TESTING AND COMMISSIONING OF

IRRIGATION SYSTEM
Commissioning of field work and equipment shall include works required
to bring the system into service and to make sure that it is operating efficiently

Tapping point connection:


Main Hole Chamber (Irrigation)
PRV (pressure release valve) pressure 4.5 bar 10 % Nominal
Isolation Valve
Water Meter

Controller:
Easy Accessibility
Check Foundation
Check for start program
Sprinkler
Sprayer
Drip
Check for manual running sequence

Solenoid Valve:
Check the location of valve box
Valve Pressure (2 to 2.5 bar)
Check for support
Check for direction of flow
Check for solenoid wire connection

Spray & Sprinkler:


Check the location of spray & sprinkler

Head Loss from first to last sprayer


Operate sprinkler & spray to check
Radius
Overlapping

Drip:
Check for emission of water from emitting points

Contracto
r

Designati
on

Signature

Consultan
t

Designati
on

Signature