GAMBARAN UMUM PROYEK CUT AND FILL

xxxxxxxxxxxxxxxxxxxxxxx
OWNER

PT. xxxxxxxxxxxxxx

MAIN KONTRAKTOR

PT. xxxxxxxxxxxxxx
PT. xxxxxxxxxxxxxx

PEMBAYARAN

: PER 500.000 M3. (SKBDN / BANK GARANSI)

VOLUME KONTRAK :

1,000,000 M3

HARGA KONTRAK

ATAU
: Rp.

WAKTU PELAKSANAAN :

6 Bulan /

50,000 DUMP
17,000.00 / M3. PADAT

180 hari

RENCANA ANGGARAN PELAKSANAAN ( PER M3. )


BIAYA RITASI DT & QUARRY :
1. SEWA DUMP TRUCK
2. BIAYA BBM DT
3. BIAYA SUPIR DT
4. SEWA EXCAVATOR
5. BIAYA BBM ALAT
6. BIAYA OPERATOR ALAT
BIAYA PEMADATAN :
1. SEWA VIBRO & BULDOZER
2. BIAYA BBM ALAT
3. BIAYA OPERATOR ALAT
BIAYA UMUM & ADMIN. :
1. PEMOTONGAN OLEH MAIN KONTRAKTOR
( UNTUK BIAYA PAJAK & ADMINISTRASI )
2. BIAYA PERSIAPAN/PENDAHULUAN
JUMLAH

= Rp.
= Rp.
= Rp.
= Rp.
= Rp.
= Rp.

2,500
348
550
1,267
387
147

= Rp.
= Rp.
= Rp.

1,699
1,476
564
7,000

= Rp.
= Rp.
= Rp.

1,325
17,261

PROFIT

= Rp.

(261)

JUMLAH

= Rp.

17,000

CATATAN : DEFISIT

Rp

(261.46) /M3.

Minus

ASUMSI - ASUMSI :
WAKTU PELAKSANAAN :
VOLUME KONTRAK
1. EXCAVATOR (BEKO)
KEMAMPUAN ALAT (EXCAVATOR)
GALI/MUAT PER HARI = 10 JAM
JML PEMAKAIAN ALAT
GALI/MUAT PER HARI = 10 JAM
JML WAKTU PELAKSANAAN
2. DUMP TRUCK :
Kapasitas Dump truk
Frequensi Dump Truk
Jumlah armada
Frequensi tiap 1 DT

1,000,000 M3.
60
600
10
6,000

M3./JAM
M3.
UNIT
M3.

167 HARI
6 BULAN
20
300
9
33

m3/DT
trip/hari
DT
trip

WAKTU SIKLUS ALAT/DT :


1. EXCAVATOR (BEKO)
Kapasitas Bucket
Kapasitas Produksi Per Jam
Jumlah Jam Kerja
Jumlah Produksi/Alat
Jumlah Pemakaian Alat
Jumlah Produksi Per Hari

1.2
60
10
600
10
6,000

M3.
M3.
Jam
M3.
Unit
M3.

GAMBARAN UMUM PROYEK CUT AND FILL


xxxxxxxxxxxxxxxxxxxxxxx
OWNER

PT. xxxxxxxxxxxxxx

MAIN KONTRAKTOR

PT. xxxxxxxxxxxxxx
PT. xxxxxxxxxxxxxx

PEMBAYARAN
: : PER 500.000 M3. (SKBDN / BANK GARANSI)
2. DUMP TRUCK :
Jarak Tempuh
Waktu muat dan manouver
Kecepatan (dgn muatan)
Waktu tempuh (dgn muatan)
Waktu bongkar dan manouver
Kecepatan (tanpa muatan)
Waktu tempuh (tanpa muatan)
Jml Waktu Bongkar/Muat/Perjalanan
Jumlah trip tiap jam
Jam kerja per hari
Total trip per hari (real time)

0.50
6
20
6
2
30
4
18
3.33
0.30
10
33

km
menit
km/jam
menit
menit
km/jam
menit
menit/trip
trip/jam
jam/trip
jam/hari
trip/hari

Total daya angkut per hari/DT


Target Volume Angkut per hari
Jumlah Dump Truk yg diperlukan

667 m3 /hr/DT
6,000 m3
9 Unit DT

PREDIKSI PELAKSANAAN PEKERJAAN PENGURUGAN :


1

PEKERJAAN PERSIAPAN :
-

DIREKSI KEET / SITE OFFICE


MOBILISASI DAN DEMOBILISASI PERLATAN & PERSONIL
PENGUKURAN LEVELING TANAH DASAR
PEMBUATAN JALAN AKSES DARI QUARRY KE JALAN UMUM

PEKERJAAN PEMATANGAN LAHAN SEPANJANG DAERAH TIMBUNAN TANAH :


-

PEMBONGKARAN TERHADAP PENGHALANG YANG MUNGKIN ADA


MEMINDAHKAN DAN MENANGANI AIR YANG ADA AGAR TIDAK TERHENTI
MEMBUANG DAN MENANGANI LOKASI TIMBUNAN TANAH YANG BERLUMPUR
MENGHENTIKAN / MENYUMBAT SUMBER AIR TANAH YANG TIMBUL APABILA ADA

PEKERJAAN PEMADATAN TANAH DASAR SEPANJANG LOKASI KERJA

PEKERJAAN PENIMBUNAN TANAH DAN PEMADATAN


- SETIAP PENGHAMPARAN 30 CM. ATAU SESUAI KETENTUAN YANG ADA DALAM
SPESIFIKASI YANG DIKELUARKAN PIHAK OWNER DAN ATAU STANDAR PT. JASA MARGA

PEKERJAAN COMMISIONING TEST PEMADATAN DENGAN MENGGUNAKAN PERALATAN


SAND CONE DAN ATAU SHEEP FOOT ROLLER SAMPAI DENGAN MEMENUHI TINGKAT
KEPADATAN DAN DAYA DUKUNG YANG DITETAPKAN SESUAI PERATURAN UNTUK
JALAN TOLL.
PERALATAN YANG DIGUNAKAN :

1
2
3
4

EXCAVATOR
DUMP TRUCK
BULDOZER
COMPACTOR / VIBRO ROLLER

5
6
7
8

MOTOR GRADER
SHEEP FOOT ROLLER
TRUCK TANGKI AIR
PERALATAN PENDUKUNG LAINNYA

RENCANA ANGGARAN PENDAPATAN DAN BIAYA OPERASIONAL


xxxxxxxxxxxxxxxxxxxxxxx
I.

PENDAPATAN :
NILAI KONTRAK

II.

1,000,000 X

17,000.00

BIAYA OPERASIONAL (PENGELUARAN PROYEK) :

A.

BIAYA RITASE DUMP TRUCK DAN QUARRY :


1

DUMP TRUCK :
SEWA
: 135 UNIT x Rp. 30.000.000,- x 11 BULAN
BBM
: 20 LTR/TRIP x 250.000 TRIP x Rp. 6.000,SUPIR
: Rp. 250.000,-/HARI x 334 HARI x 135 UNIT

Rp

15 Unit
20 Ltr/Rit
220,000 /hari

x
x
x

Rp

4 Unit
20 Liter
220,000 /hari

x
x
x

Rp
Rp

30,000,000 x
1,500 Rit
167 Hari

x
x

1,667 Jam
1,667 Jam
167 Hari

x
x
x

EXCAVATOR :
SEWA
BBM
OPERATOR

: 10 UNIT x 3.340 JAM x Rp. 140.000,- / JAM


: 20 LTR x 3.340 JAM x 10 UNIT x Rp. 6.000,: Rp. 250.000,-/HARI x 334 HARI x 10 UNIT

JUMLAH BIAYA RITASE DUMP TRUCK DAN QUARRY :


B.

BIAYA PEMADATAN :
1 SEWA ALAT :
2

BULDOZER D6
COMPACTOR/VIBRO R.
MOTOR GRADER
SHEEP FOOT ROLLER
TRUK TANGKI AIR

:
:
:
:
:

6 UNIT
3 UNIT
3 UNIT
1 UNIT
2 UNIT

x
x
x
x
x

3.340 JAM x Rp. 135.000,-/JAM


2.338 JAM x Rp. 130.000,-/JAM
2.338 JAM x Rp. 130.000,-/JAM
500 JAM x Rp. 135.000,-/JAM
Rp. 20.000.000,- x 11 BULAN

3
3
3
1
2

Unit
Unit
Unit
Unit
Unit

x
x
x
x
x

1,667
933
950
500
20,000,000

Jam
Jam
Jam
Jam

x
x
x
x
x

BBM ALAT :
- BULDOZER D6
- COMPACTOR/VIBRO R.
- MOTOR GRADER
- SHEEP FOOT ROLLER
- TRUK TANGKI AIR

:
:
:
:
:

20 LTR
15 LTR
15 LTR
15 LTR
80 LTR

x
x
x
x
x

3.340 JAM x 6 UNIT x Rp. 6.000,2.338 JAM x 3 UNIT x Rp. 6.000,2.338 JAM x 3 UNIT x Rp. 6.000,500 JAM x 1 UNIT x Rp. 6.000,334 HARI x 2 UNIT x Rp. 6.000,-

5
15
15
15
30

Liter
Liter
Liter
Liter
Liter

x
x
x
x
x

1,667
933
950
500
167

Jam
Jam
Jam
Jam
Hari

x
x
x
x
x

167
224
224
50
334

Hari
Hari
Hari
Hari
Hari

x
x
x
x
x

OPERATOR ALAT :
-

BULDOZER D6
COMPACTOR/VIBRO R.
MOTOR GRADER
SHEEP FOOT ROLLER
TRUK TANGKI AIR

Rp
Rp
Rp
Rp
Rp

220,000
220,000
220,000
220,000
220,000

JUMLAH BIAYA PEMADATAN :


C.

BIAYA PEMOTONGAN DARI MAIN KONTRAKTOR :


UNTUK BIAYA PPH PAJAK KONSTRUKSI DAN BIAYA ADMINISTRASI

D.

1,000,000 m3

BIAYA PERSIAPAN / PENDAHULUAN PROYEK :


1
2
3
4
5
6

BIAYA
BIAYA
BIAYA
BIAYA
BIAYA
BIAYA

BIKIN DIREKSI KIT / SITE OFFICE


MOBILISASI DAN DEMOBILISASI PERALATAN & PERSONIL
PENGUKURAN LEVELING TANAH DASAR
BIKIN JALAN AKSES DARI QUARRY KE JALAN UMUM
PEMATANGAN LAHAN SEPANJANG LOKASI KERJA
OVERHEAD PROYEK, BIAYA COMMISIONING TEST PEMADATAN DAN BIAYA TAK TERDUGA LAINNYA

JUMLAH BIAYA PERSIAPAN / PENDAHULUAN PROYEK :


Harga BBM Industri

REKAPITULASI :
PENDAPATAN :
BIAYA OPERASIONAL (PENGELUARAN PROYEK) :
A.
B.
C.
D.

JUMLAH
JUMLAH
JUMLAH
JUMLAH

BIAYA RITASE DUMP TRUCK DAN QUARRY


BIAYA PEMADATAN
PEMOTONGAN OLEH MAIN KONTRAKTOR
BIAYA PERSIAPAN / PENDAHULUAN PROYEK

KEUNTUNGAN KOTOR PROYEK :


NOTE : BELUM TERMASUK FEE SUKSES UNTUK PIHAK MEDIASI.-

11,600

Rp

7,000

SIONAL

17,000,000,000

Rp

6
11,600
15

Bln
/Liter
Unit

=
=
=

Rp
Rp
Rp
Rp

2,500,000,000
348,000,000
550,000,000
3,398,000,000

190,000
11,600
4

/Jam

Rp

=
=
=

Rp
Rp
Rp
Rp

1,266,666,667
386,666,667
146,666,667
1,800,000,000

Rp

5,198,000,000

=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp

675,000,000
364,000,000
370,500,000
67,500,000
222,222,222
1,699,222,222

=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp

290,000,000
487,200,000
495,900,000
87,000,000
116,000,000
1,476,100,000

=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp

110,000,000
147,840,000
147,840,000
11,000,000
146,960,000
563,640,000

Rp

3,738,962,222

Rp

7,000,000,000

Rp
Rp
Rp
Rp
Rp
Rp

75,000,000
130,000,000
10,000,000
500,000,000
275,000,000
334,500,000

= Rp. Rp

1,324,500,000

Unit

135,000
130,000
130,000
135,000
6

/Jam
/Jam
/Jam
/Jam
Bln

3
3
3
1
2

Unit
Unit
Unit
Unit
Unit

3
3
3
1
2

Unit
Unit
Unit
Unit
Unit
Unit

x
x
x
x
x

11,600
11,600
11,600
11,600
11,600

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

Rp 17,000,000,000
Rp
Rp
Rp
Rp

5,198,000,000
3,738,962,222
7,000,000,000
1,324,500,000

Rp 17,261,462,222