Tarea # 14

Movimientos de terraceras
1. Calcule las ordenadas de curvamasa y dibuje el diagrama en base a los datos:

CVV en terrapln = 1.00


CVV en corte = 0.97
OCM de la estacin 0 + 000 = 3400.00

Areas
(m2)

Resp.

Estacin

1+000.00
1+018.45
1+020.00
1+040.00
1+060.00
1+080.00
1+100.00
1+106.82
1+118.58
1+120.00
1+140.00
1+160.00
1+180.00
1+200.00
1+210.00
1+215.00
1+220.00
1+240.00
1+260.00
1+280.00
1+300.00
1+306.49
1+312.69
1+320.00
1+340.00
1+340.58
1+360.00
1+380.00
1+400.00

Corte

Terrap.

25.18
24.98
18.96
14.68
10.08
7.25
3.97
0.00
0.00
0.06
0.00
0.03
0.01
1.08
6.82
15.97
20.01
45.00
38.94
68.09
70.85
59.55
49.00
32.24
30.79
22.33
22.59
11.68
8.89

0.24
1.24
5.70
5.80
9.87
16.35
19.59
37.65
39.75
40.96
32.64
36.90
29.87
25.73
32.00
14.99
37.90
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
3.37
11.50
31.29
34.48

OCM

3400.00
3835.19
3862.84
4074.15
4157.62
4063.53
3812.96
3630.90
3175.79
3118.53
2383.11
1688.00
1020.69
475.26
224.93
162.72
117.74
369.34
1183.56
2221.75
3569.47
3979.92
4306.33
4594.36
5205.75
5219.71
5498.41
5402.93
4944.76

2. Calcule los sobreacarreos para el diagrama de masas del ejercicio anterior. (Respuesta: Ubicando la compensadora
en la OCM 4000, se tiene un total de sobreacarreo de 19598 m3xestacin)

Fecha de entrega: mircoles 3 de Diciembre (Fecha del


tercer examen parcial)