InnovayaVisual4DSimulation GettingStartedTutorialOne: Run4DAutomaticallyUsingRevitProjectPhases ThisdocumentshowsyoustepbysteplessonsonhowtouseInnovayaVisual Simulationtoautomaticallyrun4DsimulationswiththeprojectphasesdefinedinRevit. ThelessonsalsoincludehowtoworkwithMSProject with4Dschedulingfeatures. Introduction InRevit,youcandefineaseriesofprojectphaseseachassignedtocertainobjects.If thisfeatureisusedappropriately,4Dsimulationcanbecreatedautomaticallythrough InnovayaVisualSimulationwithlittleextrawork.Thiscanbeveryeffectiveifthemodel ischangedfrequentlyasanytimea4Dpresentationcanbepreparedandviewed immediatelytocommunicateprojectmilestonesandplans. 1. DefineandVerifyRevitProjectPhases InRevit,clickmenuTools>Phasestoviewdefinedphases.

Note:Itisrecommendedthatthesephasesaredefinedwithappropriatesequence andnumberedlabelingconventions.Inthisexample,weuseUniformatIITitle namingconvention.

Copyright2008Innovaya,LLC

Page1of14

2. ExportRevitmodeltoINVwith4DenabledbyPhases StartRevit,andclickmenuTools>ExternalTools>InnovayaComposerforRevit. Makesure: CurrentViewisselected UseRevitPhasesischecked Enable4DUsingRevitPhasesischecked Allphasesarechecked ClickStarttospecifythefolderandfilenametobesaved.

Copyright2008Innovaya,LLC

Page2of14

3. StartInnovayaVisualSimulation

RunInnovayaVisualSimulationfromWindowsDesktopshortcuticon ormenuStart>AllPrograms>Innovaya>2.Visual4DSimulation

4. OpenINVProjectFilefromInnovayaVisualSimulation:Start>OpenProject

Copyright2008Innovaya,LLC

Page3of14

Thefolderandfilenameshouldalreadybeautomaticallyspecifiedbasedonthe informationfromtheRevitComposerSaveDialogbox.JustclickOpeninthis case. Otherwise,openSampleINVfilefrom:ProgramFiles\Innovaya\Get Started\SampleCEMESample.inv

Copyright2008Innovaya,LLC

Page4of14

5. Run4DSimulationusingtheDateBar Clickonthedatebarinthemiddleofthewindowandslidetochangedates.View 4Dsimulation.

Copyright2008Innovaya,LLC

Page5of14

6. Run4DSimulationwithaRangeofTwoDates ChecktheRangecheckbox.Changethedatebartoanearlierdate,andthe seconddatabartoalaterdate.

See4Deffectsandprojectstatusin3Donthedifferentdates.

Copyright2008Innovaya,LLC

Page6of14

7. ViewLinkedObjectsofaTask Click4DModeling(onmenubar)>4DEnabling(Checkitwith)

RightclickontheScheduleTasklistandselectShowLinkedObjects

Copyright2008Innovaya,LLC

Page7of14

8. ExportingScheduleTaskstoMSProject Note:thefollowingstepsrequireMSProject Rightclickontheschedulename(e.g.Schedule1)toshowtheContextMenu ClickExportScheduletoMSProject

Copyright2008Innovaya,LLC

Page8of14

ClickSave

ClickYes. 9. Run4DSimulationwithMSProject Run4DsimulationsbydraggingthedatebarandseehowMSProjectschedule correspondstothedatessimultaneouslywith4D.

Copyright2008Innovaya,LLC

Page9of14

10. ModifyScheduleTasksinMSProject InMSProject,modifythedurationsanddefinethepredecessorsofeachtask exportedfromINVfile. SavetheMSProjectfileafterthemodifications. 11. SynchronizewithMSProjectSchedule ClickthemenuImportScheduleinthe4DEnablingmenugroup.

Copyright2008Innovaya,LLC

Page10of14

Copyright2008Innovaya,LLC

Page11of14

ClickYes.

ClickNext> ClickDone. InnovayaVisualSimulationwillautomaticallyupdatethetaskdateinformationin INVfromthemodifiedMSProjectfile. ClickReload>>,torecalculatethe4Ddata,andrun4Dsimulationagainusing datebars. 12. Run4DSimulationasaMovie

ClicktheForwardicon

Copyright2008Innovaya,LLC

Page12of14

Amessageboxwillshowwherethefileissaved.

IfselectingYes,aseriesofpicturesfor4Dsimulationswillbeautomatically createdandsavedtothefolderyouselected. Youcanchangetheviewpositionswhile4Dsimulationisrunning. TorecordthemovieasanAVIorFlash(recommended)file,werecommendyou useCamtasiabywww.techsmith.com. 13. ExporttoMSWord Selectadateonwhichyouwanttoreportthe4DstatusbyusingtheDateBar orDateSelector. Adjustthe3DViewtoadesiredpositionandangle. ClickmenuCommunicationsExporttoWord.

Copyright2008Innovaya,LLC

Page13of14

CheckCompletedTasksandUnstartedTasks ClickOk

Copyright2008Innovaya,LLC

Page14of14