You are on page 1of 1

Sr. No.

Item Quantity Unit Rate


Amount
(Rs Lakh)
1 Foundation Excavation
(a) Excavation overburden 469
m
3
99.00 0.46
(b) Excavation in hard rock 0
m
3
286.00 0.00
2
Concrete in foundation, abutments
(M15 with 40 MSA)
727.5
m
3
2618.00 19.05
3 Concrete M20 in deck slab 161
m
3
3284.00 5.29
4 Reinforcement steel 18.5 MT 39092.00 7.23
5 Structural steel in trusses 87 MT 43280.00 37.65
6 Wearing coat concrete (M25) 244
m
3
3716.00 9.07
7 Reinforcement for wearing coat 1.22 MT 39092.00 0.48
8 Bearings 4 no 17550 0.70
9 Hand railings 150 RM 639.00 0.96
Sub Total 80.89
Cost after due escalation 84.45
10
Launching of truss at site@ 25%
cost of steel
Lump Sum 9.83
11 Architectural treatment Lump Sum 2.00
12
De-watering charges including
connected operations of laying
pipelines, providing pumps etc. @
3% of cost of Bridge.
Lump Sum 2.53
14
Add 2% for W.C. Establishment
(excluding lump sum provision)
1.69
15
Add 3% for contingencies
(excluding lump sum provision)
2.53
Total Cost (Rs. Lakh) 103.03
TABLE 20
COST ESTIMATE
STEEL APPROACH BRIDGE ON DHAWLIGANGA RIVER (50m single span)