Professional Documents
Culture Documents
Diameter
Type
m
Depth
Quantity
Equipment
(days)
1.2
40
36.0
1,440
1/,4Piles/day=10
1.2
32
49.0
1,568
1/,4Piles/day=8
1.2
32
50.0
1,600
1/,4Piles/day=8
1.2
52
51.0
2,652
1/,4Piles/day=13
1.2
17
52.0
884
1/,4Piles/day=4
1.2
22
53.0
1,166
1/,4Piles/day=6
1.2
17
54.0
918
1/,4Piles/day=4
1.2
55.0
385
1/,4Piles/day=2
1.2
56.0
280
1/,4Piles/day=1
10
1.5
140
51.0
7,140
11
1.5
32
52.0
1,664
396
1/,4Piles/day=8
19,697
11 Other Utility
12
2
1
2
3
4
5-1
5-2
6
7
8
9
10
11
12
13
3
173
620
4 ,
26,444,356,115
1
2
3
4
5
6
7
8
9
10
341
1/,4Piles/day=35
NTD=1
19,334,754,385
D
4.0
4.0
4.0
4.0
4.0
0.0
8.0
40.0
2.0
0.0
4.0
7
7
8
6,800,000
6,800,000
3,500,000
3,500,000
3,500,000
3,500,000
3,500,000
3,500,000
3,500,000
3,500,000
2
0
2
0
4
0
3,500,000
47,600,000
47,600,000
28,000,000
0
7,000,000
0
7,000,000
0
14,000,000 *1*1 Office*1, Equipment*1
0
0 Including Crane Equipment
0
9,630,000,000 789 NTD/m
4.0
4.0
4.0
4.0
2.0
2.0
0.0
8.0
4.0
40.0
2.0
0.0
4.0
4.0
151,200,000
24.0
24.0
24.0
24.0
12.0
12.0
0.0
48.0
24.0
240.0
12.0
0.0
24.0
24.0
174,240
200,000
124,000,000
180,000,000
38,500,000
25,000,000
17,000,000
13,000,000
30,000,000
2,000,000
500,000
650,000
3,500,000
5,000,000
1,000,000
5,000,000
2,976,000,000
4,320,000,000
924,000,000
600,000,000
204,000,000
156,000,000
0
96,000,000
12,000,000
156,000,000
42,000,000
0
24,000,000
120,000,000
Rented Equipment
Rented Equipment
Rented Equipment
Rented Equipment
Rented Equipment
10 10pcs/team
*1*2 Office*1, Equipment*2
2,578,752,000 9 L/m
1
2
3
4
6
7
L
L
L
L
L
L
1/person
6.0
135,000
83,700,000
1/person
6.0
120,000
74,400,000
0/person
0.0
100,000
62,000,000
Project Manager(Taiwan)
2
Site Manager(Taiwan)
Engineer(Taiwan)
4
Engineer(Vietnam)
3
47,520
23,760
31,680
19,800
31,680
19,800
14,800
14,800
14,800
14,800
14,800
14,800
703,296,000
351,648,000
468,864,000
293,040,000
468,864,000
293,040,000
1,386,600,000 114 NTD/m
4/person
24.0
9,500,000
5
Translator(Vietnam)
4/person
24.0
6,500,000
)
6
Office Staff(Vietnam)
2/person
12.0
4,500,000
2/person
12.0
2
Foreman(Vietnam)
4/person
3
Crane Operator
8/person
4
Excavator Operator
RCD
5
Rcd Operator
6 Vietnam Worker
6
135,000
83,700,000
24.0
6,500,000
48.0
7,500,000
8/person
48.0
5,500,000
8/person
48.0
5,500,000
24/person
144.0
5,500,000
1 Water well
30m
26,000,000
20m
15,000,000
15kg/
25kg/
15kg/
kg
kg
kg
15,662
31,324
0
90
60
56,000
8,500
37,200
15kg/
kg
110
67,952
1
2
3
4
5
6
8
Spacer
Oxygen
Ethine
Welding Stick
Iron Wire
Other Utility
19,697
- Water Tank
- Temporary pond
()
1
Office Rental
182,000,000
0
877,061,688 5 / kg1.2/ Import Cost, add 5Dollor/kg for VAT
266,250,870 5 / kg2.0/ Import Cost, add 5 Dollor/kg for VAT
0 5 / kg Import Cost, add 5 Dollor/kg for VAT
0 5 / kg10/ Import Cost, add 5 Dollor/kg for VAT
672,489,827
4/2m
3.0T/
6.0T/
1.0kg/T
0.5kg/
kg
kg
1,342
1,352
676
4,056
2,028
396
5,000
70,000
300,000
32,000
20,000
500,000
1
7
100
7
7
0
0
0
45,000,000
15,000,000
5,000,000
1
2
3
4
5
Stability Polymer
6
Clay Settle medicament
7
Foreman(Taiwan)
120.0 L/
60.0 L/
80.0 L/
50.0 L/
80.0 L/
50.0 L/
30,000,000
315,000,000
105,000,000
0
0
0 (P5)
330,000,000
30,000,000
438,000,000
)
3
Staff Room Rental
5,000,000
30,000,000
5,000,000
30,000,000
18
5,000,000
90,000,000
Power Fees
2,500,000VND/
30
2,500,000
75,000,000
Other Utilities
2,500,000VND/
30
2,500,000
75,000,000
4,750,471,731
1
Fabrication of Rebar Cage
4,055.880
2 Transportation Fees
162
3 U U-Bolt
4,258.674
Pcs
2 Concrete pouring
Soil Disposal
1
2
3
750,000
3,041,910,000
2,850,000
25,000
28,476
m3
31,324
28,476
m3
37,019
2
2
1,500L
60,000
60,000
25,000,000
5,400,000
13,000
0 5 % Loss 5 %
1,708,561,731
138,000,000
1 Safety Engineer
24
2,500,000
60,000,000
2 Safety Fees
3 Other Utilities
1
2
6
12
3,000,000
5,000,000
18,000,000
60,000,000
396
500,000
198,000,000
53,957
4,342,497,191
Koden Test
Sonic Test
396
1
2
3
4
5
6
-
Sonic Pipe-Tender Quantity
61,424
60mm
10,442
6.00
2,424
,114mm,t=2.3m
5,846
114mm
1,023
Sonic Test
2 Material
3 Material
3 2*4,
Daytime-Nighttime*4 shift, 2 Place, Security Officer
396
47,304
60,220
136,271
5,732
40,000
2,456,959,680 2% Loss 2%
36,000
375,914,831 5% Loss 5%
6,500
15,752,880 2% Loss 2%
120,000
701,566,200 2% Loss 2%
56,000
57,288,000 5% Loss 5%
808
27,500
396
1,800,000
22,215,600 2% Loss 2%
712,800,000 25%, Test 25%
0
19,697
10
6,200
60mmPVC
114mm
m
m
0
0
5
9
3,000
5,700
0
0
Loading Test
Loading Test
3.0
1 Test Fee
1.2m
1.5m
0
0
180,000
0
0
2 - Transportation fee
Material Fees
1
2
3
Rebar Cage
Concrete C30
- Sand
Surveyor
1
Site engineer (TW)
2
Site engineer (VN)
3
Equipment fee
Total
m
m
nos.
P=1.2
2,000,000
0
0
0
2,650,000
550,000
0
0
356,400,000
396
396
1,452
900,000
1,629
1,009,980
m3
0.0
97
60,000
396
T
m3
m3
4,259
31,324
0
396
0.0
0.0
00 /
5,717
51,300
0 1,200 NTD/m3
84,485,308,222
4055.880T
28476.0m3
356,400,000
12,500,000
1,186,500
60,000
806
500,000
198,000,000
0.0
80,645
50,000,000
0.0
11,290
7,000,000
0.0
81
50,000
116,024,561,529
Cost Item
Construction fee
19,697
2,165
1,342,558
19,697
1,583
981,609
19,697
12
7,676
19,697
789
488,907
19,697
211
130,921
19,697
114
70,397
19,697
233
144,205
Stability Polymer
19,697
109
67,285
- Mechanical materials
19,697
55
34,142
19,697
34
21,323
19,697
27
16,754
4,259
1,799
1,115,481
Soil Disposal
19,697
182
112,765
7,734,971
19,697
11
7,006
Koden Test
396
806
500,000
Sonic Test
396
2,903
1,800,000
396
14,784
9,165,902
Sonic Test
396
2,903
1,800,000
396
Loading Test
Pile Tip contact condition checking
396
1,452
900,000
396
1,452
900,000
Material Fees
19,697
6,918
4,289,248
Rebar Cage
Concrete M350
- Pile
positioning
4,259
19,201
11,904,762
m3
31,324
1,740
1,078,636
396
0
198,000,000 USD 33.3 Cost Unit Price USD
116,024,561,529 USD 7,734,970.8 Cost Unit Price USD
187,136,390
11,868,498,922
10.23%
151,200,000
0.13%
9,960,000,000
8.58%
2,578,752,000
2.22%
4,365,000,000
3.76%
86,483,110,607
74.54%
618,000,000
0.53%
116,024,561,529
100.00%
20m
Mobilization
Renting fee
Diesel
158,878,720
Labor
2,647,979
Materia
Others
116,024,561,529
113,309,214,938
-2,715,346,590
5,890,469 VND/m
5,752,613 VND/m
-2%
27,045,556,115
1,373,080 VND/m