Testing Current Design-May end

Gasket design-2nd week June


Flange design-2nd week June
Gas venting- Order parts by May end integrate by June end
Desiccants
Last week June end-

Testing current design

Water Spray test


Water Submersion test
Dirt test?
Electrical contacts?

Gasket design

Material
Thickness
Profile

Gas Venting

Pressure changes during Thermal Runaway?- Battery destructive testing


Normal pressure fluctuations?
Pressure sensor in battery pack?

Fireproofing

Potting Material?
Runaway Propagation.
Ballistic shield?

Mechanical Impact Testing-???