Uraian
PERSIAPAN DAN MOBILISASI
Sub Total
Satuan
Volume
LS
1.0
PEKERJAAN SIPIL
Bendungan
Intake
Settlement Basin
Head Tank
Spillway and Tailrace
Penstock
Power House
Finishing
Sub Total
LS
LS
LS
LS
LS
LS
LS
LS
1.0
1.0
1.0
1.0
1.0
1.0
1.0
1.0
25 kw
26 kw
LS
3.0
3.0
1.0
DISTRIBUSI
Tiang Listrik Tegangan Rendah
Kabel Penghantar dan Aksesoris
Sub Total
LS
LS
INSTALASI
Kabel NYM
Socket, Switch, Connector, Tdus dan aksesoris lain
MCB + Box
Earthing
Sub Total
LS
LS
unit
unit
TOTAL
PPN 10 %
GRAND TOTAL
35.00
1.00
1.00
1.00
600.00
600.00
Harga
Biaya
50,649,350.65
50,649,350.65
50,649,350.65
25,324,675.32
20,259,740.26
45,584,415.58
40,519,480.52
232,987,012.99
75,974,025.97
15,194,805.19
50,649,350.65
25,324,675.32
20,259,740.26
45,584,415.58
40,519,480.52
232,987,012.99
75,974,025.97
15,194,805.19
506,493,506.49
10
5
4
9
8
46
15
3
100
109,090,909.09
50,909,090.91
65,454,545.45
327,272,727.27
152,727,272.73
65,454,545.45
545,454,545.45
60
28
12
100
1,269,016.70
177,662,337.66
44,415,584.42
177,662,337.66
222,077,922.08
20
80
10,909,000.00
21,818,000.00
48,000,000.00
5,450,000.00
86,177,000.00
20
40
30
10
80,000.00
1,410,852,324.68
141,085,232.47
1,551,937,557.14
1,090,909,091
1,200,000,000
54,545,454.55
NO
I
II
III
IV
Uraian
PERSIAPAN DAN MOBILISASI
Sub Total
Satuan
Volume
LS
1.0
PEKERJAAN SIPIL
Bendungan
Intake
Settlement Basin
Head Tank
Spillway and Tailrace
Penstock
Power House
Finishing
Sub Total
LS
LS
LS
LS
LS
LS
LS
LS
1.0
1.0
1.0
1.0
1.0
1.0
1.0
1.0
25 kw
26 kw
LS
3.0
3.0
1.0
DISTRIBUSI
Tiang Listrik Tegangan Rendah
Kabel Penghantar dan Aksesoris
Sub Total
LS
LS
INSTALASI
Kabel NYM
Socket, Switch, Connector, Tdus dan aksesoris lain
MCB + Box
Earthing
Sub Total
LS
LS
unit
unit
TOTAL
PPN 10 %
GRAND TOTAL
35.00
1.00
1.00
1.00
600.00
600.00
Harga
Biaya
50,649,350.65
50,649,350.65
50,649,350.65
25,324,675.32
20,259,740.26
45,584,415.58
40,519,480.52
232,987,012.99
75,974,025.97
15,194,805.19
50,649,350.65
25,324,675.32
20,259,740.26
45,584,415.58
40,519,480.52
232,987,012.99
75,974,025.97
15,194,805.19
506,493,506.49
10
5
4
9
8
46
15
3
100
109,090,909.09
50,909,090.91
65,454,545.45
327,272,727.27
152,727,272.73
65,454,545.45
545,454,545.45
60
28
12
100
1,269,016.70
177,662,337.66
44,415,584.42
177,662,337.66
222,077,922.08
20
80
10,909,000.00
21,818,000.00
48,000,000.00
5,450,000.00
86,177,000.00
20
40
30
10
80,000.00
1,410,852,324.68
141,085,232.47
1,551,937,557.14
1,090,909,091
1,200,000,000
54,545,454.55