Employee Code

IGL-40207

Client
Project

INDRAPRASTHA GAS LTD.


City Gas Distribution Project in NCT of Delhi &

Activity

Quality Surveillance of MDPE Pipeline Network

Zone & Location of Control Room


Location of Work

North, ROHINI SEC10

Name of the Inspector

Name: ANIL KUMAR

Name of Site In-charge (IGL)

Name: DHIRAJ KUMAR

Name of Contractor
Date
16/10/2015 (Friday)
17/10/2015 (Saturday)
18/10/2015 (Sunday)
19/10/2015 (Monday)
20/10/2015 (Tuesday)
21/10/2015 (Wednesday)
22/10/2015 (Thursday)
23/10/2015 (Friday)
24/10/2015 (Saturday)
25/10/2015 (Sunday)
26/10/2015 (Monday)
27/10/2015 (Tuesday)
28/10/2015 (Wednesday)
29/10/2015 (Thursday)
30/10/2015 (Friday)
31/10/2015 (Saturday)
01/11/2015 (Sunday)
02/11/2015 (Monday)
03/11/2015 (Tuesday)
04/11/2015 (Wednesday)
05/11/2015 (Thursday)
06/11/2015 (Friday)
07/11/2015 (Saturday)
08/11/2015 (Sunday)
09/11/2015 (Monday)
10/11/2015 (Tuesday)
11/11/2015 (Wednesday)
12/11/2015 (Thursday)
13/11/2015 (Friday)
14/11/2015 (Saturday)
15/11/2015 (Sunday)
TOTAL WORK HOURS
NO. OF PRESENT DAYS:
DEDUCTION FOR LUNCH HOURS:

Time In

Time Out

9:15:00 AM
9:15:00 AM

7:45:00 PM
7:45:00 PM

8:15:00 AM
9:15:00 AM
7:15:00 AM
9:15:00 AM
9:15:00 AM
9:15:00 AM
9:15:00 AM
8:15:00 AM
7:15:00 AM
9:15:00 AM
8:15:00 AM
8:15:00 AM
9:15:00 AM
9:15:00 AM
9:15:00 AM
8:15:00 AM
8:15:00 AM
8:15:00 AM
8:15:00 AM
9:15:00 AM
9:15:00 AM
9:15:00 AM
9:15:00 AM
2:15:00 PM
7:15:00 AM
9:15:00 AM
8:15:00 AM

6:45:00 PM
6:45:00 PM
5:45:00 PM
7:45:00 PM
7:45:00 PM
6:45:00 PM
7:45:00 PM
6:45:00 PM
7:45:00 PM
7:45:00 PM
6:45:00 PM
6:45:00 PM
6:45:00 PM
6:45:00 PM
6:45:00 PM
6:45:00 PM
6:45:00 PM
6:45:00 PM
6:45:00 PM
9:45:00 PM
5:45:00 PM
7:45:00 PM
7:15:00 PM
10:45:00 PM
6:45:00 PM
7:45:00 PM
6:45:00 PM

A
B
C=B/2

Contact

TOTAL HOURS WORKED :

D=A-C

MOODY INTERNATIONAL INDIA (P) LTD


Signature of TPI
ANIL KUMAR
Name of TPI

*Wriitng Name with signature is must. Time Sheet will not be accepted in case of unavailability of name & signa
CHECK BOX
TPI has PPEs with Uniform and it is in use while on duty
TPI has mobile phone and in use
TPI has conveyance and it is in use while on duty
All leaves in this time sheet given as per IGL approval
Safety training has been received by TPI in this month

Sign of TPI

Sign of IGL incharge

TIME SHEET
MONTH: Nov 2015
(16th OCT. to 15th NOV..)

D.
ect in NCT of Delhi & NCR

DPE Pipeline Network : PO No: 6500002689 Dated 20/FEB/2014

Contact No. 9891326460


Contact No. 7042891376

10:30
10:30

Total no. of
Hrs.
10.50
10.50

Welding pit work (ghevra)


Welding pit work (ghevra)

10:30
9:30
10:30
10:30
10:30
9:30
10:30
10:30
12:30
10:30
10:30
10:30
9:30
9:30
9:30
10:30
10:30
10:30
10:30
12:30
8:30
10:30
10:00
8:30
11:30
10:30
10:30

10.50
9.50
10.50
10.50
10.50
9.50
10.50
10.50
12.50
10.50
10.50
10.50
9.50
9.50
9.50
10.50
10.50
10.50
10.50
12.50
8.50
10.50
10.00
8.50
11.50
10.50
10.50

Line locate (VTL)


line locate ( HFCL,VTL))
Leak attend sv point
Sv cleaning work
Stone marker install
Stone marker install
New valve chamber install work
New valve chamber install work
New valve chamber install work
Digging work check
valve chamber monitoring
valve chamber monitoring
Line locate rohtak road
vtl work check
Line locate Bawana VTL
Digging work check DJB (Mangolpuri)
valve chamber monitoring
Valve chamber monitoring
valve chamber roof work (Mundka)
Dwarka shut down
Dwarka shut down
Line locate VTL Bawana
valve chamber monitoring
Line survay( Bawana)
wazirabad site inspection
Line locate(vtl) Bawana
Digging work check(sec22)

300.00
31.00
15.50

Automatically

Total Hours:Mins

Remarks

284.50
INDRAPRASTHA GAS LTD
Signature of IGL in-charge
DHIRAJ KUMAR
Name of IGL in-charge

bility of name & signature.