You are on page 1of 2

BUILT-UP RATE FOR HARDCORE / DPM

TENDER FILE NO :

PROJECT :

LOCATION :

SUPPLIER :

SUB-CONTRACTOR :

QUOTATION DATE :

Hardcore Factor : 1.635


Crusher run 36.79 per m3 22.50 per ton.
Labour cost 2.00 per m2
Plant cost 0.50 per m2 (Inclusive)

Sand Blinding Factor : 1.595


Sand (ex-mining) 19.73 per m3 15.00 per cu. yard
Labour cost 2.00 per m2
Plant cost - per m2 (Inclusive)

Damp Proof Membrane


Gauge 200 polythene sheet 0.11 per ft2 (12' x 100' @ 135.00 per roll)
Labour cost 0.05 per ft2

Cost/m2
Harcore 100mm 125mm 150mm 175mm 200mm

Material cost / m2 3.68 4.60 5.52 6.44 7.36


Compaction & Wastage @ 35% 1.29 1.61 1.93 2.25 2.58
4.97 6.21 7.45 8.69 9.93
Labour cost 2.00 2.00 2.00 2.00 21.53
Plant cost 0.50 0.50 0.50 0.50 5.38
Tender Cost / m2 7.47 8.71 9.95 11.19 36.84
Cost/m3 : 74.66 69.66 66.33 63.95 184.21

Cost/m2
Sand Blinding 50mm 100mm 125mm 150mm 175mm

Material cost / m2 0.99 1.97 2.47 2.96 3.45


Compaction & Wastage @ 39% 0.35 0.69 0.86 1.04 1.21
1.33 2.66 3.33 3.99 4.66
Labour cost 2.00 2.00 2.00 2.00 2.00
Plant cost - - - - -
Tender Cost / m2 3.33 4.66 5.33 5.99 6.66
Cost/m3 : 66.63 46.63 42.63 39.96 38.06

Damp Proof Membrane Cost/m2


Material cost / m2 1.21
Laps & Wastage @ 15% 0.18
1.39
Labour cost 0.54
Tender Cost / m2 1.93