BTS Installation Guideline for INWI Project

BTS Installation Guideline


for
INWI Project

Huawei Technologies Co., Ltd.


2015-2-4

Huawei Confidential

Page1, Total 74 ,

BTS Installation Guideline for INWI Project

Document History
Date

Version

2009-10-18

V1.0

2009-10-23

V1.1

Changes

Author

Email

First draft issued

Ge Ping

geping@huawei.com

1. Add CPRI cable and jumper connection of DRFU


and GRFU

Ge Ping

geping@huawei.com

Ge Ping

geping@huawei.com

2. Add antenna system installation


2009-11-25

V1.2

1.

Add guideline for battery cabinet installation

2.

Add guideline for E1 cable connection for


cascade site

3.

Add guideline for alarm cable distribution

2010-1-11

V1.3

1.

Add guideline for CDMA&GSM dual-band


antenna installation

Ge Ping

geping@huawei.com

2010-1-13

V1.4

1.

Add guideline for faulty antenna swap

Ge Ping

geping@huawei.com

2010-1-13

V1.5

1.

Add guideline for DBS installation

Ge Ping

geping@huawei.com

2010-3-10

V1.5

1.

Update guideline for DBS installation

Ge Ping

geping@huawei.com

2.

Change WANA to INWI

2010-4-22

V1.6

1.

Add installation guideline for IBBS200T V302

Ge Ping

geping@huawei.com

2010-5-13

V1.7

1.

Add installation guideline for IBBS200T V303

Ge Ping

geping@huawei.com

2010-5-14

V1.8

1.

Add installation guideline for DC power cable


connector making for TEC FAN in IBBS200T
V303

Ge Ping

geping@huawei.com

2015-2-4

Huawei Confidential

Page2, Total 74 ,

BTS Installation Guideline for INWI Project

Content
1.

Key Principles........................................................................................................................6

2.

Indoor BTS Installation ..........................................................................................................7

3.

2.1.

Overview of Huawei indoor BTS3900...........................................................................7

2.2.

CPRI cable layout (Singal cable between BBU and GRFU/DRFU) .............................7

2.3.

Cable routing of indoor BTS3900 .................................................................................9

2.4.

Fix the redundancy cable on top of the cabinet......................................................... 10

2.5.

All cables should be layout straightly between cable ladder and cabinet ................. 11

2.6.

All power cables and signal cables should be covered by different cable ducts ....... 11

2.7.

DDF installation in the existing transmission cabinet ................................................ 12

2.8.

E1 transmission cable connection for normal sites ................................................... 12

2.9.

E1 transmission cable connection for cascade sites ................................................. 12

2.10.

E1 cable color sequence ........................................................................................... 13

2.11.

Alarm cable connection (From INWI alarm system to BTS) ...................................... 14

2.12.

The antistatic wrist strap should be installed in the BTS cabinet .............................. 15

2.13.

No any document and labels in the back of the cabinet door ................................... 15

2.14.

No any materials in the bottom of BTS ...................................................................... 15

2.15.

Label for power cable ................................................................................................ 16

2.16.

Label for CPRI cable (Singal cable between BBU and GRFU/DRFU) ...................... 17

2.17.

BTS Power on............................................................................................................ 19

2.18.

Deal with the rubbish and clean up the shlelter ......................................................... 20

Outdoor BTS Installation .....................................................................................................21


3.1.

Overview of Huawei outdoor BTS3900A ................................................................... 21

3.2.

CPRI cable layout (Singal cable between BBU and GRFU/DRFU) .......................... 22

3.3.

Cable routing of outdoor BTS3900A.......................................................................... 22

3.4.

PGND cable connection for outdoor BTS3900A ....................................................... 25

3.5.

All power cable and signal cable should be protected with metal pipe ..................... 26

3.6.

DDF installation in the existing transmission cabinet ................................................ 27

3.7.

E1 transmission cable connection for normal sites ................................................... 27

3.8.

E1 transmission cable connection for cascade sites ................................................. 27

3.9.

E1 cable color sequence ........................................................................................... 28

3.10.

Alarm cable connection (From INWI alarm system to BTS) ...................................... 30

3.11.

The antistatic wrist strap should be installed in the BTS cabinet .............................. 31

3.12.

No any materials in the bottom of APM30 ................................................................. 31

2015-2-4

Huawei Confidential

Page3, Total 74 ,

BTS Installation Guideline for INWI Project

4.

5.

6.

3.13.

Make waterprof of the outdoor cabinets .................................................................... 32

3.14.

Label for power cable ................................................................................................ 33

3.15.

Label for CPRI cable (Singal cable between BBU and GRFU/DRFU) ...................... 33

3.16.

BTS Power on............................................................................................................ 33

3.17.

Deal with the rubbish and clean up the sites ............................................................. 35

3.18.

IBBS200 (Big Battery Cabinet) installation ................................................................ 36

3.19.

IBBS200T (Small Battery Cabinet) installation .......................................................... 43

3.20.

IBBS200T V302 (Small Battery Cabinet) installation ................................................ 45

3.21.

IBBS200T V303 (Small Battery Cabinet) installation ................................................ 48

DBS Installation ...................................................................................................................54


4.1.

Overview of Huawei DBS3900 .................................................................................. 54

4.2.

BBU installation (for scenario 1&2, BBU in APM30) ................................................. 56

4.3.

DC power cable conection (for scenario 1&2, BBU in APM30) ................................. 56

4.4.

BBU installation (for scenario 3, BBU in transmission cabinet) ................................. 57

4.5.

DC power cable conection (for scenario 3, BBU in transmission cabinet) ................ 57

4.6.

DC power cable and CPRI cable in RRU .................................................................. 58

4.7.

Outside cables of RRU .............................................................................................. 59

4.8.

Keep necessary operation space between RRUs ..................................................... 59

4.9.

Battery installation for DBS3900................................................................................ 60

4.10.

Alarm cable connection (From INWI alarm system to BTS) ...................................... 61

Antenna System Installation ...............................................................................................62


5.1.

Install the antenna according to the IO parameters .................................................. 62

5.2.

Keep at least 1 meter distance between GSM and CDMA antennas ....................... 63

5.3.

Install the grounding cables for antennas .................................................................. 63

5.4.

Install the feeder clamps 1 pcs/ meter ....................................................................... 64

5.5.

Install the grounding cables for feeders .................................................................... 64

5.6.

Make waterproof to all outside conenctors ................................................................ 65

5.7.

Make labels for jumpers and feeders ........................................................................ 66

5.8.

Reserve spare space in cable tray for 3G in future ................................................... 67

5.9.

Reserve spare space in feeder window for 3G in future ........................................... 67

5.10.

Install CDMA&GSM dual-band (Bi-technology) antenna........................................... 68

5.11.

GSM antenna swap for faulty antenna with high VSWR ........................................... 69

BTS Integration ...................................................................................................................70


6.1.

Hardware Ready for Integration ................................................................................ 70

2015-2-4

Huawei Confidential

Page4, Total 74 ,

BTS Installation Guideline for INWI Project

6.2.

Transmission Ready for Integration........................................................................... 70

6.3.

Hardware and Transmission Ready for Integration ................................................... 71

6.4.

BTS Integration .......................................................................................................... 71

6.5.

Tools and Materials for Site Engineer for BTS Integration ........................................ 72

6.6.

BSC Engineer for BTS Integration............................................................................. 72

6.7.

Possible Problem for BTS Integration and Solution .................................................. 72

6.8.

BTS Integration Status Check ................................................................................... 74

2015-2-4

Huawei Confidential

Page5, Total 74 ,

BTS Installation Guideline for INWI Project

1. Key Principles
1. Before you enter the site, please call INWI NOC(529000800/529000604);
2. Before you leave the site, please call INWI NOC(529000800/529000604);
3. Before leaving the indoor site, please check the air conditioner is
working normal and the light already power off;
4. If there is any action which will cause the site down, please inform and
discuss with Huawei and INWI. The dangerous action should get
approval from Huawei and INWI before implementation;

2015-2-4

Huawei Confidential

Page6, Total 74 ,

BTS Installation Guideline for INWI Project

2. Indoor BTS Installation


2.1. Overview of Huawei indoor BTS3900

900M S111

900M S222~S555

900M&1800M

2.2. CPRI cable layout


ayout (Singal cable between BBU and GRFU/DRFU)

900M

900M &1800M
1800M

Notes: Only connect CPRI cable to down CPRI port (Not up CPRI port)!

2015-2-4

Huawei Confidential

Page7, Total 74 ,

BTS Installation Guideline for INWI Project

DRFU

GRFU

CPRI cable to BBU

CPRI cable to BBU

Notes: Only connect CPRI cable to down CPRI port (Not up CPRI port)!

2015-2-4

Huawei Confidential

Page8, Total 74 ,

BTS Installation Guideline for INWI Project

2.3. Cable routing of indoor BTS3900

2015-2-4

Huawei Confidential

Page9, Total 74 ,

BTS Installation Guideline for INWI Project

2.4. Fix the redundancy cable on top of the cabinet

E1 Cable

Alarm Cable

Power Cable

2015-2-4

Huawei Confidential

Page10, Total 74 ,

BTS Installation Guideline for INWI Project

2.5. All cables should be layout straightly between cable ladder and cabinet
without any loop or angle

2.6. All power cables and signal cables should be covered by different
cable ducts
Cable duct for

Cable duct for

DC power cable

E1 cable and
alarm cable

2015-2-4

Huawei Confidential

Page11, Total 74 ,

BTS Installation Guideline for INWI Project

2.7. DDF installation in the existing transmission cabinet


Huawei

Huawei alarm

E1 DDF

DDF

3 holes

3 holes

2.8. E1 transmission cable connection for normal sites


Huawei
BBU
(GTMU)

Huawei
E1 DDF

Huawei
Responsible

INWI
IDU

INWI
DDF
Huawei
Responsible

INWI
Responsible

2.9. E1 transmission cable connection for cascade sites


Huawei
BBU
(GTMU)

Huawei
Responsible

2015-2-4

Huawei
E1 DDF

INWI
DDF
Huawei
Responsible

Huawei Confidential

INWI IDU to up hop


INWI IDU to next hop

INWI
Responsible

Page12, Total 74 ,

BTS Installation Guideline for INWI Project

2.10. E1 cable color sequence


E1
No.1 E1

No.2 E1

No.3 E1

No.4 E1

2015-2-4

PIN
X.19
X.20
X.1
X.2
X.21
X.22
X.3
X.4
X.23
X.24
X.5
X.6
X.25
X.26
X.7
X.8

Wire Color
gray
white
blue
white
blue
red
orange
white
orange
red
green
white
green
red
brown
white

Remarks
TX+
TXRX+
RXTX+
TXRX+
RXTX+
TXRX+
RXTX+
TXRX+
RX-

Huawei Confidential

Huawei E1 DDF port


1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16

Page13, Total 74 ,

BTS Installation Guideline for INWI Project

2.11. Alarm cable connection (From INWI alarm system to BTS)


Huawei
BBU
(UPEU)

Huawei
Alarm DDF

Huawei
Responsible

INWI
Alarm System

INWI
Responsible

Huawei alarm DDF

Huawei
E1 DDF

Alarm cable distribution in UPEU


Alarm DDF DCDU

FAN

The alarm label should be printed


and sticked on the DDF

Label for Alarm


DDF.xls

2015-2-4

Huawei Confidential

Page14, Total 74 ,

BTS Installation Guideline for INWI Project

2.12. The antistatic wrist strap should be installed in the BTS cabinet

2.13. No any document and labels in the back of the cabinet door

2.14. No any materials in the bottom of BTS

2015-2-4

Huawei Confidential

Page15, Total 74 ,

BTS Installation Guideline for INWI Project

2.15. Label for power cable

Label in the bottom of BTS

Label in the top of the BTS

Label in INWI power cabinet

2015-2-4

Huawei Confidential

Page16, Total 74 ,

BTS Installation Guideline for INWI Project

2.16. Label for CPRI cable (Singal cable between BBU and GRFU/DRFU)
CPRI lable in BBU side:

CPRI lable in GRFU/DRFU side:

2015-2-4

Huawei Confidential

Page17, Total 74 ,

BTS Installation Guideline for INWI Project

2015-2-4

Huawei Confidential

Page18, Total 74 ,

BTS Installation Guideline for INWI Project

2.17. BTS Power on


1. When should we power on BTS?
1.1. For new sites, the BTS should be power on after hardware installation;
1.2. For the sites which already installed, please power on the BTS when you enter
the sites for clean up/ pre-acceptance/ acceptance with INWI.
2. Measure input voltage before power on BTS and record the voltage value.
The input voltage of the indoor BTS should be between -44V DC~-57V DC;
The input voltage of the outdoor BTS should be between 180V AC~260V AC;
3. If the voltage is out of the range, please record the problem and inform your
PM to ask INWI to solve the rectifier problem.
4. Indoor BTS power on sequence:
1) Switch on the switch for 2G BTS in INWI power cabinet;
2) Switch on FAN;
3) Switch on BBU;
4) Switch on UPEU (in BBU);
5) Switch on GRFU/DRFU;
DCDU01 in BTS3900 cabinet:

5. Indoor BTS power off sequence:


1) Switch off GRFU/DRFU;
2) Switch off UPEU (in BBU);
3) Switch off BBU;
4) Switch off FAN;
5) Switch off the switch for 2G BTS in INWI power cabinet;

2015-2-4

Huawei Confidential

Page19, Total 74 ,

BTS Installation Guideline for INWI Project

2.18. Deal with the rubbish and clean up the shlelter

2015-2-4

Huawei Confidential

Page20, Total 74 ,

BTS Installation Guideline for INWI Project

3. Outdoor
door BTS Installation
3.1. Overview of Huawei outdoor BTS3900A

900M S111

2015-2-4

900M S222~S555

Huawei Confidential

900M&1800M

Page21, Total 74 ,

BTS Installation Guideline for INWI Project

3.2. CPRI cable layout (Singal cable between BBU and GRFU/DRFU)

900M

900M &1800M

Notes: Only connect CPRI cable to down CPRI port (Not up CPRI port)!

3.3. Cable routing of outdoor BTS3900A


Cable holes at the bottom of the BTS cabinet (RFC):

2015-2-4

Huawei Confidential

Page22, Total 74 ,

BTS Installation Guideline for INWI Project

No.

Item

Description

Left cable trough

AC power cables, PGND cables and AC power cables from battery cabinet to APM30

Right cable trough

Battery power cable, E1 cables, alarm cable from battery cabinet to APM30

Cable hole for Jumpers

1/2 Jumpers

Reserved cable hole

CPRI cables and monitoring signal cable between two BTS.

Cable holes at the bottom of the power cabinet (APM30):

No.

Description

AC power cables and PGND cables

CPRI cables between BTS cabinet and APM30 cabinet

DC power cable from PDU to DCDU (Already connected before


delivery)

Battery power cable,E1 cables, alarm cable from battery cabinet to


APM30

The jumper holes can only used for jumpers:

2015-2-4

Huawei Confidential

Page23, Total 74 ,

BTS Installation Guideline for INWI Project

Wrong connection of AC cable/PGND cable/battery cables.

2015-2-4

Huawei Confidential

Page24, Total 74 ,

BTS Installation Guideline for INWI Project

3.4. PGND cable connection for outdoor BTS3900A

The PGND cable from battery cabinet should be connected to the


grounding bar in APM30 cabinet.

2015-2-4

Huawei Confidential

Page25, Total 74 ,

BTS Installation Guideline for INWI Project

3.5. All power cable and signal cable should be protected with metal pipe

Metal pipe for


AC power cable

Metal pipe for


E1 and alarm cable

2015-2-4

Huawei Confidential

Page26, Total 74 ,

BTS Installation Guideline for INWI Project

3.6. DDF installation in the existing transmission cabinet

Huawei DDF Rack

3 holes

3.7. E1 transmission cable connection for normal sites


Huawei
BBU
(GTMU)

Huawei
E1 DDF

Huawei
Responsible

INWI
IDU

INWI
DDF
Huawei
Responsible

INWI
Responsible

3.8. E1 transmission cable connection for cascade sites


Huawei
BBU
(GTMU)

Huawei
Responsible

2015-2-4

Huawei
E1 DDF

INWI
DDF
Huawei
Responsible

Huawei Confidential

INWI IDU to up hop


INWI IDU to next hop

INWI
Responsible

Page27, Total 74 ,

BTS Installation Guideline for INWI Project

3.9. E1 cable color sequence


E1
No.1 E1

No.2 E1

No.3 E1

No.4 E1

2015-2-4

PIN
X.19
X.20
X.1
X.2
X.21
X.22
X.3
X.4
X.23
X.24
X.5
X.6
X.25
X.26
X.7
X.8

Wire Color
gray
white
blue
white
blue
red
orange
white
orange
red
green
white
green
red
brown
white

Remarks
TX+
TXRX+
RXTX+
TXRX+
RXTX+
TXRX+
RXTX+
TXRX+
RX-

Huawei Confidential

Huawei E1 DDF port


1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16

Page28, Total 74 ,

BTS Installation Guideline for INWI Project

The E1 cable should be grounded in the APM30 cabinet:

Metal shielding layer (25 mm)

E1 cable from IDU

E1 lighting-protection
From MW IDU
E1 grounding clip

To GTMU

E1 grounding
clip

2015-2-4

Huawei Confidential

Page29, Total 74 ,

BTS Installation Guideline for INWI Project

3.10. Alarm cable connection (From INWI alarm system to BTS)


Huawei
BBU
(UPEU)

Huawei
Alarm DDF

Huawei
Responsible

INWI
Alarm System

INWI
Responsible

Huawei alarm DDF

Huawei
E1 DDF

Alarm cable distribution in UPEU


Alarm DDF

HPMI in APM30

FMUA in BTS cabinet

2015-2-4

Huawei Confidential

The alarm label should be printed


and sticked on the DDF

Label for Alarm


DDF.xls

Page30, Total 74 ,

BTS Installation Guideline for INWI Project

3.11. The antistatic wrist strap should be installed in the BTS cabinet

3.12. No any materials in the bottom of APM30

2015-2-4

Huawei Confidential

Page31, Total 74 ,

BTS Installation Guideline for INWI Project

3.13. Make waterprof of the outdoor cabinets

Make waterproof of the 2

Make waterproof of the 2

cable holes of each cabinet

cable holes of each cabinet

2015-2-4

Huawei Confidential

Page32, Total 74 ,

BTS Installation Guideline for INWI Project

3.14. Label for power cable

Label in INWI power cabinet

3.15. Label for CPRI cable (Singal cable between BBU and GRFU/DRFU)
Same standard with the indoor BTS

3.16. BTS Power on


1. When should we power on BTS?
1.1. For new sites, the BTS should be power on after hardware installation;
1.2. For the sites which already installed, please power on the BTS when you enter
the sites for clean up/ pre-acceptance/ acceptance with INWI.
2. Measure input voltage before power on BTS and record the voltage value.
The input voltage of the outdoor BTS should be between 180V AC~260V AC;
3. If the voltage is out of the range, please record the problem and inform your
PM to ask INWI to solve the rectifier problem.
4. Outdoor BTS power on sequence:
1) Switch on the switch for 2G BTS in INWI power cabinet;
2) Switch on AC Main in APM30;
3) Switch on SW9 (DCDU0), SW8 (DCDU1), SW5 (BBU), SW4 (HEUA);
4) Switch on UPEU (in BBU);
5) Switch on FMUA (in BTS cabinet);
6) Switch on GRFU/DRFU (in BTS cabinet);
7) Switch on Battery after battery installation;
2015-2-4

Huawei Confidential

Page33, Total 74 ,

BTS Installation Guideline for INWI Project

Battery Switch
Switch 0~9
AC Main

DC power switch 0~9 in APM30:


Switch

Switch Name

Operation

SW9

DCDU0 (30A)

Need to switch on

SW8

DCDU1 (30A)

Need to switch on

SW7

SPARE5 (30A)

SW6

SPARE4 (30A)

SW5

BBU (12A)

Need to switch on

SW4

HEUA (12A)

Need to switch on

SW3

SPARE3 (4A)

SW2

SPARE2 (4A)

SW1

SPARE1 (4A)

SW0

SPARE0 (4A)

5. Outdoor BTS power off sequence:


1) Switch off Battery;
2) Switch off GRFU/DRFU (in BTS cabinet);
3) Switch off FMUA (in BTS cabinet);
4) Switch off UPEU (in BBU);
5) Switch off SW9 (DCDU0), SW8 (DCDU1), SW5 (BBU), SW4 (HEUA);
6) Switch off AC Main in APM30;
7) Switch off the switch for 2G BTS in INWI power cabinet;
2015-2-4

Huawei Confidential

Page34, Total 74 ,

BTS Installation Guideline for INWI Project

3.17. Deal with the rubbish and clean up the sites

2015-2-4

Huawei Confidential

Page35, Total 74 ,

BTS Installation Guideline for INWI Project

3.18. IBBS200 (Big Battery


Batt
Cabinet) installation
Scenario 1: Have extra space for Huawei battery space
Install Huawei battery cabinet in extra place.
Battery layout in the battery cabinet:

Huawei Battery Group 2


Huawei Battery Group 1
Power cable connection of scenario 1:

Huawei Battery Group 2

Huawei Battery Group 1

2015-2-4

Huawei Confidential

Page36, Total 74 ,

BTS Installation Guideline for INWI Project

Scenario 2: No extra space for Huawei battery space

Dismantle ZTE battery cabinet and install


install Huawei battery cabinet in original place.
The ZTE battery and power cable will be reused.
The ZTE battery cabinet can be removed as rubbish.
Battery layout in the battery cabinet:
Huawei Battery Group 2
Huawei Battery Group 1
ZTE Battery Group 2
ZTE Battery Group 1

2015-2-4

Huawei Confidential

Page37, Total 74 ,

BTS Installation Guideline for INWI Project

Power cable connection of scenario 2:

Huawei Battery Group 2

Huawei Battery Group 1

ZTE Battery Group 2

ZTE Battery Group 1

Huawei battery cabinet installation after swap ZTE battery cabinet:

2015-2-4

Huawei Confidential

Page38, Total 74 ,

BTS Installation Guideline for INWI Project

ZTE battery cabinet dismantling and Huawei battery installation steps:


1) Check the AC power and battery is working normally
ly for ZTE BTS;
2) Switch off ZTE battery
attery from ZTE BTS cabinet;
3) Dismantle
ismantle ZTE battery and battery cabinet;
4) Install Huawei battery cabinet;
cabinet
5) Remove the battery switch from layer1 to layer3 in Huawei battery cabinet;
6) Disconnect the RTN (+) power cable (red color) between two copper wiring bars
(between layer2 and layer3);
layer3)
7) Disconnect the NEG (-48V) power cable (black color) between two copper wiring
bars (between layer2 and layer3);
layer3)
8) Install ZTE battery and connect power cable to ZTE BTS;
9) Install Huawei battery and connect power cable to Huawei BTS;
BTS
Notes: There is no battery switch in ZTE battery cabinet. The switch for battery is in
ZTE BTS cabinet.

2015-2-4

Huawei Confidential

Page39, Total 74 ,

BTS Installation Guideline for INWI Project

Battery installation check


1) Measure the battery voltage and make sure the value is -48V to -54V;
2) Switch on battery in battery cabinet and APM30;

Battery Switch in APM30

Battery Switch in battery cabinet

3) Swith off the AC power to check if the battery is working normally or not;
4) After the check, switch on the AC power finally.
Do the same test for ZTE battery installation to check the ZTE battery is working
normally.

2015-2-4

Huawei Confidential

Page40, Total 74 ,

BTS Installation Guideline for INWI Project

Temperature
emperature sensor connection in battery cabinet
Connect battery temperature sensor to RTN+ connector in Huawei
uawei battery group 1.

Alarm
larm cable connection from battery cabinet to APM30
Temperature alarm cable connection (orange white);
white)
Door alarm cable connection (green white);
white)
Temperature alarm and door alarm cable connection in battery cabinetion:
cabinetion
To sensor

To sensor

Orange

White

White
hite

Green

White

Orange
range Green
White

To APM30

2015-2-4

To APM30

Huawei Confidential

Page41, Total 74 ,

BTS Installation Guideline for INWI Project

Temperature alarm and door alarm cable connection in APM30 cabinet:

Temperature alarm cable

Door alarm cable

After the alarm cable installation, please contact BSC engineer to confirm the
door open alarm of battery cabinet.
Name

ID

Position

BTS Integration Hotline

0000001

BTS Integration Hotline

Mobile-Phone No.
INWI

Email

IAM

0646117035

If the BTS integration hotline is busy, you can also contact with the following BSC engineers:
EN NAQI Abdelilah
WX22053 BSC Engineer for Integration 0646117029 0662120789

2015-2-4

Huawei Confidential

naqi@huawei.com

Page42, Total 74 ,

BTS Installation Guideline for INWI Project

3.19. IBBS200T (Small Battery Cabinet) installation


There are 2 hardware versions of BTS3900A and IBBS200T: V302 and V303.
1) IBBS200T(V302) using 25mm battery power cable with OT terminal;
2) IBBS200T(V303) using16mm battery power cable with special connector;
BTS3900A (V302) and IBBS200T (V302)

2015-2-4

Huawei Confidential

Page43, Total 74 ,

BTS Installation Guideline for INWI Project

BTS3900A (V303) and


an IBBS200T (V303)

2015-2-4

Huawei Confidential

Page44, Total 74 ,

BTS Installation Guideline for INWI Project

3.20. IBBS200T V302 (Small Battery Cabinet) installation

BTS3900A V302

IBBS200T V302

2015-2-4

Huawei Confidential

Page45, Total 74 ,

BTS Installation Guideline for INWI Project

Battery power cable connection:

Not used for INWI project

Not used for INWI project

2015-2-4

Huawei Confidential

Page46, Total 74 ,

BTS Installation Guideline for INWI Project

Alarm cable connection:

After the alarm cable installation, please contact BTS integration hotline to
confirm the door open alarm of battery cabinet.
2015-2-4

Huawei Confidential

Page47, Total 74 ,

BTS Installation Guideline for INWI Project

3.21. IBBS200T V303 (Small Battery Cabinet) installation

BTS3900A V303

IBBS200T V303

2015-2-4

Huawei Confidential

Page48, Total 74 ,

BTS Installation Guideline for INWI Project

Battery power cable connection:

Battery cable connector in APM30H cabinet:

2015-2-4

Battery cable connector in IBBS200T cabinet:

Huawei Confidential

Page49, Total 74 ,

BTS Installation Guideline for INWI Project

TEC FAN power cable connection:

Connection point for TEC FAN


power cable in IBBS200T

Connection point for battery


power cable in IBBS200T

2015-2-4

Huawei Confidential

Page50, Total 74 ,

BTS Installation Guideline for INWI Project

Make TEC FAN power cable connector:


The DC power cable for TEC FAN should be made in site.

Load 3 for TEC FAN

2015-2-4

Huawei Confidential

Page51, Total 74 ,

BTS Installation Guideline for INWI Project

2015-2-4

Huawei Confidential

Page52, Total 74 ,

BTS Installation Guideline for INWI Project

Alarm cable connection:

Alarm cable in IBBS200T cabinet (Ethernet cable, RJ45 connector):

After the alarm cable installation, please


contact BTS integration hotline to confirm
the door open alarm of battery cabinet.
2015-2-4

Huawei Confidential

Page53, Total 74 ,

BTS Installation Guideline for INWI Project

4. DBS Installation
4.1. Overview of Huawei DBS3900
For all DBS sites, the site survey should be performed with INWI maintenance
engineers before equipment delivery and installation.
During the site survey, the installation strategy (install BBU in APM30 or
transmission cabinet)/space requirement/power requirement and cable connection
should be confirmed and agreed with INWI maintenance engineers.

TSSR for DBS3900


Instalaltion

Scenario 1: BBU in APM30 (on the ground), RRU in tower or Pole (3 Poles)
APM30H V303
RRU1
RRU2
RRU3

2015-2-4

Huawei Confidential

Page54, Total 74 ,

BTS Installation Guideline for INWI Project

Scenario 2: BBU in APM30 (on the tower), RRU in tower or Pole (1 Pole)

APM30 Cabinet

Scenario 3: BBU in transmission cabinet, RRU in tower or pole

BBU in transmission cabinet

2015-2-4

Huawei Confidential

Page55, Total 74 ,

BTS Installation Guideline for INWI Project

4.2. BBU installation (for scenario 1&2, BBU in APM30)

4.3. DC power cable conection (for scenario 1&2, BBU in APM30)

DC power cable for RRU1


DC power cable for HPMI
DC power cable for BBU
DC power cable for RRU2

DC power cable for RRU3

2015-2-4

Huawei Confidential

Page56, Total 74 ,

BTS Installation Guideline for INWI Project

4.4. BBU installation (for scenario 3, BBU in transmission cabinet)

4.5. DC power cable conection (for scenario 3, BBU in transmission


cabinet)
If the BBU was installed in the transmission cabinet (no APM30), the DC power
switch for BBU and RRU should be provided by INWI in the transmission cabinet or
DC power cabinet.
DC Switch for BBU (5A~10A)
DC Switch for RRU (10A~20A)

2015-2-4

1 DC switch for BBU


1 DC switch for 1 RRU (3 switchs for 3 RRUs)

Huawei Confidential

Page57, Total 74 ,

BTS Installation Guideline for INWI Project

4.6. DC power cable and CPRI cable in RRU

CPRI_W

CPRI Cable to BBU

DC Power Cable

2015-2-4

Huawei Confidential

Page58, Total 74 ,

BTS Installation Guideline for INWI Project

4.7. Outside cables of RRU

Jumpers

CPRI Cable

RRU DC
Power Cable
Grounding
Cable

4.8. Keep necessary operation space between RRUs

2015-2-4

Huawei Confidential

Page59, Total 74 ,

BTS Installation Guideline for INWI Project

4.9. Battery installation for DBS3900


Please refer to 3.22 IBBS200T V303 (Small Battery Cabinet) installation
Remark: IBBS200T can be installed with APM30H stackable:

2015-2-4

Huawei Confidential

Page60, Total 74 ,

BTS Installation Guideline for INWI Project

4.10. Alarm cable connection (From INWI alarm system to BTS)


Huawei
BBU
(UPEU)

Huawei
Alarm DDF

Huawei
Responsible

INWI
Alarm System

INWI
Responsible

Huawei alarm DDF

Huawei
E1 DDF

Alarm cable distribution in UPEU


HPMI in APM30
Alarm DDF

The alarm label should be printed


and sticked on the DDF

(if there is APM30)

Label for Alarm


DDF.xls

2015-2-4

Huawei Confidential

Page61, Total 74 ,

BTS Installation Guideline for INWI Project

5. Antenna System Installation


5.1. Install the antenna according to the IO parameters
Design Sector 3
AZ
(Azimuth)

HMA TER
(Antenna
to roof)

HMA SOL
(Antenna
to ground)

230

8.8

31.3

Antenna 3

Electrical
Tilt

Mechanical
Tilt

H.
Building
Pylne
(m)

Mast
(m)

Agisson DXX-824-960
1710-2170-6565-17.5i18i-MM

22.5

1. Mechanical Tilt

2. Electrical Tilt

2015-2-4

Huawei Confidential

Page62, Total 74 ,

BTS Installation Guideline for INWI Project

5.2. Keep at least 1 meter distance between GSM and CDMA antennas

1
meter

5.3. Install the grounding cables for antennas

About 2.5m between antenna and ground bar

2015-2-4

Huawei Confidential

Page63, Total 74 ,

BTS Installation Guideline for INWI Project

5.4. Install the feeder clamps 1 pcs/ meter

1m
1m
1m
1m

5.5. Install the grounding cables for feeders


If the feeder is between 10m~40m, 3 points of cable grounding:
Top of the tower/Tri-pole/
pole/ Guyed mast;
Bottom of the tower/Tri-pole/
tower/Tri
Guyed mast;
Outside of feeder window;
window
If the feeder is more than 40m, 4 points of cable grounding:
Top of the tower/Tri-pole/
pole/ Guyed mast;
Middle of the tower/Tri-pole/
tower/Tri
Guyed mast;
Bottom of the tower/Tri-pole/
tower/Tri
Guyed mast;
Outside of feeder window;
window

Top of the tower/Tri-pole/


pole/ Guyed mast

2015-2-4

Middle of the tower/Tri-pole/


tower/Tri
Guyed mast

Huawei Confidential

Page64, Total 74 ,

BTS Installation Guideline for INWI Project

Bottom of the tower/Tri-pole/ Guyed mast

Outside of feeder window

5.6. Make waterproof to all outside conenctors

2015-2-4

Huawei Confidential

Page65, Total 74 ,

BTS Installation Guideline for INWI Project

5.7. Make labels for jumpers and feeders


Antenna Jumper to antenna side
Antenna Jumper to feeder side
Feeder close to antenna
Feeder close to antenna

Feeder outside of feeder window


Feeder outside of feeder window
Feeder window
Feeder inside of feeder window
BTS Jumper to feeder side

BTS Jumper to BTS side

2015-2-4

Huawei Confidential

Page66, Total 74 ,

BTS Installation Guideline for INWI Project

5.8. Reserve spare space in cable tray for 3G in future

2G 3G

5.9. Reserve spare space in feeder window for 3G in future

3G 2G

2015-2-4

Huawei Confidential

Page67, Total 74 ,

BTS Installation Guideline for INWI Project

5.10. Install CDMA&GSM dual-band (Bi-technology) antenna


Connectors in CDMA&GSM antenna (View from Back face of the antenna)
Connector in antenna bottom
Jumer from BTS

45

45

45

45

CDMA TX

CDMA RX

GSM TX

GSM RX

Stand Operation Procedure:


Start
Time

End
Time

9:30

9:30

9:30

13:00

12:30

13:00

14:00

14:05

Power off CDMA BTS

14:05

14:10

VSWR test for existing CDMA sectors

14:10

14:30

Connect CDMA feeder to CDMA filter

14:30

15:30

15:30

17:30

VSWR test for new CDMA sectors (0.1)

17:30

17:45

VSWR test for new GSM sectors (1.4)

17:45

18:00

18:00

18:30

Power on CDMA BTS

18:30

18:35

Power on GSM BTS

18:30

18:35

On-tower Activity

In-site Activity
Before enter the site, contact with INWI NOC

Install new feeder for GSM


BTS

Dismantle and delivery


CDMA antenna from tower
to site (sector by sector)

Install GSM filter and connect to GSM BTS (if


GSM filter is needed for this site)
Install CDMA filter
Connect GSM feeder to GSM filter (if GSM filter is
needed for this site)
Contact with INWI NOC before power off CDMA
BTS

OMC Activity
Be informed site
enter

Be informed CDMA
BTS will be power off

Delivery and install new


CDMA&GSM dual-band
antennas from site to
tower (sector by sector)
Check Mechanical tilt and
electrical tilt

Troubleshooting if there is any VSWR problem


Make waterproof for new
antenna/jumper
connectors

Contact with INWI NOC after power on CDMA


BTS

Alarm monitor for


CDMA BTS

18:35

18:40

Contact with Huawei BTS integration hotline after


power on GSM BTS

Alarm monitor for


GSM BTS

18:40

18:45

Packing CDMA antennas with existing GSM


packing materials

18:45

19:45

Site cleaning

19:45

20:00

Troubleshooting if there is any BTS alarm

2015-2-4

Huawei Confidential

Page68, Total 74 ,

BTS Installation Guideline for INWI Project

Contact with INWI NOC before leaving the site

Leaving approval

20:00

Delivery CDMA antenna to subcontractor's


warehouse

20:00

20:00

Notes:
INWI NOC: 529000800/529000604
Huawei BTS integration hotline: 0646117035

5.11. GSM antenna swap for faulty antenna with high VSWR
Stand Operation Procedure:
Start
Time

End
Time

Enter the site


Unpack the materials

9:30
9:30

9:30
10:00

Record the Bar Code of new antenna


(sector by sector)

9:30

10:00

Power off GRFU/DRFU

10:00

10:00

Dismantle and delivery old GSM


antenna from tower to site (sector by
sector)

10:00

11:00

Delivery and install new GSM


antennas from site to tower (sector
by sector)

11:00

12:30

12:30

12:40

12:40

12:50

12:50

13:00

13:00

13:15

13:15

13:15

13:15

13:25

13:25

13:30

On-tower Activity

Check distance between GSM and


CDMA antenna (1m)
Check antenna Azimuth and Height
Check Mechanical tilt and Electrical
tilt

In-site Activity

OMC
Activity

VSWR test for new GSM sectors (


1.4)
Troubleshooting if there is any VSWR
problem

Make waterproof for new


antenna/jumper connectors
Power on GRFU/DRFU
After 10 minutes, contact with INWI
NOC/Huawei BTS integration hotline
to check the alarm
Troubleshooting if there is any BTS
alarm
Site cleaning

Alarm
monitor for
GSM BTS

Delivery swapped GSM antenna to


subcontractor's warehouse

Notes:
INWI NOC: 529000800/529000604
Huawei BTS integration hotline: 0646117035
2015-2-4

Huawei Confidential

Page69, Total 74 ,

BTS Installation Guideline for INWI Project

6. BTS Integration
6.1. Hardware Ready for Integration
BTS was installed (with GRFU/DRFU);
E1 cable was connected from BTS to INWI DDF;
BTS was power on;

6.2. Transmission Ready for Integration


BSC engineer perform the loop test with INWI the check the E1 link from Microwave
IDU to BSC
Soft-loop from INWI IDU
to Huawei BSC

Huawei

Huawei

BTS

INWI

E1 DDF

DDF

INWI

INWI

IDU

ADM

Huawei

Huawei

INWI

Responsible

Responsible

Responsible

INWI
ODF
Huawei
BSC

BTS Site

2015-2-4

Huawei Confidential

BSC POP

Page70, Total 74 ,

BTS Installation Guideline for INWI Project

6.3. Hardware and Transmission Ready for Integration


1. BTS was installed (with GRFU/DRFU);
2. E1 cable was connected from BTS to INWI DDF;
3. BTS was power on;
4. E1 loop test was done by INWI&Huawei and the E1 link from IDU to BSC is OK;

6.4. BTS Integration


If the BTS is power on and E1 connection is done without problem, the BTS can be
integrated automatically.
If the BTS cant be integrated, site engineer should visit the sites for troubleshooting.
For example, the following sites need to be visited for integration:
No.

BSC

Site ID

Hardware
Filter
TR Actived TR Loop Test by TR Ready Hardware
for
and TR
Installation Installation by INWI INWI&Huawei
and Power
Integration Ready for
on
Integration

Integration

CAS_BSC1 CAS-1099

2009-9-5

2009-9-30 2009-9-3

2009-9-24

2009-10-3 2009-10-3

Need visit

CAS_BSC1 CAS-1080

2009-9-7

2009-10-1 2009-9-3

2009-10-6

2009-10-6 2009-10-6

Need visit

12 CAS_BSC1 CAS-1083

2009-9-6

2009-9-30 2009-9-3

2009-9-25

2009-9-25 2009-9-25

Need visit

15 CAS_BSC1 CAS-1120

2009-8-5

2009-9-20 2009-9-25

2009-10-8

2009-10-8 2009-10-3

Need visit

26 CAS_BSC1 CAS-1167 2009-7-22 2009-9-26 2009-9-3

2009-10-6

2009-10-6 2009-10-6

Need visit

27 CAS_BSC1 CAS-1102

2009-9-30 2009-9-3

2009-9-25

2009-9-25 2009-9-25

Need visit

28 CAS_BSC1 CAS-1037 2009-9-15 2009-9-30 2009-9-3

2009-9-24

2009-10-3 2009-10-3

Need visit

30 CAS_BSC1 CAS-1047

2009-9-5

2009-9-30 2009-9-3

2009-10-3

2009-10-3 2009-10-3

Need visit

31 CAS_BSC1 CAS-1039

2009-9-5

2009-9-24 2009-9-3

2009-9-26

2009-10-3 2009-10-3

Need visit

2015-2-4

2009-9-5

Huawei Confidential

Page71, Total 74 ,

BTS Installation Guideline for INWI Project

6.5. Tools and Materials for Site Engineer for BTS Integration
When you go to the sites, please take necessary tools and materials and try to close
the installation problem in sites. Do not just record and report the problem.
1) Master Key for sites;
2) Multimeter;
3) Krone E1 connection tool;
4) E1 cable (20 meters);
5) E1 loop cable;
6) Key for Indoor BTS3900;
7) Key for outdoor BTS3900A;
8) Key for the outdoor transmission cabinet;
9) DC power cable and connectors (10 meters);
10) AC power cable and connectors (10 meters);

6.6. BSC Engineer for BTS Integration


When you enter the sites for BTS integration, please call BTS Integration Hotline to
check the BTS integration status with BSC engineer:
Mobile-Phone No.

Name

ID

Position

BTS Integration Hotline

0000001

BTS Integration Hotline

INWI

Email

IAM

0646117035

If the BTS integration hotline is busy, you can also contact with the following BSC engineers:
EN NAQI Abdelilah
WX22053 BSC Engineer for Integration 0646117029 0662120789

naqi@huawei.com

6.7. Possible Problem for BTS Integration and Solution


No

Problem

Solution

Access problem (Owner refuse)

Contact with INWI deployment engineer

Access problem (No suitable key)

Contact with INWI deployment engineer

Access problem (Lock was broken)

Use screw driver for help

2015-2-4

Huawei Confidential

Page72, Total 74 ,

BTS Installation Guideline for INWI Project

No

Problem

Solution

BTS didnt power on

Power on BTS

E1 cable didnt be connected from BTS Connect E1 cable


to INWI DDF

E1 cable connection mistake;

Reconnect E1 cable

GRFU/DRFU board didnt be installed

Record the problem and inform RPM

Transmission problem

Physic loop from Huawei DDF to BSC to


check INWI transmission from IDU to BSC;
(BSC engineer will check status)
Physic loop from Huawei DDF to BTS to
check the E1 cable connection;
(If the LIU0 LED light is off, the E1 cable
connection is OK)

INWI didnt connect E1 cable from IDU Contact INWI deployment engineer for
to INWI DDF
help and connect the E1 cable by ourself

10

INWI didnt remark TX/RX in INWI DDF Contact INWI deployment engineer for
help and connect the E1 cable by ourself

11

[Outdoor] INWI didnt connect AC Record the problem and inform INWI
power cable from TGBT to the fuse (for deployment engineer and Huawei RPM
2G BTS)

12

[Outdoor] INWI didnt provide AC power Connect the AC power cable by ourself
cable from fuse (for 2G BTS) to BTS

13

[Outdoor] INWI outdoor power doesnt Record the problem and inform INWI
work
deployment engineer and Huawei RPM

14

[Outdoor] No key for INWI outdoor Contact with INWI deployment engineer
transmission cabinet

2015-2-4

Huawei Confidential

Page73, Total 74 ,

BTS Installation Guideline for INWI Project

6.8. BTS Integration Status Check


1. If the LIU0 LED light is off, that means the transmission to BTS is OK,

LIU0 light should be off

2. Also please check with BSC engineer that if he can see the BTS in BSC.
If the BTS can be monitored in BSC, the BTS is integrated successfully!
3. Check if there is any alarm of the BTS in site. All the LED lights should be off or
green. No any red light.

4. Check with BSC engineer if there is any alarm of the BTS in BSC.

2015-2-4

Huawei Confidential

Page74, Total 74 ,