FIRE PREVENTION DEPARTMENT GENERAL DIRECTORATE OF CIVIL DEFENCE MINISTRY OF THE INTERIOR, STATE OF QATAR

GUIDELINES FOR MECHANICAL VENTILATION PLAN SUBMISSIONS


This document provides the minimum information required in the submission of applications for ACMV plan approvals. Accomplish this form correctly by checking the applicable provision/s for each item. This document shall form part of the attachments of the plan/drawings to be submitted for QCDD review/approval. Note: Non-inclusion of this form could mean rejection of plan submission. Item 1.0 1.1 1.2 GENERAL Plan Submission and Contents Drawings in ACAD file format, completely done, bonded, prepared with corresponding model space and paper space layouts Drawing page contains complete information such as the following: a) The complete name/title of the project b) Name of the Owner of the project c) Location of the project d) Name of the consulting firm, its logo/stamp e) Name of the consulting firms designated responsible Consultant f) Consultant endorsement stating among others specific laws, codes and standards governing the design of the project as well as the practice of engineering in Qatar; Consultants acknowledgement of his responsibilities being the person in-charge of the design of the project, Consultant discipline and UPDA license, etc. g) Scale of all drawings h) History/revisions of the plan i) Drawing title, sheet no. j) Space for QCDD signature/stamp Drawing cover page in accordance to QCDD recommended format. Information on drawing cover page:
MV-01-2013

MV-01-2013

PS-_____-MV

DESCRIPTION

Provisions Y N NA

1.3

General Notes Lists of the Codes, Standards and other references used in the design Legends and symbols Summary of the Design Criteria and Objectives for each type of smoke control system provided in the building Event matrix Schedule of equipment (where the same can be accommodated in the same page; otherwise provide on a separate page) Summary of other assumptions and design considerations List of other fire protection systems provided in the building
Page 1

FIRE PREVENTION DEPARTMENT GENERAL DIRECTORATE OF CIVIL DEFENCE MINISTRY OF THE INTERIOR, STATE OF QATAR

GUIDELINES FOR MECHANICAL VENTILATION PLAN SUBMISSIONS


This document provides the minimum information required in the submission of applications for ACMV plan approvals. Accomplish this form correctly by checking the applicable provision/s for each item. This document shall form part of the attachments of the plan/drawings to be submitted for QCDD review/approval. Note: Non-inclusion of this form could mean rejection of plan submission. Item 1.4 DESCRIPTION

MV-01-2013

PS-_____-MV

Provisions Y N NA

Associated documents such as design, calculation and analysis reports are attached in the submission 2.0 MINIMUM INFORMATION TO BE PROVIDED ON THE PLANS AND OTHER SUPPORTING DOCUMENTS 2.1 Background of the Project and Design 2.1.a Detailed Design Report a narrative report which provides the following: - Description of the building, uses and occupancies of each spaces, passive and active fire protection system that will work together with the smoke control system. - Design criteria and objectives. - Smoke control system rational analysis. - Type/s of smoke control system provided in the building: Passive smoke control system (fire or smoke barrier construction). Active smoke control systems. Smoke containment system; e.g. pressurization system Smoke management system; e.g. smoke-heat exhaust ventilation system. - Method of operation of each zone (how the system will be initiated in each zone and associated system responses. - Event matrix relating to the methods of operation of the systems in the building. - CFD analysis and other calculations associated with smoke control system. - Fire modeling and other performance based analysis where utilized in the design of smoke control system. - Design Fire: Anticipated fuel load, type of fuel/s, fuel characteristics, fire behavior. Design of heat release assumption. Analysis on sprinkler effectiveness, its effect to the fire and smoke. 2.1.b Drawings/layout showing the compartmentation procedures employed in the building; clear identification of the smoke zone boundaries and respective fire ratings. 2.1.c Drawings/layout of the specific smoke control systems components; e.g. equipment and ductworks.
MV-01-2013 Page 2

FIRE PREVENTION DEPARTMENT GENERAL DIRECTORATE OF CIVIL DEFENCE MINISTRY OF THE INTERIOR, STATE OF QATAR

GUIDELINES FOR MECHANICAL VENTILATION PLAN SUBMISSIONS


This document provides the minimum information required in the submission of applications for ACMV plan approvals. Accomplish this form correctly by checking the applicable provision/s for each item. This document shall form part of the attachments of the plan/drawings to be submitted for QCDD review/approval. Note: Non-inclusion of this form could mean rejection of plan submission. Item DESCRIPTION

MV-01-2013

PS-_____-MV

Provisions Y N NA

* N.B. Must be drawn on the approved architectural plan background. 2.1.d Schematic/riser diagrams showing connections and arrangement of each component of the system. The systems logic of operation must be provided with the schematic/riser diagram on the same drawing page. 2.1.e Matrix of events describing the specific initiating devices, its location, associated system response, etc. 2.1.f Schedule of equipment 2.2 2.2.a Fan capacities and ratings as per calculation report Fan components temperature and fire ratings Duct materials and joints thickness, temperature and fire ratings Type of dampers (fire, fire/smoke dampers), temperature and fire ratings

Technical Information Relevant information and details such as but not limited to the following are provided on the plan submission: Smoke Containment System (smokeproof enclosures, zoned smoke control, etc.) Method/s employed: Mechanical means Natural means Calculations: leakages, number of open doors, door opening forces, pressure differentials, air velocities, ACH, etc. Over-pressurization control provisions Fans and its rated capacities, temperature and fire ratings Stand-by fans (where required) Means/method of supplying pressurization air (single injection, multiple injection)
Page 3

MV-01-2013

FIRE PREVENTION DEPARTMENT GENERAL DIRECTORATE OF CIVIL DEFENCE MINISTRY OF THE INTERIOR, STATE OF QATAR

GUIDELINES FOR MECHANICAL VENTILATION PLAN SUBMISSIONS


This document provides the minimum information required in the submission of applications for ACMV plan approvals. Accomplish this form correctly by checking the applicable provision/s for each item. This document shall form part of the attachments of the plan/drawings to be submitted for QCDD review/approval. Note: Non-inclusion of this form could mean rejection of plan submission. Item DESCRIPTION N.B. QCDD permits single injection up to five (5) floor levels being served by the stairwell or up to 30.5 m total stair shaft height 2.2.b Primary and secondary power supplies Wiring systems (separate from any other circuit, approved and listed for the specific use, protected against exposure to fire, etc.) Means of actuating the system (fire alarm and/or smoke control initiating devices) Manual system override Supply air intake points distance and orientation relative to building exhausts

MV-01-2013

PS-_____-MV

Provisions Y N NA

Smoke-heat exhaust ventilation system (Atriums, Vertical Openings and Communicating Spaces, etc.) Types/construction Ducted Jet fans Others Fans and ducts, its components temperature and fire ratings Means of actuating the system Primary and secondary power supplies Wiring systems (separate from any other circuit, approved and listed for the specific use, protected against exposure to fire, etc.) Calculations/CFD analysis Manual system override

MV-01-2013

Page 4

FIRE PREVENTION DEPARTMENT GENERAL DIRECTORATE OF CIVIL DEFENCE MINISTRY OF THE INTERIOR, STATE OF QATAR

GUIDELINES FOR MECHANICAL VENTILATION PLAN SUBMISSIONS


This document provides the minimum information required in the submission of applications for ACMV plan approvals. Accomplish this form correctly by checking the applicable provision/s for each item. This document shall form part of the attachments of the plan/drawings to be submitted for QCDD review/approval. Note: Non-inclusion of this form could mean rejection of plan submission. Item 2.2.c Natural Locations and sizes of fixed ventilation openings, % of total enclosure area Orientation to normal wind directions, other structures on site DESCRIPTION

MV-01-2013

PS-_____-MV

Provisions Y N NA

2.3 2.4

2.5 2.6

2.7 2.8

Smoke control analysis and associated calculations confirming efficacy of the system Location and ventilation of refuge floor, where required for the building - Demonstrate compliance to QCD FSS 1.5 Location/s of fire fighter smoke control station in the building; details of smoke control system fan panels, manual activation/deactivation and override switches, etc. Location and ventilation of vital system installations such as the fire pump room, generator room, fire lift/lift machine room, etc. Schematic/riser and control diagrams showing the connections and arrangement of the components of the system according to its logic of operation Diagram of the smoke control system wiring connections Complete drawings/layout of the smoke control system plans which provides among others the following: Cover page Respective floor plans Full height section details showing installation of the equipment relative to the building or spaces being served Mechanical equipment and complete duct works layout Duct transitions and wall penetration seals, details and type of fire sealant materials used Associated dampers (description, locations, installation details, respective supervised positions, actuation temperature of fusible link type dampers, etc.) Air quantities on duct inlets and outlets
Page 5

MV-01-2013

FIRE PREVENTION DEPARTMENT GENERAL DIRECTORATE OF CIVIL DEFENCE MINISTRY OF THE INTERIOR, STATE OF QATAR

GUIDELINES FOR MECHANICAL VENTILATION PLAN SUBMISSIONS


This document provides the minimum information required in the submission of applications for ACMV plan approvals. Accomplish this form correctly by checking the applicable provision/s for each item. This document shall form part of the attachments of the plan/drawings to be submitted for QCDD review/approval. Note: Non-inclusion of this form could mean rejection of plan submission. Item DESCRIPTION Extent of protection enclosure on pressurization ducts not contained in protected shafts or those that can be exposed to a fire from the space/s where it passes through Extent of protection enclosure provided on other ventilation ducts which inevitably have to pass or run inside smoke stop lobbies Orientation and distances between pressurization air supply intake points and building exhausts discharge points (on floor plans and section details Extent of each control zone/compartment and enclosure fire ratings Other important notes and declarations

MV-01-2013

PS-_____-MV

Provisions Y N NA

Note:

Herein listed minimum required information is only those deemed necessary to proceed with the plan review/evaluation. QCDD may require additional information during the course of its review/evaluation of the plans and documents submitted. Similarly, the Consultant may opt to provide additional information he believed would be beneficial in the review/evaluation and approval of the plans.

Name, Signature & Stamp of Consultant Engineer

Date