Job on Hand - Utaya Kumar

Work
TNST
Roof Drawing
Wall Framing
Staircase
Awning

Action
Rev. 3 Submitted to MES (2 drawing as per comment)
Rev. 1 Submitted to MES,
Drawing received partially from TNST
Drawing received, will have discussion with TNST & CJ

Hong Leong
Rebar Crushing
DTS / PCB Drawings

Waiting for HL revise drawing


Complete Design drawings

CSC
As-built Piling Data & ECC drawing

Submitted to MES to get RE sign

CAST IN ITEM
Roof Frame Cast-in item
Revise Cast-in drawing

Drawing commented, waiting for revise copy


Ammend drawing as per in latest wall drawing

As-Built Drawing
KKL As-built

Revise drawings with approved RFI

CBP As-Built

Revise drawings with approved RFI

Target

Approval

9/10/2015
9/10/2015

9/10/2015
9/10/2015
9/18/2015
9/18/2015

9/10/2015
9/10/2015

9/16/2015
9/16/2015

9/4/2015

9/9/2015

9/3/2015
9/9/2015

9/18/2015
9/18/2015

will coordinate from HQ


will coordinate from HQ