (Zone Verification)


Line: 132KV J.P.H-1 E14Q1
Tested by: Adeel Zafar, A.M(P&I)
Device name: 7SA522
Device type: Distance
Serial/model:

Substation: 220KV Grid Station, Wapda Town


Lahore
Test Item: Zone Verification
Manufacturer: Siemens
Device address:
note:

Setting
Set fixed value: Zone 1(A)=4 , Zone 2(A)=2
Zone 3(A)=2 , Zone 4(A)=2 , Zone 5(A)=2
Prefault: 1 ; Postfault: 0.5
Health voltage after fault: No
.
Select fault: A-E, B-E, C-E, A-B, B-C, C-A, A-B-C,

Test mode: Auto


Earth Compensation
Mode: KL , KL: 0.65 , Angle: -5
Close angle: 0
CT Direction : Object
Zone 1:
Test points: 0.95, 1.05, 0.5,
Z Setting(L-L): R=1.065 , X=0.432
.
Binary input setting:
Bin 1
Trigger Logic : or

Z Setting(L-N): R=2.57 , X=0.435


Time Setting(s): 0
.
.
Input name: Trip1

Test results
Trip time(s)

Fault Type

Z Setting(ohm)

Fixed Val

Judge

0.0335

A-E

Zone 1: 2.607

95

4A

Passed

0.033

A-E

Zone 1: 2.607

105

4A

Failure

0.0165

A-E

Zone 1: 2.607

50

4A

Passed

0.033

B-E

Zone 1: 2.607

95

4A

Passed

0.0335

B-E

Zone 1: 2.607

105

4A

Failure

0.016

B-E

Zone 1: 2.607

50

4A

Passed

0.0335

C-E

Zone 1: 2.607

95

4A

Passed

0.033

C-E

Zone 1: 2.607

105

4A

Failure

0.0165

C-E

Zone 1: 2.607

50

4A

Passed
1 / 2

Page

Annual Testing of 132KV J.P.H-1 E14Q1


Report Time: 4/22/2013 11:00:31 AM

0.0335

A-B

Zone 1: 1.149

95

4A

Passed

No Trip

A-B

Zone 1: 1.149

105

4A

Passed

0.0165

A-B

Zone 1: 1.149

50

4A

Passed

0.033

B-C

Zone 1: 1.149

95

4A

Passed

No Trip

B-C

Zone 1: 1.149

105

4A

Passed

0.016

B-C

Zone 1: 1.149

50

4A

Passed

0.0335

C-A

Zone 1: 1.149

95

4A

Passed

No Trip

C-A

Zone 1: 1.149

105

4A

Passed

0.017

C-A

Zone 1: 1.149

50

4A

Passed

0.0435

A-B-C

Zone 1: 1.149

95

4A

Passed

No Trip

A-B-C

Zone 1: 1.149

105

4A

Passed

0.0335

A-B-C

Zone 1: 1.149

50

4A

Passed

2 / 2

Page

Annual Testing of 132KV J.P.H-1 E14Q1


Report Time: 4/22/2013 11:07:47 AM

Zone Verification
Test objects

Test Time:2013-04-22 11:04:40

Test Object: Line Protection (Zone Verification)


Line: 132KV J.P.H-1 E14Q1
Tested by: Adeel Zafar, A.M(P&I)
Device name: 7SA522
Device type: Distance
Serial/model:

Substation: 220KV Grid Station, Wapda Town


Lahore
Test Item: Zone Verification
Manufacturer: Siemens
Device address:
note:

Setting
Set fixed value: Zone 1(A)=4 , Zone 2(A)=2
Zone 3(A)=2 , Zone 4(A)=2 , Zone 5(A)=2
Prefault: 1 ; Postfault: 0.5
Health voltage after fault: No
.
Select fault: A-E, B-E, C-E, A-B, B-C, C-A, A-B-C,

Test mode: Auto


Earth Compensation
Mode: KL , KL: 0.65 , Angle: -5
Close angle: 0
CT Direction : Object
Zone 2:
Test points: 0.95, 1.05, 0.9,
Z Setting(L-L): R=1.091 , X=0.612
Zone 3:
Test points: 0.95, 1.05, 0.9,
Z Setting(L-L): R=1.162 , X=1.021
.
Binary input setting:
Bin 1
Trigger Logic : or

Z Setting(L-N): R=2.594 , X=0.613


Time Setting(s): 0.35
Select fault: A-E, B-E, C-E, A-B, B-C, C-A, A-B-C,
Z Setting(L-N): R=2.656 , X=1.02
Time Setting(s): 0.7
.
.
Input name: Trip1

Test results
Trip time(s)

Fault Type

Z Setting(ohm)

Fixed Val

Judge

0.368

A-E

Zone 2: 2.665

95

2A

Passed

0.3695

A-E

Zone 2: 2.665

105

2A

Failure

0.369

A-E

Zone 2: 2.665

90

2A

Passed

0.373

B-E

Zone 2: 2.665

95

2A

Passed

0.369

B-E

Zone 2: 2.665

105

2A

Failure

0.3735

B-E

Zone 2: 2.665

90

2A

Passed

0.37

C-E

Zone 2: 2.665

95

2A

Passed
1 / 3

Page

Annual Testing of 132KV J.P.H-1 E14Q1


Report Time: 4/22/2013 11:07:47 AM

0.3695

C-E

Zone 2: 2.665

105

2A

Failure

0.37

C-E

Zone 2: 2.665

90

2A

Passed

0.373

A-B

Zone 2: 1.251

95

2A

Passed

No Trip

A-B

Zone 2: 1.251

105

2A

Passed

0.3735

A-B

Zone 2: 1.251

90

2A

Passed

0.3725

B-C

Zone 2: 1.251

95

2A

Passed

No Trip

B-C

Zone 2: 1.251

105

2A

Passed

0.373

B-C

Zone 2: 1.251

90

2A

Passed

0.3735

C-A

Zone 2: 1.251

95

2A

Passed

No Trip

C-A

Zone 2: 1.251

105

2A

Passed

0.3685

C-A

Zone 2: 1.251

90

2A

Passed

0.389

A-B-C

Zone 2: 1.251

95

2A

Passed

No Trip

A-B-C

Zone 2: 1.251

105

2A

Passed

0.383

A-B-C

Zone 2: 1.251

90

2A

Passed

0.7335

A-E

Zone 3: 2.845

95

2A

Passed

0.733

A-E

Zone 3: 2.845

105

2A

Failure

0.733

A-E

Zone 3: 2.845

90

2A

Passed

0.7335

B-E

Zone 3: 2.845

95

2A

Passed

0.733

B-E

Zone 3: 2.845

105

2A

Failure

0.7395

B-E

Zone 3: 2.845

90

2A

Passed

0.739

C-E

Zone 3: 2.845

95

2A

Passed

0.7395

C-E

Zone 3: 2.845

105

2A

Failure

0.733

C-E

Zone 3: 2.845

90

2A

Passed

0.733

A-B

Zone 3: 1.547

95

2A

Passed

No Trip

A-B

Zone 3: 1.547

105

2A

Passed

0.733

A-B

Zone 3: 1.547

90

2A

Passed

0.7335

B-C

Zone 3: 1.547

95

2A

Passed

No Trip

B-C

Zone 3: 1.547

105

2A

Passed
2 / 3

Page

Annual Testing of 132KV J.P.H-1 E14Q1


Report Time: 4/22/2013 11:07:47 AM

0.7335

B-C

Zone 3: 1.547

90

2A

Passed

0.733

C-A

Zone 3: 1.547

95

2A

Passed

No Trip

C-A

Zone 3: 1.547

105

2A

Passed

0.733

C-A

Zone 3: 1.547

90

2A

Passed

0.739

A-B-C

Zone 3: 1.547

95

2A

Passed

No Trip

A-B-C

Zone 3: 1.547

105

2A

Passed

0.732

A-B-C

Zone 3: 1.547

90

2A

Passed

3 / 3

Page