The Factory Acceptance Test (FAT) Checklist is a list of all required inspections and tests, presented as inspection and test plan which must be done by the vendor to determine that the line pipes and related fittings are produced according to the project specification and applicable international codes and
standards.
Section 2.0 belowpresents the Factory Acceptance Test Checklist for line pipes on the Gas Supply to Ogijo customers EPC Project
2.0 LINE PIPES FACTORY ACCEPTANCE TESTS CHECKLIST
Reference Document Characteristics of Check Type of Check Acceptance Criteria Verifying documents
2.1
Raw material inspection Project Specification -Dimension -Visual Project Specification The original or authenticated copies of mill certificates of material would be examined for Original material &
API 5L -Visual -Spectro Analysis API 5L compliance with specifications and where appropriate, drawings. Test certificates
-Chemical Properties The review includes checks on:
-Certificate No.
-Heat No.
-Chemical composition
-Mechanical properties.
-Heat treated condition.
-NDE applied and results.
-Details of welding consumables
2.2
2.2.1 Pipe Forming API 5L Profile/shape Visual API 5L Procedure
2.2.2 Heat Treatment API 5L
Normalizing / Quenching /
Tempering Heat Treatment Cycle API 5L Procedure
2.2.3 Chemical Testing API 5L -Chemical -Chemical API 5L Report
2.2.4 Mechanical Property Testing API 5L -Mechanical -Tensile API 5L
-Impact
2.2.5 Hydrostatic Testing Procedure/API 5L Pressure Test Pressure Test Procedure/API 5L Report
2.2.6 Ultrasonic Testing Procedure/API 5L Procedure/API 5L Report
2.2.7 Dimensional Inspection API 5L API 5L Report
2.2.8 Visual Inspection API 5L API 5L Report
2.2.9 Body Marking Check API 5L API 5L Report
2.3
2.3.1 Final Visual & dimensional Check Datasheet/ Spec Surface dimension & Shape Measurement/Visual Datasheet/ Spec Report
2.3.2 Surface Preparation & Coating Datasheet/ Spec Datasheet/ Spec Report
2.3.3 Check of Final Book Project Specification Project Specification Datasheet/P.O
2.4
2.4.1 Documentation Datasheet/ Spec Mill Test Certificates Verification Datasheet/ Spec Report
2.5
2.5.1 Preservation and Packing Project Specification Project Specification Report
2.5.2 Marking Project Specification Project Specification Report
2.5.3 Loading Inspection Project Specification Project Specification Report
2.5.4 Shipping Document Control Procedure Procedure Parking List
Final Inspection
INTRODUCTION
Documentation
Pre-Shipment Inspection
FACTORY ACCEPTANCE TESTS (FAT)
During Fabrication
Before Manufacturing
Are Requirements Met (Yes/No) Inspection & Test Plan Requirements Remarks