You are on page 1of 1

Project:

Client:

Ref No.:

M/S AL HAMLA W.L.L

2B+G+M+PODIUM+25 HOTEL BUILDING


Consultant:

Revision:

SWA/SOR/ME/016

Contractor:

Date Opened:

0
Date Closed:

27-Nov-2014
Sub Contractor

SITE OBSERVATION REPORT


WORK DESCRIPTION: MECHANICAL WORKS DEFICIENCIES AT 25TH FLOOR - FAHU (MECHANICAL FLOOR)
PART A: DETAILS OF CONSTRUCTION ACTIVITIES (Please attach separate sheet if necessary)
During ocular inspection, we observe the following deficiences for mechanical works at 25th floor-FAHU (Mechanical Floor).
although several verbal instructions.
See attached documents for works deficiences.

CONSULTANT

Note:
Failure to address the deficiency finding within a reasonable period of time may result into a Non-Conformace Report(NCR)
or any other action in accordance with the contract.
PART B: DISCUSSION WITH CONTRACTOR (VERBAL)
Verbally instructed.

PART C: ACTUAL OR POTENTIAL NON-CONFORMITIES OBSERVED


Received by the Contractor

QCS-2010 section 1 part 8, clause 8.9


QCS-2010 section 22 part 1, clause 1.1.13
QCS-2010 section 22 part 5, clause 5.2.2 , clause 5.3
QCS-2010 section 22

Classification of Actual/Potential Non-Conformities:

Cause of Actual/Potential Non-Conformities:

Critical

Major

Minor

Unknown

Material

Process

Equipment

Documentation

QCS-2010 section 1 part 1, section 22


ASAP

Doc. Ref. (Spec, ITP, Drawg, Standard, etc.):


Required Completion Date:

ANANDA SETHUGE

Actioned By:

SWA - QA/QC Engineer

Date

ALEXANDER I. JUAN

Noted by:

SWA - QA/QC Engineer

Engr. Ghassan Al Yacoub

Confirmed By:
Date

SWA - Deputy Manager

Date

CONTRACTOR

PART D: REPLY/REMEDIAL/CORRECTIVE ACTION BY CONTRACTOR


Received by the Consultant

Name:

Signature:

Position:

Date:

PART E: ACCEPTANCE

CONSULTANT

Reply/Remedial/Corrective action have been undertaken and are acceptable. This SOR may be closed out.
Reply/Remedial/Corrective action undertaken by the Contractor are not acceptable for the following reasons and this SOR may n ot be closed out.

(Contractor must be address this issue otherwise may constitute to NCR)


Received by the Contractor

ANANDA SETHUGE

Actioned By:

SWA - QA/QC Engineer

Date

ALEXANDER I. JUAN

Noted by:

SWA - QA/QC Engineer

Copy Furnished to SWA

Date

Planning

Confirmed By:

Engr. Ghassan Al Yacoub


SWA - Deputy Manager

Date

Quantity Surveyor

Tender/Contract

SEE NEXT PAGE FOR NOTES AND ATTACHEMENTS (PHOTOS, SKETCHES, ETC.)

You might also like