The precast concrete element will be shifted to site using Truck Trailer
Erection Sequence
Footing (1 MT) (1.8 m*1.2 m* 0.25m)
Column (1 MT) ( 3.35 m
Tightening of Nuts
After sufficient number of Footing have been placed wall planks will be
placed
Backfilling will be done before the close of days work
Erection Methodology
The precast member will be lifted through lifting hooks /holes provided in
members using arrangement made of Steel Pipes , SW rope and D shackles/ ring
attachments
Lifting shall be done using hooks in crawler type crane / crawler tractor
suitably redesigned for lifting.
Member shall be placed in position previously prepared as per line and levels.