Professional Documents
Culture Documents
Owner
Subject
COST ESTIMATE
ITEM DESCRIPTION
I.
QTY.
GENERAL REQUIREMENTS
A. Mobilization/Demobilization
B. Temporary Facilities
C. Safety & Housekeeping
D. Technical Support & Supervision
E. Permits & Licenses (including MERALCO and Maynilad/Manila Waters)
UNIT
COST PROPOSAL
UNIT COST
MATERIAL
LABOR
1.00
1.00
1.00
1.00
BY OWNER
TOTAL
UNIT COST
50,000.00
50,000.00
50,000.00
50,000.00
-
5,000.00
250.00
5,000.00
120.00
60.00
20,000.00
5,000.00
250.00
5,000.00
120.00
60.00
20,000.00
SUB-TOTAL (Item I)
II.
EARTHWORKS:
a. Site Clearing/Lay-outing/Staking
b. Excavation & Backfilling
c. Dewatering Works
d. Soil Poisoning & Gravel Bedding
e. Sub-Grade Preparation & Compaction
f. Disposal of Unsuitable Materials / Debris
1.00
162.00
1.00
108.00
108.00
1.00
lot
m
lot
m
m
lot
966.00
966.00
483.00
2,415.00
m
m
m
400.00
180.00
180.00
150.00
120.00
120.00
550.00
300.00
300.00
38.40
13.44
30.24
3.60
10.80
53.76
40.50
190.74
m
m
m
m
m
m
m
3,000.00
3,000.00
3,000.00
3,000.00
3,000.00
3,000.00
3,000.00
150.00
150.00
150.00
150.00
150.00
150.00
150.00
3,150.00
3,150.00
3,150.00
3,150.00
3,150.00
3,150.00
3,150.00
38.00
38.00
38.00
38.00
38.00
38.00
38.00
5.00
5.00
5.00
5.00
5.00
5.00
5.00
43.00
43.00
43.00
43.00
43.00
43.00
43.00
120.00
120.00
120.00
120.00
120.00
120.00
120.00
440.00
440.00
440.00
440.00
440.00
440.00
440.00
STRUCTURAL WORKS
A. Masonry Works
1.0 CHB Laying
2.0 Interior Plastering
Exterior Plastering
B. Concreting Works
1.0 Footing
2.0 Footing Tie Beam / Wall Footing
3.0 R. C. Columns
4.0 Staircase
5.0 Slab on Grade
6.0 Suspended Beams / Girders
7.0 Suspended Slabs
C. Rebar Works
1.0 Footing
2.0 Footing Tie Beam / Wall Footing
3.0 R. C. Columns
4.0 Staircase
5.0 Slab on Grade
6.0 Suspended Beams / Girders
7.0 Suspended Slab
2,800.32
5,600.67
5,449.34
85.25
2,192.00
15,902.00
11,045.00
43,074.58
kgs.
kgs.
kgs.
kgs.
kgs.
kgs.
kgs.
76.80
134.40
12.00
331.20
10.80
537.60
108.00
1,210.80
m
m
m
m
m
m
m
320.00
320.00
320.00
320.00
320.00
320.00
320.00
1.00
143.00
lot
m
40,000.00
450.00
ARCHITECTURAL WORKS
A. Tileworks
1.0 T & B:
- wall (ht = 2.40m)
- floor
2.0 Hallway/Corridor/Deck
3.0 Bedrooms
4.0 Liv/Din/Fam/Kit
115.20
48.00
165.60
108.00
108.00
m
m
m
m
m
140.00
140.00
140.00
140.00
140.00
150.00
150.00
150.00
150.00
150.00
290.00
290.00
290.00
290.00
290.00
B. Painting Works
1.0 Interior
2.0 Exterior
3.0 Ceiling
624.00
483.00
324.00
m
m
m
135.00
135.00
135.00
90.00
90.00
90.00
225.00
225.00
225.00
C. Carpentry Works
1.0 Ceiling
2.0 Closet cabinets @ bedrooms (2.40 x 1.20m)
3.0 Kitchen cabinets
324.00
25.92
36.00
m
m
m
450.00
450.00
450.00
250.00
250.00
250.00
700.00
700.00
700.00
10,500.00
7,500.00
4,500.00
3,500.00
650.00
650.00
650.00
650.00
11,150.00
8,150.00
5,150.00
4,150.00
40,000.00
450.00
2.00
4.00
2.00
4.00
units
units
units
units
5.0 D5
6.0 D6
B. Windows
1.0 W1
2.0 W2
3.0 W3
4.0 W4
5.0 W5
1.00
1.00
unit
unit
13,650.00
3,000.00
2.40
1.20
0.80
0.30
0.40
2.00
3.00
1.00
2.00
3.00
units
units
unit
units
units
15,000.00
7,500.00
5,500.00
3,500.00
2,500.00
15,000.00
7,500.00
5,500.00
3,500.00
2,500.00
1.00
lot
300,000.00
300,000.00
m
lot
650.00
200,000.00
1,500.00
x
x
x
x
x
1.20m
1.20m
1.20m
2.10m
0.60m
650.00
13,650.00
3,650.00
SUB-TOTAL (Item V)
VI.
ELECTRICAL WORKS
1.0 Service entrance
2.0 Rough-ins
3.0 Wires and conduits
4.0 Fixtures
BY OWNER
SUB-TOTAL (Item VI)
VII.
PLUMBING WORKS
1.0 Septic vault
2.0 Rough-ins
3.0 Fixtures
4.0 Water proofing (deck)
18.00
1.00
BY OWNER
108.00
350.00
1,000.00
200,000.00
1,500.00
5,847,791.0
TOTAL
AMOUNT
50,000.00
50,000.00
-
b.
###
100,000.00
5,000.00
40,500.00
5,000.00
12,960.00
6,480.00
20,000.00
P
89,940.00
531,300.00
289,800.00
144,900.00
966
966
483
2,415.00
400
180
180
386400
173880
86940
386400
173880
86940
647,220.00
120,960.00
42,336.00
95,256.00
11,340.00
34,020.00
169,344.00
127,575.00
18.90
9.00
13.44
3.24
10.80
18.00
40.50
113.88
3000
3000
3000
3000
3000
3000
3000
56700
27000
40320
9720
32400
54000
121500
56700
27000
40320
9720
32400
54000
121500
341,640.00
120,413.76
240,828.81
234,321.79
3,665.66
94,256.00
683,786.00
474,935.00
725.004
1109.7
4,971.46
47.952
663.84
2126.25
3,983.04
13627.242
27550.152
42168.6
188915.328
1822.176
25225.92
80797.5
151355.52
27550.152
42168.6
188915.328
1822.176
25225.92
80797.5
151355.52
517,835.20
33,792.00
59,136.00
5,280.00
145,728.00
4,752.00
236,544.00
47,520.00
50.4
90.00
10.8
201.6
10.8
225.00
45.00
633.6
16128
28800
3456
64512
3456
72000
14400
1,709,447.20
16128
28800
3456
64512
3456
72000
14400
202,752.00
38
38
38
38
38
38
38
320
320
320
320
320
320
320
40,000.00
64,350.00
P
1,709,447.20
4,056,140.02
structure
33,408.00
13,920.00
48,024.00
31,320.00
31,320.00
140,400.00
108,675.00
72,900.00
226,800.00
18,144.00
25,200.00
P
750,111.00
22,300.00
32,600.00
10,300.00
16,600.00
manpower
20
days
hours
6
weeks
12
electrical
205,133.66
plumbing
136,755.78
16
rate (400/8hrs)
50
1,152,000.00
1,493,889.44
labor/materials
contingencies
3,203,336.64
96,100.10
3,299,436.73
13,650.00
3,650.00
30,000.00
22,500.00
5,500.00
7,000.00
7,500.00
P
171,600.00
300,000.00
300,000.00
1500
18,000.00
200,000.00
162,000.00
380,000.00
5,847,791.02
Project
Owner
Subject
COST ESTIMATE
ITEM DESCRIPTION
I.
QTY.
STRUCTURAL WORKS
A. Concreting Works ( 3,000psi @ 28 day )
1.0 Footing
2.0 Footing Tie Beam / Wall Footing
3.0 R. C. Columns
4.0 Staircase
5.0 Slab on Grade
6.0 Suspended Beams / Girders
7.0 Suspended Slab
COST PROPOSAL
UNIT COST
TOTAL
UNIT
UNIT
MATERIAL LABOR
COST
38.40
13.44
30.24
1.80
10.80
53.76
40.50
m
m
m
m
m
m
m
4,100.00
4,100.00
4,100.00
4,100.00
4,100.00
4,100.00
4,100.00
150.00
150.00
150.00
150.00
150.00
150.00
150.00
4,250.00
4,250.00
4,250.00
4,250.00
4,250.00
4,250.00
4,250.00
163,200.00
57,120.00
128,520.00
7,650.00
45,900.00
228,480.00
172,125.00
B. Rebar Works
1.0 Footing
2.0 Footing Tie Beam / Wall Footing
3.0 R. C. Columns
4.0 Staircase
5.0 Slab on Grade
6.0 Suspended Beams / Girders
7.0 Suspended Slab
8.0 Ga 16 GI Tie Wire
###
###
###
85.25
###
###
###
50.00
kgs.
kgs.
kgs.
kgs.
kgs.
kgs.
kgs.
rolls
38.00
38.00
38.00
38.00
38.00
38.00
38.00
2,200.00
3.50
3.50
3.50
3.50
3.50
3.50
3.50
41.50
41.50
41.50
41.50
41.50
41.50
41.50
2,200.00
124,513.28
261,477.89
226,147.78
3,537.79
298,501.20
784,433.66
873,392.40
110,000.00
76.80
134.40
12.00
331.20
10.80
537.60
108.00
m
m
m
m
m
m
m
350.00
350.00
350.00
350.00
350.00
350.00
350.00
120.00
120.00
120.00
120.00
120.00
120.00
120.00
470.00
470.00
470.00
470.00
470.00
470.00
470.00
36,096.00
63,168.00
5,640.00
155,664.00
5,076.00
252,672.00
50,760.00
SUB-TOTAL (Item I)
II.
###
ARCHITECTURAL WORKS
A. Masonry Works
1.0 CHB Laying
2.0 Interior Plastering
Exterior Plastering
3.0 Linear Plastering
966.00
483.00
483.00
652.00
m
m
m
l.m.
B. Tileworks
1.0 T & B:
- wall (ht = 2.40m)
- floor
2.0 Hallway/Corridor/Deck
3.0 Bedrooms
4.0 Liv/Din/Fam/Kit
115.20
48.00
165.60
108.00
108.00
C. Painting Works
1.0 Interior
2.0 Exterior
3.0 Ceiling
D. Carpentry Works (ceiling)
1.0 Ground flr.
2.0 2nd flr.
3.0 3rd flr.
875.00
120.00
120.00
90.00
90.00
110.00
110.00
60.00
965.00
230.00
230.00
150.00
932,190.00
111,090.00
111,090.00
97,800.00
m
m
m
m
m
180.00
180.00
180.00
180.00
180.00
180.00
180.00
180.00
180.00
180.00
20,736.00
8,640.00
29,808.00
19,440.00
19,440.00
624.00
483.00
324.00
m
m
m
90.00
90.00
90.00
90.00
90.00
90.00
56,160.00
43,470.00
29,160.00
108.00
108.00
108.00
m
m
m
165.00
165.00
165.00
615.00
615.00
615.00
66,420.00
66,420.00
66,420.00
450.00
450.00
450.00
TOTAL
AMOUNT
###
2.00
4.00
2.00
4.00
1.00
1.00
units
units
units
units
unit
unit
###
7,500.00
4,500.00
3,500.00
###
3,000.00
B. Windows
1.0 W1
2.0 W2
3.0 W3
4.0 W4
5.0 W5
x
x
x
x
x
2.00
3.00
1.00
2.00
3.00
units
units
unit
units
units
###
6,480.00
4,320.00
2,835.00
1,080.00
2.40
1.20
0.80
0.30
0.40
1.20m
1.20m
1.20m
2.10m
0.60m
3,675.00
2,625.00
1,575.00
1,225.00
1,050.00
###
###
6,075.00
4,725.00
###
4,050.00
28,350.00
40,500.00
12,150.00
18,900.00
13,650.00
4,050.00
###
6,480.00
4,320.00
2,835.00
1,080.00
25,920.00
19,440.00
4,320.00
5,670.00
3,240.00
###
5,908,549.00
ficem
4.32
8.88
2.16
0.36
13.8
#REF!
3.6
#REF!
10.8
10.80
15.75
15.75
113.40
8.88
5.76
1.8
#REF!
41.965
19.075
40.875
17.44
119.36
Project
Perimeter Fence
Owner
Fairlaine
Subject
COST ESTIMATE
ITEM DESCRIPTION
I.
QTY.
EARTHWORKS:
a. Site Clearing/Lay-outing/Staking
b. Excavation & Backfilling
c. Dewatering Works
d. Soil Poisoning & Gravel Bedding
e. Sub-Grade Preparation & Compaction
f. Disposal of Unsuitable Materials / Debris
SUB-TOTAL (Item I)
II.
STRUCTURAL WORKS
A. Masonry Works
1.0 CHB Laying
2.0 Plastering
B. Concreting Works
1.0 Footing
2.0 Footing Tie Beam / Wall Footing
3.0 R. C. Columns
4.0 Staircase
5.0 Slab on Grade
6.0 Suspended Beams / Girders
7.0 Suspended Slabs
C. Rebar Works
1.0 Footing
2.0 Footing Tie Beam / Wall Footing
3.0 R. C. Columns
4.0 Staircase
5.0 Slab on Grade
6.0 Suspended Beams / Girders
7.0 Suspended Slab
D. Formworks & Scaffolds
1.0 Footing
2.0 Footing Tie Beam / Wall Footing
3.0 Staircase
4.0 R. C. Columns
5.0 Slab on Grade
6.0 Suspended Beams / Girders
7.0 Suspended Slab
10.80
21.60
1.60
0.60
0.54
35.52
15.98
25.57
6.40
3.00
8.64
ARCHITECTURAL WORKS
A. Tileworks
1.0 T & B:
- wall (ht = 1.20m)
- floor
2.0 Bedrooms
3.0 Liv/Din/Fam/Kit
B. Painting Works
1.0 wall
2.0 Exterior
3.0 Ceiling
21.60
STEEL WORKS
A.
1.0 Fence
2.0
3.0
4.0
3.60
B.
ELECTRICAL WORKS
1.0 Post lamps
2.0 Rough-ins & Wires
3.0
4.0
1.00
SUB-TOTAL (Item V)
VI.
PLUMBING WORKS
1.0 Septic vault
2.0 Rough-ins
3.0 Fixtures
4.0 Water proofing (deck)
SUB-TOTAL (Item VI)
COST PROPOSAL
UNIT COST
UNIT
MATERIAL
LABOR
m
m
lot
m
m
lot
TOTAL
TOTAL
UNIT COST
AMOUNT
m
m
m
400.00
180.00
180.00
150.00
120.00
120.00
550.00
300.00
300.00
5,940.00
6,480.00
-
m
m
m
m
m
m
m
3,000.00
3,000.00
3,000.00
3,000.00
3,000.00
3,000.00
3,000.00
150.00
150.00
150.00
150.00
150.00
150.00
150.00
3,150.00
3,150.00
3,150.00
3,150.00
3,150.00
3,150.00
3,150.00
5,040.00
1,890.00
1,701.00
-
38.00
38.00
38.00
38.00
38.00
38.00
38.00
5.00
5.00
5.00
5.00
5.00
5.00
5.00
43.00
43.00
43.00
43.00
43.00
43.00
43.00
1,527.36
687.31
1,099.70
-
320.00
320.00
320.00
320.00
320.00
320.00
320.00
120.00
120.00
120.00
120.00
120.00
120.00
120.00
440.00
440.00
440.00
440.00
440.00
440.00
440.00
2,816.00
1,320.00
3,801.60
-
kgs.
kgs.
kgs.
kgs.
kgs.
kgs.
kgs.
m
m
m
m
m
m
m
lot
m
40,000.00
650.00
40,000.00
650.00
m
m
m
m
140.00
140.00
140.00
140.00
150.00
150.00
150.00
150.00
290.00
290.00
290.00
290.00
m
m
m
135.00
135.00
135.00
90.00
90.00
90.00
225.00
225.00
225.00
4,860.00
-
10,500.00
7,500.00
3,500.00
3,000.00
650.00
650.00
650.00
650.00
11,150.00
8,150.00
4,150.00
3,650.00
7,500.00
5,500.00
2,500.00
4,860.00
40,140.00
-
7,500.00
5,500.00
2,500.00
lot
32,302.97
40,140.00
-
1500
m
lot
650.00
200,000.00
1,500.00
350.00
1,000.00
200,000.00
1,500.00
P
77,302.97
77,302.97