Professional Documents
Culture Documents
September 2012
Page 1
4------------------------------------------------------------------------------------------------------------
5--------------------------------------------------------------------------------------------
5-----------------------------------------------------------------------------------
7---------------------------------------------------------------------------------
9------------------------------------------------------------------------------
11 ---------------------------------------------------------------------
11 -------------------------------------------------------------------------------------
15 ------------------------------------------------------------------
17 --------------------------------------------------------------------
19 --------------------------------------------------------------------------
11 ------------------------------------------------------------------------------------------
11 --------------------------------------------------------------
15 ---------------------------------------------------------------
15 -------------------------------------------------------
17 ------------------------------------------------------------------
41 ----------------------------------------------------------------------------------------------------
( ) 41 ------------------------------------------------------------
41 ---------------------------------------------------------------------------------
45 ----------------------------------------------------------------------------------
47 -------------------------------------------------------------------------
49 ----------------------------------------------------------------------------------------
51 -----------------------------------------------------------------------------
51 --------------------------------------------------------------
55 ------------------------------------------------------------------------------------------
Page 2
55 -------------------------------------------------------------------------------------------------------
55 --------------------------------------------------------- Building Permit Application Flow Chart
56 ------------------------------------------------------------------------- Permit Issuance Checklist
55 ------------------------------------------------------------------------------ General Requirements
71 ------------------------------------------------------- Architectural Submission Requirements
51 ----------------------------------------------------------- Structural Submission Requirements
94 --------- Building Permit Application Form 1 New & Under-Construction Buildings
97 ----------------------------------- Building Permit Application Form 2 Existing Buildings
166 -- Quarterly Site Progress Report Form 3 New & Under-Construction Buildings
Page 3
0202
,
( )%02
0200 .. -:
.0
.
.0 .
.0 .
.0
.
.5
.
.6
.
Page 4
/
.
NOC
Page 5
Required Documents
Document
Page 6
Required Documents
Page 7
Required Documents
X
( )
) (
) (
:
Page 8
Required Documents
Document
NOC
Page 9
( )
Page 10
Document
Recently Land Architect
Recently Research Certificate
Owner Request
Contractor license copy
Labor residence Contract in the ICAD
Required Documents
Required Documents
Permit Request
CRM
CDP
NOC
Page 11
Page 12
Document
Copy of UPD Approval
Owner Request
Required Documents
Required Documents
Registration Certificate
Page 13
Page 14
Document
Required Documents
Required Documents
( / /)
.
Page 15
()
Page 16
Document
Request from Owner
Required Documents
Required Documents
Drawing Approval
CDP
Page 17
Required Documents
Document
Page 18
Required Documents
Page 19
Required Documents
Document
Page 20
Original License
Required Documents
/
.
Page 21
Required Documents
Document
-:
Required Documents
- 1
-:
( )layout
.
. . . .
.
.
.
- 2
.
3
.
0
.
-:
5
-:
( )layout
( )
Page 22
2
3
0
.
.
.
.
(.)PDF
.
.
-:
5
2
3
-:
( )layout
( )
.
.
.
.
.
(.)PDF
.
.
.
Page 23
( )PDF (.)jpg
(.)DWF
-:
( )Version
( ,)Version
.
-:
] [
-:
-:
o
( : - - ,,,,,, - )
-:
Page 24
/
.
Page 25
Required Documents
Document
Page 26
Required Documents
3
( ) .
4-6
3
:
(
)
(
)
(
)
Required Documents
:
(
)
(
)
(
)
Wind Tunnel
3 .
:
:
o
o
o
o
o
o
o
Page 27
(
)
(
)
o
o
o
o
o
(
)
: ()
o
o
o
o
o
o
o
o
o
o
o
o
o
o
(
)
(
)
(
)...
(
)
Page 28
( )
( 4 )
( 1 )
( )
( )
( )
( 22 )
Page 29
Required Documents
Required Documents
( 7 )
Required Documents
Integrity Testing
%511
%2 %5
2
Static Load Test on Working pile
%1
( )3
( )4 .
Page 30
.................................................................................................................
........................... :
........................................
...........................................
..............................................
:
..............................................
-:
...................... :
..................
Page 31
20
.........................:
..................................................:
...........................:
...............................................................:
...............................................................:
.............................................................:
..........................................................:
.....................................:
...............................:
.................................:
............................:
............................................:
-1
)(Static
)(Dynamic
-2
:
):(Load Test
.................:
................:
................................................:
)(Integrity Test
:
-3
......................................................:
................................
-4
.........................................................................:
28
:
...........................................................
:
.........................:
............................................................................................................................................:
............................................................................................................................................................
:
............................................................................................................................................:
............................................................................................................................................................
Page 32
-5
-2
-3
-4
22
-5
-6
-7
) (Integrity Test
-8
-9
( )
:
-5
-2
-3
Page 33
:
.5
.2
.3
.4
.1
.6
.7
.2
PDF
DWF
5:511 5:21 5:21 5:211 5:211
:
.5
.2
.3
.4
.1
" "
( )
Page 34
/
.
Page 35
Document
MEP Drawings Approval Request
Page 36
Required Documents
Required Documents
/
.
Page 37
Required
Documents
Document
Page 38
Required Documents
( )
( )
:
.0
CDP.
.0
.
.0
.
.0
.
.5 U-Value
.
.6
.U-Value
.7
U-
.Value
.8
K
Values .
.9
.
.02 Water
calculator .
.00
.
.00
( )
.00
( )
9
75222 0
0222
( ).
:
.0
.
.0
.
.0
:
.0
.0 /
.
:
.0
.0
.0
.0
.5
.6
.7
.8
.9
.02 .
.
:
.0
.0
.0
Page 39
:
.0
.0
.0
.0
0
/
52 0 5
05
.
:
.0
.0
.0
.
CDP
Estidama Zip Folder
Page 40
( )
.
.
( )
.
.
- 4
()7-1
,
.
- 1
.
- 3
,
- 6
) (FM.01
( )
Page 41
-2
).(CDP
- 5
)
CDP
- 7
- 8
) (FM.01
- 51
) (FM.01 -
- 9
( )0
.
Required Documents
Document
) - (FM.01
) - (FM.02
) - (FM.03
) - (FM.04
) (FM.05
) -(FM.06
:
-0
-0
-0
-0
-5
-6
-7
-8
https://cdp001.dma.ae/cdpabudhabi/cdppublicportal/
( + + + + )
GIS
( ) +
Page 42
Required Documents
Document
.
.
- 4
(
%511
FM.07
( )FM.08
- 3
( )2.
-2
- 5
( )%21
- 5
- 3
- 2
.
- 4 ()
Page 43
Document
Required Documents
( . ) ( 6
)
[ (])FM.01
( )
) - (FM.01
) - (FM.07
) - (FM.08
:
( )
Page 44
Required Documents
Document
.
- 3
( )2
( - )FM.09
)(CDP
-2
()2
- 5
( )FM.10 (
)
Page 45
%022
( - )FM.08
( )
Required Documents
Document
) - (FM.08
) - (FM.09
) - (FM.10
Page 46
Required Documents
Document
()
.
:
- 4
)(CDP
)(FM11
- 3
,
-2
).(CDP
- 5
)
(
( ( CDP
- 1
( )FM 11
Page 47
Required
Documents
Document
) (FM11
Page 48
Required
Documents
Document
/ /
.
- 4
( )1
1
/
Page 49
- 3
( )FM.13 ,
-2
(
)
- 5
.
Required
Documents
Document
( )
( )FM.01 (
)
Required
Documents
Document
( -)FM.01
( -)FM.13 .
Page 50
( )
4
)- (FM.14
- 3
.
.
-2
- 5
) (CDP
Page 51
Required Documents
Document
Required Documents
Document
) - (FM.14
Page 52
.
.
- 4
( )Hard copy
(
)
1
.
Page 53
- 3
( - )FM.12 ,
.
-2
.
.
- 5
Required
Documents
Document
( )FM.12
Page 54
Required
Documents
Document
INT - 01
1
FC 01
2
PI 01
3
GR 01
4
ARCH 01
5
STR 01
6
MEP 01
7
DPPS-Form 1
8
DPPS-Form 2
9
DPPS-Form 3
10
Page 55
Rev 0 -1/7/12
Rev 0 -1/7/12
Rev 0 -1/7/12
Rev 0 -1/7/12
Rev 0 -1/7/12
Rev 0 -1/7/12
Rev 0 -1/7/12
Rev 0 -1/7/12
Rev 0 -1/7/12
Rev 0 -1/7/12
1-7-2012
1
Title
Date
INT 01
-
Document No.
Revision No.
) (DPPS
.
,
.
.
1
.
.
www.adm.gov.ae
1
. www.adm.gov.ae
(Go to Service Directory/View by Section/Town Planning
Sector/Construction Permits Division and click on the respective permit
types for the service explanation & administrative requirements).
-:
Chapter FC-01 :. )a .
Chapter PI-01 : )b ( )A4
()CDP
.
Chapter GR-01 : )c
Page 56
4
.
()DPSS
.
Page 57
Building Permit Application Flow Chart
Title
Date
FC 01
-
Document No.
Revision No.
0
): (CDP
)a
)b
)c
)d
)e
)f
)g
)h
)i
)j
.
.
.
.
.
0 & 0 .
.
.
.
Page 58
Consultant-of-Record/Applicant
/-
NT-01 &FC-
)(Refer *Checklist for Permit Application
pdf
Refer Doc.GR-01
Refer Doc.ARCH-01/STR-01/MEP-01
dwf / dwg
/
)(1 to 2 working days
)(1 to 2 working days
Page 59
) (to be completed at Customer Service Counter, Central Atrium
Permit Issuance Checklist
Title
Date
PI 01
-
Document No.
Revision No.
.0.
/
.
.0
0 0
()
()
/
()
(
)
Page 60
... )
/
()
11
12
13
14
15
16
17
18
10
19
20
21
0 0 8 9
.
Page 61
.0
-
-
(
)
/ /
(
/ )
)
( /)
/ / /
:
/ /
/
Page 62
Item
Description
Building Permit
Application Form
2 (original)*
ADM Town
Planning
Affection Site
Plan (original)*
Master Developer
Affection Site
Plan (original)*
Developers Own
ers NOC Letter
for proposed fitout works
(original)*
To be
uploaded
upon
project
registratio
n by
Remarks
Applicant
All Parties as
appeared in the
form.
ADM
reviewer/projec
t coordinator
will sign before
Applicant
uploads.
Applicant
Abu Dhabi
Municipality
6 months
validity.
Applicant
Master
Developer &
Infrastructure
Planner
Applicant
Developers Own
ers Appointment
Applicant
Letter for 3rd party
(original)*
Applicants valid
Applicant
Trade License
To be signed
/stamped by :
Developer/Owne
r or other
appointed 3rd
party
Letter shall
clearly state
the tenanted
unit/store no.
and intended
usage as per
approved
building
plan(s). And
shall be
supported by a
key plan
showing its
location. If 3rd
party is
appointed, item
5 shall be
submitted.
Developer/Owne
r
Issuing
Authority
Page 63
10
11
12
13
(copy)
Applicants Letter
for the design
and supervision
liability (original)*
Consultant-ofRecord
Registration
Certificate (copy)
Owners Tenants
Appointment
Letter for fit-out
contractor
(original)*
Fit-out
contractors valid
Trade License
(copy)
Fit-out
contractors
username
Building
Completion
Certificate (copy)
Other
special/supportin
g approvals from
external
agencies-if any
(copy)
Applicant
Consultant
-of-Record
Issuing
Authority
Applicant
Owner/Tenant
Contractor
Issuing
Authority
Contractor
Applicant
Applicant
Applicant can
make the fitout application
but no fit-out
permit will be
issued without
the
contractors
documents and
information
Abu Dhabi
Municipality
Issuing
Authority/Agenc
y
Required if
warranted by
external
agencies (case
by case
evaluation)
9 8 0 0
.
.
Page 64
General Requirements
General Requirements
1-7-2012
Title
Date
GR 01
-
Document No.
Revision No.
.0
.0 .
.
.
.
:
.
.
.
.0
A3
.
/ /
:
()
Page 65
MEP Meh 01-elect 01- plamb-01
.
.0
:
0.0
A2,A1 & A0 .
.
0.0
:
1:10,000
1:500, 1:1,000
1:100, 1:200
1:10, 1:20, 1:50
1:50
0.0
0
,
.
0.0.0 :
:
.
: :
.
.
(.)datum
Page 66
.
/
/
0-0 .
:
A. International Building Code IBC 2009 edition published by the
)International Code Council (www.iccsafe.org
B. User Guide for the International Building Code in the Emirates of Abu
Dhabi published by the Department of Municipal Affairs Abu Dhabi
)(http://abudhabibuildingcodes.ae/
C. American National Standard on Accessible and Usable Building and
Facilities -ICC/ANSI A117.1-2003 edition published by the
International Code Council.
D. Uniform Plumbing Code of Abu Dhabi Emirate published by
)Environmental Agency Abu Dhabi. (www.ead.ae/en/library/
Page 67
( 5 ) ( )
022 5
RS10
( 05 ) ( 07 :
) .
.0.5.0
:0 ( )
( 0 + + 02 + )
0 02
0 .
0.5.0 :
0 ( )
0
C10 02 .
0.5.0
C10 02 .
5.5.0
SB 01 0
.
6.5.0
00 0
- 082.0
Page 69
6.0
:
: 0.6.0
A.
B.
C.
D.
E.
F.
G.
H.
Drawing List
Site Plan / Landscape Plan
Floor Plans
Elevations
Sections
Details
Code Analysis Drawings
Gross Floor Area Drawings
022
.)A 1001- A1999 (
. : 0.6.0
. : 0.6.0
. : 0.6.0
:
A.
B.
C.
D.
E.
F.
G.
H.
I.
J.
Drawing List
Site Plan/Affection Plan
Floor Plans (Water Supply)
Floor Plans (Foul Drainage)
Floor Plans (Storm Drainage)
Riser Diagrams (Water Supply)
Riser Diagrams (Foul Drainage)
Riser Diagrams (Storm Drainage)
Details and Cross-Sections
Calculation Sheets
Page 70
.5
-
-
.
A4
0
.
PDF
.
.
0
.
.
:
o
o
o ( )
/
.
, .
.
Page 71
Page 72
Architectural Submission Requirements
Document
ARCH 01 Title Architectural Submission Requirements
No.
Revision No.
- Date
1-7-2012
.0
INT-01, section 3.0
:
FC-01 .
.
.
0.2
.
DWf
( )
.0
.
.
(
) .
.
(
)
Page 73
.
p1-01
( A4 ) .
(
) a.fouad@adm.abudhabi.ae .
.0
A1 A0 :
5
.
.
/
:
- .
.
.
.
02.222 :0
522 :0 0222 :0
( ).
(
.)..
.
.
.0 .
( - - -
) .
PL-01
Page 74
.
.
.5
( ).
.
/
:
o -
-
.
o .
o .
02.222 :0
522 :0 0222 :0
(
.
( ...
hard & soft :
0:52 ( )
022 :0 52 :0 0:02
( ....
.6 .
.
02 00
:
o
o .
Page 75
( )
.7
( )
.
.
.
:
.
o .
o
.
.8 .
/
.
.
.
Page 76
:
(
).
(
).
(
).
(
).
( ).
.
(
).
.
0.2
:
.
.
.
.
Page 77
Diagram 5A Project Record Sheet-1
Page 78
Diagram 5A Project Record Sheet-2
Page 79
Diagram 5B Drawing List
Page 80
Diagram 5C Project Data Analysis Sheet
Page 81
Diagram 5D Code Analysis Sheet
Page 82
Document No.
Revision No.
1.0
STR 01
-
Title
Date
INTRODUCTION
This document outlines the general requirements applicable to all Structural submissions.
Structural submission can be broadly categorized into two main headings Substructure and
Superstructure.
This document provides clear guidelines to enable the applicant to lodge the appropriate
submittals.
2.0
CONTENT
2.1
2.2
Substructure
2.1.1 Geotechnical Report
2.1.2 Information to be shown on Drawings
2.1.2.1
Shoring
2.1.2.2
Marine Works
2.1.2.3
Shallow Foundation
2.1.2.4
Deep Foundation (piles)
2.1.3 Calculations
2.1.3.1
Load Calculation
2.1.3.1.1 Gravity Load
2.1.3.1.2 Lateral Load
2.1.3.1.3 Earthquake Loads
2.1.3.1.4 Thermal Loads
Superstructure
2.2.1 General Requirements
2.2.1.1
Concrete Building
2.2.2 Design Checklist
2.2.3 Additional Foundation Requirements
2.2.4 Additional Vertical Element Requirements
2.2.5 Additional Horizontal Element Requirements
Page 83
2.1
SUBSTRUCTURE
2.1.1
GEOTECHNICAL REPORT
Detailed geotechnical investigation reports shall be submitted with the structural
drawings for every project by the consultant shall ensure that the required amount of
boreholes are carried out to the required depth by the geotechnical engineer, to the
requirements of the nominated code of practice for site investigations .
Geotechnical investigation reports are to contain, but not be limited to, the following
information applicable:
Page 84
All works have been carried out in accordance with the nominated code of practice
for site investigations.
Proper equipment and tools, duly calibrated, have been used by qualified and
experienced personnel during all soil investigation and testing works, and that the
test results have been reviewed and approved by the consultant.
2.1.2
2.1.2.1
SHORING
Drawing containing existing gnawed level, all deferent excavation level,
underground water table level.
All level referred to NADD.
Proposed dewatering system and the profile of predicted seepage water line.
Guarantee letter from shoring subcontractor.
2.1.2.2
MARINE WORKS
Sea water levels HAT, MAT, LAT..etc.
Existing ground level, final plate form level and final dredging level (NADD).
Type and thickness of bed protection.
Considered Wave height.
Considered Seismic category.
Considered Mooring and berthing loads.
Surcharge load.
2.1.2.3
SHALLOW FOUNDATION
Soil laboratory name and soil report reference number.
Excavation depth and bearing capacity.
Any special requirements recommended in the soil report.
columns load values for the most critical load combination (service)
2.1.2.4
DEEP FOUNDATION
Piling plan showing pile length, reinforcement, legend for pile capacity, pile
testing and cut-off levels etc.
Pile caps layout including column and shear wall location with dimensions.
Pile caps sections showing thickness, steel reinforcement and levels relative to
datum.
Structural framing (general arrangements) for all floors including column
locations, floating column location if any, slabs etc. including the load transfer
mechanism.
columns load values for the most critical load combination
piles reactions due to the most critical load combination (service)
2.1.3
CALCULATIONS
Page 85
2.1.3.1
LOAD CALCULATION
2.1.3.1.1
GRAVITY LOAD
Dead load: weight of material, equipment and land scaped roof (saturated soil)
should be calculated according to IBC 2009 chapter 16 or alternatively in
conformance with table C 3-1 and C 3-2 of ASCE 7.
Live loads: live load calculation will be in accordance with IBC 2009 chapter 16.
Adopted dead and live loads shell satisfy the recommendations of Abu Dhabi
Municipality.
2.1.3.1.2
LATERAL LOAD
Soil lateral load: soil load calculation in accordance with IBC 2009 table 1610.1.
Wind load :
1) Minimum design loads for building and other structures, including
supplement 1 & 2 ( ASCE 7-05)
2) Wind load shell be based on basic wind speed ( 3- second gust ) 26.8 m/
sec. 10 years return period and 38.0 m/ sec. 50 years return period.
3) Reliable wind tunnel test study reflecting climatic site condition where it
looks provision not applicable.
4) All buildings shall be designed to limit maximum drift under 10 years return
period wind speed to 1/500 of building height above ground.
5) All buildings shall be designed to resist 50 year return period wind load.
6) Adequate provisions shall be adopted to eliminate risk and damage to non
structure element due to story drift.
7) The maximum allowed story acceleration due to 10 year retune period wind
load shall be limited to 15 mg for residential and hotels and 20 mg for
offices towers.
2.1.3.1.3
EARTHQUAKE LOADS
Minimum design loads for buildings and the structure including supplements
1&2 ( ASCE 7-05)
Seismic loads shall be based on mapped spectral response accelerations Ss and
S1 issued by Abu Dhabi jurisdiction.
For the design of substructure purposes the structure response modification
coefficient (R shall be equal one= 1. 0)
2.1.3.1.4
THERMAL LOADS
For structures are to exposed to we other the members shall be designed for 25
a uniform temperature changes.
For structures are exposed to the atmosphere from the outside surface the
members shall he designed for 25 non uniform temperature.
Members provided with expansion joints at maximum distances 60 meters do
not need thermal effect study
Page 86
2.2
SUPERSTRUCTURE
2.2.1
GENERAL REQUIREMENTS
2.2.1.1
2.2.2
CONCRETE BUILDING
The design of concrete structural members will be based on IBC 2009
and relevant standards.
Structural design of all projects submitted to the municipality for
approval shell ensure that the work is carried out by licensed and
qualified consultant with structural engineers having the necessary
qualifications and experience .
Design philosophy, complete design criteria and full calculation and
analysis shell be submittal in soft and hard Copy format.
Consultant shall ensure that structure is economically designed (as
appropriate) and must ensure that design and details are buildable.
DESIGN CHECKLIST
Consultants submitting structural drawings for approval must ensure they have designed the
foundations and the superstructure in accordance with the following general checklist:
Fire Rating Requirements
Structural adequacy
Integrity
Insulation
Durability Requirements
Corrosion resistance
Chemical attack resistance
Crack control
Waterproofing
Loading Requirements
Dead loads
Live load ( including any pattern load and heavy load / compactus requirements )
Wind load
Earthquake loads
Earth pressures
Water pressures
Buoyancy loads
Ground movements and differential foundation settlements
Dynamic effects / vibration resonance loads
Thermal loads
Creep
Page 87
Serviceability requirements
Deflections/sag ( including allowance long term creep and shrinkage effects )
Hogging ( especially for post tensioned beams and cantilever back spans )
Axial shortening / extension
Rotation due to torsional effects
Crack control ( minimum pre stress level for post tensioned concrete )
Allowance for articulation of masonry wall as required
Allowance for brittle finishes
Stability requirements
Overturning and uplift
Buoyancy
Sliding
Strength requirements
Flexural strength ( including minimum strength requirements )
Beam shear strength (including minimum strength requirements )
Punching shear strength
Torsional strength
Bearing strength
Anchor strength for post tensioned beams
Foundation strength
Pre stress levels within acceptable limits
Detailing requirements
Tendon placement priority over reinforcement
Tendon/ reinforcement clash at columns etc
Penetrations through slabs and beams
Set downs, steps and sloping surfaces
Page 88
2.2.3
Buildings with basements require approval of all basement floor plans from the town planning
department of the buildings directorate and concerned service departments.
The submitted drawings shall clearly indicate the distance to the outer face of any permanent or
temporary training system. ( i.e. diaphragm walls, secant pile walls, contiguous pile walls etc. )
from the inner face of the basement walls.
Ground anchors supporting retaining systems for excavations, shall not extend into adjacent
plots into areas of highly concentrated utilities and service lines in all circumstances, clearances
shall be obtained from the relevant service departments.
Pile foundations together with shallow foundations shall not be permitted to support the same
superstructure, unless isolated.
Foundations calculations shall ( If required by the municipality ) address the design issues of
stability, durability and ultimate general requirements are:
Stability
Overturning and uplift
Buoyancy
Slope stability
Durability
Corrosion resistance
Chemical attack resistance
Crack control if required
Serviceability
Deflections/sag including allowance long term creep and shrinkage effects
Axial shortening ( in particular for piles )
Rotation of footings
Bearing stress
Ultimate
Punching shear
Beam shear
Flexural strength
Torsional strength
Anchor strength
*Geotechnical reports shall be submitted to the requirements of part 1, piling.
Page 89
2.2.4
Load calculation by tributary area method and moment shear factor method should
accompanied by plan drawings indicating the tributary areas. The use of software to calculate
column reactions is permitted, although should be accompanied by hand calculations using the
prior mentioned methods.
Calculations must show if columns are short or slender, according to the code provision.
All column design must be accompanied by moment interaction diagrams taking into account
slenderness effects.
Additional bending moments due to column beam/slab joints must be included in calculations,
including any secondary effects ( hyper static reactions ) from unbalanced post tensioning
reactions.
2.2.5
Edge beams around a radius and general torsionally loaded beams must allow for additional
longitudinal reinforcement and stirrups. All stirrups must be closed to ensure adequate
tensional resistance is achieved.
Slabs modeled using finite element method must clearly indicate all assumptions considered to
predict deflections, and must ensure that full moment connections are not modeled where they
can develop into pinned connections.
Transfer slabs must be limit deflections to span/1000 to ensure that elements and partitions on
above floors do not crack.
Include:
All plans and sections relevant to the project for all structural elements
Class and, where appropriate, grade designation of concrete
Exposure classification
Reference number and date of issue of applicable design standard
Fire rating (if not specified on architectural drawings)
Loading (superimposed dead load and live load to all slab plans and wind and
earthquake loads)
Grade and type of reinforcement and tendons
General notes
Concrete cover to reinforcement
The finish and method of control for unformed surfaces
Class of formwork for the surface finish
Curing procedure and duration
The force required in each tendon, the maximum jacking force to be applied and the
order in which the tenders are to be stressed
The location and details of planned construction or movement joints connections and
splices , and the method to be used for their protection
Page 90
The minimum period of time before stripping of forms and removal of shores
Any constraints on construction assumed in the design
Any special protective coatings
Characteristic compressive strength at 28 days
Characteristic flexural strength if required
Characteristic indirect tensile strength if required
Mean 7 days strength
Other early age strength
Slump of concrete
Cement type
Maximum aggregate size
Water/cement ratio
Maximum 56 day shrinkage
Density if required
Maximum water soluble acid(chloride ion) if required
Maximum sulphate concrete (SO3) if required
Temperature range at point of discharge if required
Testing requirements if required
Project assessment of concrete production if required
Page 91
Plumbing Submission
Requirements
1-7-2012
Title
Date
PLUMB
01
-
Document No.
Revision No.
.0.
:
.
.0
.
( )NOC
.
()
.
.
.0
:
( 022 :0
0:022 0:52
05:0
()
Page 92
.0 .
02 00 .
.
.5
:
5 7
.ADM
Page 93
Project Title
2.0
Plot(s)
Project Description
Sector
Land Use
GFA (sqm)
GLA (sqm)
Phasing
Other Remarks
Sub-Plot No
Podium 1
Tower 1
Sub-Plot No
Podium 2
Tower 2
3.0
Applicants Information
Contact Details
Office / Mobile No.
Page 94
Email Address
Consultants Name
Contact Details
Office / Mobile No.
Email Address
Contractors Name
Contact Details
Office / Mobile No.
Email Address
4.0
Land Reclamation
Foundation
Land-Water Interface
Piling
Page 95
5.0
Project ID
Building Officials
Project Coordinator
Architectural Reviewer
Structural Reviewer
Plan ID(s)
Signature
Date
Page 96
Building Permit Application Form 2 Existing Buildings
Project Title
7.0
Plot(s)
Project Description
Sector
Detailed Project Information (for modification / addition / change of use permit application only)
Land Use
GFA (sqm)
GLA (sqm)
Other Remarks
Sub-Plot No
Podium 1
Tower 1
Sub-Plot No
Podium 2
Tower 2
Page 97
8.0
Floor
Unit No.
Approved Occupancy
Fit-Out Description
9.0
Modification
10.0
Addition
Change of Use
Applicants Information
Contact Details
Office / Mobile No.
Email Address
Consultants Name
Contact Details
Office / Mobile No.
Email Address
Contractors Name
Contact Details
Office / Mobile No.
Email Address
Page 98
11.0
Parent Project ID
Building Officials
Project Coordinator
Architectural Reviewer
Structural Reviewer
Project ID
Signature
Plan ID(s)
Date
Page 99
Quarterly Site Progress Report Form 3 New & Under-Construction Buildings
Project Title
Sector
Project Description
ADM Project ID
Start Date
2.0
S/no
Permit ID
3.0
Site Team
Supervising
Consultants
Company
Name
Plot(s)
Parent ID
Title
Permit Type
Name
Completion Date
Permit Status
Issue Date
Issued To
Contact
Email Address
Project Manager
Tel:
Mob:
Architect
Tel:
Mob:
Structural Engineer
Tel:
Mob:
Mechanical Engineer
Tel:
Mob:
Electrical Engineer
Tel:
Mob:
Plumbing Engineer
Tel:
Mob:
Page 100
Main
Contractors
Company
Name
4.0
Safety Officer
Tel:
Mob:
Project Manager
Tel:
Mob:
Construction Manager
Tel:
Mob:
Site Engineer
Tel:
Mob:
Safety Officer
Tel:
Mob:
Shoring works
Piling works
Waterproofing works
Demolition works
Foundation works
Insulation works
External landscaping
Dewatering works
Columns/Cores casting
MEP works
Excavation works
Slabs casting
Cladding works
5.0
Baseline Construction Schedule & Milestones (spreadsheet can be attached as annex separately)
6.0
7.0
8.0
Construction Forecast for Next Quarter (spreadsheet can be attached as annex separately)
Page 101
9.0
Narrative
1
Picture 1
Narrative
2
Picture 2
Narrative
3
Picture 3
Narrative
4
Picture 4
Page 102
10.0
S/no
11.0
Violation Description
Issue Date
Issue To
Issue By
Corrected Date
Inspected By
Inspection Date
(dd/mm/yy)
(Contractors Name)
(Municipal Center)
(dd/mm/yy)
(Municipal Center)
(dd/mm/yy)
Project ID
Building Officials
1
Project Coordinator
Architect
Structural Engineer
Mechanical Engineer
Electrical Engineer
Plumbing Engineer
Plan ID(s)
Signature
Date
Page 103