Professional Documents
Culture Documents
ACTIVITIES
O GENERAL REQUIREMENTS
PERIMETER FENCING
I.A.1 Excavation Works
I.A.2 Concrete/Finishing/Masonry Works
I.A.3 Steel/Iron Works
I.A.4 Painting Works
CONCRETE PAVEMENT
I.B.1 Demolition/Clearing
I.B.2 Concrete Works
I.B.3 Roofing Works/Roofing Accessories
I.B.4 Doors and Windows
I.B.5 Painting Works
Smoke & Preparation Area
II.A.1 Excavation Works
II.A.2 Reinforced Concrete Works
II.A.3 Masonry Works
II.A.4 Finishing Works/Floor Topping
II.A.6 Carpentry Works
II.A.7 Roofing Works/Roofing Accessories
II.A.8 Doors and Windows
II.A.9 Iron Works for Dryer
II.A.1 Painting Works
0
II.A.1 Electrical Works
1
SIGNBOARDS
O1
III.A.
1
III.A.
2
III.A.
3
III.A.
4
III.A.
5
FINISH
DURATION
2 days
PRECEDENCE
NONE
94 days
60 days
112 days
O
I.A.1
I.A.2
I.A.3
75
30
60
30
50
21
days
days
days
days
days
days
O
I.B.1
I.B.2
I.B.1
I.B.3, I.B.4
O
II.A.1
II.A.2
II.A.3
II.A.5
9 days
A,B,C,D,E,F
G
H
I
J
K
L
M