You are on page 1of 39

CONTENTS

SL. N O .

DESCRIPTION

01.

CO L D ST AR T - U P

02.

IN T E GRA T E D ST AR T U P PR O C EDU R E C O LD S TAR T U P

03.

H O T AN D WA RM S TA RT U PS.

04.

IN T E GRA T E D ST AR T U P PR O C EDU R E WAR M S TAR T UP

05.

IN T E GRA T E D ST AR T U P PR O C EDU R E H O T ST AR T U P .

06.

10.

STA RT U P B Y CU RV ES F O R ABS O LU T E CO L D ST AR T W IT H HP /L P B YP ASS


SYS T E M.
STA RT UP CU RV ES AFT E R 4 8 H OUR S SH AT D O W N W IT H H P/ LP BY PA SS
SYS T E M.
STA RT U P P RO C E DU RE A FT E R 8 H O URS S HU T D O W N W IT H HP/ L P B YP ASS
SYS T E M.
T EC H N ICA L DA TA L IM IT CUR V ES F O R T URB IN E VA LV E S WA LL OF T H E
CAS IN G S HA FT S.
WAR M IN G UP A N D S TAR T IN G T H E TUR B IN E T EM P ER AT UR E CR IT E R IA.

11.

T EC H N ICA L DA TA RE AC T IV E CA PAC IT Y CU RV E F OR TUR B O G E N ERA T ORS .

07.
08.
09.

COLD START UP
(With Aux Steam available)
A cold start up is by definition, one of which the maximum of HP casing and HP shaft is less
than 1500C. This normally means that the unit is shut down from the maximum load for
more than five days. If machine is started from ambient temperature (HPC/HP shaft temp
approx. 400C), heating up of casting is required. This is accomplished by soaking the
machine at 360 rpm at warming up steam parameters (40kg/cm2, 3600 C), till the TSE
margin are satisfactory.
The rifle construction of the water wall combined with the boiler circulating water
pumps permits very high rate of pressure rising of boiler. An upper limit of 2000C/hr
saturation temperature gradient can be allowed, i.e. approximately the boiler pressure can
be brought to 20 kg/cm2 within an hour of cold start up. But actual temperature gradient is
limited by the thick walled Y piece provided in the main steam and HRH lines. A main steam
line heating is to be started as early as possible (at approx. 4 kg/cm 2) as maximum
differential temperature allowed between inner (98%) and mid wall temperature (50%)

is 400C. So boiler loading is accordingly regulated. It may be preferably to start only two
CC pumps in order to minimise flashing in down comers (and subsequent vibration) when
the boiler water is in range of 850C to 1250C. The third pump should be started before drum
pressure reaches 7 kg/cm2 to minimise the temperature transients experienced by the
pump casing (this is to avoid fast load out back on the boiler in the event of any CC pump
tripping).
To get the rolling parameters, normally two elevation oil guns are taken with
approx. 70 to 80t/hr flow through HP-LP bypass. At that time M.S. parameters would be 40
kg/cm2 and 3600C, HRH parameters would be 12 kg/cm2 and 3600C.
As soon as the turbine loading has started, HP/LP bypass closes and gets completely closed
as the turbine reaches the boiler load. First mill is put into operation around 10% of
generator load. Second mill is put into operation around 25% while third mill is at 40% of
generator load. Fourth and fifth mills are put into operation at 60% and 80% of generator
load respectively. Sixth mill is taken to reach full generator load.
During loading the RH outlet steam temperature has to be kept as close as possible to
SH outlet steam temperature Burner tilt, SH spray, RH spray controls has to be adjusted
accordingly. The turbine-loading rate is decided by a selection circuit which compares the
external load gradient, TSE margin and time dependant gradient (set internally) and
frequency influence.

INTEGRATED START-UP PROCEDURE


COLD START-UP
(AUXILIARY STEAM AVAILABLE)
REF. DRG NO. 20 BPE 691
STEP

TIME

UNIT CONDITION

OPERATION

NOTES

..

Boiler pr. 0 kg/cm (g) Charge Aux. Steam


and Ambient
header 16 ata, 2600C,
temperature
from existing units.

Charge steam to fuel oil


pump house, atomising
steam and tracing steam
deaerator warming up.

Start tank heating of


LSHS oil.

Start one LSHS pump on


recirculation as soon as
the sufficient oil
temperature at inlet is
achieved.

Charge LSHS to boiler


front and keep it on long
recirculation, with
heaters control set on
Auto to maintain 1101290C.

All the steam tracing


lines and electrical
tracings in pump house
& boiler to be charged.

Fill water in drum upto


+200mm.

Ensure that the suction


and discharge valves of
all the CC pumps are
open and the pump
suction and discharge
lines are vented.

Start Bearing cooling


water system pumps for
Boiler, Turbine and TG
auxiliaries .

Check all circuits have


sufficient flow. Before
starting the pumps, the
emergency cooling water
tank level to be checked
and made normal.

Start instrument air


compressor and check
that all the lines to
Boiler and TG are
charged.

Check that all circuits


have sufficient air
pressure.

Start service air


compressor and fill the
air receiver tanks of
SRAPH & PRAPH are
filled.

Ensure that purge air to


HEA is open in all
corners.

Line up Air and flue gas


circuits for startup.

ESP ready in all


respects.

Furnace bottom ash


system and seal through
lined up.

FSSS panel ready in all


respects.

EAST panel ready in all


respects.

Excitation panel ready in


all respects.

Generator protection
panel ready in all
respects.

Generator H2 gas
pressure is 4 kg/cm2

Check purity of H2 gas is


normal.

Generator stator water


system ready in all
respects.

Check purity of
generator stator water is
normal.

Check dampers and


gates register position.

H2 cooling water system


ready in all respects with
SLC on.

Check for level in


LP & HP chemical dozing Hydrazine, Ammonia
system is ready.
and phosphate
preparation tanks.

SADC panel readiness.

Check for air pressure in


all the corners and
elevations.

Power supply for all the


valves and dampers are
ON.

Ensure Aux. air dampers


and modulating.

Supply for all auxiliaries


of SG, Turbine and
Generator is ensured.

Readiness of HP bypass
panel in all respects.

Ensure the oil unit is


running and all the
bypass and spray valves
are closed.
Ensure drum level is
+200 mm, and the drum
air vents are closed.
Ensure drum level is
normal.

Start one of the CC


pumps.

Start the second CC


pump.

Start scanner air fan.

Ensure that all the inlet


Start both the secondary
and outlet air gas
air preheaters.
dampers are open.

Start both the primary


air preheaters.

Ensure that the gas


dampers are closed.

Start one set of ID and


FD fans.

Adjust 30% air flow, and


furnace draft minus 5 to
10 mm WCL.
After purge completion
Boiler trip valves will get
reset.

Charge steam coil


preheater concerned
with the running FD
fans.

Initiate Boiler Purge


(duration 5 minutes).

Also, after purge, adjust


the wind box dampers to
get 30-40 mm
WCL. Wind box dp.

Lub oil system


stopped.

Start one vapour


extraction fan, keep
other fan standby.

Check oil level in MOT.

Line up lub oil cooler


and thrust bearing filter
Start one AOP.

Put on SLCs for other


AOP and EOP.

--

Put lub oil temperature


controller on.

Start one JOP.

--

Put off SLCs JOP 1, 2 &


3. Stop running JOP.

Open gate valve


gearing.

Start one JOP and switch


on SLCs for JOPs.

Check out auto start of


AOP and EOP.
Put on SLCs for other
JOP and DC-JOP.
Check out auto start of
JOP and DC-JOP.
Switch on SLC gate
valve gearing.
-

M/c. comes on barring.

MOT level 50 mm oil


temp. 450C JOP header
pr. 140 kg/cm2 speed 80
100 rpm.

The sequential operation


narrated above on Lub
oil system stopped is
achieved by SGC
mode.

If the programme gets


interrupted, the step
and criteria to be
checked and to be
fulfilled for the
programme to proceed
further.

M/c on barring.

FRF system in stopped


Check FRF tank level.
condition.

Start centrifuge with


both heaters

Line up FRF cooler and


duplex filters in 32-bar
system start one CEP.
Check auto start of
standby CEP.

Establish control fluid


supply to various
services.

Start one VEF.

+200 mm.

FRF tank level O


(normal).
-

Start one recirculation


pump and include one
Filters earth and ultra
fine.

Switch on FRF heater


and keep SLC ON for
FRF temperature 550C.
temperature control, and
control fluid pumps.

Switch ON control fluid


SGC.

FRF system, SGC is


on.

The sequential operation


narrated above in FRF
system stopped
condition is achieved by
SGC-FRF system on
starting programme
mode.

01

oo

Boiler ready for light


up and Turbine on
Turning gear.

Start 4 burners in AB
elevation with LSHS.

SH & RH drains are


open.

MSVs closed and drains


before MSV open.

Regulate oil pressure to


8-10 kg/cm2.

Ensure atomising steam


pressure about 6
kg/cm2.
Insert furnace probe and
ensure that the
temperature is below
5350C.

If the programme gets


interrupted the step and
criteria to be checked
and fulfilled for the
programme to proceed
further.
Check that SH & RH
vents are open.

After 30 minutes, take


additional burners, so as
to ensure a drum metal
temperature raise of
about 20C/min.

Check drum level and


give blow down.

Keep open the Eco.


recirculation valve when
there is no feeding to
drum.

Start motor driven feed


pump on recirculation.

Charge the feed line


upto feed control
station.

Charge heating steam to


deaerator from Aux.
PRDS.

Check deaerator level.

Start condensate pumps


and feed to deaerator as Check hotwell level.
and when required.

--

Start hotwell make up


pumps and feed hotwell
as and when required.

Aux. PRDS steam


15kg/cm2 (g) 2600C

CW system is charged.

CW boxes to ensure
ventilating of water
boxes.

Start one gland steam


exhauster fan.

Line up vacuum pumps


and start one by one
Gradually admit gland
steam when condenser
vacuum reaches
0.2kg/cm2(g).

Vacuum building can be


done through SGC
vacuum on starting
programme mode, gland
steam exhauster has to
be started manually.

Open all drains


connected to flash tanks
and flash boxes
connected to condenser.

Vacuum 09kg/cm2 (g).

Ensure gland steam


admission temperature
is always above 2000C.

--

Open HPBP warm up


valves.

Switch on SLC drains.

02

60'

Close SH & RH header


vents.

Close SH & RH header


drains.

Open MSV by pass lines.

MS, HRH, & CRH lines


will get warmed up.

03

100

Switch on automatic
control interface of LP
bypass.

As soon as the fixed set


point reaches 12
kg/cm2, it seizes.

Boiler pressure 2kg


/cm2

Boiler pressure 5kg


/cm2.

Automatic control
interface gets switched
off when the hot reheat
steam pressure reaches
13kg/cm2 i.e. after
synchronisation.

Open Main steam


valves.

Open HP by pass.

Start third C.C. pump


when boiler pressure
reaches 9 kg/cm2.

Take additional guns in


CD & EF elevation.

Close HPBP warm up


valves.

Air heater soot blowing


to be carried out.
-

A ROLLING THROUGH HYDRAULIC GOVERNOR


Boiler pressure:15
kg/cm2
04

150

Temperature:1802000C

Open HPESVs & IPESVs


for warming up by
operating starting device
to approximately 42%.

Check and ensure that


speed set point is zero
and speeder gear is 0%
position.

Ensure TSE influence is


switched on and
available margins are
greater than = 300 K.

HRH Pressure:812Kg/cm2
-

M. S. Pr. 50 kg/cm2
M.S. temp. 3500C

05

-300

H. R. H. Pr. 12 kg/cm2

Raise the speed set


point of EHC to 3200
rpm

If the oil system of EHC


is isolated at speed Gov.
rack, speed set point
need not be raised.

Gradually raise the


starting device to bring
the speed to 360 rpm

Starting device position


approximately 56%.

Hold the speed at 360


rpm for about 35 to 40
mts.

Ensure closure of gate


valve gearing at 240
rpm. Monitor bearing
vibrations, shaft
vibrations, TSE margins,
bearing temperature &
Turbosupervisory
readings at 360 rpm.

HRH temp. : 3500C


-

Turbine ready for


Rolling.

06

-360

Raise the speed upto


M. S. Pr. 50
2400 rpm through
2
0
kg/cm /350 C. Turbine
starting device at the
running at 360 rpm.
rate of 600 rpm.

Ensure tripping of JOP at


540 rpm.

Raise further speed upto


Starting device will be at
3000 rpm through
90%.
speeder gear.

Monitoring bearing
temperature and
vibrations, shaft
vibrations, TSE margins
and Turbovisory
readings, Seal oil,
Primary water and gas
temperatures &
Generator winding
temperature.

Ensure trippinf of AOP at


2950 rpm.

Speeder gear position


will be approximately at
50 to 60%.

MS Pr. 50 kg/cm2.
Temperature:
Put AVR on Auto.
3500C Turbine running
at 3000 rpm.

07

370

Close field breaker.

Set manually the


generator voltage to grid
voltage.

Synchronise the
generator with grid.
-

Pick up 50 MW load by
operating speeder gear.

Ensure closure of HPBP


Increase HPBP set point. steam valves & spray
valves.

Drain pot drains of MS,


CRH & HRH and
Close other drains, M.S.
extraction steam lines
HRH, keeping SLC drains
will operate as per the
on.
actuation of level
switches.

B - ROLLING THROUGH EHC.

04

150'

MS Pr.: 15 kg/cm2.
Temperature:1802000C HRH
Pressure:8to12kg/cm2.

Check and ensure that


Open HPESVs & IPESVs TSE influences is
for warming up by
switched on and
operating starting device available margins are
to approximately 42%.
0
greater than 30 K.
-

Check and ensure that


speed set point is zero
and speeder gear is 0%
position.

MS Pressure: 50
kg/cm2
MS
Temperature:3500C
05

300'

HRH Pressure:
12kg/cm2
HRH Temperature:
3500C.

Check and ensure


opening of valves in
Raise the starting device
HP/IP secondary fluid
to about 70%.
lines to EHC at speed
control rack.

Turbine Ready for


rolling

Raise the speed set


point to 360 rpm and
watch the actual speed.

Raise the speeder gear


to 100%

Hold the speed at 360


rpm for about 35 to 40
mts.

MS Pressure:50
kg/cm2
06

360'
MS
Temperature:3500C

Turbine speed: 360


rpm.

Raise the speed set


point to 3000 rpm.

If tracking device is
switched ON, starting
device position will
automatically track the
EHC position

Ensure closure of gate


valve gearing at 240
rpm.
Monitoring bearing
vibrations, bearing
temperatures, shaft
vibrations, TSE margins
and Turbovisory
readings.
Ensure tripping of
jacking oil pump at 540
rpm.
The rate of acceleration
will be 600 to 850 rpm.

Monitor bearing
vibration and
temperatures, shaft
vibrations, Turbovisory
readings and TSE
margins

Monitor and control,


SEAL oil temperatures,
Primary water temp.
Hydrogen gas
temperature and
winding temperature.

Ensure tripping of AOP


at 2950 rpm.

MS Pressure: 50
kg/cm2
07

370'

MS Temperature:
3500C

Put AVR on auto, Close


Field Breaker.

Set manually generator


voltage to grid voltage.

Turbine speed: 3000


rpm.
-

Speed set point will raise


automatically by 8 rpm
and load will be picked
upto 20MW.

Synchronise the
generator with grid.

Raise the speed set


point and pick up the
load to 50 MW.

Ensure closure of HPBP


Increase HPBP set point. steam valves & spray
valves.

Drain pot drains of MS,


CRH, HRH and
extraction steam lines
will operate as per the
actuation of level
switches.

Close other drains of


MS, CRH, HRH, keeping
SLC drains 'ON'.

C - ROLLING THROUGH SGC - TURBINE.


MS Pressure: 15
kg/cm2
04

150'

MS Temp.:180-200 C
HRH Pressure: 12

Switch on the start up


programme of SGC
Turbine.

Ensure TSE influence is


switched on.

kg/cm2

If the programme
interrupts the particular
step and criteria to be
checked and corrected
for the programme to
proceed further.

All operations as
explained under EHC
rolling will be carried out
by SHC Turbine
programme sequentially.

MS Pressure: 50
kg/cm2
MS Temperature:
3500C
05

300'

HRH Pressure: 12
kg/cm2

Turbine speed will be


raised to 360 rpm
through SGC
Programme.

Ensure closure of gate


valve gearing at 240
rpm.

HRH Temp.: 3500C.


Turbine Ready for
rolling

Monitor bearing
vibration, bearing
temperature, shaft
vibration, TSE margins
and Turbovisory
readings.

To achieve the
programme as per the
starting curve, the main
steam temperature
should be maintained
steadily till loading upto
50 MW.

MS Pressure: 50
kg/cm2
06

360'

MS Temperature:
3500C

Turbine speed will be


raised upto 3000rpm
through SGCprogramme.

Ensure tripping of JOP at


540 rpm.

Turbine running at 360


rpm.
-

MS Pressure: 50
kg/cm2
07

370'

MS Temperature:
3500C
Turbine
speed:3000rpm.

Ensure tripping of AOP


at 2950 rpm.

Monitor bearing temp


and vibrations, shaft
vibrations, TSE margins
and turbovisory readings
seal oil, primary water,
Hydrogen gas and
Generator winding
temperatures.

SGC programme will


switch ON field breaker, Ensure SGC start up
put AVR on auto,
programme is
synchronise and pick up completed.
load upto 20 MW.

Raise the speed set


point and pick up the
load upto 50 MW.

Ensure closure of HPBP


Increase HPBP set point. steam valves and spray
valves.

Drain pot drains of MS,


Close other drains of
CRH, HRH extraction
M.S. CRH and HRH,
steam lines will operate
keeping SLC drains ON. as per the actuation of
level switches.

Load : 55 MW

08

390'

M.S. :
54kg/cm2/3500C
HRH : 12
kg/cm2/3400C

Before starting P.A. fan,


Start seal air fan and PA
ensure that air and gas
fan and take first mill in
dampers of Primary Air
service.
Preheaters are open.

Charge ESP fields

Ensure Ash handling


system is ready.

Start the second set of


ID & FD fans.

Make ready SH & RH


spray systems.

Cut in L.P. heaters 2 &


3.

Ensure switching on of
load controller above
60MW.

Cut out heating steam


from Aux. P.R.D.S. to
Deaerator.

Peg Deaerator from CRH


steam gradually upto 2
kg/cm2.

Cut in auto controllers.

Load : 55 MW

M.S. :
54kg/cm2/3500C
HRH : 12
kg/cm2/3400C

Charge Aux. PRDS


station from CRH. Cut in
spray and maintain a
temperature of 2500C.

Ensure energizing of
solenoid in trimming
device at and above 100
MW load.

Raise the pressure set


Peg Deaerator gradually point of Deaerator
to 4 kg/cm2.
pressure controller
gradually.

Cut in IInd mill and cut


in auto controllers.

Start withdrawing oil


support gradually.

Control main steam and


reheat steam
temperatures by using
spray if required.

Increase the wind box to


furnace differential
pressure to 100mm
W.C. by adjusting SADC.

Ensure fire ball scanner


healthiness

Load : 160 MW
M.S. :
90kg/cm2/3800C
10

440'
HRH : 20
kg/cm2/3800C
Steam flow : 580t/hr.

Charge H.P. heaters 5A,


5B, 6A and 6B.

Put controllers on auto.

Start first TDBFP &


second CEP.

Charge Deareator
Ensure Deareator
pegging steam flow CRH
Pressure controller
to Extraction around 200
remains as auto.
MW load.

Load : 250 MW
M.S. :
120kg/cm2/4200C
11

480'
HRH : 26
kg/cm2/3400C

Cut in IIIrd mill and cut


in auto controllers.

Steam flow : 820t/hr.


-

Start second P.A. Fan.

Before starting P.A. fan


ensure that air and gas
dampers of PAPHs are
open.

Load : 320 MW
M.S. :
125kg/cm2/3500C
12

510'
HRH : 28-30
kg/cm2/3400C

Cut in IVth mill and cut


in auto controllers.

Steam flow : 1040t/hr.


-

Cut of oil support


completely.

Ensure healthiness of
fire ball scanners.

Load : 405 MW
M.S. :
145kg/cm2/4600C
13

550'

HRH : 33
kg/cm2/4600C

Cut in Vth mill and cut in


auto controllers.

Cut in second TD BFP


and switch off motor
driven BFP.

If full load is not reached


cut in VIth mill along
with its controllers.
Increase the set point of
SH & RH spray
controllers such that
rated parametes are

Steam flow : 1310


t/hr.
-

Load : 500 MW

14

590'

M.S. : 170
kg/cm2/4750C
HRH : 40.5
kg/cm2/4750C

achieved gradually.
Load : 405 MW
M.S. :
145kg/cm2/4600C
15

670'

HRH : 33
kg/cm2/4600C

Steam flow : 1310


t/hr.

WARM AND HOT START UPS


(With Aux. Steam Available).
A warm start up is, by definition, one which the maximum of HP casing/HP shaft
temperature is between 1500C and 3500C. This normally means that the unit is shut down
from the maximum load for one to four days. Depending upon the absolute temperature of
HP casing and HP shaft, steam parameters are derived. A hot start up is by definition one
which the maximum of HP casing/shaft temperature is more than 3500C. In this case to get
the rolling parameters two mills are taken into service keeping HP, LP by pass in
operation. (Again the flow rate is restricted by the Y pieces constraints i.e., 400C). In
both the cases, curves are given to derive the rolling parameters. In case when machine is
rolled through EAST, curve generators, calculate and give permissive for rolling.

INTEGRATED START-UP PROCEDURE


WARM START UP (AFTER 48 HOURS SHUT DOWN).
TIME IN
MINUTES

UNIT CONDITION

OPERATION

NOTES.

One CC pump in
operation and scanner
fan in operation.

Motor operated BFP is


run as and when
required to maintain the
drum level.

Both SAPHs and PAPHs


in operation.

STEP

Turbine on bearing
gear with AOP, JOP
and seal oil pumps in
operation.

Control fluid system


ready in all respects.
One circulating pump
in operation with one
earth filter and ultra
fine filter in circuit.

Generator gas system,


seal oil system and
primary water system
in operation.

Bearing cooling water


system in operation.

HT and LT auxiliaries
power supply available.

HP bypass system
ready in all respects.

ESP ready in all


respects.

EAST panels ready in


all respects.

Furnace bottom ash


system and seal trough
lined up.

Vacuum pumps lined


up and ready for
operation.

Gland steam and leak


steam controllers are
lined up and ready for
operation.

Generator protection
panel and exciter
panels ready in all
respects.

Boiler drum pressure =


0 kg/cm2.
SH
temperature between
1300C and 1500C.

1. Charge auxiliary
steam header from
existing units. Pr. 16ata
temp. 2600C.

2. Charge steam to fuel


oil pump house,
atomising steam and
tracing steam.

3. Start tank heating of


LSHS oil.

4. Start one LSHS pump


on recirculation as soon
as sufficient oil temp. at
inlet is achieved.

Start instrument oil


compressor and service
air compressors and
check that all lines to
boiler and TG are
charged.

Charge LSHS pump to


boiler front and keep it
on long recirculation
with heaters control set
on auto to maintain
1200C.

Start circulating water


pump for condenser and
deaerate the condenser
water boxes.

Ensure running of
motor driven BFP
continuously for
maintaining drum
level.

Start second CC Pump.

Start one set of ID and


FD fans.

Initiate boiler purge.

Start one CEP and keep


the hot well make up in
service.

Start one of the control


fluid pumps and keep
the second as auto
standby.

Keep the control fluid


temperature control on
auto.

Line up main steam,


CRH and HRH steam
lines for charging by
opening respective line
drains.

Line up FSSS panels in


all respects

01

oo

SH & RH drains are


open.

MSVs closed and


drains before MSV
open.

Ensure atomising
steam pressure of
about 6 kg/cm2

Ensure motor operated


BFP is in service.

Start Gland steam


Exhauster.

Start one by one


vacuum pumps.

Admit gland steam


Ensure gland steam
when vacuum reaches admission temperature
0.2 kg/cm2.
is always above 2000C.

Vacuum building can be


done through SGC
vacuum on starting
programme mode.
Gland steam exhauster
has to be started
manually.

Charge heating steam


line to Deaerator from
Aux. PRDS.

Boiler ready for light


up and turbine on
turning gear.

Start 4 burners in AB
elevation with LSHS.

Check that SH & RH


vents are open.

Open all drains


connected to flash tanks Ensure condenser
and flash boxes
vacuum of 0.8
connected to
kg/cm2.
condenser.

Switch on SLC drains.

Close SH & RH header


vents and drains.

Ensure boiler pressure


is 2kg/cm2.

Open HPBP warming up


valves.

Open MSV bypass lines.

Switch Automatic
control interface of LP
bypass.

As soon as the fixed


set point reaches
12kg/cm2, it seizes.

Automatic control
interface gets switched
off when the hot
reheat steam pressure
reaches 13kg/cm2(i.e.)
after synchronisation.

Open Main steam stop


valves.

Open HP bypass and


Ensure Boiler pressure
close the HPBP warm up
is 5kg/cm2.
valves.

Start third CC pump.

Ensure MS, CRH & HRH


lines get warmed up.

Ensure Boiler pressure


is 9kg/cm2.

Put HP bypass controller


on auto and vary the
Ensure Boiler pressure
set point according to
is 10kg/cm2
the gradient of pipeline
temperatures.

Put HP bypass spray


control on auto.

Take additional guns


according to the
requirement.

Air heater soot blowing


to be carried out.

A ROLLING THROUGH HYDRAULIC GOVERNOR.


MS: 50 kg/cm2/3650C
02

180'

Open HPESV and IPESV


HRH: 12 kg/cm2/3250C for warming up by
operating starting
device to approx. 42%
By pass steam flow:
170t/hr.

MS: 60 kg/cm2/4000C
Raise the speed set
HRH: 12 kg/cm2/3500C
point of EHC to 3200
rpm.
By pass steam flow:
200t/hr.

Check and ensure that


speed set point is zero
and speeder gear is
0%.
Ensure TSE influence is
switched on and
available margins are
0
greater than 30 K.
If the oil system of
EHC is isolated at
speed Gov. rack, speed
set point need not be
raised.

03

210'

Gradually rise the


starting device to bring
the speed to 360 rpm.

Starting device
position approximately
56%.

Hold the speed at 360


rpm for about 5
minutes.

Ensure closure of gate


valve gearing at 240
rpm.

04

215'

Raise the speed upto


Turbine running at 360 2400 rpm through
rpm.
starting device at the
rate of 600 rpm.
-

Monitor bearing
vibrations, shaft
vibrations, TDE
margins, bearing temp.
& Turbovisory readings
at 360rpm.
Ensure tripping of JOP
at 540 rpm.

Raise further speed


Starting device will be
upto 3000 rpm through
at 90%.
speeder gear.

Monitor bearing temp


& vibrations, shaft
vibrations, TSE
margins and
Turbovisory readings.
Seal oil, Primary water
and gas temperatures
& Generator winding
temperature.

Ensure tripping of AOP


at 2950 rpm.

Speeder gear position


will be approx. at 50 to
60 %.

05

220'

Turbine running at
3000 rpm

Put AVR on auto.

Close field breaker.

Set manually the


generator voltage to
grid voltage.

Synchronise the
generator with grid.
Pick up 50 MW load by
operating speeder gear.

Increase HPBP set


point.

Drain pot drains of MS,


CRH, and HRH and
Close other drains, M.S.
extraction steam lines
HRH, keeping SLC
will operate as per the
drains on.
actuation of level
switches.

Ensure closure of HPBP


steam valves & spray
valves.

Further load raising will


be done by operating
the speeder gear
according to the start
up curve.

B ROLLING THROUGH EHC


MS: 50 kg/cm2/3650C
02

180'

Open HPESVs and


HRH: 12 kg/cm2/3250C IPESVs for warming up
by operating starting
device to approx. 42%.
By pass steam flow:
170t/hr.
-

Check and ensure that


TSE influence is
switched on and
available margins are
0
greater than 30 K.
Check and ensure that
speed set point is zero
and speeder gear is
0%.

MS: 60 kg/cm2/4000C
HRH: 12 kg/cm2/3500C
03

210'

By pass steam flow:


200t/hr.

Raise the starting


device to about 70%.

Check and ensure


opening of valves in
HP/IP secondary fluid
lines to EHC at speed
control rack.

Turbine ready for


rolling.

If tracking device is
Raise the speed set
switched on starting
point to 360 rpm and
device position will
watch the actual speed. automatically track the
EHC position

Raise the speeder gear


to 100%.

Ensure closure of gate


valve gearing at 240
rpm.

Hold the speed at 360


rpm for about 5
minutes.

Monitor bearing
vibrations bearing
temperatures, shaft
vibrations, TSE
margins & turbovisory
readings.

Raise the speed set


point to 3000 rpm.

Ensure tripping of
Jacking oil pump at
340 rpm.

04

215'

Turbine running at
360rpm.

Monitor bearing
vibrations and temps,
shaft vibration,
turbovisory readings
and TSE margins.

05

225'

Turbine speed: 3000


rpm.

Ensure tripping of AOP


at 2950 rpm.

Put AVR on auto close


Field breaker.

Set manually generator


voltage to grid voltage.

Speed set point will be


raise automatically by
about 8 rpm & load will
be picked upto 20 MW.

Synchronise the
generator with grid.

Raise the speed set


point and pick up the
load to 50 MW.

Increase HPBP set


points.

Ensure closure of HPBP


steam valves and
spray valves.

Close other drains of


MS, CRH, and HRH
keeping SLC drains
ON.

Drain pot drains of MS,


CRH, HRH and
extraction steam lines
will operate as per the
actuation of level
switches.

C ROLLING THROUGH SGC TURBINE.


MS: 50 kg/cm2/3650C
02

180'

HRH: 12 kg/cm2/3250C
By pass steam flow:
170t/hr.

Switch on the start up


programme of SGC
Turbine.

Ensure TSE influence is


switched on.

If the programme
interrupts the
particular step and
criteria to be checked
and corrected for the
programme to proceed
further.

All operations as
explained under EHC
rolling will be carried
out by SGC Turbine
programme
sequentially.

MS: 50 kg/cm2/3650C
HRH: 12 kg/cm2/3250C

03

210'

By pass steam flow:


170t/hr.
Turbine ready for
rolling.

Turbine speed will be


raised to 360 rpm
through SGCProgramme.

Ensure closure of gate


valve gearing at 240
rpm.

Monitor bearing
vibration, bearing
temp, shaft vibration,
TSE margins and
Turbovisory readings.

To achieve the
programme as per the
starting curve, the
main steam
temperature should be
maintained steadily till
loading upto 50 MW.

MS: 60 kg/cm2/4000C
04

215'

Turbine speed will be


Turbine running at 360 raised upto 3000 rpm
rpm.
through SGC
Programme.

MS: 60 kg/cm2/4000C
05

225'

Turbine speed: 3000


rpm.

Ensure tripping of JOP


at 540 rpm. Ensure
tripping of A.O.P. at
2950 rpm.
Monitor bearing temp
& vibrations, shaft
vibrations, TSE margin
and turbovisory
readings, seal oil,
primary water,
Hydrogen gas and
Generator winding
temperatures.

SGC programme will


switch ON field breaker, Ensure SGC Start up
put AVR on auto,
programme is
synchronise and pick up completed.
load upto 20 MW.
Raise the speed set
point and pick up load
upto 50 MW.

Ensure closure of HPBP


Increase HPBP set point steam valves and
spray valves.

Close other drains of


M.S., CRH and HRH,
keeping SLC drains
ON.

Drain pot drains of


M.S., CRH, HRH and
Extraction steam lines
will operate as per the
actuator of level
switches.

Cut in L.P. heaters 2


and 3.

Ensure switching on of
load controller at 60
MW.

Load: 60 MW
06

230'

MS: 60 kg/cm2/4100C
HRH: 14 kg/cm2/3600C

Cut out heating steam


from Aux. PRDS to
Deaerator.

Peg Deaerator from


CRH steam gradually
upto 2 kg/cm2.

Cut in all auto


controllers.

Start seal air fan and


P.A. fan

Cut in further oil guns


for raising parameters.

Before starting P.A.


fan, ensure that air
and gas dampers of
Primary Air Preheaters
are open.
-

Load: 110 MW
MS: 80 kg/cm2/4200C
HRH: 19 kg/cm2/3800C
07

Cut in 1st coal mill and


cut in Auto controllers.

Make ready SH & RH


spray system.

Charge ESP Fields.

Ensure Ash handling


system is ready.

Charge Aux. PRDS


station from CRH. Cut
in spray and maintain a
temperature of 2500C.

245'
Main steam flow:
470t/hr.
Trimming device is in
OFF.

Raise the pressure set


Peg Deaerator gradually point of Deaerator
upto 4 kg/cm2.
pressure controller
gradually

Cut in H.P. heaters and


put the level controls on
auto.

Start first TD BFP and


second CEP around a
load of 170 MW.

Increase the windbox to


furnace diff. pressure to
100mm. W.C. by
adjusting SADC.

Load: 200 MW
MS: 100 kg/cm2/4350C
08

270'

Cut in IInd mill and cut


HRH: 19 kg/cm2/4000C in auto controllers.

Main steam flow:


750t/hr.
-

Start withdrawing oil


support gradually.

Control main steam and


reheat steam
temperature by using
spray if required.

Change Deaerator
pegging steam from
CRH to Extraction
steam.

Cut in IIIrd mill and cut


in auto controllers.

Start second P.A. fan.

Ensure healthiness of
fire ball scanners.
-

Ensure Deaerator
pressure controller
remains on auto.
Before starting P.A. fan
ensure that air and gas
dampers of PAPH are
open.

Load: 320 MW
MS: 125 kg/cm2/4500C
09

300'

Cut in IVth mill and cut


HRH: 30 kg/cm2/4300C in auto controllers.
Main steam flow:
1080t/hr.

Cut off oil support


completely.

Ensure healthiness of
fire ball scanners.

Cut in Vth coal mill and


cut in auto controllers.

Start second TDBFP and


switch off motor driven
BFP.

Cut in VIth coal mill and


cut in auto controllers.

Check all parameters at


full load and ensure
them within limits.

Increase the set point


of SH & RH spray
controllers such that
rated parameters are
achieved.

Load: 500 MW
MS: 170 kg/cm2/4800C
10

340'

HRH: 40.5
kg/cm2/4800C
Main steam flow:
1620t/hr.

Load: 500 MW
MS: 170 kg/cm2/5350C
11

420'

HRH: 40.5
kg/cm2/5350C

Main steam flow:


1570t/hr.

INTEGRATED START UP PROCEDURE


HOT START UP (AFTER 8 HOURS SHUT DOWN)

STEP

TIME IN
MINUTES.

UNIT CONDITION

OPERATION

NOTES.

Two CC pumps in
operation and scanner
fan in operation.

Motor operated BFP is


run as and when
required to maintain the
drum level. If necessary
BFP should be kept
running continuously.

Both SAPHs and PAPHs


in operation.

Turbine on barring
gear with AOP, JOP
and seal oil pumps in
operation.

Control fluid pump in


operation. One
circulating pump in
operation with one
earth filter and ultra
fine filter in circuit.

Generator gas system,


seal oil system and
primary water system
in operation.

Bearing cooling water


system in operation.

Condenser circulating
water system in
operation.

Service air and


instrument air
compressors in
operation.

One condensate pump


in operation and hot
well make up in
service.

Aux. steam header


charged from existing
units (16ata 2600C).

LSHS pump in
operation on long
recirculation upto
boiler front with
heaters control set on

HP bypass system
ready in all respects.

LP & HP and chemical


dosing system ready.

ESP panels ready in all


respects.

EAST panels ready in


all respects.

Furnace bottom ash


system and seal trough
lined up.

Vacuum pumps lined


up and ready for
operation.

Gland steam and leak


steam controllers are
lined up and ready for
operation.

Generator protection
panel and exciter
panels ready in all
respects.

FSSS panel ready in all


respects.

Boiler drum Pr. 75


kg/cm2 SH. Temp.
between 4150C and
4300C.

Start one gland steam


exhauster.

Start one by one


vacuum pumps.

Admit gland steam


Ensure gland steam
when vacuum reaches admission temperature
0.2 kg/cm2.
is always above 2000C.

Vacuum building can be


done through SGC
vacuum on starting
programme mode.
Gland steam exhauster
has to be started
manually.

Line up main steam,


CRH and HRH steam
lines for charging by
opening respective line
drains.

Ensure MSV is closed.

Open all drains


connected to flash tanks
Ensure condenser
and flash boxes
vacuum of 0.8 kg/cm2.
connected to
condenser.

Ensure condenser
vacuum of 0.8 kg/cm2.

Open HPBP warming up


valves.

Switch Automatic
control interface of LP
bypass.

Start third CC pump.

As soon as the fixed


set point reaches 12
kg/cm2, it seizes.
Automatic control
interface gets switched
off when the hot
reheat steam pressure
reaches 13
kg/cm2(i.e.) after
synchronisation.
Ensure differential
temp. is within
permissible limits.
Ensure running of
motor driven BFP
continuously for
maintaining drum
level.

Start both ID & FD fans

Initiate boiler purge.

Charge heating steam


line to Deaerator from
Aux. PRDS.

01

oo

Boiler ready for light


up and turbine on
turning gear.

Start 4 burners in AB
elevation with LSHS.

Ensure atomising
steam pressure of
about 6kg/cm2.

Drum Pr. 75 kg/cm2


SH. Temp. 4150C and
4300C.

Ensure motor operated


BFP is in service.

Open drains before


MSV.

Open MSV by pass


lines.

Open Main steam stop


valves.

Open HP bypass and


close the HPBP warm up
valves.

Put HP bypass
controllers on auto and
vary the set point
according to the
gradient of pipeline

Ensure MS, CRH, HRH


lines got warmed up.

temperatures.

Put HP bypass spray


control on auto.

Take additional guns


according to the
requirement.

Air heater soot blowing


to be carried out.

Before starting P.A.


Fans ensure that air
Start both P.A. fans and
and gas dampers of
seal air fans.
Primary air preheaters
are open.

Line up milling system


for starting.

A ROLLING THROUGH HYDRAULIC GOVERNOR


MS: 85 kg/cm2/4850C
02

40'

HRH: 12 kg/cm2/4400C Cut in first coal mill &


cut in auto controllers.
Bypass steam flow:
280t/hr.

Make ready SH and RH


spray system.

Ensure Ash handling


system is ready.

Charge ESP fields.

Increase the windbox to


furnace diff. Pressure to
100mm W.C. by
adjusting S.A.D.C.

Cut in second mill and


cut in auto controllers.

Peg the deaerator from


CRH gradually upto 2
kg/cm2.

Open HPESVs and


IPESVs for warming up
by operating starting
device to approximately
42%.

Check and ensure that


speed set point is zero
and speeder gear is at
0%.

Ensure TSE influence is


switched on and
available margins are
0
greater than 30 K.

MS Pressure: 85
kg/cm2
MS Temperature:
5000C
HRH Pressure: 12
kg/cm2
03

50'
HRH Temperature:
4500C.

Raise the speed set


point of EHC to 3200
rpm.

If the oil of EHC is


isolated at speed Gov.
rack, speed set point
need not be raised.

Gradually raise the


starting device to bring
the speed to 360 rpm

Starting device
position approximately
56%.

Bypass steam flow:


360t/hr.
Turbine Ready for
rolling
-

04

Turbine running at
360rpm.

52'

Ensure closure of gate


valve gearing at 240
rpm.

Monitoring bearing
vibrations, shaft
vibrations, TSE
margins, bearing temp
& Turbovisory readings
at 360 rpm.

Raise speed upto 2400


rpm through starting
device at the rate of
600 rpm.

Ensure tripping of JOP


at 540 rpm.

Raise further speed


upto 300 rpm through
speeder gear.

Starting device will be


at 90%.

Monitor bearing temp


and vibrations, shaft
vibrations, TSE
margins and
turbovisory readings.
Seal oil Primary water
and gas temperatures
and Generator winding
temperature.

Ensure tripping of AOP


at 2950 rpm.

05

56'

Turbine running at
3000rpm

Speeder gear position


will be approximately
at 50 to 60%.

Put AVR on auto.

Close field breaker.

Set manually the


generator voltage to
grid voltage.

Synchronise the
Generator with grid.
Pick up 50 MW load by
operating speeder gear.

Increase HPBP set


point.

Drain pot drains of MS,


CRH, and HRH and
Close other drains, M.S.
extraction steam lines
CRH, HRH, keeping SLC
will operate as per the
drains on.
actuation of level
switches.

Further load raising will


be done by operating
the speeder gear
according to the start
up curve.

Ensure closure of HPBP


steam valves & spray
valves.

B ROLLING THROUGH EHC


MS Pressure: 85
kg/cm2
MS Temperature:
4850C
02

40'

HRH Pressure: 12
kg/cm2

Cut in first coal mill &


cut in auto controllers.

Make ready SH & RH


spray systems.

Charge ESP fields.

Ensure Ash handling


system is ready.

HRH Temperature:
4400C.
Bypass steam flow:
280t/hr.
-

Increase the windbox to


furnace diff. Pressure to
100mm W.C. by
adjusting S.A.D.C.

Cut in second mill and


cut in auto controllers.

Peg the deareator from


CRH gradually upto 2
kg/cm2.

Open HPESVs and


IPESVs for warming up
by operating starting
device to approximately
42%.

Check and ensure that


speed set point is zero
and speeder gear is at
0%.

Ensure TSE influence is


switched on and
available margins are
0
greater than 30 K.

MS Pressure: 85
kg/cm2
MS Temperature:
5000C

03

50'

HRH Pressure: 12
kg/cm2

Raise the starting


device to about 70%.

HRH Temperature:
4500C.

Check and ensure


opening of valves in
HP/IP secondary fluid
lines to EHC at speed
control rack.

Turbine Ready for


rolling. Bypass steam
flow: 360t/hr.

If tracking device is
Raise the speed set
switched on starting
point to 360 rpm and
device position will
watch the actual speed. automatically track the
EHC position.

Raise the speeder gear


to 100%.

Ensure closure of gate


valve gearing at 240
rpm.

Hold the speed at 360


rpm for about 5
minutes.

Monitor bearing
vibrations, bearing
temperatures, shaft
vibrations, TSE
margins and
turbovisory readings.

04

52'

Turbine reading at 360 Raise the speed set


rpm.
point to 300 rpm.
-

Ensure tripping of
Jacking oil pump at
540 rpm.

The rate of
acceleration will be
600 to 800 rpm2.

Monitor bearing
vibrations and
temperatures, shaft
vibration, turbovisory
readings and TSE
margins.

Monitor and control,


seal oil temperatures,
primary water
temperature. Hydrogen
gas temperature and
winding temperature.

Ensure tripping of AOP


at 2950 rpm.

05

56'

Turbine speed: 3000


rpm.
-

Put AVR on auto Close


field breaker.

Set Manually generator


voltage to grid voltage.

Synchronise the
generator with grid.

Speed set point will be


raised automatically by
about 8 rpm and load
will be picked upto 20
MW.

Synchronise the
generator with grid.

Increase HPBP set


point.

Ensure closure of HPBP


steam valves and
spray valves.

Close other drains of


MS. CRH and HRH,
keeping SLC drains
ON.

Drain pot drains of MS,


CRH, HRH and
extraction steam lines
will operate as per the
actuation of level
switches.

C ROLLING THROUGH SGC TURBINE.


MS: 85 kg/cm2/4850C
02

40'

HRH: 12kg/cm2.
Bypass steam flow:
280t/hr.

Cut in first coal mill &


cut in auto controllers.

Make ready SH & RH


spray systems.

Ensure Ash handling


system is ready.

Charge ESP fields.

Increase the windbox to


furnace diff. Pressure to
100mm W.C. by
adjusting S.A.D.C.

Cut in second mill and


cut in auto controllers.

Peg the deaerator from


CRH gradually upto 2
kg/cm2.

Switch on the start up


programme of SGCTurbine.

Ensure TSE influence is


switched ON.

If the programme
interrupts, the
particular step and
criteria to be checked
and corrected for the
programme to proceed
further.

All operations as
explained under EHC
rolling will be carried
out by SGC-Turbine
programme
sequentially.

Turbine ready for


rolling.
Turbine speed will be
raised to 360 rpm
through SGCHRH: 12kg/cm2/4500C
programme.
MS: 85 kg/cm2/5000C
03

50'

Ensure closure of gate


valve gearing at 240
rpm.

Bypass steam flow:


360t/hr.

Monitor bearing
vibration, bearing
temperature, shaft
vibration, TSE margins
and Turbovisory
readings.

To achieve the
programme as per the
start up curve, the
main steam
temperature should be
maintained steadily till

loading of 50 MW.

04

52'

Turbine speed will be


Turbine reading at 360 raised upto 3000 rpm
rpm.
through SGCprogramme.
-

Ensure tripping of JOP


at 540 rpm.

Ensure tripping of AOP


at 2950 rpm.

Monitor bearing
temperature and
vibrations, shaft
vibrations, TSE
margins, Turbovisory
readings, seal oil,
primary water,
Hydrogen gas and
Generator winding
temperatures.

Turbine speed: 3000


rpm.
SGC Programme will
switch ON field breaker, Ensure SGC-start up
put AVR on auto
programme is
HRH: 12kg/cm2/4500C synchronise and pick up completed.
load upto 20 MW.
Bypass steam flow:
360t/hr.
MS: 85 kg/cm2/5000C
05

56'

Raise the speed set


point and pick up load
upto 50 MW.

Increase HPBP set


point.

Ensure closure of HPBP


steam valves & spray
valves.

Close other drains of


M.S, CRH and HRH,
keeping SLC drains
ON.

Drain pot drains of MS,


CRH, HRH and
Extraction steam lines
will operate as per the
actuation of level
switches.

Cut in L.P. heaters 2


and 3.

Ensure switching on of
load controller at 60
MW.

LOAD: 60 MW.
06

60'

MS: 85 kg/cm2/5000C
HRH: 16kg/cm2/4700C

Cut out heating steam


from Aux. PRDS to
Deaerator.

Raise the generator


pressure from
2kg/cm2 to 4kg/cm2.

Cut in auto controller.

Start withdrawing oil


support gradually.

Raise the pressure set


point of Deaerator
pressure controller.
Ensure healthiness of
fire ball scanners.

LOAD: 150 MW.


MS: 100 kg/cm2/5000C
HRH: 20kg/cm2/4800C
07

65'
Main steam flow:
1620t/hr.

Charge Aux. PRDS


station from CRH. Cut
in spray and maintain a
temperature of 2500C.

Trimming device is in
OFF.
-

Cut in H.P. heaters and


put the level controls on
auto.

Start first TD BFP and


second CEP around a
load of 170 MW.

Control main steam and


reheat steam
temperature by using
spray if required.

Change deaerator
pegging steam from
CRH to Extraction
steam.

Cut in IIIrd mill and cut


in auto controllers.

Cut in IVth mill and cut


HRH: 20kg/cm2/4950C in auto controllers.

Ensure Deaeator
pressure controller
remains on auto.

LOAD: 230 MW.


MS: 120 kg/cm2/5000C
08

70'

Main steam flow:


820t/hr.
-

Cut off oil support


completely.

Ensure healthiness of
fire ball scanners.

Cut in Vth coal mill and


cut in auto controllers.

Start second TD BFP


and switch off motor
driven BFP.

Cut in VIth coal mill and


cut in auto controllers.

Check all parameters at


full load and ensure
them within limits.

Increase the set point


of SH & RH spray
controllers such that
rated parameters are
achieved.

LOAD: 500 MW.


MS: 170 kg/cm2/5000C
09

86'

HRH:
40.5kg/cm2/5000C
Main steam flow:
1620t/hr.

LOAD: 500 MW.


MS: 170 kg/cm2/5000C
10

135'

HRH: 40.5
kg/cm2/4800C

Main steam flow: 1570


t/hr.

********************

You might also like