PROGRAMACION CIVILES
Duracin
04Fin
may '15
S
PROGRAMACION CIVILES
32 das
1 INICIO
0 das
2 OBRAS PRELIMINARES
3 das
2.1 LIMPIEZA DE TERRENO
1 da
2.2 TRAZO DE NIVELES
2 das
3 MOVILIZACION DE TIERRAS
24 das
3.1 EXCAVACION DE ZANJAS
6 das
3.2 RELLENO MATERIAL PROPIO
2 das
3.3 ELIMINACION MATERIAL EXCEDENTE
2 das
4 OBRAS CONCRETO SIMPLE
15 das
4.1 CIMIENTO CORRIDO
5 das
4.2 ENCOFRADO Y DESENCOFRADO SOBRECIMIENTO
10 das
4.3 CONCRETO SOBRECIMIENTO
2 das
5 OBRAS CONCRETO ARMADO
29 das
5.1 COLUMNA
29 das
5.1.1 ENCOFRADO Y DESENCOFRADO
9 das
5.1.2 CONCRETO
1 da
5.1.3 ACERO HABILITACION Y COLOCACION 2 das
6 FIN
0 das
Comienzo
11 may '15
L M X
09:35 p.m.
J
18 may '15
L M X
25 may '15
L M X
01 jun '15
L M X
08 jun '15
L M X
11/05
lun 11/05/15
mi 13/05/15
11/05
lun 11/05/15 11/05
12/05
13/05
mi 13/05/15
sb 06/06/15
14/05
mar 19/05/15
jue 04/06/15
sb 06/06/15
mar 02/06/15
19/05
sb 23/05/15
mar 02/06/15
mar 26/05/15
jue 11/06/15
jue 11/06/15
jue 11/06/15
jue 04/06/15
14/05
15/05
vie 15/05/15
jue 11/06/15
19/05
03/06
05/06
06/06
23/05
24/05
25/05
02/06
26/05
03/06
04/06
11/06
04/06
11/06
Tarea
Tarea resumida
Tarea inactiva
Resumen manual
Divisin
Hito inactivo
solo el comienzo
Hito
Hito resumido
Resumen inactivo
solo fin
Resumen
Progreso resumido
Tarea manual
Fecha lmite
Tareas externas
solo duracin
Tarea crtica
Hito externo
Progreso
Pgina 1
04/06