We are used to calculate progress in excel by applying weightings based on Man-hours, Cost and
planned dates by scheduling from Primavera. Further Plan and actual percentage daily, weekly and
Monthly wise produced.
Also we use Primavera for critical path analysis and comparing deflection of actual from Baseline plan.
My concern is that if I want to calculate progress in Primavera (P6) only, I have three options1. Schedule % Complete
2. Duration % Complete
3. Physical % Complete
In Schedule % Complete, Daily, Weekly and Monthly Plan value is not viewable as well Actual %
Complete at overall and WBS level. Progress reflects at activity level only.
In Duration % Complete, I am only able to view Actual % Complete at Overall and WBS level.
Also In Physical % Complete, Daily, Weekly and Monthly Plan value is not viewable as well Actual %
Complete at overall and WBS level. Progress reflects at activity level only.
Had i applied proper view setting?