Use of Emergent Works- CHECKLIST


PROJECT TITLE:

CONTRACT NO:

LOCATION:

FILE NO:

CONTRACTOR:

Type of emergent work:


Location:
Work described in Specification?
Work shown on Drawings?
Emergent work recommended?
Scoping carried out?
Applicable Day Work rates or prices in BOQ?
Request For Price issued?
Contractors price proposal received?
Value of emergent work agreed with Contractor?
Prepared Provisional Sum Authority form?
Received Approval for use of Provisional sum
for emergent work?
Provisional Sum order No.:
Provisional Sum order issued to the contractor?