PROCEDURES MANUAL FOR


CUSTOMER SERVICES

September 2012

Page 1

Town Planning Sector


Construction Permit Division

4------------------------------------------------------------------------------------------------------------
5--------------------------------------------------------------------------------------------
5-----------------------------------------------------------------------------------
7---------------------------------------------------------------------------------
9------------------------------------------------------------------------------
11 ---------------------------------------------------------------------
11 -------------------------------------------------------------------------------------
15 ------------------------------------------------------------------
17 --------------------------------------------------------------------
19 --------------------------------------------------------------------------
11 ------------------------------------------------------------------------------------------
11 --------------------------------------------------------------
15 ---------------------------------------------------------------
15 -------------------------------------------------------
17 ------------------------------------------------------------------
41 ----------------------------------------------------------------------------------------------------
( ) 41 ------------------------------------------------------------
41 ---------------------------------------------------------------------------------
45 ----------------------------------------------------------------------------------
47 -------------------------------------------------------------------------
49 ----------------------------------------------------------------------------------------
51 -----------------------------------------------------------------------------
51 --------------------------------------------------------------
55 ------------------------------------------------------------------------------------------

Page 2

Town Planning Sector


Construction Permit Division

55 -------------------------------------------------------------------------------------------------------
55 --------------------------------------------------------- Building Permit Application Flow Chart
56 ------------------------------------------------------------------------- Permit Issuance Checklist
55 ------------------------------------------------------------------------------ General Requirements
71 ------------------------------------------------------- Architectural Submission Requirements
51 ----------------------------------------------------------- Structural Submission Requirements
94 --------- Building Permit Application Form 1 New & Under-Construction Buildings
97 ----------------------------------- Building Permit Application Form 2 Existing Buildings
166 -- Quarterly Site Progress Report Form 3 New & Under-Construction Buildings

Page 3

Town Planning Sector


Construction Permit Division

0202
,

( )%02


0200 .. -:
.0
.
.0 .
.0 .
.0
.
.5
.
.6
.

Page 4

Town Planning Sector


Construction Permit Division

Building Permit Request


/
.





NOC

Page 5

Required Documents

Document

Page 6

Required Documents

Original Temporary permit in center


()
municipality
Original description letter from
()
consultant
Original letter from consultant
()
Contractor license copy
( )
Consultant license copy
( )
NOC on the System
( )NOC
New investigation certificate 15 days
51
validity
)Soil Test report (original
()
User name contractor

2 set architect + 2 set structural drawing
+ 2 2 ()
with original documents
/ / ()
Labor residence Contract in the ICAD

Rents Clearance in case of Industrial or
( )
Private facilities
Letter from Municipality Center that
found Permanent fence or do
( )
Temporary fence in case of additions
For issue Commercial license the additional documents required:
:
:
DOT Approval
DOT
UPC Approval

Renewal Permit Request


Page 7



Required Documents
X

Assignment order from the owner


Original letter from consultant by supervise,
design , and contractor execution
Copy from previous permit license
Contractor license
Consultant license
Investigation certificate (residential/commercial)
not for industrial and Private facilities
Review with Inspection section to bring a report
User name contractor
Fees Payment Receipt (fees as per renewal
permit type)
Labor residence Contract in the ICAD
In case change the contractor required the following Approval:
Health and Safety, and Roads Department
Pay new insurance and fees as per building type




( )
) (
) (



:

Page 8

Required Documents

Document

Permit Building Demolition Request




.




NOC

Page 9




( )

Page 10

Document
Recently Land Architect
Recently Research Certificate
Owner Request
Contractor license copy
Labor residence Contract in the ICAD

Required Documents

Required Documents

Permit Request



CRM
CDP

NOC

Page 11

Page 12

Document
Copy of UPD Approval

Owner Request

Labor residence Contract in the ICAD

New Site Plan

Required Documents

Required Documents

Registration Certificate

Contractor Commercial License

Permission Permit Request


Page 13

Page 14

Document

For Night Work Permission the following documents required:


Contractor Request
Permit License
External umbrellas license the following approval required:
Landlord Approval
New Site Plan
Copy from Passport or Emirates ID

Required Documents

Required Documents

Extract Approved DWG



( / /)
.

Page 15

()

Page 16

Document
Request from Owner

Or Owner Assignment letter to Consultant

Or Construction License for Contractor

Required Documents

Required Documents

Drawing Approval




CDP

Page 17

Required Documents

Document

Original Structural DWG

Consultant Commercial License

Contractor Commercial License

Page 18

In addition to the all attachments which submit


with DWG

Required Documents

Original Architectural DWG

Drawing Stamp in the archive

Page 19

Required Documents

Document

Original Structural DWG 2 copies

Page 20

Original License

Contractor Commercial License

In addition to the all attachments which submit


with DWG

Required Documents

Original Architectural DWG 2 copies

Architectural Drawing Approval Process


/
.

Page 21

Architectural Drawing Approval Documents

Required Documents

Document

-:

Required Documents

- 1
-:
( )layout



.
. . . .
.
.
.
- 2


.
3

.
0
.

-:
5

-:
( )layout

( )

Page 22

2
3
0


.

.
.
.

(.)PDF


.

.

-:
5

2
3

-:
( )layout

( )

.
.
.
.
.

(.)PDF


.




.

.

Page 23

( )PDF (.)jpg

(.)DWF

-:

( )Version

( ,)Version
.

-:

] [

-:

-:
o

( : - - ,,,,,, - )

-:

Page 24

Structural Drawing Approval Process


/
.

Page 25

Structural Drawing Approval Documents

Required Documents

Document

Page 26

Required Documents


3
( ) .
4-6
3

:




(



)
(
)





(
)

Required Documents

:






(



)
(
)








(
)
Wind Tunnel


3 .
:

:
o
o
o
o

o
o
o

Page 27





(



)
(
)

o
o
o
o
o




(
)

: ()
o
o
o
o

o
o
o
o
o
o
o
o
o
o





(



)
(
)




(
)...


(
)

Page 28

( )
( 4 )

Approved Foundation drawing


Soil Investigation report
) Piles design report ( 4- copies
Piles layout plan stamped by consultant


( 1 )

)Casting Permission forms (5-copies


Letter from consultant

Requirements For Piling Test


Results Approval
Testing results Format 3 original copies
Valid Building Permit
Copy of the approved pile design
Piles layout showing the tested piles
and approved testing dates

( )

)Load test results report ( 1 copy

( )

)Integrity test results report (1 copy

( )

)Dynamic test results report (If any


28-days Cubes test results report

( 22 )

The original reading site sheet

All documents mentioned above must

be signed and stamped by the Report


issuance firm, Consultant and
Contractor

Page 29

Required Documents

Valid Building Permit

Required Documents

Requirements for Piles design


submittal

Requirements for Piles


design submittal

Valid Building Permit

Piles layout showing the piles


proposed to be tested

( 7 )

7 days cubs tests results report

Copy of the approved piles design

Required Documents

Letter from consultant

Integrity Testing

%511
%2 %5

2
Static Load Test on Working pile

In case Using Dynamic Load Test


3

)Dynamic Load Test on Working pile (If Required

)Sonic Coring (If Required by Consultant

%1

( )3
( )4 .

Page 30

.................................................................................................................

........................... :

........................................

...........................................

..............................................
:

..............................................

-:

...................... :

..................

Page 31

20
.........................:

..................................................:

...........................:

...............................................................:

...............................................................:

.............................................................:

..........................................................:
.....................................:

...............................:

.................................:

............................:
............................................:

-1
)(Static
)(Dynamic
-2

:
):(Load Test
.................:
................:

................................................:

)(Integrity Test
:

-3

......................................................:

................................

):(Sonic Coring Test


..................:

-4

.........................................................................:

28
:

...........................................................

:
.........................:
............................................................................................................................................:
............................................................................................................................................................

:
............................................................................................................................................:
............................................................................................................................................................

Page 32


-5

-2

-3

-4

22

-5

-6

-7

) (Integrity Test

-8

-9

( )

:
-5

-2

-3

Page 33

:
.5
.2
.3
.4
.1
.6
.7
.2

PDF
DWF
5:511 5:21 5:21 5:211 5:211





:
.5
.2
.3
.4
.1





" "

( )

Page 34

MEP Drawing Approval Process


/
.

Page 35

MEP Drawing Approval Documents

Document
MEP Drawings Approval Request

Original Approved Site Plan

Original Approved Architectural Drawings

Original Approved MEP Drawing

Page 36

Required Documents

Required Documents

Estidama Drawing Approval Process


/
.

Page 37

Estidama Approval Documents

Required
Documents

Document

Page 38

Required Documents




( )
( )
:
.0
CDP.
.0
.
.0

.
.0




.
.5 U-Value
.
.6


.U-Value
.7
U-
.Value
.8
K
Values .
.9
.
.02 Water
calculator .
.00
.
.00



( )
.00

( )


9
75222 0

0222
( ).
:
.0

.
.0
.
.0

:
.0
.0 /

.

:
.0
.0
.0
.0
.5
.6
.7
.8
.9
.02 .
.


:
.0
.0
.0

Page 39


:
.0
.0
.0

.0



0
/

52 0 5

05



.

:
.0
.0
.0
.

CDP
Estidama Zip Folder

Page 40

( )


.

.
( )
.
.


- 4


()7-1



,

.

- 1



.

- 3








,

- 6




) (FM.01



( )

Page 41

-2


).(CDP

- 5
)


CDP

- 7


- 8
) (FM.01





- 51
) (FM.01 -

- 9


( )0
.

Required Documents

Document

) - (FM.01
) - (FM.02
) - (FM.03
) - (FM.04
) (FM.05
) -(FM.06

:
-0
-0
-0
-0
-5
-6
-7
-8

https://cdp001.dma.ae/cdpabudhabi/cdppublicportal/

( + + + + )
GIS

( ) +

Page 42

Required Documents

Document




.

.

- 4




(
%511
FM.07

( )FM.08

- 3




( )2.

-2


- 5



( )%21

- 5


- 3



- 2
.

- 4 ()

Page 43

Document

Required Documents


( . ) ( 6
)

[ (])FM.01

( )

) - (FM.01
) - (FM.07
) - (FM.08

:





( )

Page 44

Required Documents

Document




.



- 3



( )2





( - )FM.09

)(CDP

-2



()2

- 5




( )FM.10 (
)

Page 45


%022
( - )FM.08

( )

Required Documents

Document

) - (FM.08
) - (FM.09
) - (FM.10

Page 46

Required Documents

Document



()

.


:


- 4



)(CDP
)(FM11

- 3






,

-2


).(CDP

- 5
)

(
( ( CDP


- 1
( )FM 11


Page 47

Required
Documents

Document

) (FM11

Page 48

Required
Documents

Document





/ /


.

- 4


( )1

1
/


Page 49

- 3



( )FM.13 ,

-2




(
)

- 5

.


Required
Documents

Document

( )

( )FM.01 (
)

Required
Documents

Document

( -)FM.01
( -)FM.13 .

Page 50




( )




4


)- (FM.14

- 3




.


.

-2









- 5


) (CDP

Page 51

Required Documents

Document

Required Documents

Document

) - (FM.14

Page 52





.


.

- 4

( )Hard copy

(
)

1


.

Page 53

- 3


( - )FM.12 ,

.

-2

.



.

- 5


Required
Documents

Document

( )FM.12

Page 54

Required
Documents

Document


INT - 01
1
FC 01
2
PI 01
3
GR 01
4
ARCH 01
5
STR 01
6
MEP 01
7
DPPS-Form 1
8
DPPS-Form 2
9
DPPS-Form 3
10

Page 55


Rev 0 -1/7/12
Rev 0 -1/7/12
Rev 0 -1/7/12
Rev 0 -1/7/12
Rev 0 -1/7/12
Rev 0 -1/7/12
Rev 0 -1/7/12
Rev 0 -1/7/12
Rev 0 -1/7/12
Rev 0 -1/7/12

1-7-2012
1

Title
Date

INT 01
-

Document No.
Revision No.


) (DPPS
.
,

.

.
1


.
.

www.adm.gov.ae
1
. www.adm.gov.ae
(Go to Service Directory/View by Section/Town Planning
Sector/Construction Permits Division and click on the respective permit
types for the service explanation & administrative requirements).
-:
Chapter FC-01 :. )a .
Chapter PI-01 : )b ( )A4
()CDP
.
Chapter GR-01 : )c

Page 56

4

.

()DPSS


.

Page 57



Building Permit Application Flow Chart

Building Permit Application Flow Chart


1-7-2012

Title
Date

FC 01
-

Document No.
Revision No.

0

): (CDP
)a
)b
)c
)d
)e
)f
)g
)h
)i
)j

.


.
.
.
.
0 & 0 .

.

.

.

Page 58



Consultant-of-Record/Applicant
/-

NT-01 &FC-

Online Project Registration via CDP


Refer Doc.PI-01

)(Use Building Permit Application Form 1

)(Use Building Permit Application Form 1


)(Refer *Checklist for Permit Application


pdf

Refer Doc.GR-01

Refer Doc.ARCH-01/STR-01/MEP-01

dwf / dwg

/

)(1 to 2 working days


)(1 to 2 working days


Page 59


) (to be completed at Customer Service Counter, Central Atrium

)( to be completed at Archive Office, Entrance 10


12
9



Permit Issuance Checklist

Permit Issuance Checklist


1-7-2012

Title
Date

PI 01
-

Document No.
Revision No.

.0.


/
.
.0


0 0

()



()
/
()

(
)

Page 60



... )


/
()








11

12
13
14
15
16

17

18

10

19
20
21



0 0 8 9
.



Page 61



.0

-
-

(
)
/ /
(
/ )
)


( /)


/ / /

:
/ /
/

Page 62

Item

Description

Building Permit
Application Form
2 (original)*

ADM Town
Planning
Affection Site
Plan (original)*

Master Developer
Affection Site
Plan (original)*

Developers Own
ers NOC Letter
for proposed fitout works
(original)*

To be
uploaded
upon
project
registratio
n by

Remarks

Applicant

All Parties as
appeared in the
form.

ADM
reviewer/projec
t coordinator
will sign before
Applicant
uploads.

Applicant

Abu Dhabi
Municipality

6 months
validity.

Applicant

Master
Developer &
Infrastructure
Planner

Applicant

Developers Own
ers Appointment
Applicant
Letter for 3rd party
(original)*
Applicants valid
Applicant
Trade License

To be signed
/stamped by :

Developer/Owne
r or other
appointed 3rd
party

Letter shall
clearly state
the tenanted
unit/store no.
and intended
usage as per
approved
building
plan(s). And
shall be
supported by a
key plan
showing its
location. If 3rd
party is
appointed, item
5 shall be
submitted.

Developer/Owne
r
Issuing
Authority
Page 63

10

11

12

13

(copy)
Applicants Letter
for the design
and supervision
liability (original)*
Consultant-ofRecord
Registration
Certificate (copy)
Owners Tenants
Appointment
Letter for fit-out
contractor
(original)*
Fit-out
contractors valid
Trade License
(copy)
Fit-out
contractors
username
Building
Completion
Certificate (copy)
Other
special/supportin
g approvals from
external
agencies-if any
(copy)

Applicant

Abu Dhabi Civil


Defense

Consultant
-of-Record

Issuing
Authority

Applicant

Owner/Tenant

Contractor

Issuing
Authority

Contractor

Applicant

Applicant

Applicant can
make the fitout application
but no fit-out
permit will be
issued without
the
contractors
documents and
information

Abu Dhabi
Municipality

Issuing
Authority/Agenc
y

Required if
warranted by
external
agencies (case
by case
evaluation)



9 8 0 0
.



.

Page 64



General Requirements
General Requirements
1-7-2012

Title
Date

GR 01
-

Document No.
Revision No.

.0


.0 .


.


.

.


:
.
.
.
.0
A3

.
/ /

:










()

Page 65




MEP Meh 01-elect 01- plamb-01
.

.0
:
0.0
A2,A1 & A0 .
.
0.0

:
1:10,000
1:500, 1:1,000
1:100, 1:200
1:10, 1:20, 1:50
1:50

Key Plan / Reference Plan


Site Plan / Setting-out Plan
Plans / Sections / Elevations
Design details
Door, window elevations & schedules

0.0
0

,
.
0.0.0 :
:
.
: :

.

.
(.)datum


Page 66




.

/


/










0-0 .

:
A. International Building Code IBC 2009 edition published by the
)International Code Council (www.iccsafe.org
B. User Guide for the International Building Code in the Emirates of Abu
Dhabi published by the Department of Municipal Affairs Abu Dhabi
)(http://abudhabibuildingcodes.ae/
C. American National Standard on Accessible and Usable Building and
Facilities -ICC/ANSI A117.1-2003 edition published by the
International Code Council.
D. Uniform Plumbing Code of Abu Dhabi Emirate published by
)Environmental Agency Abu Dhabi. (www.ead.ae/en/library/

Page 67

;E. Other standards and reference from accredited institutions/societies


)i. British Standards Institution BSI (latest edition
)ii. American Concrete Institute ACI (latest edition
iii. American Institute of Steel Construction AISC (latest edition) for
structural steel works.
iv. Urban Building Code for Seismic Design UBC for seismic design.
v. American Society for Testing and Materials ASTM
vi. American Society of Mechanical Engineers ASME
vii. American Society of Heating, Refrigerating and Air-Conditioning
Engineers handbook- ASHRAE
5.0
.
:

/



.

:0 :
( 0 + + 02 + )
0 ,
02/ 0 .
( 0 ):
( ) c10
02 .
( 0 ):
( 5 + 0+ 05+ )
05 05 0
5 02 0
.
0 6 :
( 0 + 02 + 6) 0
( 02 022 )
( 02 052 ) -
SB10 5
.
Page 68



( 5 ) ( )
022 5
RS10
( 05 ) ( 07 :
) .
.0.5.0
:0 ( )
( 0 + + 02 + )
0 02
0 .
0.5.0 :
0 ( )
0
C10 02 .
0.5.0


C10 02 .
5.5.0

SB 01 0
.
6.5.0
00 0
- 082.0

Page 69

6.0
:
: 0.6.0
A.
B.
C.
D.
E.
F.
G.
H.

Drawing List
Site Plan / Landscape Plan
Floor Plans
Elevations
Sections
Details
Code Analysis Drawings
Gross Floor Area Drawings

A001 (0 series ie. 01-09)


A010 (10 series ie. 10-99)
A100 (100 series ie. 100-199)
A200 (200 series ie. 200-299)
A300 (300 series ie. 300-399)
A400 (400 series ie. 400-499)
A500 (500 series ie. 500-599)
A600 (600 series ie. 600-699)

022
.)A 1001- A1999 (
. : 0.6.0
. : 0.6.0
. : 0.6.0
:
A.
B.
C.
D.
E.
F.
G.
H.
I.
J.

Drawing List
Site Plan/Affection Plan
Floor Plans (Water Supply)
Floor Plans (Foul Drainage)
Floor Plans (Storm Drainage)
Riser Diagrams (Water Supply)
Riser Diagrams (Foul Drainage)
Riser Diagrams (Storm Drainage)
Details and Cross-Sections
Calculation Sheets

- P001 (0 series ie. 01-09)


- P010 (10 series ie. 10-99)
- P100 (100 series ie. 100-199)
- P200 (200 series ie. 200-299)
- P300 (300 series ie. 300-399)
- P400 (400 series ie. 400-499)
- P500 (500 series ie. 500-599)
- P600 (600 series ie. 600-699)
- P700 (700 series ie. 700-799)
- P800 (800 series ie. 800-899)

Page 70

.5

-
-
.
A4
0

.
PDF

.
.
0
.

.


:
o
o
o ( )

/
.
, .

.

Page 71

Diagram 4 - Drawing Title Block


(CAD template can be provided upon request)

Page 72



Architectural Submission Requirements
Document
ARCH 01 Title Architectural Submission Requirements
No.

Revision No.
- Date
1-7-2012
.0

INT-01, section 3.0
:

FC-01 .


.
.

0.2

.
DWf
( )


.0


.

.


(
) .
.


(
)

Page 73



.
p1-01
( A4 ) .

(
) a.fouad@adm.abudhabi.ae .
.0
A1 A0 :
5
.
.
/

:


- .
.
.
.
02.222 :0
522 :0 0222 :0
( ).
(
.)..


.

.
.0 .

( - - -
) .
PL-01

Page 74






.


.
.5
( ).

.
/

:
o -
-
.
o .
o .
02.222 :0
522 :0 0222 :0
(
.
( ...

hard & soft :

0:52 ( )

022 :0 52 :0 0:02

( ....
.6 .

.

02 00
:
o
o .
Page 75

( )

.7




( )
.

.



.

:
.
o .
o



.
.8 .
/
.

.

.

Page 76


:
(
).
(
).
(
).
(
).
( ).


.
(
).

.
0.2
:




.
.
.



.

Page 77



Diagram 5A Project Record Sheet-1

Page 78



Diagram 5A Project Record Sheet-2

Page 79



Diagram 5B Drawing List

Page 80



Diagram 5C Project Data Analysis Sheet

Page 81



Diagram 5D Code Analysis Sheet

Structural Submission Requirements

Page 82



Document No.
Revision No.
1.0

STR 01
-

Title
Date

Structural Submission Requirements


1-7-2012

INTRODUCTION

This document outlines the general requirements applicable to all Structural submissions.
Structural submission can be broadly categorized into two main headings Substructure and
Superstructure.
This document provides clear guidelines to enable the applicant to lodge the appropriate
submittals.
2.0

CONTENT
2.1

2.2

Substructure
2.1.1 Geotechnical Report
2.1.2 Information to be shown on Drawings
2.1.2.1
Shoring
2.1.2.2
Marine Works
2.1.2.3
Shallow Foundation
2.1.2.4
Deep Foundation (piles)
2.1.3 Calculations
2.1.3.1
Load Calculation
2.1.3.1.1 Gravity Load
2.1.3.1.2 Lateral Load
2.1.3.1.3 Earthquake Loads
2.1.3.1.4 Thermal Loads
Superstructure
2.2.1 General Requirements
2.2.1.1
Concrete Building
2.2.2 Design Checklist
2.2.3 Additional Foundation Requirements
2.2.4 Additional Vertical Element Requirements
2.2.5 Additional Horizontal Element Requirements

Page 83



2.1

SUBSTRUCTURE

2.1.1

GEOTECHNICAL REPORT
Detailed geotechnical investigation reports shall be submitted with the structural
drawings for every project by the consultant shall ensure that the required amount of
boreholes are carried out to the required depth by the geotechnical engineer, to the
requirements of the nominated code of practice for site investigations .
Geotechnical investigation reports are to contain, but not be limited to, the following
information applicable:

Parameters for the geotechnical design of piles.


Assessment of geotechnical conditions of pile construction and installation.
Potential for ground heave, damage to adjacent structures or neighboring piles.
Vibration effects and potential for damage to adjacent structures.
Near surface conditions for lateral load design.
Spring stiffness of vertical and lateral soil (varying with depth) as required for design
purposes (for piles and rafts).
Allowable bearing capacity of the founding material.
Allowable shaft adhesion.
Recommendations for shallow foundation such bearing capacity, excavation depth,
cement type etc.
Short term and long term design parameters, in particular for retaining walls.
Allowable anchor restraint parameters for shoring design.
Potential for slope instability.
Potential for liquefaction and design requirements and/ or ground improvement
techniques to overcome the phenomenon.
Assessment of site conditions on pile durability ( sulphates, chlorides, PH in soil and
water ).
Groundwater level, dewatering requirements and possible affect on surrounding
buildings.
Earthquake ground classification factor in accordance to the requirements of the
uniform building code.
Excavation of soil and rock.
Porosity of the soil for possible concrete aggression.
Any other comments relevant to design and construction as may revealed by the
investigation and testing.
Subsequent to completion of soil investigation works and all necessary laboratory
testing, the consultant must submit documents certifying that:
All soil investigation works and laboratory works have been witnessed by a qualified
representative of the consultant.

Page 84



All works have been carried out in accordance with the nominated code of practice
for site investigations.
Proper equipment and tools, duly calibrated, have been used by qualified and
experienced personnel during all soil investigation and testing works, and that the
test results have been reviewed and approved by the consultant.
2.1.2

INFORMATION TO BE SHOWN ON DRAWINGS

2.1.2.1

SHORING
Drawing containing existing gnawed level, all deferent excavation level,
underground water table level.
All level referred to NADD.
Proposed dewatering system and the profile of predicted seepage water line.
Guarantee letter from shoring subcontractor.

2.1.2.2

MARINE WORKS
Sea water levels HAT, MAT, LAT..etc.
Existing ground level, final plate form level and final dredging level (NADD).
Type and thickness of bed protection.
Considered Wave height.
Considered Seismic category.
Considered Mooring and berthing loads.
Surcharge load.

2.1.2.3

SHALLOW FOUNDATION
Soil laboratory name and soil report reference number.
Excavation depth and bearing capacity.
Any special requirements recommended in the soil report.
columns load values for the most critical load combination (service)

2.1.2.4

DEEP FOUNDATION
Piling plan showing pile length, reinforcement, legend for pile capacity, pile
testing and cut-off levels etc.
Pile caps layout including column and shear wall location with dimensions.
Pile caps sections showing thickness, steel reinforcement and levels relative to
datum.
Structural framing (general arrangements) for all floors including column
locations, floating column location if any, slabs etc. including the load transfer
mechanism.
columns load values for the most critical load combination
piles reactions due to the most critical load combination (service)

2.1.3

CALCULATIONS

Page 85



2.1.3.1

LOAD CALCULATION
2.1.3.1.1
GRAVITY LOAD
Dead load: weight of material, equipment and land scaped roof (saturated soil)
should be calculated according to IBC 2009 chapter 16 or alternatively in
conformance with table C 3-1 and C 3-2 of ASCE 7.
Live loads: live load calculation will be in accordance with IBC 2009 chapter 16.
Adopted dead and live loads shell satisfy the recommendations of Abu Dhabi
Municipality.
2.1.3.1.2
LATERAL LOAD
Soil lateral load: soil load calculation in accordance with IBC 2009 table 1610.1.
Wind load :
1) Minimum design loads for building and other structures, including
supplement 1 & 2 ( ASCE 7-05)
2) Wind load shell be based on basic wind speed ( 3- second gust ) 26.8 m/
sec. 10 years return period and 38.0 m/ sec. 50 years return period.
3) Reliable wind tunnel test study reflecting climatic site condition where it
looks provision not applicable.
4) All buildings shall be designed to limit maximum drift under 10 years return
period wind speed to 1/500 of building height above ground.
5) All buildings shall be designed to resist 50 year return period wind load.
6) Adequate provisions shall be adopted to eliminate risk and damage to non
structure element due to story drift.
7) The maximum allowed story acceleration due to 10 year retune period wind
load shall be limited to 15 mg for residential and hotels and 20 mg for
offices towers.
2.1.3.1.3
EARTHQUAKE LOADS
Minimum design loads for buildings and the structure including supplements
1&2 ( ASCE 7-05)
Seismic loads shall be based on mapped spectral response accelerations Ss and
S1 issued by Abu Dhabi jurisdiction.
For the design of substructure purposes the structure response modification
coefficient (R shall be equal one= 1. 0)
2.1.3.1.4
THERMAL LOADS
For structures are to exposed to we other the members shall be designed for 25
a uniform temperature changes.
For structures are exposed to the atmosphere from the outside surface the
members shall he designed for 25 non uniform temperature.
Members provided with expansion joints at maximum distances 60 meters do
not need thermal effect study

Page 86

2.2

SUPERSTRUCTURE

2.2.1

GENERAL REQUIREMENTS
2.2.1.1

2.2.2

CONCRETE BUILDING
The design of concrete structural members will be based on IBC 2009
and relevant standards.
Structural design of all projects submitted to the municipality for
approval shell ensure that the work is carried out by licensed and
qualified consultant with structural engineers having the necessary
qualifications and experience .
Design philosophy, complete design criteria and full calculation and
analysis shell be submittal in soft and hard Copy format.
Consultant shall ensure that structure is economically designed (as
appropriate) and must ensure that design and details are buildable.

DESIGN CHECKLIST

Consultants submitting structural drawings for approval must ensure they have designed the
foundations and the superstructure in accordance with the following general checklist:
Fire Rating Requirements
Structural adequacy
Integrity
Insulation
Durability Requirements
Corrosion resistance
Chemical attack resistance
Crack control
Waterproofing
Loading Requirements
Dead loads
Live load ( including any pattern load and heavy load / compactus requirements )
Wind load
Earthquake loads
Earth pressures
Water pressures
Buoyancy loads
Ground movements and differential foundation settlements
Dynamic effects / vibration resonance loads
Thermal loads
Creep

Page 87

Moisture variation ( shrinkage and swelling )


Expansion loads
Axial shortening of columns
Pre-stress ( hyperstatic reactions )
Impact and breaking loads
Fatigue
Construction loads

Serviceability requirements
Deflections/sag ( including allowance long term creep and shrinkage effects )
Hogging ( especially for post tensioned beams and cantilever back spans )
Axial shortening / extension
Rotation due to torsional effects
Crack control ( minimum pre stress level for post tensioned concrete )
Allowance for articulation of masonry wall as required
Allowance for brittle finishes
Stability requirements
Overturning and uplift
Buoyancy
Sliding
Strength requirements
Flexural strength ( including minimum strength requirements )
Beam shear strength (including minimum strength requirements )
Punching shear strength
Torsional strength
Bearing strength
Anchor strength for post tensioned beams
Foundation strength
Pre stress levels within acceptable limits
Detailing requirements
Tendon placement priority over reinforcement
Tendon/ reinforcement clash at columns etc
Penetrations through slabs and beams
Set downs, steps and sloping surfaces

Page 88



2.2.3

ADDITIONAL FOUNDATION REQUIREMENTS

Buildings with basements require approval of all basement floor plans from the town planning
department of the buildings directorate and concerned service departments.
The submitted drawings shall clearly indicate the distance to the outer face of any permanent or
temporary training system. ( i.e. diaphragm walls, secant pile walls, contiguous pile walls etc. )
from the inner face of the basement walls.
Ground anchors supporting retaining systems for excavations, shall not extend into adjacent
plots into areas of highly concentrated utilities and service lines in all circumstances, clearances
shall be obtained from the relevant service departments.
Pile foundations together with shallow foundations shall not be permitted to support the same
superstructure, unless isolated.
Foundations calculations shall ( If required by the municipality ) address the design issues of
stability, durability and ultimate general requirements are:

Stability
Overturning and uplift
Buoyancy
Slope stability

Durability
Corrosion resistance
Chemical attack resistance
Crack control if required
Serviceability
Deflections/sag including allowance long term creep and shrinkage effects
Axial shortening ( in particular for piles )
Rotation of footings
Bearing stress
Ultimate
Punching shear
Beam shear
Flexural strength
Torsional strength
Anchor strength
*Geotechnical reports shall be submitted to the requirements of part 1, piling.

Page 89



2.2.4

ADDITIONAL VERTICAL ELEMENT REQUIREMENTS

Load calculation by tributary area method and moment shear factor method should
accompanied by plan drawings indicating the tributary areas. The use of software to calculate
column reactions is permitted, although should be accompanied by hand calculations using the
prior mentioned methods.
Calculations must show if columns are short or slender, according to the code provision.
All column design must be accompanied by moment interaction diagrams taking into account
slenderness effects.
Additional bending moments due to column beam/slab joints must be included in calculations,
including any secondary effects ( hyper static reactions ) from unbalanced post tensioning
reactions.
2.2.5

ADDITIONAL HORIZONTAL ELEMENT REQUIREMENTS

Edge beams around a radius and general torsionally loaded beams must allow for additional
longitudinal reinforcement and stirrups. All stirrups must be closed to ensure adequate
tensional resistance is achieved.
Slabs modeled using finite element method must clearly indicate all assumptions considered to
predict deflections, and must ensure that full moment connections are not modeled where they
can develop into pinned connections.
Transfer slabs must be limit deflections to span/1000 to ensure that elements and partitions on
above floors do not crack.
Include:
All plans and sections relevant to the project for all structural elements
Class and, where appropriate, grade designation of concrete
Exposure classification
Reference number and date of issue of applicable design standard
Fire rating (if not specified on architectural drawings)
Loading (superimposed dead load and live load to all slab plans and wind and
earthquake loads)
Grade and type of reinforcement and tendons
General notes
Concrete cover to reinforcement
The finish and method of control for unformed surfaces
Class of formwork for the surface finish
Curing procedure and duration
The force required in each tendon, the maximum jacking force to be applied and the
order in which the tenders are to be stressed
The location and details of planned construction or movement joints connections and
splices , and the method to be used for their protection

Page 90

The minimum period of time before stripping of forms and removal of shores
Any constraints on construction assumed in the design
Any special protective coatings
Characteristic compressive strength at 28 days
Characteristic flexural strength if required
Characteristic indirect tensile strength if required
Mean 7 days strength
Other early age strength
Slump of concrete
Cement type
Maximum aggregate size
Water/cement ratio
Maximum 56 day shrinkage
Density if required
Maximum water soluble acid(chloride ion) if required
Maximum sulphate concrete (SO3) if required
Temperature range at point of discharge if required
Testing requirements if required
Project assessment of concrete production if required

Page 91

Plumbing Submission
Requirements
1-7-2012

Title
Date

PLUMB
01
-

Document No.
Revision No.

.0.

:
.
.0


.
( )NOC
.
()

.
.
.0

:
( 022 :0
0:022 0:52
05:0
()






Page 92

.0 .


02 00 .

.

.5

:




5 7


.ADM

Page 93

Building Permit Application Form 1 New & Under-Construction Buildings

Municipality of Abu Dhabi City Town Planning Division


Building Permits Directorate Development Projects Section
Building Permit Application Form-1 For New and Under-Construction Project Only
1.0

General Project Information


Area
Name

Project Title

2.0

Plot(s)

Project Description

Site / Plot Area (sqm)

Sector

Site Coverage (%)

Total GFA (sqm)

Total GLA (sqm)

Detailed Project Information

Number of Building(s) within a Single Plot

Land Use

GFA (sqm)

GLA (sqm)

Building Height (m)

Phasing

Other Remarks

Sub-Plot No
Podium 1
Tower 1
Sub-Plot No
Podium 2
Tower 2

3.0

Applicants Information

Developers / Owners Name

Contact Details
Office / Mobile No.

Signature & Stamp

Page 94



Email Address
Consultants Name

Contact Details
Office / Mobile No.

Signature & Stamp

Email Address
Contractors Name

Contact Details
Office / Mobile No.

Signature & Stamp

Email Address

4.0

Type of Permit Application

(check the relevant boxes)

Land Reclamation

Foundation

*Modification (no permit issued if submit before BCC)

Land-Water Interface

Substructure (for phased permit)

*Addition (no permit issued if submit before BCC)

Excavation (includes open-cut)

Superstructure (for phased permit)

*Addition (no permit issued if submit before BCC)

Shoring (includes temporary shoring)

Full Building Permit

*Change of Use (no permit issued if submit before BCC)

Piling

Temporary Building Permit

Page 95

5.0

Municipal Official Use

Project ID
Building Officials

Project Coordinator

Architectural Reviewer

Structural Reviewer

Plan ID(s)
Signature

Date

Comments (if any)

Page 96



Building Permit Application Form 2 Existing Buildings

Municipality of Abu Dhabi City Town Planning Division


Building Permits Directorate Development Projects Section
Building Permit Application Form-2 For Existing Building(s) Only
6.0

General Project Information


Area
Name

Project Title

7.0

Plot(s)

Project Description

Site / Plot Area (sqm)

Sector

Site Coverage (%)

Total GFA (sqm)

Total GLA (sqm)

Detailed Project Information (for modification / addition / change of use permit application only)

Number of Building(s) within a Single Plot

Land Use

GFA (sqm)

GLA (sqm)

Building Height (m)

Other Remarks

Sub-Plot No
Podium 1
Tower 1
Sub-Plot No
Podium 2
Tower 2

Page 97

8.0

Detailed Fit-Out Information

Building Name / No.

Floor

Unit No.

Approved Occupancy

Fit-Out Description

9.0

Type of Permit Application

Modification

10.0

Addition

(check the relevant boxes)


Fit-Out

Change of Use

Applicants Information

Developers / Owners Name

Contact Details
Office / Mobile No.

Signature & Stamp

Email Address
Consultants Name

Contact Details
Office / Mobile No.

Signature & Stamp

Email Address
Contractors Name

Contact Details
Office / Mobile No.

Signature & Stamp

Email Address

Page 98

11.0

Municipal Official Use

Parent Project ID
Building Officials

Project Coordinator

Architectural Reviewer

Structural Reviewer

Project ID
Signature

Plan ID(s)
Date

Comments (if any)

Page 99



Quarterly Site Progress Report Form 3 New & Under-Construction Buildings

Municipality of Abu Dhabi City Town Planning Division


Building Permits Directorate Development Projects Section
Quarterly Site Progress Report Form-3 - For New and Under-Construction Project Only
1.0

General Project Information


Area
Name

Project Title

Sector

Project Description

ADM Project ID

Start Date

2.0

Building Permit Status (expand where necessary)

S/no

Permit ID

3.0

Technical Staff Information (expand where necessary)

Site Team

Supervising
Consultants
Company
Name

Plot(s)

Parent ID

Title

Permit Type

Name

Completion Date

Permit Status

Issue Date

Project Cost (AED)

Issued To

Contact

Email Address

Project Manager

Tel:

Mob:

Architect

Tel:

Mob:

Structural Engineer

Tel:

Mob:

Mechanical Engineer

Tel:

Mob:

Electrical Engineer

Tel:

Mob:

Plumbing Engineer

Tel:

Mob:

Page 100

Main
Contractors
Company
Name

4.0

Safety Officer

Tel:

Mob:

Project Manager

Tel:

Mob:

Construction Manager

Tel:

Mob:

Site Engineer

Tel:

Mob:

Safety Officer

Tel:

Mob:

Construction Status (check relevant boxes)


Not commenced

Shoring works

Block works & partition

Internal finishes works

Site mobilization & fencing

Piling works

Waterproofing works

External finishes works

Demolition works

Foundation works

Insulation works

External landscaping

Dewatering works

Columns/Cores casting

MEP works

Testing & commissioning

Excavation works

Slabs casting

Cladding works

5.0

Baseline Construction Schedule & Milestones (spreadsheet can be attached as annex separately)

6.0

Actual Construction Progress (spreadsheet can be attached as annex separately)

7.0

Cause for Delay (explained if any)

8.0

Construction Forecast for Next Quarter (spreadsheet can be attached as annex separately)

Page 101



9.0

Site Progress Photographs (expand where necessary)

Narrative
1

Picture 1

Narrative
2

Picture 2

Narrative
3

Picture 3

Narrative
4

Picture 4

Page 102



10.0

Construction Violation Record (provide details if any)

S/no

11.0

Violation Description

Issue Date

Issue To

Issue By

Corrected Date

Inspected By

Inspection Date

(dd/mm/yy)

(Contractors Name)

(Municipal Center)

(dd/mm/yy)

(Municipal Center)

(dd/mm/yy)

Municipal Official Use

Project ID
Building Officials
1

Project Coordinator

Architect

Structural Engineer

Mechanical Engineer

Electrical Engineer

Plumbing Engineer

Plan ID(s)
Signature

Date

Comments (if any)