Professional Documents
Culture Documents
SL. N O .
DESCRIPTION
01.
CO L D ST AR T - U P
02.
03.
H O T AN D WA RM S TA RT U PS.
04.
05.
IN T E GRA T E D ST AR T U P PR O C EDU R E H O T ST AR T U P .
06.
10.
11.
07.
08.
09.
COLD START UP
(With Aux Steam available)
A cold start up is by definition, one of which the maximum of HP casing and HP shaft is less
than 1500C. This normally means that the unit is shut down from the maximum load for
more than five days. If machine is started from ambient temperature (HPC/HP shaft temp
approx. 400C), heating up of casting is required. This is accomplished by soaking the
machine at 360 rpm at warming up steam parameters (40kg/cm2, 3600 C), till the TSE
margin are satisfactory.
The rifle construction of the water wall combined with the boiler circulating water
pumps permits very high rate of pressure rising of boiler. An upper limit of 2000C/hr
saturation temperature gradient can be allowed, i.e. approximately the boiler pressure can
be brought to 20 kg/cm2 within an hour of cold start up. But actual temperature gradient is
limited by the thick walled Y piece provided in the main steam and HRH lines. A main steam
line heating is to be started as early as possible (at approx. 4 kg/cm 2) as maximum
differential temperature allowed between inner (98%) and mid wall temperature (50%)
is 400C. So boiler loading is accordingly regulated. It may be preferably to start only two
CC pumps in order to minimise flashing in down comers (and subsequent vibration) when
the boiler water is in range of 850C to 1250C. The third pump should be started before drum
pressure reaches 7 kg/cm2 to minimise the temperature transients experienced by the
pump casing (this is to avoid fast load out back on the boiler in the event of any CC pump
tripping).
To get the rolling parameters, normally two elevation oil guns are taken with
approx. 70 to 80t/hr flow through HP-LP bypass. At that time M.S. parameters would be 40
kg/cm2 and 3600C, HRH parameters would be 12 kg/cm2 and 3600C.
As soon as the turbine loading has started, HP/LP bypass closes and gets completely closed
as the turbine reaches the boiler load. First mill is put into operation around 10% of
generator load. Second mill is put into operation around 25% while third mill is at 40% of
generator load. Fourth and fifth mills are put into operation at 60% and 80% of generator
load respectively. Sixth mill is taken to reach full generator load.
During loading the RH outlet steam temperature has to be kept as close as possible to
SH outlet steam temperature Burner tilt, SH spray, RH spray controls has to be adjusted
accordingly. The turbine-loading rate is decided by a selection circuit which compares the
external load gradient, TSE margin and time dependant gradient (set internally) and
frequency influence.
TIME
UNIT CONDITION
OPERATION
NOTES
..
Generator protection
panel ready in all
respects.
Generator H2 gas
pressure is 4 kg/cm2
Check purity of
generator stator water is
normal.
Readiness of HP bypass
panel in all respects.
--
--
M/c on barring.
+200 mm.
01
oo
Start 4 burners in AB
elevation with LSHS.
--
CW system is charged.
CW boxes to ensure
ventilating of water
boxes.
--
02
60'
03
100
Switch on automatic
control interface of LP
bypass.
Automatic control
interface gets switched
off when the hot reheat
steam pressure reaches
13kg/cm2 i.e. after
synchronisation.
Open HP by pass.
150
Temperature:1802000C
HRH Pressure:812Kg/cm2
-
M. S. Pr. 50 kg/cm2
M.S. temp. 3500C
05
-300
H. R. H. Pr. 12 kg/cm2
06
-360
Monitoring bearing
temperature and
vibrations, shaft
vibrations, TSE margins
and Turbovisory
readings, Seal oil,
Primary water and gas
temperatures &
Generator winding
temperature.
MS Pr. 50 kg/cm2.
Temperature:
Put AVR on Auto.
3500C Turbine running
at 3000 rpm.
07
370
Synchronise the
generator with grid.
-
Pick up 50 MW load by
operating speeder gear.
04
150'
MS Pr.: 15 kg/cm2.
Temperature:1802000C HRH
Pressure:8to12kg/cm2.
MS Pressure: 50
kg/cm2
MS
Temperature:3500C
05
300'
HRH Pressure:
12kg/cm2
HRH Temperature:
3500C.
MS Pressure:50
kg/cm2
06
360'
MS
Temperature:3500C
If tracking device is
switched ON, starting
device position will
automatically track the
EHC position
Monitor bearing
vibration and
temperatures, shaft
vibrations, Turbovisory
readings and TSE
margins
MS Pressure: 50
kg/cm2
07
370'
MS Temperature:
3500C
Synchronise the
generator with grid.
150'
MS Temp.:180-200 C
HRH Pressure: 12
kg/cm2
If the programme
interrupts the particular
step and criteria to be
checked and corrected
for the programme to
proceed further.
All operations as
explained under EHC
rolling will be carried out
by SHC Turbine
programme sequentially.
MS Pressure: 50
kg/cm2
MS Temperature:
3500C
05
300'
HRH Pressure: 12
kg/cm2
Monitor bearing
vibration, bearing
temperature, shaft
vibration, TSE margins
and Turbovisory
readings.
To achieve the
programme as per the
starting curve, the main
steam temperature
should be maintained
steadily till loading upto
50 MW.
MS Pressure: 50
kg/cm2
06
360'
MS Temperature:
3500C
MS Pressure: 50
kg/cm2
07
370'
MS Temperature:
3500C
Turbine
speed:3000rpm.
Load : 55 MW
08
390'
M.S. :
54kg/cm2/3500C
HRH : 12
kg/cm2/3400C
Ensure switching on of
load controller above
60MW.
Load : 55 MW
M.S. :
54kg/cm2/3500C
HRH : 12
kg/cm2/3400C
Ensure energizing of
solenoid in trimming
device at and above 100
MW load.
Load : 160 MW
M.S. :
90kg/cm2/3800C
10
440'
HRH : 20
kg/cm2/3800C
Steam flow : 580t/hr.
Charge Deareator
Ensure Deareator
pegging steam flow CRH
Pressure controller
to Extraction around 200
remains as auto.
MW load.
Load : 250 MW
M.S. :
120kg/cm2/4200C
11
480'
HRH : 26
kg/cm2/3400C
Load : 320 MW
M.S. :
125kg/cm2/3500C
12
510'
HRH : 28-30
kg/cm2/3400C
Ensure healthiness of
fire ball scanners.
Load : 405 MW
M.S. :
145kg/cm2/4600C
13
550'
HRH : 33
kg/cm2/4600C
Load : 500 MW
14
590'
M.S. : 170
kg/cm2/4750C
HRH : 40.5
kg/cm2/4750C
achieved gradually.
Load : 405 MW
M.S. :
145kg/cm2/4600C
15
670'
HRH : 33
kg/cm2/4600C
UNIT CONDITION
OPERATION
NOTES.
One CC pump in
operation and scanner
fan in operation.
STEP
Turbine on bearing
gear with AOP, JOP
and seal oil pumps in
operation.
HT and LT auxiliaries
power supply available.
HP bypass system
ready in all respects.
Generator protection
panel and exciter
panels ready in all
respects.
1. Charge auxiliary
steam header from
existing units. Pr. 16ata
temp. 2600C.
Ensure running of
motor driven BFP
continuously for
maintaining drum
level.
01
oo
Ensure atomising
steam pressure of
about 6 kg/cm2
Start 4 burners in AB
elevation with LSHS.
Switch Automatic
control interface of LP
bypass.
Automatic control
interface gets switched
off when the hot
reheat steam pressure
reaches 13kg/cm2(i.e.)
after synchronisation.
180'
MS: 60 kg/cm2/4000C
Raise the speed set
HRH: 12 kg/cm2/3500C
point of EHC to 3200
rpm.
By pass steam flow:
200t/hr.
03
210'
Starting device
position approximately
56%.
04
215'
Monitor bearing
vibrations, shaft
vibrations, TDE
margins, bearing temp.
& Turbovisory readings
at 360rpm.
Ensure tripping of JOP
at 540 rpm.
05
220'
Turbine running at
3000 rpm
Synchronise the
generator with grid.
Pick up 50 MW load by
operating speeder gear.
180'
MS: 60 kg/cm2/4000C
HRH: 12 kg/cm2/3500C
03
210'
If tracking device is
Raise the speed set
switched on starting
point to 360 rpm and
device position will
watch the actual speed. automatically track the
EHC position
Monitor bearing
vibrations bearing
temperatures, shaft
vibrations, TSE
margins & turbovisory
readings.
Ensure tripping of
Jacking oil pump at
340 rpm.
04
215'
Turbine running at
360rpm.
Monitor bearing
vibrations and temps,
shaft vibration,
turbovisory readings
and TSE margins.
05
225'
Synchronise the
generator with grid.
180'
HRH: 12 kg/cm2/3250C
By pass steam flow:
170t/hr.
If the programme
interrupts the
particular step and
criteria to be checked
and corrected for the
programme to proceed
further.
All operations as
explained under EHC
rolling will be carried
out by SGC Turbine
programme
sequentially.
MS: 50 kg/cm2/3650C
HRH: 12 kg/cm2/3250C
03
210'
Monitor bearing
vibration, bearing
temp, shaft vibration,
TSE margins and
Turbovisory readings.
To achieve the
programme as per the
starting curve, the
main steam
temperature should be
maintained steadily till
loading upto 50 MW.
MS: 60 kg/cm2/4000C
04
215'
MS: 60 kg/cm2/4000C
05
225'
Ensure switching on of
load controller at 60
MW.
Load: 60 MW
06
230'
MS: 60 kg/cm2/4100C
HRH: 14 kg/cm2/3600C
Load: 110 MW
MS: 80 kg/cm2/4200C
HRH: 19 kg/cm2/3800C
07
245'
Main steam flow:
470t/hr.
Trimming device is in
OFF.
Load: 200 MW
MS: 100 kg/cm2/4350C
08
270'
Change Deaerator
pegging steam from
CRH to Extraction
steam.
Ensure healthiness of
fire ball scanners.
-
Ensure Deaerator
pressure controller
remains on auto.
Before starting P.A. fan
ensure that air and gas
dampers of PAPH are
open.
Load: 320 MW
MS: 125 kg/cm2/4500C
09
300'
Ensure healthiness of
fire ball scanners.
Load: 500 MW
MS: 170 kg/cm2/4800C
10
340'
HRH: 40.5
kg/cm2/4800C
Main steam flow:
1620t/hr.
Load: 500 MW
MS: 170 kg/cm2/5350C
11
420'
HRH: 40.5
kg/cm2/5350C
STEP
TIME IN
MINUTES.
UNIT CONDITION
OPERATION
NOTES.
Two CC pumps in
operation and scanner
fan in operation.
Turbine on barring
gear with AOP, JOP
and seal oil pumps in
operation.
Condenser circulating
water system in
operation.
LSHS pump in
operation on long
recirculation upto
boiler front with
heaters control set on
HP bypass system
ready in all respects.
Generator protection
panel and exciter
panels ready in all
respects.
Ensure condenser
vacuum of 0.8 kg/cm2.
Switch Automatic
control interface of LP
bypass.
01
oo
Start 4 burners in AB
elevation with LSHS.
Ensure atomising
steam pressure of
about 6kg/cm2.
Put HP bypass
controllers on auto and
vary the set point
according to the
gradient of pipeline
temperatures.
40'
MS Pressure: 85
kg/cm2
MS Temperature:
5000C
HRH Pressure: 12
kg/cm2
03
50'
HRH Temperature:
4500C.
Starting device
position approximately
56%.
04
Turbine running at
360rpm.
52'
Monitoring bearing
vibrations, shaft
vibrations, TSE
margins, bearing temp
& Turbovisory readings
at 360 rpm.
05
56'
Turbine running at
3000rpm
Synchronise the
Generator with grid.
Pick up 50 MW load by
operating speeder gear.
40'
HRH Pressure: 12
kg/cm2
HRH Temperature:
4400C.
Bypass steam flow:
280t/hr.
-
MS Pressure: 85
kg/cm2
MS Temperature:
5000C
03
50'
HRH Pressure: 12
kg/cm2
HRH Temperature:
4500C.
If tracking device is
Raise the speed set
switched on starting
point to 360 rpm and
device position will
watch the actual speed. automatically track the
EHC position.
Monitor bearing
vibrations, bearing
temperatures, shaft
vibrations, TSE
margins and
turbovisory readings.
04
52'
Ensure tripping of
Jacking oil pump at
540 rpm.
The rate of
acceleration will be
600 to 800 rpm2.
Monitor bearing
vibrations and
temperatures, shaft
vibration, turbovisory
readings and TSE
margins.
05
56'
Synchronise the
generator with grid.
Synchronise the
generator with grid.
40'
HRH: 12kg/cm2.
Bypass steam flow:
280t/hr.
If the programme
interrupts, the
particular step and
criteria to be checked
and corrected for the
programme to proceed
further.
All operations as
explained under EHC
rolling will be carried
out by SGC-Turbine
programme
sequentially.
50'
Monitor bearing
vibration, bearing
temperature, shaft
vibration, TSE margins
and Turbovisory
readings.
To achieve the
programme as per the
start up curve, the
main steam
temperature should be
maintained steadily till
loading of 50 MW.
04
52'
Monitor bearing
temperature and
vibrations, shaft
vibrations, TSE
margins, Turbovisory
readings, seal oil,
primary water,
Hydrogen gas and
Generator winding
temperatures.
56'
Ensure switching on of
load controller at 60
MW.
LOAD: 60 MW.
06
60'
MS: 85 kg/cm2/5000C
HRH: 16kg/cm2/4700C
65'
Main steam flow:
1620t/hr.
Trimming device is in
OFF.
-
Change deaerator
pegging steam from
CRH to Extraction
steam.
Ensure Deaeator
pressure controller
remains on auto.
70'
Ensure healthiness of
fire ball scanners.
86'
HRH:
40.5kg/cm2/5000C
Main steam flow:
1620t/hr.
135'
HRH: 40.5
kg/cm2/4800C
********************