CONTRACTOR
GENERAL ITEM
A-7, A-8
Location
21/09/2015
No. of Drawing
No.
Date
In
Out
Title of
Shop Drawing
SITE PLAN AREA 1
SD-BW.1-001
ENGINEER DORMITORY(1/4)
SD-BW.1-002
ENGINEER DORMITORY(2/4)
SD-BW.1-003
ENGINEER DORMITORY(3/4)
SD-BW.1-004
ENGINEER DORMITORY(4/4)
SD-BW.1-005
ENGINEER OFFICE(1/4)
SD-BW.1-006
ENGINEER OFFICE(2/4)
SD-BW.1-007
ENGINEER OFFICE(3/4)
SD-BW.1-008
ENGINEER OFFICE(4/4)
SD-BW.1-009
OWNER OFFICE(1/5)
SD-BW.1-010
OWNER OFFICE(2/5)
SD-BW.1-011
OWNER OFFICE(3/5)
SD-BW.1-012
OWNER OFFICE(4/5)
SD-BW.1-013
OWNER OFFICE(5/5)
SD-BW.1-014
EMPLOYER
Knowledge by :
Date/Time :
(..)
Drawing
No.
Revision of
ENGINEER
Checked by :
Date/Time :
(..)
Approved by :
Date/Time :
(..)
Prepared by
Date/Time
Note of Revision
CONTRACTOR
:Construction Eng.
:
(..)
Submited by
Date/Time
:Construction Mgr.
:
(..)
CONSULTANT
CONTRACTOR
GENERAL ITEM
A-7, A-8
Location
21/09/2015
No. of Drawing
No.
Date
In
Out
Title of
Shop Drawing
MUSHOLA (1/2)
SD-BW.1-015
MUSHOLA (2/2)
SD-BW.1-016
SD-BW.1-017
SD-BW.1-018
SD-BW.1-019
SD-BW.1-020
SD-BW.1-021
SD-BW.1-022
SD-BW.1-023
SD-BW.1-024
SD-BW.1-025
EMPLOYER
Knowledge by :
Date/Time :
Drawing
No.
ENGINEER
Checked by :
Date/Time :
(..)
(..)
Approved by :
Date/Time :
(..)
Revision of
Note of Revision
CONTRACTOR
Prepared by :Construction Eng.
Date/Time
:
(..)
Submited by
Date/Time
:Construction Mgr.
:
(..)
CONSULTANT
CONTRACTOR
GENERAL ITEM
A-5,A-6,A-8
Location
21/09/2015
No. of Drawing
No.
Date
In
Out
Title of
Shop Drawing
SITE PLAN AREA 2
SD-BW.2-001
MUSHOLA (1/5)
SD-BW.2-002
MUSHOLA (2/5)
SD-BW.2-003
MUSHOLA (3/5)
SD-BW.2-004
MUSHOLA (4/5)
SD-BW.2-005
MUSHOLA (5/5)
SD-BW.2-006
WORKSHOP(1/5)
SD-BW.2-007
WORKSHOP(2/5)
SD-BW.2-008
WORKSHOP(3/5)
SD-BW.2-009
WORKSHOP(4/5)
SD-BW.2-010
WORKSHOP(5/5)
SD-BW.2-011
BARBENDING SHOP(1/5)
SD-BW.2-012
BARBENDING SHOP(2/5)
SD-BW.2-013
BARBENDING SHOP(3/5)
SD-BW.2-014
EMPLOYER
Knowledge by :
Date/Time :
(..)
Drawing
No.
ENGINEER
Checked by :
Date/Time :
(..)
Approved by :
Date/Time :
(..)
Revision of
Note of Revision
CONTRACTOR
Prepared by :Construction Eng.
Date/Time
:
(..)
Submited by
Date/Time
:Construction Mgr.
:
(..)
CONSULTANT
CONTRACTOR
GENERAL ITEM
A-5,A-6,A-8
Location
21/08/2015
No. of Drawing
No.
Date
In
Out
Title of
Shop Drawing
BARBENDING SHOP (4/5)
SD-BW.2-015
SD-BW.2-016
SD-BW.2-017
SD-BW.2-018
SD-BW.2-019
SD-BW.2-020
SD-BW.2-021
SD-BW.2-022
SD-BW.2-023
SD-BW.2-024
SD-BW.2-025
SD-BW.2-026
CONTRACTOR STAFF
DORMITORY (1/4)
CONTRACTOR STAFF
DORMITORY (2/4)
SD-BW.2-027
EMPLOYER
Knowledge by :
Date/Time :
(..)
Drawing
No.
Revision of
Note of Revision
SD-BW.2-028
ENGINEER
Checked by :
Date/Time :
(..)
Approved by :
Date/Time :
(..)
CONTRACTOR
Prepared by :Construction Eng.
Date/Time
:
(..)
Submited by
Date/Time
:Construction Mgr.
:
(..)
CONSULTANT
CONTRACTOR
GENERAL ITEM
A-5,A-6,A-8
Location
21/09/2015
No. of Drawing
No.
Date
In
Out
Title of
Shop Drawing
CONTRACTOR STAFF
DORMITORY (3/4)
CONTRACTOR STAFF
DORMITORY (4/4)
CANTEEN 1 (1/4)
SD-BW.2-029
CANTEEN 1 (2/4)
SD-BW.2-032
CANTEEN 1 (3/4)
SD-BW.2-033
CANTEEN 1 (4/4)
SD-BW.2-034
CANTEEN 2 (1/4)
SD-BW.2-035
CANTEEN 2 (2/4)
SD-BW.2-036
CANTEEN 2 (3/4)
SD-BW.2-037
CANTEEN 2 (4/4)
SD-BW.2-038
LABORATORY (1/5)
SD-BW.2-039
LABORATORY (2/5)
SD-BW.2-040
LABORATORY (3/5)
SD-BW.2-041
LABORATORY (4/5)
SD-BW.2-042
LABORATORY (5/5)
SD-BW.2-043
EMPLOYER
Knowledge by :
Date/Time :
(..)
Drawing
No.
Revision of
Note of Revision
SD-BW.2-030
SD-BW.2-031
ENGINEER
Checked by :
Date/Time :
(..)
Approved by :
Date/Time :
(..)
CONTRACTOR
Prepared by :Construction Eng.
Date/Time
:
(..)
Submited by
Date/Time
:Construction Mgr.
:
(..)