ITEM PEMBAYARAN No. : 9.

4
JENIS PEKERJAAN : PEKERJAAN HARIAN
SATUAN PEMBAYARAN : JAM URAIAN ANALISA HARGA SATUAN
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

No. U R A I A N KODE KOEF. SATUAN KET.
A. URAIAN PERALATAN
1. Jenis Peralatan DUMP TRUCK 3-4 M3 (E08)
2. Tenaga Pw 100.0 HP
3. Kapasitas Cp 6.0 Ton
4. Umur Ekonomis A 5.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 2,000 Jam Alat Baru
6. Harga Alat B 120,176,000 Rupiah Alat Baru
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x Harga Alat Baru C 9,240,454 Rupiah
2. Faktor Angsuran Modal = i x (1 + i)^A D 0.29128 -
(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B - C ) x D E 16,156.85 Rupiah
W
b. Asuransi, dll = 0.002 x B F 120.18 Rupiah
W
Biaya Pasti per Jam = ( E + F ) G 16,277.03 Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 34,375.00 Rupiah
2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 17,500.00 Rupiah
3. Perawatan dan (12,5 % - 17,5 %) x B K 7,511.00 Rupiah
perbaikan = W
4. Operator = ( 1 Orang / Jam ) x U1 L 5,714.29 Rupiah
5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 4,285.71 Rupiah
Biaya Operasi per Jam = (H+I+K+L+M) P 69,386.00 Rupiah
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 85,663.03 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 14.00 % / Tahun
2. Upah Operator / Sopir L 5,714.29 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir M 4,285.71 Rp./Jam
4. Bahan Bakar Bensin Mb 3,240.00 Liter
5. Bahan Bakar Solar Ms 2,750.00 Liter
6. Minyak Pelumas Mp 17,500.00 Liter
File : 89627764.xls.ms_office
ITEM PEMBAYARAN No. : 9.5
JENIS PEKERJAAN : PEKERJAAN HARIAN
SATUAN PEMBAYARAN : JAM URAIAN ANALISA HARGA SATUAN
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

No. U R A I A N KODE KOEF. SATUAN KETERANGAN
A. URAIAN PERALATAN
1. Jenis Peralatan FLAT BED TRUCK 3-4 M3 (E11)
2. Tenaga Pw 125.0 HP
3. Kapasitas Cp 4.0 M3
4. Umur Ekonomis A 5.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 2,000 Jam Alat Baru
6. Harga Alat B 105,005,159 Rupiah Alat Baru
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x Harga Alat Baru C 10,500,516 Rupiah
2. Faktor Angsuran Modal = i x (1 + i)^A D 0.33438 -
(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B - C ) x D E 15,800.22 Rupiah
W
b. Asuransi, dll = 0.002 x B F 105.01 Rupiah
W
Biaya Pasti per Jam = ( E + F ) G 15,905.22 Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 29,531.25 Rupiah
2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 15,000.00 Rupiah
3. Perawatan dan (12,5 % - 17,5 %) x B K 6,562.82 Rupiah
perbaikan = W
4. Operator = ( 1 Orang / Jam ) x U1 L 5,000.00 Rupiah
5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 3,928.57 Rupiah
Biaya Operasi per Jam = (H+I+K+L+M) P 60,022.64 Rupiah
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 75,927.86 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 5,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 3,928.57 Rp./Jam
4. Bahan Bakar Bensin Mb 1,810.00 Liter
5. Bahan Bakar Solar Ms 1,890.00 Liter
6. Minyak Pelumas Mp 12,000.00 Liter
File : 89627764.xls.ms_office
ITEM PEMBAYARAN No. : 9.6
JENIS PEKERJAAN : PEKERJAAN HARIAN
SATUAN PEMBAYARAN : JAM URAIAN ANALISA HARGA SATUAN
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

No. U R A I A N KODE KOEF. SATUAN KETERANGAN
A. URAIAN PERALATAN
1. Jenis Peralatan WATER TANKER 3000-4500 L. (E23)
2. Tenaga Pw 125.0 HP
3. Kapasitas Cp 4,000.0 Liter
4. Umur Ekonomis A 5.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 2,000 Jam Alat Baru
6. Harga Alat B 105,005,159 Rupiah Alat Baru
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x Harga Alat Baru C 10,500,516 Rupiah
2. Faktor Angsuran Modal = i x (1 + i)^A D 0.33438 -
(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B - C ) x D E 15,800.22 Rupiah
W
b. Asuransi, dll = 0.002 x B F 105.01 Rupiah
W
Biaya Pasti per Jam = ( E + F ) G 15,905.22 Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 29,531.25 Rupiah
2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 15,000.00 Rupiah
3. Perawatan dan (12,5 % - 17,5 %) x B K 6,562.82 Rupiah
perbaikan = W
4. Operator = ( 1 Orang / Jam ) x U1 L 5,000.00 Rupiah
5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 3,928.57 Rupiah
Biaya Operasi per Jam = (H+I+K+L+M) P 60,022.64 Rupiah
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 75,927.86 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 5,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 3,928.57 Rp./Jam
4. Bahan Bakar Bensin Mb 1,810.00 Liter
5. Bahan Bakar Solar Ms 1,890.00 Liter
6. Minyak Pelumas Mp 12,000.00 Liter
File : 89627764.xls.ms_office
ITEM PEMBAYARAN No. : 9.7
JENIS PEKERJAAN : PEKERJAAN HARIAN
SATUAN PEMBAYARAN : JAM URAIAN ANALISA HARGA SATUAN
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

No. U R A I A N KODE KOEF. SATUAN KETERANGAN
A. URAIAN PERALATAN
1. Jenis Peralatan BULLDOZER 100-150 HP (E04)
2. Tenaga Pw 140.0 HP
3. Kapasitas Cp - -
4. Umur Ekonomis A 5.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 2,000 Jam Alat Baru
6. Harga Alat B 588,028,890 Rupiah Alat Baru
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x Harga Alat Baru C 58,802,889 Rupiah
2. Faktor Angsuran Modal = i x (1 + i)^A D 0.33438 -
(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B - C ) x D E 88,481.22 Rupiah
W
b. Asuransi, dll = 0.002 x B F 588.03 Rupiah
W
Biaya Pasti per Jam = ( E + F ) G 89,069.25 Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 33,075.00 Rupiah
2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 16,800.00 Rupiah
3. Perawatan dan (12,5 % - 17,5 %) x B K 36,751.81 Rupiah
perbaikan = W
4. Operator = ( 1 Orang / Jam ) x U1 L 5,000.00 Rupiah
5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 3,928.57 Rupiah
Biaya Operasi per Jam = (H+I+K+L+M) P 95,555.38 Rupiah
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 184,624.62 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 5,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 3,928.57 Rp./Jam
4. Bahan Bakar Bensin Mb 1,810.00 Liter
5. Bahan Bakar Solar Ms 1,890.00 Liter
6. Minyak Pelumas Mp 12,000.00 Liter
File : 89627764.xls.ms_office
ITEM PEMBAYARAN No. : 9.8
JENIS PEKERJAAN : PEKERJAAN HARIAN
SATUAN PEMBAYARAN : JAM URAIAN ANALISA HARGA SATUAN
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

No. U R A I A N KODE KOEF. SATUAN KETERANGAN
A. URAIAN PERALATAN
1. Jenis Peralatan MOTOR GRADER >100 HP (E13)
2. Tenaga Pw 125.0 HP
3. Kapasitas Cp - -
4. Umur Ekonomis A 5.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 2,000 Jam Alat Baru
6. Harga Alat B 424,220,842 Rupiah Alat Baru
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x Harga Alat Baru C 42,422,084 Rupiah
2. Faktor Angsuran Modal = i x (1 + i)^A D 0.33438 -
(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B - C ) x D E 63,832.88 Rupiah
W
b. Asuransi, dll = 0.002 x B F 424.22 Rupiah
W
Biaya Pasti per Jam = ( E + F ) G 64,257.10 Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 29,531.25 Rupiah
2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 15,000.00 Rupiah
3. Perawatan dan (12,5 % - 17,5 %) x B K 26,513.80 Rupiah
perbaikan = W
4. Operator = ( 1 Orang / Jam ) x U1 L 5,000.00 Rupiah
5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 3,928.57 Rupiah
Biaya Operasi per Jam = (H+I+K+L+M) P 79,973.62 Rupiah
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 144,230.72 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 5,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 3,928.57 Rp./Jam
4. Bahan Bakar Bensin Mb 1,810.00 Liter
5. Bahan Bakar Solar Ms 1,890.00 Liter
6. Minyak Pelumas Mp 12,000.00 Liter
File : 89627764.xls.ms_office
ITEM PEMBAYARAN No. : 9.9
JENIS PEKERJAAN : PEKERJAAN HARIAN
SATUAN PEMBAYARAN : JAM URAIAN ANALISA HARGA SATUAN
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

No. U R A I A N KODE KOEF. SATUAN KETERANGAN
A. URAIAN PERALATAN
1. Jenis Peralatan WHEEL LOADER 1.0-1.6 M3 (E15)
2. Tenaga Pw 125.0 HP
3. Kapasitas Cp 1.5 M3
4. Umur Ekonomis A 5.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 2,000 Jam Alat Baru
6. Harga Alat B 399,019,604 Rupiah Alat Baru
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x Harga Alat Baru C 39,901,960 Rupiah
2. Faktor Angsuran Modal = i x (1 + i)^A D 0.33438 -
(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B - C ) x D E 60,040.83 Rupiah
W
b. Asuransi, dll = 0.002 x B F 399.02 Rupiah
W
Biaya Pasti per Jam = ( E + F ) G 60,439.85 Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 29,531.25 Rupiah
2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 15,000.00 Rupiah
3. Perawatan dan (12,5 % - 17,5 %) x B K 24,938.73 Rupiah
perbaikan = W
4. Operator = ( 1 Orang / Jam ) x U1 L 5,000.00 Rupiah
5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 3,928.57 Rupiah
Biaya Operasi per Jam = (H+I+K+L+M) P 78,398.55 Rupiah
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 138,838.39 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 5,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 3,928.57 Rp./Jam
4. Bahan Bakar Bensin Mb 1,810.00 Liter
5. Bahan Bakar Solar Ms 1,890.00 Liter
6. Minyak Pelumas Mp 12,000.00 Liter
File : 89627764.xls.ms_office
ITEM PEMBAYARAN No. : 9.10
JENIS PEKERJAAN : PEKERJAAN HARIAN
SATUAN PEMBAYARAN : JAM URAIAN ANALISA HARGA SATUAN
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

No. U R A I A N KODE KOEF. SATUAN KETERANGAN
A. URAIAN PERALATAN
1. Jenis Peralatan TRACK LOADER 75-100 HP (E14)
2. Tenaga Pw 95.0 HP
3. Kapasitas Cp 1.5 M3
4. Umur Ekonomis A 5.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 2,000 Jam Alat Baru
6. Harga Alat B 504,024,763 Rupiah Alat Baru
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x Harga Alat Baru C 50,402,476 Rupiah
2. Faktor Angsuran Modal = i x (1 + i)^A D 0.33438 -
(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B - C ) x D E 75,841.04 Rupiah
W
b. Asuransi, dll = 0.002 x B F 504.02 Rupiah
W
Biaya Pasti per Jam = ( E + F ) G 76,345.07 Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 22,443.75 Rupiah
2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 11,400.00 Rupiah
3. Perawatan dan (12,5 % - 17,5 %) x B K 31,501.55 Rupiah
perbaikan = W
4. Operator = ( 1 Orang / Jam ) x U1 L 5,000.00 Rupiah
5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 3,928.57 Rupiah
Biaya Operasi per Jam = (H+I+K+L+M) P 74,273.87 Rupiah
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 150,618.94 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 5,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 3,928.57 Rp./Jam
4. Bahan Bakar Bensin Mb 1,810.00 Liter
5. Bahan Bakar Solar Ms 1,890.00 Liter
6. Minyak Pelumas Mp 12,000.00 Liter
File : 89627764.xls.ms_office
ITEM PEMBAYARAN No. : 9.11
JENIS PEKERJAAN : PEKERJAAN HARIAN
SATUAN PEMBAYARAN : JAM URAIAN ANALISA HARGA SATUAN
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

No. U R A I A N KODE KOEF. SATUAN KETERANGAN
A. URAIAN PERALATAN
1. Jenis Peralatan EXCAVATOR 80-140 HP (E10)
2. Tenaga Pw 80.0 HP
3. Kapasitas Cp 0.5 M3
4. Umur Ekonomis A 5.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 2,000 Jam Alat Baru
6. Harga Alat B 504,024,763 Rupiah Alat Baru
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x Harga Alat Baru C 50,402,476 Rupiah
2. Faktor Angsuran Modal = i x (1 + i)^A D 0.33438 -
(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B - C ) x D E 75,841.04 Rupiah
W
b. Asuransi, dll = 0.002 x B F 504.02 Rupiah
W
Biaya Pasti per Jam = ( E + F ) G 76,345.07 Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 18,900.00 Rupiah
2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 9,600.00 Rupiah
3. Perawatan dan (12,5 % - 17,5 %) x B K 31,501.55 Rupiah
perbaikan = W
4. Operator = ( 1 Orang / Jam ) x U1 L 5,000.00 Rupiah
5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 3,928.57 Rupiah
Biaya Operasi per Jam = (H+I+K+L+M) P 68,930.12 Rupiah
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 145,275.19 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 5,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 3,928.57 Rp./Jam
4. Bahan Bakar Bensin Mb 1,810.00 Liter
5. Bahan Bakar Solar Ms 1,890.00 Liter
6. Minyak Pelumas Mp 12,000.00 Liter
File : 89627764.xls.ms_office
ITEM PEMBAYARAN No. : 9.12
JENIS PEKERJAAN : PEKERJAAN HARIAN
SATUAN PEMBAYARAN : JAM URAIAN ANALISA HARGA SATUAN
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

No. U R A I A N KODE KOEF. SATUAN KETERANGAN
A. URAIAN PERALATAN
1. Jenis Peralatan CRANE 10-15 TON (E07)
2. Tenaga Pw 150.0 HP
3. Kapasitas Cp 25.0 Ton
4. Umur Ekonomis A 5.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 2,000 Jam Alat Baru
6. Harga Alat B 777,038,177 Rupiah Alat Baru
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x Harga Alat Baru C 77,703,818 Rupiah
2. Faktor Angsuran Modal = i x (1 + i)^A D 0.33438 -
(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B - C ) x D E 116,921.61 Rupiah
W
b. Asuransi, dll = 0.002 x B F 777.04 Rupiah
W
Biaya Pasti per Jam = ( E + F ) G 117,698.65 Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 35,437.50 Rupiah
2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 18,000.00 Rupiah
3. Perawatan dan (12,5 % - 17,5 %) x B K 48,564.89 Rupiah
perbaikan = W
4. Operator = ( 1 Orang / Jam ) x U1 L 5,000.00 Rupiah
5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 3,928.57 Rupiah
Biaya Operasi per Jam = (H+I+K+L+M) P 110,930.96 Rupiah
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 228,629.60 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 5,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 3,928.57 Rp./Jam
4. Bahan Bakar Bensin Mb 1,810.00 Liter
5. Bahan Bakar Solar Ms 1,890.00 Liter
6. Minyak Pelumas Mp 12,000.00 Liter
File : 89627764.xls.ms_office
ITEM PEMBAYARAN No. : 9.13
JENIS PEKERJAAN : PEKERJAAN HARIAN
SATUAN PEMBAYARAN : JAM URAIAN ANALISA HARGA SATUAN
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

No. U R A I A N KODE KOEF. SATUAN KETERANGAN
A. URAIAN PERALATAN
1. Jenis Peralatan STEEL WHEEL ROLLER 6-9 T. (E16)
2. Tenaga Pw 60.0 HP
3. Kapasitas Cp 8.0 Ton
4. Umur Ekonomis A 5.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 2,000 Jam Alat Baru
6. Harga Alat B 155,407,635 Rupiah Alat Baru
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x Harga Alat Baru C 15,540,764 Rupiah
2. Faktor Angsuran Modal = i x (1 + i)^A D 0.33438 -
(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B - C ) x D E 23,384.32 Rupiah
W
b. Asuransi, dll = 0.002 x B F 155.41 Rupiah
W
Biaya Pasti per Jam = ( E + F ) G 23,539.73 Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 14,175.00 Rupiah
2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 7,200.00 Rupiah
3. Perawatan dan (12,5 % - 17,5 %) x B K 9,712.98 Rupiah
perbaikan = W
4. Operator = ( 1 Orang / Jam ) x U1 L 5,000.00 Rupiah
5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 3,928.57 Rupiah
Biaya Operasi per Jam = (H+I+K+L+M) P 40,016.55 Rupiah
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 63,556.28 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 5,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 3,928.57 Rp./Jam
4. Bahan Bakar Bensin Mb 1,810.00 Liter
5. Bahan Bakar Solar Ms 1,890.00 Liter
6. Minyak Pelumas Mp 12,000.00 Liter
File : 89627764.xls.ms_office
ITEM PEMBAYARAN No. : 9.14
JENIS PEKERJAAN : PEKERJAAN HARIAN
SATUAN PEMBAYARAN : JAM URAIAN ANALISA HARGA SATUAN
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

No. U R A I A N KODE KOEF. SATUAN KETERANGAN
A. URAIAN PERALATAN
1. Jenis Peralatan VIBRATORY ROLLER 5-8 T. (E19)
2. Tenaga Pw 60.0 HP
3. Kapasitas Cp 8.0 Ton
4. Umur Ekonomis A 4.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 2,000 Jam Alat Baru
6. Harga Alat B 197,409,699 Rupiah Alat Baru
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x Harga Alat Baru C 19,740,970 Rupiah
2. Faktor Angsuran Modal = i x (1 + i)^A D 0.38629 -
(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B - C ) x D E 34,315.75 Rupiah
W
b. Asuransi, dll = 0.002 x B F 197.41 Rupiah
W
Biaya Pasti per Jam = ( E + F ) G 34,513.16 Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 14,175.00 Rupiah
2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 7,200.00 Rupiah
3. Perawatan dan (12,5 % - 17,5 %) x B K 12,338.11 Rupiah
perbaikan = W
4. Operator = ( 1 Orang / Jam ) x U1 L 5,000.00 Rupiah
5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 3,928.57 Rupiah
Biaya Operasi per Jam = (H+I+K+L+M) P 42,641.68 Rupiah
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 77,154.83 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 5,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 3,928.57 Rp./Jam
4. Bahan Bakar Bensin Mb 1,810.00 Liter
5. Bahan Bakar Solar Ms 1,890.00 Liter
6. Minyak Pelumas Mp 12,000.00 Liter
File : 89627764.xls.ms_office
ITEM PEMBAYARAN No. : 9.15
JENIS PEKERJAAN : PEKERJAAN HARIAN
SATUAN PEMBAYARAN : JAM URAIAN ANALISA HARGA SATUAN
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

No. U R A I A N KODE KOEF. SATUAN KETERANGAN
A. URAIAN PERALATAN
1. Jenis Peralatan VIBRATORY COMPACTOR (E25)
2. Tenaga Pw 5.0 HP
3. Kapasitas Cp 0.200 Ton
4. Umur Ekonomis A 4.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 1,000 Jam Alat Baru
6. Harga Alat B 6,720,330 Rupiah Alat Baru
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x Harga Alat Baru C 672,033 Rupiah
2. Faktor Angsuran Modal = i x (1 + i)^A D 0.38629 -
(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B - C ) x D E 2,336.39 Rupiah
W
b. Asuransi, dll = 0.002 x B F 13.44 Rupiah
W
Biaya Pasti per Jam = ( E + F ) G 2,349.83 Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 1,181.25 Rupiah
2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 600.00 Rupiah
3. Perawatan dan (12,5 % - 17,5 %) x B K 840.04 Rupiah
perbaikan = W
4. Operator = ( 1 Orang / Jam ) x U1 L 5,000.00 Rupiah
5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 3,928.57 Rupiah
Biaya Operasi per Jam = (H+I+K+L+M) P 11,549.86 Rupiah
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 13,899.69 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 5,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 3,928.57 Rp./Jam
4. Bahan Bakar Bensin Mb 1,810.00 Liter
5. Bahan Bakar Solar Ms 1,890.00 Liter
6. Minyak Pelumas Mp 12,000.00 Liter
File : 89627764.xls.ms_office
ITEM PEMBAYARAN No. : 9.16
JENIS PEKERJAAN : PEKERJAAN HARIAN
SATUAN PEMBAYARAN : JAM URAIAN ANALISA HARGA SATUAN
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

No. U R A I A N KODE KOEF. SATUAN KETERANGAN
A. URAIAN PERALATAN
1. Jenis Peralatan TIRE ROLLER 8-10 T. (E18)
2. Tenaga Pw 60.0 HP
3. Kapasitas Cp 10.0 Ton
4. Umur Ekonomis A 5.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 1,800 Jam Alat Baru
6. Harga Alat B 176,408,667 Rupiah Alat Baru
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x Harga Alat Baru C 17,640,867 Rupiah
2. Faktor Angsuran Modal = i x (1 + i)^A D 0.33438 -
(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B - C ) x D E 29,493.74 Rupiah
W
b. Asuransi, dll = 0.002 x B F 196.01 Rupiah
W
Biaya Pasti per Jam = ( E + F ) G 29,689.75 Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 14,175.00 Rupiah
2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 7,200.00 Rupiah
3. Perawatan dan (12,5 % - 17,5 %) x B K 12,250.60 Rupiah
perbaikan = W
4. Operator = ( 1 Orang / Jam ) x U1 L 5,000.00 Rupiah
5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 3,928.57 Rupiah
Biaya Operasi per Jam = (H+I+K+L+M) P 42,554.17 Rupiah
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 72,243.92 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 5,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 3,928.57 Rp./Jam
4. Bahan Bakar Bensin Mb 1,810.00 Liter
5. Bahan Bakar Solar Ms 1,890.00 Liter
6. Minyak Pelumas Mp 12,000.00 Liter
File : 89627764.xls.ms_office
ITEM PEMBAYARAN No. : 9.17
JENIS PEKERJAAN : PEKERJAAN HARIAN
SATUAN PEMBAYARAN : JAM URAIAN ANALISA HARGA SATUAN
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

No. U R A I A N KODE KOEF. SATUAN KETERANGAN
A. URAIAN PERALATAN
1. Jenis Peralatan COMPRESSOR 4000-6500 L\M (E05)
2. Tenaga Pw 80.0 HP
3. Kapasitas Cp - -
4. Umur Ekonomis A 5.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 2,000 Jam Alat Baru
6. Harga Alat B 54,602,683 Rupiah Alat Baru
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x Harga Alat Baru C 5,460,268 Rupiah
2. Faktor Angsuran Modal = i x (1 + i)^A D 0.33438 -
(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B - C ) x D E 8,216.11 Rupiah
W
b. Asuransi, dll = 0.002 x B F 54.60 Rupiah
W
Biaya Pasti per Jam = ( E + F ) G 8,270.72 Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 18,900.00 Rupiah
2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 9,600.00 Rupiah
3. Perawatan dan (12,5 % - 17,5 %) x B K 3,412.67 Rupiah
perbaikan = W
4. Operator = ( 1 Orang / Jam ) x U1 L 5,000.00 Rupiah
5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 3,928.57 Rupiah
Biaya Operasi per Jam = (H+I+K+L+M) P 40,841.24 Rupiah
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 49,111.95 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 5,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 3,928.57 Rp./Jam
4. Bahan Bakar Bensin Mb 1,810.00 Liter
5. Bahan Bakar Solar Ms 1,890.00 Liter
6. Minyak Pelumas Mp 12,000.00 Liter
File : 89627764.xls.ms_office
ITEM PEMBAYARAN No. : 9.18
JENIS PEKERJAAN : PEKERJAAN HARIAN
SATUAN PEMBAYARAN : JAM URAIAN ANALISA HARGA SATUAN
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

No. U R A I A N KODE KOEF. SATUAN KETERANGAN
A. URAIAN PERALATAN
1. Jenis Peralatan CONCRETE MIXER 0.3-0.6 M3 (E06)
2. Tenaga Pw 15.0 HP
3. Kapasitas Cp 500.0 Liter
4. Umur Ekonomis A 4.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 2,000 Jam Alat Baru
6. Harga Alat B 117,605,778 Rupiah Alat Baru
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x Harga Alat Baru C 11,760,578 Rupiah
2. Faktor Angsuran Modal = i x (1 + i)^A D 0.38629 -
(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B - C ) x D E 20,443.42 Rupiah
W
b. Asuransi, dll = 0.002 x B F 117.61 Rupiah
W
Biaya Pasti per Jam = ( E + F ) G 20,561.03 Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 3,543.75 Rupiah
2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 1,800.00 Rupiah
3. Perawatan dan (12,5 % - 17,5 %) x B K 7,350.36 Rupiah
perbaikan = W
4. Operator = ( 1 Orang / Jam ) x U1 L 5,000.00 Rupiah
5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 3,928.57 Rupiah
Biaya Operasi per Jam = (H+I+K+L+M) P 21,622.68 Rupiah
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 42,183.71 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 5,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 3,928.57 Rp./Jam
4. Bahan Bakar Bensin Mb 1,810.00 Liter
5. Bahan Bakar Solar Ms 1,890.00 Liter
6. Minyak Pelumas Mp 12,000.00 Liter
File : 89627764.xls.ms_office
ITEM PEMBAYARAN No. : 9.19
JENIS PEKERJAAN : PEKERJAAN HARIAN
SATUAN PEMBAYARAN : JAM URAIAN ANALISA HARGA SATUAN
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

No. U R A I A N KODE KOEF. SATUAN KETERANGAN
A. URAIAN PERALATAN
1. Jenis Peralatan WATER PUMP 70-100 mm (E22)
2. Tenaga Pw 6.0 HP
3. Kapasitas Cp - -
4. Umur Ekonomis A 2.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 2,000 Jam Alat Baru
6. Harga Alat B 9,450,464 Rupiah Alat Baru
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x Harga Alat Baru C 945,046 Rupiah
2. Faktor Angsuran Modal = i x (1 + i)^A D 0.65455 -
(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B - C ) x D E 2,783.59 Rupiah
W
b. Asuransi, dll = 0.002 x B F 9.45 Rupiah
W
Biaya Pasti per Jam = ( E + F ) G 2,793.04 Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 1,417.50 Rupiah
2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 720.00 Rupiah
3. Perawatan dan (12,5 % - 17,5 %) x B K 590.65 Rupiah
perbaikan = W
4. Operator = ( 1 Orang / Jam ) x U1 L 5,000.00 Rupiah
5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 3,928.57 Rupiah
Biaya Operasi per Jam = (H+I+K+L+M) P 11,656.72 Rupiah
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 14,449.77 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 5,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 3,928.57 Rp./Jam
4. Bahan Bakar Bensin Mb 1,810.00 Liter
5. Bahan Bakar Solar Ms 1,890.00 Liter
6. Minyak Pelumas Mp 12,000.00 Liter
File : 89627764.xls.ms_office
ITEM PEMBAYARAN No. : 9.20
JENIS PEKERJAAN : PEKERJAAN HARIAN
SATUAN PEMBAYARAN : JAM URAIAN ANALISA HARGA SATUAN
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

No. U R A I A N KODE KOEF. SATUAN KETERANGAN
A. URAIAN PERALATAN
1. Jenis Peralatan JACK HAMMER E26
2. Tenaga Pw 3.0 HP
3. Kapasitas Cp - -
4. Umur Ekonomis A 4.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 1,000 Jam Alat Baru
6. Harga Alat B 27,721,362 Rupiah Alat Baru
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x Harga Alat Baru C 2,772,136 Rupiah
2. Faktor Angsuran Modal = i x (1 + i)^A D 0.38629 -
(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B - C ) x D E 9,637.61 Rupiah
W
b. Asuransi, dll = 0.002 x B F 55.44 Rupiah
W
Biaya Pasti per Jam = ( E + F ) G 9,693.06 Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 708.75 Rupiah
2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 360.00 Rupiah
3. Perawatan dan (12,5 % - 17,5 %) x B K 3,465.17 Rupiah
perbaikan = W
4. Operator = ( 1 Orang / Jam ) x U1 L 5,000.00 Rupiah
5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 3,928.57 Rupiah
Biaya Operasi per Jam = (H+I+K+L+M) P 13,462.49 Rupiah
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 23,155.55 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 5,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 3,928.57 Rp./Jam
4. Bahan Bakar Bensin Mb 1,810.00 Liter
5. Bahan Bakar Solar Ms 1,890.00 Liter
6. Minyak Pelumas Mp 12,000.00 Liter
File : 89627764.xls.ms_office
URAIAN ANALISA HARGA SATUAN FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. : 9.4 PERKIRAAN VOL. PEK. : 140.00
JENIS PEKERJAAN : PEKERJAAN HARIAN TOTAL HARGA (Rp.) : 9,906,118.60
DUMP TRUCK 3-4 M3 % THD. BIAYA PROYEK : 0.03
SATUAN PEMBAYARAN : JAM (E08)
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. PEKERJA
1. - - - -
2. - - - -
B. BAHAN
1. - - - -
2. - - - -
C. ALAT
1. DUMP TRUCK 3-4 M3 jam 1.0000 85,663.03 85,663.03
2. - jam - - -
D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 85,663.03
E. OVERHEAD & PROFIT 10.0 % x D 8,566.30
F. HARGA SATUAN PEKERJAAN ( D + E ) 94,229.33
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-94
File : 89627764.xls.ms_office
URAIAN ANALISA HARGA SATUAN FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. : 9.5 PERKIRAAN VOL. PEK. : 140.00
JENIS PEKERJAAN : PEKERJAAN HARIAN TOTAL HARGA (Rp.) : 11,692,891.00
FLAT BED TRUCK 3-4 M3 % THD. BIAYA PROYEK : 0.04
SATUAN PEMBAYARAN : JAM (E11)
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. PEKERJA
1. - - - -
2. - - - -
B. BAHAN
1. - - - -
2. - - - -
C. ALAT
1. FLAT BED TRUCK 3-4 M3 jam 1.0000 75,927.86 75,927.86
2. - jam - - -
D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 75,927.86
E. OVERHEAD & PROFIT 10.0 % x D 7,592.79
F. HARGA SATUAN PEKERJAAN ( D + E ) 83,520.65
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-95
File : 89627764.xls.ms_office
URAIAN ANALISA HARGA SATUAN FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. : 9.6 PERKIRAAN VOL. PEK. : 70.00
JENIS PEKERJAAN : PEKERJAAN HARIAN TOTAL HARGA (Rp.) : 5,846,445.50
WATER TANKER 3000-4500 L. % THD. BIAYA PROYEK : 0.02
SATUAN PEMBAYARAN : JAM (E23)
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. PEKERJA
1. - - - -
2. - - - -
B. BAHAN
1. - - - -
2. - - - -
C. ALAT
1. WATER TANKER 3000-4500 L. jam 1.0000 75,927.86 75,927.86
2. - jam - - -
D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 75,927.86
E. OVERHEAD & PROFIT 10.0 % x D 7,592.79
F. HARGA SATUAN PEKERJAAN ( D + E ) 83,520.65
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-96
File : 89627764.xls.ms_office
URAIAN ANALISA HARGA SATUAN FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. : 9.7 PERKIRAAN VOL. PEK. : 70.00
JENIS PEKERJAAN : PEKERJAAN HARIAN TOTAL HARGA (Rp.) : 14,216,095.60
BULLDOZER 100-150 HP % THD. BIAYA PROYEK : 0.05
SATUAN PEMBAYARAN : JAM (E04)
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. PEKERJA
1. - - - -
2. - - - -
B. BAHAN
1. - - - -
2. - - - -
C. ALAT
1. BULLDOZER 100-150 HP jam 1.0000 184,624.62 184,624.62
2. - jam - - -
D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 184,624.62
E. OVERHEAD & PROFIT 10.0 % x D 18,462.46
F. HARGA SATUAN PEKERJAAN ( D + E ) 203,087.08
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-97
File : 89627764.xls.ms_office
URAIAN ANALISA HARGA SATUAN FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. : 9.8 PERKIRAAN VOL. PEK. : 70.00
JENIS PEKERJAAN : PEKERJAAN HARIAN TOTAL HARGA (Rp.) : 11,105,765.30
MOTOR GRADER >100 HP % THD. BIAYA PROYEK : 0.04
SATUAN PEMBAYARAN : JAM (E13)
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. PEKERJA
1. - - - -
2. - - - -
B. BAHAN
1. - - - -
2. - - - -
C. ALAT
1. MOTOR GRADER >100 HP jam 1.0000 144,230.72 144,230.72
2. - jam - - -
D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 144,230.72
E. OVERHEAD & PROFIT 10.0 % x D 14,423.07
F. HARGA SATUAN PEKERJAAN ( D + E ) 158,653.79
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-98
File : 89627764.xls.ms_office
URAIAN ANALISA HARGA SATUAN FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. : 9.9 PERKIRAAN VOL. PEK. : 70.00
JENIS PEKERJAAN : PEKERJAAN HARIAN TOTAL HARGA (Rp.) : 10,690,556.06
WHEEL LOADER 1.0-1.6 M3 % THD. BIAYA PROYEK : 0.04
SATUAN PEMBAYARAN : JAM (E15)
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. PEKERJA
1. - - - -
2. - - - -
B. BAHAN
1. - - - -
2. - - - -
C. ALAT
1. WHEEL LOADER 1.0-1.6 M3 jam 1.0000 138,838.39 138,838.39
2. - jam - - -
D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 138,838.39
E. OVERHEAD & PROFIT 10.0 % x D 13,883.84
F. HARGA SATUAN PEKERJAAN ( D + E ) 152,722.23
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-99
File : 89627764.xls.ms_office
URAIAN ANALISA HARGA SATUAN FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. : 9.10 PERKIRAAN VOL. PEK. : 70.00
JENIS PEKERJAAN : PEKERJAAN HARIAN TOTAL HARGA (Rp.) : 11,597,658.10
TRACK LOADER 75-100 HP % THD. BIAYA PROYEK : 0.04
SATUAN PEMBAYARAN : JAM (E14)
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. PEKERJA
1. - - - -
2. - - - -
B. BAHAN
1. - - - -
2. - - - -
C. ALAT
1. TRACK LOADER 75-100 HP jam 1.0000 150,618.94 150,618.94
2. - jam - - -
D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 150,618.94
E. OVERHEAD & PROFIT 10.0 % x D 15,061.89
F. HARGA SATUAN PEKERJAAN ( D + E ) 165,680.83
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-910
File : 89627764.xls.ms_office
URAIAN ANALISA HARGA SATUAN FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. : 9.11 PERKIRAAN VOL. PEK. : 70.00
JENIS PEKERJAAN : PEKERJAAN HARIAN TOTAL HARGA (Rp.) : 11,186,189.00
EXCAVATOR 80-140 HP % THD. BIAYA PROYEK : 0.04
SATUAN PEMBAYARAN : JAM (E10)
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. PEKERJA
1. - - - -
2. - - - -
B. BAHAN
1. - - - -
2. - - - -
C. ALAT
1. EXCAVATOR 80-140 HP jam 1.0000 145,275.19 145,275.19
2. - jam - - -
D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 145,275.19
E. OVERHEAD & PROFIT 10.0 % x D 14,527.52
F. HARGA SATUAN PEKERJAAN ( D + E ) 159,802.70
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-911
File : 89627764.xls.ms_office
URAIAN ANALISA HARGA SATUAN FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. : 9.12 PERKIRAAN VOL. PEK. : 70.00
JENIS PEKERJAAN : PEKERJAAN HARIAN TOTAL HARGA (Rp.) : 17,604,479.20
CRANE 10-15 TON % THD. BIAYA PROYEK : 0.06
SATUAN PEMBAYARAN : JAM (E07)
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. PEKERJA
1. - - - -
2. - - - -
B. BAHAN
1. - - - -
2. - - - -
C. ALAT
1. CRANE 10-15 TON jam 1.0000 228,629.60 228,629.60
2. - jam - - -
D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 228,629.60
E. OVERHEAD & PROFIT 10.0 % x D 22,862.96
F. HARGA SATUAN PEKERJAAN ( D + E ) 251,492.56
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-912
File : 89627764.xls.ms_office
URAIAN ANALISA HARGA SATUAN FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. : 9.13 PERKIRAAN VOL. PEK. : 70.00
JENIS PEKERJAAN : PEKERJAAN HARIAN TOTAL HARGA (Rp.) : 4,893,833.00
STEEL WHEEL ROLLER 6-9 T. % THD. BIAYA PROYEK : 0.02
SATUAN PEMBAYARAN : JAM (E16)
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. PEKERJA
1. - - - -
2. - - - -
B. BAHAN
1. - - - -
2. - - - -
C. ALAT
1. STEEL WHEEL ROLLER 6-9 T. jam 1.0000 63,556.28 63,556.28
2. - jam - - -
D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 63,556.28
E. OVERHEAD & PROFIT 10.0 % x D 6,355.63
F. HARGA SATUAN PEKERJAAN ( D + E ) 69,911.90
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-913
File : 89627764.xls.ms_office
URAIAN ANALISA HARGA SATUAN FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. : 9.14 PERKIRAAN VOL. PEK. : 70.00
JENIS PEKERJAAN : PEKERJAAN HARIAN TOTAL HARGA (Rp.) : 5,940,922.40
VIBRATORY ROLLER 5-8 T. % THD. BIAYA PROYEK : 0.02
SATUAN PEMBAYARAN : JAM (E19)
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. PEKERJA
1. - - - -
2. - - - -
B. BAHAN
1. - - - -
2. - - - -
C. ALAT
1. VIBRATORY ROLLER 5-8 T. jam 1.0000 77,154.83 77,154.83
2. - jam - - -
D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 77,154.83
E. OVERHEAD & PROFIT 10.0 % x D 7,715.48
F. HARGA SATUAN PEKERJAAN ( D + E ) 84,870.32
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-914
File : 89627764.xls.ms_office
URAIAN ANALISA HARGA SATUAN FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. : 9.15 PERKIRAAN VOL. PEK. : 70.00
JENIS PEKERJAAN : PEKERJAAN HARIAN TOTAL HARGA (Rp.) : 1,070,276.20
VIBRATORY COMPACTOR % THD. BIAYA PROYEK : 0.00
SATUAN PEMBAYARAN : JAM (E25)
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. PEKERJA
1. - - - -
2. - - - -
B. BAHAN
1. - - - -
2. - - - -
C. ALAT
1. VIBRATORY COMPACTOR jam 1.0000 13,899.69 13,899.69
2. - jam - - -
D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 13,899.69
E. OVERHEAD & PROFIT 10.0 % x D 1,389.97
F. HARGA SATUAN PEKERJAAN ( D + E ) 15,289.66
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-915
File : 89627764.xls.ms_office
URAIAN ANALISA HARGA SATUAN FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. : 9.16 PERKIRAAN VOL. PEK. : 70.00
JENIS PEKERJAAN : PEKERJAAN HARIAN TOTAL HARGA (Rp.) : 5,562,781.70
TIRE ROLLER 8-10 T. % THD. BIAYA PROYEK : 0.02
SATUAN PEMBAYARAN : JAM (E18)
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. PEKERJA
1. - - - -
2. - - - -
B. BAHAN
1. - - - -
2. - - - -
C. ALAT
1. TIRE ROLLER 8-10 T. jam 1.0000 72,243.92 72,243.92
2. - jam - - -
D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 72,243.92
E. OVERHEAD & PROFIT 10.0 % x D 7,224.39
F. HARGA SATUAN PEKERJAAN ( D + E ) 79,468.31
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-916
File : 89627764.xls.ms_office
URAIAN ANALISA HARGA SATUAN FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. : 9.17 PERKIRAAN VOL. PEK. : 49.00
JENIS PEKERJAAN : PEKERJAAN HARIAN TOTAL HARGA (Rp.) : 2,647,134.35
COMPRESSOR 4000-6500 L\M % THD. BIAYA PROYEK : 0.01
SATUAN PEMBAYARAN : JAM (E05)
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. PEKERJA
1. - - - -
2. - - - -
B. BAHAN
1. - - - -
2. - - - -
C. ALAT
1. COMPRESSOR 4000-6500 L\M jam 1.0000 49,111.95 49,111.95
2. - jam - - -
D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 49,111.95
E. OVERHEAD & PROFIT 10.0 % x D 4,911.20
F. HARGA SATUAN PEKERJAAN ( D + E ) 54,023.15
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-917
File : 89627764.xls.ms_office
URAIAN ANALISA HARGA SATUAN FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. : 9.18 PERKIRAAN VOL. PEK. : 49.00
JENIS PEKERJAAN : PEKERJAAN HARIAN TOTAL HARGA (Rp.) : 2,273,701.92
CONCRETE MIXER 0.3-0.6 M3 % THD. BIAYA PROYEK : 0.01
SATUAN PEMBAYARAN : JAM (E06)
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. PEKERJA
1. - - - -
2. - - - -
B. BAHAN
1. - - - -
2. - - - -
C. ALAT
1. CONCRETE MIXER 0.3-0.6 M3 jam 1.0000 42,183.71 42,183.71
2. - jam - - -
D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 42,183.71
E. OVERHEAD & PROFIT 10.0 % x D 4,218.37
F. HARGA SATUAN PEKERJAAN ( D + E ) 46,402.08
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-918
File : 89627764.xls.ms_office
URAIAN ANALISA HARGA SATUAN FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. : 9.19 PERKIRAAN VOL. PEK. : 49.00
JENIS PEKERJAAN : PEKERJAAN HARIAN TOTAL HARGA (Rp.) : 778,842.26
WATER PUMP 70-100 mm % THD. BIAYA PROYEK : 0.00
SATUAN PEMBAYARAN : JAM (E22)
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. PEKERJA
1. - - - -
2. - - - -
B. BAHAN
1. - - - -
2. - - - -
C. ALAT
1. WATER PUMP 70-100 mm jam 1.0000 14,449.77 14,449.77
2. - jam - - -
D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 14,449.77
E. OVERHEAD & PROFIT 10.0 % x D 1,444.98
F. HARGA SATUAN PEKERJAAN ( D + E ) 15,894.74
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-919
File : 89627764.xls.ms_office
URAIAN ANALISA HARGA SATUAN FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO. : 9.20 PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : PEKERJAAN HARIAN TOTAL HARGA (Rp.) : 778,842.26
JACK HAMMER % THD. BIAYA PROYEK : 0.00
SATUAN PEMBAYARAN : JAM E26
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. PEKERJA
1. - - - -
2. - - - -
B. BAHAN
1. - - - -
2. - - - -
C. ALAT
1. JACK HAMMER jam 1.0000 23,155.55 23,155.55
2. - jam - - -
D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 23,155.55
E. OVERHEAD & PROFIT 10.0 % x D 2,315.55
F. HARGA SATUAN PEKERJAAN ( D + E ) 25,471.10
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-920
File : 89627764.xls.ms_office