<-------------Responsibility----------->
<-------------Planned------------>
Deptt.
Start
Executive
End
Reminder <----------Actual----------->
Days
Days
Start
End
Delay
Days
NOTTY KID
Shipment Date 31/12/2013
Target Date / /
Cancellation Date / /
KIDS ROMPER
15/11/2013
17/11/2013
/ /
/ /
17
2 MATERIAL REQUIRMENT
17/11/2013
18/11/2013
/ /
/ /
16
3 FABRIC PURCHASE
18/11/2013
03/12/2013
15
/ /
/ /
4 TRIM PURCHASE
18/11/2013
03/12/2013
15
/ /
/ /
5 CUTTING
03/12/2013
08/12/2013
/ /
/ /
6 STITCHING
04/12/2013
14/12/2013
10
/ /
/ /
14/12/2013
16/12/2013
/ /
/ /
8 DESPATCH
16/12/2013
31/12/2013
15
/ /
/ /
35
04/12/2013