GENERATING UNITS OUTAGE STATUS IN SOUTHERN REGION

AS ON DATE 15-Jul-14 TIME 06:00 HRS



1 A. Generating Units Revived during Last 30 HRS ( 00:00 HRS of 14-Jul-14 to 06:00 HRS of 15-Jul-14)
1 B. Generating Units Under Planned Outage ( Status at 06:00 HRS of 15-Jul-14)
1 C. Generating Units Under Forced Outage ( Status at 06:00 HRS of 15-Jul-14)
POWER SYSTEM OPERATION CORPORATION LIMITED.
SOUTHERN REGIONAL LOAD DESPATCH CENTRE
S No. STATION AGENCY UNITNO CAPACITY
OUTAGE REVIVAL
REASON OF OUTAGE
DATE TIME DATE TIME
CENTRAL SECTOR
1 RAMAGUNDAM STPS NTPC UNIT 7 500 MW 12-JUL-2014 23:28:00 14-JUL-2014 06:50:00 BOILER TUBE LEAKAGE
2
3
4
5
STATE SECTOR
1 KOTHAGUDAM TPS TGGENCO UNIT 2 60 MW 13-JUL-2014 05:20:00 14-JUL-2014 00:55:00 BOILER TUBE LEAKAGE
2
3
4
5
S No. STATION AGENCY UNITNO CAPACITY
OUTAGE
EXPECTED
DATE
REASON OF OUTAGE
DATE TIME
CENTRAL SECTOR
1 NEYVELI II NLC UNIT 6 210 MW 01-JUL-2014 00:05:00 01-AUG-2014 ANNUAL MAINTENANCE
2 RAMAGUNDAM STPS NTPC UNIT 3 200 MW 26-JUN-2014 00:18:00 24-JUL-2014 ANNUAL MAINTENANCE
3
4
5
STATE SECTOR
1 KOTHAGUDAM TPS TGGENCO UNIT 8 120 MW 24-MAY-2014 11:20:00 20-JUL-2014 ANNUAL MAINTENANCE
2 MEENAKSHI MEPL UNIT 1 150 MW 26-MAY-2014 19:37:00 30-JUL-2014 ANNUAL MAINTENANCE
3 MEENAKSHI MEPL UNIT 2 150 MW 01-JUN-2014 00:10:00 30-JUL-2014 ANNUAL MAINTENANCE
4 NEYVELI I TNEB UNIT 3 50 MW 09-JUL-2014 00:28:00 17-JUL-2014 ANNUAL MAINTENANCE
5 RAYALASEEMA TPS APGENCO UNIT 3 210 MW 11-JUL-2014 04:06:00 26-JUL-2014 ANNUAL MAINTENANCE
S No. STATION AGENCY UNITNO CAPACITY
OUTAGE
EXPECTED
DATE
REASON OF OUTAGE
DATE TIME
CENTRAL SECTOR
1 NEYVELI TS II EXP NLC UNIT 1 250 MW 28-MAY-2014 00:08:00 01-AUG-2014 DUE TO PUNCTURE HEAT EXCHANGER
2 TALCHER STG II NTPC UNIT 5 500 MW 11-JUL-2014 03:05:00 10-AUG-2014 ANNUAL MAINTENANCE
3
4
5
STATE SECTOR
1 ENNORE TPS TNEB UNIT 2 60 MW 26-APR-2014 11:34:00 21-JUL-2014 AXIAL SHIFT HIGH
2 ENNORE TPS TNEB UNIT 3 110 MW 05-MAY-2014 06:20:00 19-JUL-2014 BUS BAR PROTECTION OPERATED.
3 KOTHAGUDAM TPS TGGENCO UNIT 3 60 MW 13-JUL-2014 05:10:00 20-JUL-2014 BOILER TUBE LEAKAGE
4 METTUR ST3 TNEB UNIT 1 600 MW 22-JUN-2014 20:30:00 19-JUL-2014 COOLING SYSTEM HYDROGEN LEAKAGE
5 METTUR TPS TNEB UNIT 4 210 MW 30-MAY-2014 10:30:00 20-JUL-2014
GT BUCHOLZ RELAY ACTED AND CONVERTED TO
AOH
6 NEYVELI I TNEB UNIT 7 100 MW 20-MAY-2014 10:12:00 22-JUL-2014 STEAM LEAKAGE
7 NORTH CHENNAI TPS TNEB UNIT 3 210 MW 10-JUL-2014 20:20:00 19-JUL-2014 BOILER TUBE LEAKAGE
8 RAICHUR TPS KPCL UNIT 8 250 MW 14-JUL-2014 22:42:00 COAL FEED PROBLEM
9 RAYALASEEMA TPS APGENCO UNIT 5 210 MW 14-JUL-2014 19:44:00 BOILER TUBE LEAKAGE
10 SDS TPS APGENCO UNIT 1 800 MW 03-JUL-2014 10:27:00 18-JUL-2014 COAL SHORTAGE
11 UPCL LANCO UNIT 2 600 MW 11-JUL-2014 13:40:00 18-JUL-2014 TRIPPED DUE TO SPS OPERATION
Page 7 of 16