You are on page 1of 7

TENGIZCHEVROIL

MAJOR CAPITAL PROJECT


X-000-056-07
Tengizchevroil

Plant Firewater
Upgrade Project

TECHNICAL PIPING PASSPORT (TPP)


()

1-031-L-TPP-10002
Hydro test of the Spools in the Contractors shop

TCO PLANT FIREWATER UPGRADE PROJECT

Subsystem: 05607-WF-Q758-01
: 05607-WF-Q758-01
Subsystem Description: KTL 1 -Fire Water Double Red Zone.DMC.
Installation & Modification of Fire Hydrant FH-173 (Old FH-A1), Fire Monitors
FM-47 (Old FM-B1), VP-109 (Old VP-13).
1 - ,
.
-173 ( -A1), -47
( -B1), -109 ( -13)
Job Package No:
No:
Contractor:
:

JPK-056-07-Q-0758
JPK-056-07-Q-0758
MUNAIGASKURYLYS (MGK)
()

TENGIZCHEVROIL
MAJOR CAPITAL PROJECT

X-000-056-07
Tengizchevroil

Plant Firewater
Upgrade Project

TECHNICAL PIPING PASSPORT (TPP)


()
Hydro test of the Spools in the Contractors shop

TCO PLANT FIREWATER UPGRADE PROJECT


APPROVAL REGISTER FOR 1-031-L-TPP-10002
1-031-L-TPP-10002

TENGIZCHEVROIL
MAJOR CAPITAL PROJECT

X-000-056-07
Tengizchevroil

Plant Firewater
Upgrade Project

Technical Piping Passport 1-031-L-TPP-10002 for Sub-System 05607-WF-Q758-01


JPK-056-07-Q-0758 was reviewed and approved by:
1-031-L-TPP-10002
05607-WF-Q758-01 JPK-056-07-Q-0758 :
#

Department

1.

Contractor /

2.

TCO PFU Construction/


3.

TCO PFU Quality/

4.

TCO OPS/

Position, initials
MGK QA/QC engineer/

Signature, stamp, date

Technical Piping Passport 1-200-L-TPP-10001 was checked and approved by after Hydro test:
1-200-L-TPP-10001 (
):
#

Department

1
.

Contractor /

2
.

TCO PFU Quality/

3
.

TCO PFU Construction/


6
.

TCO OPS /

7
.

TCO Facility Owner


Designate/

Position, initials
MGK QA/QC engineer/

Signature, stamp, date

TENGIZCHEVROIL
MAJOR CAPITAL PROJECT

X-000-056-07
Tengizchevroil

Plant Firewater
Upgrade Project

List of diagrams, drawings and other Handover documentation as specified in Requirements of


Industrial Safety at operation of industrial pipelines from 27 of July 2009 - 176 or required by
effective Regulation, specifications, or design:
Pressure Test Acceptance Certificate
P&ID
Weld Map ISOs
Pressure Test Clearance Report (NDE)
Piping Passport Pressure Test Results Copy Attached
PWHT report and Hardness Test Results (if required)
For Welders and Heat-Treaters Qualification Certificates see General System Dossier

, ,
/ ,
27 2009
176, :
.
.


-
(
).

, .

TENGIZCHEVROIL
MAJOR CAPITAL PROJECT

X-000-056-07
Tengizchevroil

Plant Firewater
Upgrade Project

Installation data

The piping was constructed by:
:

Munaigazkurylys LLP

in complete accordance with design developed by:



:
as per design drawing(s):
:

1-000-L-5145 rev.2, 1-000-L-5172 rev.2,


1-000-B-2000-05607

Welding process applied in the piping construction:


,
:
Fill metal data:

:

PSN Kazstroy

Represented on Welding log


sheet

Represented on Welding log sheet


.

All welding performed during the pipeline construction complies with the requirement
RD 38.13.004-86. All welders were qualified as per GGT approved Rules for
Electric and Gas Welder Qualification.
38. 13. 00486 ,
.

TENGIZCHEVROIL
MAJOR CAPITAL PROJECT

X-000-056-07
Tengizchevroil

Plant Firewater
Upgrade Project

Test Results

The pipeline/spool was leak tested at the following
pressure:
/
:
Pressure at test start:
:
as per design drawing(s):
:
The pipeline/Spool was visually
inspected with the followings
findings:
/
.
:
Pressure at test finish:

Test duration:

Pressure drop:

:

No defects, leak and condensation areas are


detected
,
.

TENGIZCHEVROIL
MAJOR CAPITAL PROJECT

X-000-056-07
Tengizchevroil

Plant Firewater
Upgrade Project

Conclusion

The pipeline/Spool was fabricated and constructed in compliance with the effective
regulation. The pipeline was accepted for operation within design specifications.
/
, , .

Pipeline owners signature:


:

______________________________________________________

Installation enterprise representatives signature:


:

______________________________________________________

You might also like