You are on page 1of 1

DAILY PROGRESS REPORT

LOGOS CONSTRUCTIONS PVT LTD

22.12.14

PROJECT

REPORT DATE

Name of Work:
Employer:
Contract No.:
Contractor:

SITE

Dur. in Days:

CONSTRUCTION OF EXIM GODOWN

Project
Start Date

JDA/4101/2013/E Dt 04/06/2014

Project
Completion

Total

Normal Day

Elapsed

Rainy
LOCATION

UNIT

To:

TOTAL QTY.

Balance
Site Conditions:
FOR THE DAY

PLANNED

ACHIEVED

Slushy
PL. NEXT
DAY

Dry

CUMM. TILL
DATE

% COMP

WORK PROGRESS

ACTIVITY DESCRIPTION

From:

06.09.14

MAN POWER
PLANNED

ACTUAL

DESCRIPTION

UNIT

RECEIPTS
FOR DAY

TILL DATE

CONSUMPTION
FOR DAY

TILL DATE

REMARKS

CONSSTRAINTS & INPUTS REQUIRED

LABOUR & MATERIAL

DESCRIPTION

MATERIAL

Executive Engineer visited our site today.He


asked Engineer details as per agreement and
office container.

Distribution

Prepared by:

Project Manager