You are on page 1of 6

6

CURVA S - AVANCE FISICO (RELLENO - SECTORES 3)


CONDOMINIO CABO MERLIN - ZORRITOS
MOVIMIENTO DE TIERRAS
Periodo del 02 de Diciembre de 2,013 al 25 de Enero de 2,014

CURVA S DE AVANCE
Semana 1
DESCRIPCION DE LAS PARTIDAS

### BATIDO DE MATERIAL CON AGUA

CANTCONTRACT.

MONTOS ($)

PESO

% AVANCE
% AVANCE
PROGRAMADO
REAL

VARIACIN

### TRANSPORTE DE MATERIAL HASTA 1KM

EXTENDIDO Y COMPACTACION DE MATERIAL EN


CAPAS DE 0.30

Semana 5

Semana 6

Semana 7

Semana 8

23-Dec

30-Dec

6-Jan

13-Jan

20-Jan

22-Dec

29-Dec

5-Jan

12-Jan

19-Jan

26-Jan

100.00%

CURVA S

31,400.00

77,872.00

12.10%

12.50%

12.27%

-0.23%

Programado
Real

12.50%

27.50%

42.50%

55.00%

67.50%

82.50%

97.50%

2.24%

9.08%

12.27%

12.27%

12.27%

12.27%

12.27%

12.27%

31,400.00

125,286.00

19.46%

9.30%

12.27%

2.97%

Programado

9.30%

23.26%

37.21%

48.84%

60.47%

74.42%

88.37%

100.00%

Real

2.24%

9.08%

12.27%

12.27%

12.27%

12.27%

12.27%

12.27%

23.26%

37.21%

48.84%

60.47%

74.42%

88.37%

100.00%

m3

31,400.00

30,772.00

4.78%

9.30%

12.27%

2.97%

Programado

9.30%

Real

2.24%

9.08%

12.27%

12.27%

12.27%

12.27%

12.27%

12.27%

m3

31,400.00

97,968.00

15.22%

9.30%

12.27%

2.97%

Programado

9.30%

23.26%

37.21%

48.84%

60.47%

74.42%

88.37%

100.00%

Real

2.24%

9.08%

12.27%

12.27%

12.27%

12.27%

12.27%

12.27%

m3

31,400.00

311,802.00

48.44%

9.30%

12.27%

2.97%

Programado

9.30%

23.26%

37.21%

48.84%

60.47%

74.42%

88.37%

100.00%

Real

2.24%

9.08%

12.27%

12.27%

12.27%

12.27%

12.27%

12.27%

41630

41 637

41644

41651

41 658

41665

100.0%

41 623

643,700.00

AVANCE PROGRAMADO ACUMULADO :

Semana 4

16-Dec

15-Dec

41616

COSTO DIRECTO

Semana 3

9-Dec

8-Dec

m3

0.0 0%

###

Semana 2

2-Dec

m3

### CARGUIO DE MATERIAL

% 60 .00% 40 .00% 20 .00%


100.0 0% 80 .00

### BATIDO DE MATERIAL PROPIO + HORMIGON

UND

41610
Sem ana 1

41617
Semana 2

41624
Sem ana 3

41631
Sem ana 4

41638
Semana 5

41645
Sem ana 6

41652
Semana 7

41659
Sem ana 8

9.69%

23.77%

37.85%

49.58%

61.32%

75.40%

89.48%

100.00%

AVANCE PROGRAMADO SEMANAL :

9.69%

14.08%

14.08%

11.73%

11.73%

14.08%

14.08%

10.52%

AVANCE ACTUAL ACUMULADO :

2.24%

9.08%

12.27%

12.27%

12.27%

12.27%

12.27%

12.27%

AVANCE ACTUAL SEMANAL :

2.24%

6.84%

3.19%

0.00%

0.00%

0.00%

0.00%

0.00%

MARGEN :

-7.45%

-14.69%

-25.58%

-37.31%

-49.05%

-63.13%

-77.21%

-87.73%

Propietario
Obra
Sub Proyecto
Ejecuta
Plazo

:
:
:
:
:

MANTTO DEVELOPMENT SAC


CONDOMINIO CABO MERLIN - ZORRITOS
MOVIMIENTO DE TIERRAS - SECTORES 1 Y 2
MANTTO SAC
45 DIAS

PROGRAMACIN SEMANALES DE PRODUCCIN

Semana
Semana
Semana
Semana
Semana
Semana
Semana
Semana

Semana
Semana
Semana
Semana
Semana
Semana
Semana
Semana

1
2
3
4
5
6
7
8

1
2
3
4
5
6
7
8

BATIDO DE MATERIAL PROPIO + HORMIGON


FECHAS
Volumen
Volumen
Avance
Avance
Inicio
Fin
Programado Acumulado Programado Acumulado
12/2/2013 12/8/2013
3,925.00
3,925.00
12.50%
12.50%
12/9/2013 12/15/2013 4,710.00
8,635.00
15.00%
27.50%
12/16/2013 12/22/2013 4,710.00
13,345.00
15.00%
42.50%
12/23/2013 12/29/2013 3,925.00
17,270.00
12.50%
55.00%
12/30/2013 1/5/2014
3,925.00
21,195.00
12.50%
67.50%
1/6/2014
1/12/2014
4,710.00
25,905.00
15.00%
82.50%
1/13/2014 1/19/2014
4,710.00
30,615.00
15.00%
97.50%
1/20/2014 1/26/2014
785.00
31,400.00
2.50%
100.00%
M3 31,400.00
100.00%
785
TRANSPORTE DE MATERIAL HASTA 1KM
FECHAS
Volumen
Volumen
Avance
Avance
Inicio
Fin
Programado Acumulado Programado Acumulado
12/2/2013 12/8/2013
2,920.93
2,920.93
9.30%
9.30%
12/9/2013 12/15/2013 4,381.40
7,302.33
13.95%
23.26%
12/16/2013 12/22/2013 4,381.40
11,683.72
13.95%
37.21%
12/23/2013 12/29/2013 3,651.16
15,334.88
11.63%
48.84%
12/30/2013 1/5/2014
3,651.16
18,986.05
11.63%
60.47%
1/6/2014
1/12/2014
4,381.40
23,367.44
13.95%
74.42%
1/13/2014 1/19/2014
4,381.40
27,748.84
13.95%
88.37%
1/20/2014 1/26/2014
3,651.16
31,400.00
11.63%
100.00%
M3 31,400.00
100.00%

Semana
Semana
Semana
Semana
Semana
Semana
Semana
Semana

Semana
Semana
Semana
Semana
Semana
Semana
Semana
Semana

1
2
3
4
5
6
7
8

1
2
3
4
5
6
7
8

BATIDO DE MATERIAL CON AGUA


FECHAS
Volumen
Volumen
Avance
Avance
Inicio
Fin
Programado Acumulado Programado Acumulado
12/2/2013
12/8/2013
2,920.93
2,920.93
9.30%
9.30%
12/9/2013
12/15/2013
4,381.40
7,302.33
13.95%
23.26%
12/16/2013
12/22/2013
4,381.40
11,683.72
13.95%
37.21%
12/23/2013
12/29/2013
3,651.16
15,334.88
11.63%
48.84%
12/30/2013
1/5/2014
3,651.16
18,986.05
11.63%
60.47%
1/6/2014
1/12/2014
4,381.40
23,367.44
13.95%
74.42%
1/13/2014
1/19/2014
4,381.40
27,748.84
13.95%
88.37%
1/20/2014
1/26/2014
3,651.16
31,400.00
11.63%
100.00%
M3 31,400.00
100.00%

EXTENDIDO Y COMPACTACION DE MATERIAL EN CAPAS DE 0.30


FECHAS
Volumen
Volumen
Avance
Avance
Inicio
Fin
Programado Acumulado Programado Acumulado
12/2/2013
12/8/2013
2,920.93
2,920.93
9.30%
9.30%
12/9/2013
12/15/2013
4,381.40
7,302.33
13.95%
23.26%
12/16/2013
12/22/2013
4,381.40
11,683.72
13.95%
37.21%
12/23/2013
12/29/2013
3,651.16
15,334.88
11.63%
48.84%
12/30/2013
1/5/2014
3,651.16
18,986.05
11.63%
60.47%
1/6/2014
1/12/2014
4,381.40
23,367.44
13.95%
74.42%
1/13/2014
1/19/2014
4,381.40
27,748.84
13.95%
88.37%
1/20/2014
1/26/2014
3,651.16
31,400.00
11.63%
100.00%
M3 31,400.00
100.00%

Semana
Semana
Semana
Semana
Semana
Semana
Semana
Semana

1
2
3
4
5
6
7
8

CARGUIO DE MATERIAL
FECHAS
Volumen
Volumen
Avance
Avance
Inicio
Fin
Programado Acumulado Programado Acumulado
12/2/2013 12/8/2013
2,920.93
2,920.93
9.30%
9.30%
12/9/2013 12/15/2013 4,381.40
7,302.33
13.95%
23.26%
12/16/2013 12/22/2013 4,381.40
11,683.72
13.95%
37.21%
12/23/2013 12/29/2013 3,651.16
15,334.88
11.63%
48.84%
12/30/2013 1/5/2014
3,651.16
18,986.05
11.63%
60.47%
1/6/2014
1/12/2014
4,381.40
23,367.44
13.95%
74.42%
1/13/2014 1/19/2014
4,381.40
27,748.84
13.95%
88.37%
1/20/2014 1/26/2014
3,651.16
31,400.00
11.63%
100.00%
M3 31,400.00
100.00%

TOTAL
Cristhiam +
Sarmiento:
MATERIAL PROPIO
HORMIGON
Ingresar metrados
Volumen ejecutados
Ejecutado
Avance
semanales

Semana
Semana
Semana
Semana
Semana
Semana
Semana
Semana

Semana
Semana
Semana
Semana
Semana
Semana
Semana
Semana

1
2
3
4
5
6
7
8

1
2
3
4
5
6
7
8

BATIDO DE
FECHAS
Inicio
Fin
Ejecutado Acumulado
12/2/2013
12/8/2013
704.40
704.40
12/9/2013
12/15/2013
2,146.94
2,851.34
12/16/2013
12/22/2013
1,001.10
3,852.44
12/23/2013
12/29/2013
3,852.44
12/30/2013
1/5/2014
3,852.44
1/6/2014
1/12/2014
3,852.44
1/13/2014
1/19/2014
3,852.44
1/20/2014
1/26/2014
3,852.44
M3 3,852.44

Real
2.24%
6.84%
3.19%
0.00%
0.00%
0.00%
0.00%
0.00%
12.27%

TOTAL
TRANSPORTE DE MATERIAL
HASTA 1KM
Cristhiam Sarmiento:
FECHAS
Volumen Ingresar
Ejecutado
metrados Avance
ejecutados semanales
Inicio
Fin
Ejecutado Acumulado
Real
12/2/2013
12/8/2013
704.40
704.40
2.24%
12/9/2013
12/15/2013
2,146.94
2,851.34
6.84%
12/16/2013
12/22/2013
1,001.10
3,852.44
3.19%
12/23/2013
12/29/2013
3,852.44
0.00%
12/30/2013
1/5/2014
3,852.44
0.00%
1/6/2014
1/12/2014
3,852.44
0.00%
1/13/2014
1/19/2014
3,852.44
0.00%
1/20/2014
1/26/2014
3,852.44
0.00%
M3 3,852.44
12.27%

METRADOS EJECUTADOS SEMANALES


31,400.00

MIGON
Avance
Acumulado
2.24%
9.08%
12.27%
12.27%
12.27%
12.27%
12.27%
12.27%

Semana
Semana
Semana
Semana
Semana
Semana
Semana
Semana

1
2
3
4
5
6
7
8

31,400.00
1KM
Avance
Acumulado
2.24%
9.08%
12.27%
12.27%
12.27%
12.27%
12.27%
12.27%

Semana
Semana
Semana
Semana
Semana
Semana
Semana
Semana

1
2
3
4
5
6
7
8

TOTAL
BATIDO DE MATERIAL CON AGUA Cristhiam Sarmie
Ingresar metrados
FECHAS
Volumen
Ejecutado
ejecutados seman
Inicio
Fin
Ejecutado
Acumulado
12/2/2013
12/8/2013
704.40
704.40
12/9/2013
12/15/2013
2,146.94
2,851.34
12/16/2013
12/22/2013
1,001.10
3,852.44
12/23/2013
12/29/2013
3,852.44
12/30/2013
1/5/2014
3,852.44
1/6/2014
1/12/2014
3,852.44
1/13/2014
1/19/2014
3,852.44
1/20/2014
1/26/2014
3,852.44
M3 3,852.44

TOTAL
EXTENDIDO Y COMPACTACION DE MATERIAL EN CAPASCristhiam
DE 0.3
FECHAS
Volumen
Ejecutado
Ingresar m
ejecutados
Inicio
Fin
Ejecutado
Acumulado
12/2/2013
12/8/2013
704.40
704.40
12/9/2013
12/15/2013
2,146.94
2,851.34
12/16/2013
12/22/2013
1,001.10
3,852.44
12/23/2013
12/29/2013
3,852.44
12/30/2013
1/5/2014
3,852.44
1/6/2014
1/12/2014
3,852.44
1/13/2014
1/19/2014
3,852.44
1/20/2014
1/26/2014
3,852.44
M3 3,852.44

MANALES

L CON

31,400.00
AGUA Cristhiam Sarmiento:
Ingresar metrados
Avance
Avance
ejecutados semanales
Programado
2.24%
6.84%
3.19%
0.00%
0.00%
0.00%
0.00%
0.00%
12.27%

Acumulado
2.24%
9.08%
12.27%
12.27%
12.27%
12.27%
12.27%
12.27%

31,400.00
MATERIAL EN CAPASCristhiam
DE 0.30Sarmiento:
AvanceIngresar metrados
Avance
ejecutados semanales
Programado Acumulado
2.24%
2.24%
6.84%
9.08%
3.19%
12.27%
0.00%
12.27%
0.00%
12.27%
0.00%
12.27%
0.00%
12.27%
0.00%
12.27%
12.27%

Semana
Semana
Semana
Semana
Semana
Semana
Semana
Semana

1
2
3
4
5
6
7
8

CARGUIO DE MATERIAL
FECHAS
Volumen
Inicio
Fin
Ejecutado
12/2/2013
12/8/2013
704.40
12/9/2013
12/15/2013
2,146.94
12/16/2013 12/22/2013
1,001.10
12/23/2013 12/29/2013
12/30/2013
1/5/2014
1/6/2014
1/12/2014
1/13/2014
1/19/2014
1/20/2014
1/26/2014
M3 3,852.44

TOTAL
31,400.00
Cristhiam
Sarmiento:
RGUIO DE MATERIAL
Ingresar metrados
Ejecutado
Avance
Avance
ejecutados
semanales
Acumulado Programado Acumulado
704.40
2.24%
2.24%
2,851.34
6.84%
9.08%
3,852.44
3.19%
12.27%
3,852.44
0.00%
12.27%
3,852.44
0.00%
12.27%
3,852.44
0.00%
12.27%
3,852.44
0.00%
12.27%
3,852.44
0.00%
12.27%
12.27%

You might also like