School of Energy, Geoscience, Infrastructure and Society
Foundation Engineering
CLASS EXAMPLE
A building (with a large plan area) was constructed on a clay deposit
over a period extending from May 2005 to May 2007. In May 2010, the average measured settlement was found to be 25mm. The ultimate settlement of the building was calculated as 65mm. Estimate the settlement of the structure in May 2015.
100 80 U% 10 20 30 40 50 60 70 80 90
60
Ulayer
40 20 0
0.2
0.4 Time Factor, T
0.6 cv t
H2 d
T 0.008 0.031 0.071 0.126 0.197 0.287 0.403 0.567 0.848