Activity ID

Activity Name

Total
Baseline_United_Actualizado 20150810

Original Physical Start


Finish Jun 07 Jun 14 Jun 21 Jun 28 Jul 05 Jul 12 Jul 19 Jul 26 Aug 02 Aug 09 Aug 16 Aug 23 Aug 30 Sep 06 Sep 13 Sep 20 Sep 27 Oct 04 Oct 11 Oct 18 Oct 25 Nov 01 Nov 08 Nov 15 Nov 22 Nov 29 Dec 06 Dec 13 Dec 20 Dec 27 Jan 03 Jan 10 Jan 17 Jan 24 Jan 31 Feb 07 Feb 14 Feb 21 Feb 28 Mar 06 Mar 13 Mar 20 Mar 27 Apr 03 Apr 10 Apr 17 Apr 24 May 01 May 08 May 15 May 22 May 29 Jun 05 Jun 12 Jun 19 Jun 26 Jul 03 Jul 10 Jul 17 Jul 24
%
Duration Complete
674
15-Feb-15 12-Jan-17
A
674
15-Feb-15 A 12-Jan-17

Contract Milestones

456

14-Oct-15

12-Jan-17
ML DJR Completed/ Termino DJR,

A1050

ML DJR Completed/ Termino DJR

0%

14-Dec-15

A1070

ML Coloso Port Finish/ Termino Puerto Coloso

0%

25-Oct-15

A1090

ML Coloso Tunnel Finish/ termino Tunel Coloso

0%

14-Oct-15

A1110

ML KM SJ 2 to La Negra Finish/ Termino Km 2 a la 0Negra 0%

20-Nov-15

ML KM SJ 2 to La Negra Finish/ Termino Km 2 a la Negra,

A1115

ML KM DJ 2 to La Negra Finish/ Termino Km 2 a la0Negra 0%

20-Nov-15

ML KM DJ 2 to La Negra Finish/ Termino Km 2 a la Negra,

A1130

ML Tie-Ins Finish/Termino Tie-Ins

0%

12-Feb-16

10

A1150

ML Special Crossing Finish/ Termino Cruce Especial


0

0%

22-Apr-16

11

A1170

ML KM-18 to 164 Finish/Termino Km 18 al 164

0%

16-Jan-16

12

A1180

ML KM-164 to 178 Start/ Inicio Km 164 al 178

0% 20-Nov-15

13

A1190

ML KM-164 to 178 SJ Finish/Termino Km 164 al 178


0

0%

12-Dec-15

14

A1195

ML KM-164 to 178 DJ Finish/Termino Km 164 al 178


0

0%

11-Feb-16

15

A1200

ML Reservoir Area Start/Inicio Area Reservorio

0% 11-Feb-16

16

A1210

ML Reservoir Finish/Termino Reservorio

0%

17

A1220

ML Demobilization Start/Inicio Desmobilizacion

0% 18-Jun-16

18

A1230

ML Demobilization Finish/ Termino Desmovilizacion0

0%

19

A1240

ML Close Out Start/ Inicio del Cierre

0% 17-Jul-16

A1250

ML Close Out Complete/ Cierre

0%

20
21
22
23
24
25
26
27
28
29

DJR
DJR Production
A1870
DJR Cleaning Process/ Proceso de Limpieza

ML Tie-Ins Finish/Termino Tie-Ins,


ML Special Crossing Finish/ Termino Cruce Especial,
ML KM-18 to 164 Finish/Termino Km 18 al 164,
ML KM-164 to 178 Start/ Inicio Km 164 al 178, 20-Nov-15
ML KM-164 to 178 SJ Finish/Termino Km 164 al 178,
ML KM-164 to 178 DJ Finish/Termino Km 164 al 178,
ML Reservoir Area Start/Inicio Area Reservorio, 11-Feb-16
ML Reservoir Finish/Termino Reservorio,

17-Jun-16

ML Demobilization Start/Inicio Desmobilizacion, 18-Jun-16


ML Demobilization Finish/ Termino Desmovilizacion,

16-Jul-16

ML Close Out Start/ Inicio del Cierre, 17-Jul-16


12-Jan-17

257

20-Mar-15 A 14-Dec-15

14-Dec-15, DJR
14-Dec-15, DJR Production
DJR Cleaning Process/ Proceso de Limpieza

257
235

20-Mar-15 A 14-Dec-15
46% 20-Mar-15 A 13-Dec-15

A1880

DJR Coating Process/ Proceso de Revestimiento


235

46% 20-Mar-15 A 13-Dec-15

A1890

DJR Inspection Process/ Proceso de Inspeccion235

46% 21-Mar-15 A 14-Dec-15

199

06-Mar-15 A 25-Oct-15

199
41
40

06-Mar-15 A 25-Oct-15
06-Mar-15 A 16-Aug-15
84.2% 06-Mar-15 A 15-Aug-15

16-Aug-15, Port FBE Section 19 Jts./ FBE Puerto Seccion 19 jts.


CP Cleaning Process/Proceso de limpieza
CP Coating Process/Process de Revestimiento

Coloso Port
Coloso Port Production
Port FBE Section 19 Jts./ FBE Puerto Seccion 19 jts.
A2410 CP Cleaning Process/Proceso de limpieza

30

A2420

CP Coating Process/Process de Revestimiento 40

84.2% 06-Mar-15 A 15-Aug-15

31

A2430

CP Inspection Process /Proceso de Inspeccion 40

84.2% 07-Mar-15 A 16-Aug-15

32
33

ML Coloso Port Finish/ Termino Puerto Coloso,


ML Coloso Tunnel Finish/ termino Tunel Coloso,

Port Prod. C&C 64 Jts./ Produccion Puerto C&C 64 jts.


A2440 CP Cleaning Process/Proceso de limpieza

DJR Coating Process/ Proceso de Revestimiento


DJR Inspection Process/ Proceso de Inspeccion
25-Oct-15, Coloso Port
25-Oct-15, Coloso Port Production

CP Inspection Process /Proceso de Inspeccion

71
70

16-Aug-15
0% 16-Aug-15

25-Oct-15
24-Oct-15

25-Oct-15, Port Prod. C&C 64 Jts./ Produccion Puerto C&C 64 jts.


CP Cleaning Process/Proceso de limpieza
CP Coating Process/Process de Revestimiento

34

A2450

CP Coating Process/Process de Revestimiento 70

0% 16-Aug-15

24-Oct-15

35

A2460

CP Inspection Process /Proceso de Inspeccion 70

0% 17-Aug-15

25-Oct-15

36

Coloso Tunel

71

29-Jul-15 A 14-Oct-15

71
71
70

29-Jul-15 A 14-Oct-15
29-Jul-15 A 12-Oct-15
10% 29-Jul-15 A 11-Oct-15

14-Oct-15, Coloso Tunnel Prod 267 jts.


12-Oct-15, 2a Phase 2/Fase 2a
TN Cleaning Process/Proceso de limpieza

A2540

TN Coating Process/Process de Revestimiento 70

10% 29-Jul-15 A 11-Oct-15

TN Coating Process/Process de Revestimiento

A2550

TN Inspection Process /Proceso de Inspeccion 70

10% 31-Jul-15 A 12-Oct-15

37
38
39

Coloso Tunnel Prod 267 jts.


2a Phase 2/Fase 2a
A2530 TN Cleaning Process/Proceso de limpieza

40
41
42
43

2b Phase 2/Fase 2b
A2560 Cleaning Process/Proceso de limpieza

44

A2570

Coating Process/Process de Revestimiento

45

A2580

Inspection Process /Proceso de Inspeccion

46
47
48

Special Crossins
Special Crossings Production
A2650
SC Cleaning Process/Proceso de limpieza

30-Jul-15 A 14-Oct-15
7% 30-Jul-15 A 13-Oct-15

14-Oct-15, 2b Phase 2/Fase 2b


Cleaning Process/Proceso de limpieza

70

7% 30-Jul-15 A 13-Oct-15

Coating Process/Process de Revestimiento

70

7% 31-Jul-15 A 14-Oct-15

257

01-Jun-15 A 22-Apr-16

257
256

01-Jun-15 A 22-Apr-16
2% 01-Jun-15 A 11-Apr-16

A2660

SC Coating Process/Process de Revestimiento 256

2% 01-Jun-15 A 21-Apr-16

50

A2670

SC Inspection Process /Proceso de Inspeccion 256

2% 02-Jun-15 A 22-Apr-16

187

11-May-15 A 20-Nov-15

52
53
54

Km 2 to la Negra

56

A2600

kM2S Coating Process/Process de Revestimiento


186

45% 11-May-15 A 19-Nov-15

A2610

kM2S Inspection Process /Proceso de Inspeccion


186

45% 11-May-15 A 20-Nov-15

La Negra Prod. 1000 DJts.


A2620 kM2D Cleaning Process/Proceso de limpieza

59

kM2D Coating Process/Process de Revestimiento


185

45% 11-May-15 A 19-Nov-15

A2640

kM2D Inspection Process /Proceso de Inspeccion


186

45% 11-May-15 A 20-Nov-15

334

15-Feb-15 A 16-Jan-16

Km-18 to 164 Production


334
A2680
KM 18-164 Cleaning Process/Proceso de limpieza
201

15-Feb-15 A 16-Jan-16
21% 15-Feb-15 A 15-Jan-16

67
68
69
70
71
72
73
74

A2690

KM 18-164 Coating Process/Process de Revestimiento


201
21% 15-Feb-15 A 15-Jan-16

A2700

KM 18-164 Inspection Process /Proceso de Inspeccion


201
21% 16-Feb-15 A 16-Jan-16

KM 18-164 Coating Process/Process de Revestimiento


KM 18-164 Inspection Process /Proceso de Inspeccion
12-Feb-16, Tie-Ins
12-Feb-16, Tie-In Production
TIE Cleaning Process/Proceso de limpieza

A2720

TIE Coating Process/Process de Revestimiento197

9% 17-May-15 A 11-Feb-16

TIE Coating Process/Process de Revestimiento

A2730

TIE Inspection Process /Proceso de Inspeccion197

9% 17-May-15 A 12-Feb-16

307

01-Aug-15 A 11-Feb-16

Km-164 to Km-178

Km-164 to Km 178 Production


307
Km-164 to 178 Prod. 875- Sjts.
307
A2770 Km 164-178S Cleaning Process/Proceso de limpieza
83

TIE Inspection Process /Proceso de Inspeccion


11-Feb-16, Km-164 to Km-178
11-Feb-16, Km-164 to Km 178 Production

01-Aug-15 A 11-Feb-16
01-Aug-15 A 12-Dec-15
73% 01-Aug-15 A 11-Dec-15

Km 164-178S Coating Process/Process de Revestimiento


83
73% 01-Aug-15 A 11-Dec-15
Km 164-178S Inspection Process /Proceso de Inspeccion
83
73% 01-Aug-15 A 12-Dec-15

82
83

16-Jan-16, Km-18 to 164


16-Jan-16, Km-18 to 164 Production
KM 18-164 Cleaning Process/Proceso de limpieza

17-May-15 A 12-Feb-16
9% 17-May-15 A 11-Feb-16

A2830

81

kM2D Inspection Process /Proceso de Inspeccion

246
197

Tie-In Production
A2710
TIE Cleaning Process/Proceso de limpieza

A2780

80

kM2S Inspection Process /Proceso de Inspeccion

17-May-15 A 12-Feb-16

76

79

kM2S Coating Process/Process de Revestimiento

246

Tie-Ins

75

77
78

20-Nov-15, Km-2 to la Negra Production


20-Nov-15, La Negra Prod. 668 SJts (Spread slow)/ Prod. La negra 668 Sjts (frente lento)
kM2S Cleaning Process/Proceso de limpieza

kM2D Coating Process/Process de Revestimiento

A2630

66

SC Inspection Process /Proceso de Inspeccion


20-Nov-15, Km 2 to la Negra

20-Nov-15, La Negra Prod. 1000 DJts.


kM2D Cleaning Process/Proceso de limpieza

Km-18 to 164

65

SC Coating Process/Process de Revestimiento

11-May-15 A 20-Nov-15
45% 11-May-15 A 19-Nov-15

61

64

22-Apr-16, Special Crossins


22-Apr-16, Special Crossings Production
SC Cleaning Process/Proceso de limpieza

187
186

60
62
63

Inspection Process /Proceso de Inspeccion

Km-2 to la Negra Production


187
11-May-15 A 20-Nov-15
La Negra Prod. 668 SJts (Spread slow)/ Prod. La negra 668
186Sjts (frente11-May-15
lento)
A 20-Nov-15
A2590 kM2S Cleaning Process/Proceso de limpieza 186
45% 11-May-15 A 19-Nov-15

55
57
58

TN Inspection Process /Proceso de Inspeccion

71
70

49
51

CP Inspection Process /Proceso de Inspeccion


14-Oct-15, Coloso Tunel

12-Dec-15, Km-164 to 178 Prod. 875- Sjts.


Km 164-178S Cleaning Process/Proceso de limpieza
Km 164-178S Coating Process/Process de Revestimiento
Km 164-178S Inspection Process /Proceso de Inspeccion

20-Nov-15
0% 20-Nov-15

11-Feb-16
10-Feb-16

11-Feb-16, Km-164 to 178 Prod.538- Djts.


Km 164-178D Cleaning Process/Proceso de limpieza

A2810

Km 164-178D Coating Process/Process de Revestimiento


83
0% 20-Nov-15

10-Feb-16

Km 164-178D Coating Process/Process de Revestimiento

A2820

Km 164-178D Inspection Process /Proceso de Inspeccion


83
0% 21-Nov-15

11-Feb-16

Km-164 to 178 Prod.538- Djts.


84
A2800 Km 164-178D Cleaning Process/Proceso de limpieza
83

128

Reservoir

11-Feb-16

Km 164-178D Inspection Process /Proceso de Inspeccion


17-Jun-16, Reservoir

17-Jun-16
11-Feb-16, Reservoir Set-Up
RSV Mech Test Rervoir Custom Coating Lances/ Verificacion Mecanica Lanzas revestimiento personalizadas

Reservoir Set-Up
0
11-Feb-16 11-Feb-16
A2360
RSV Mech Test Rervoir Custom Coating Lances/ Verificacion
0
0% Mecanica
11-Feb-16
Lanzas
11-Feb-16
revestimiento personalizadas

84

A2370

RS Mech Test Insp Modules/ Verificacion e Inspeccion


0 Mecanica
0% 11-Feb-16
modulos

11-Feb-16

RS Mech Test Insp Modules/ Verificacion e Inspeccion Mecanica modulos

85

A2380

RSV FBE PQT

0% 11-Feb-16

11-Feb-16

RSV FBE PQT

86

A2390

RSV Liquid PQT

0% 11-Feb-16

11-Feb-16

RSV Liquid PQT

128
127

11-Feb-16
0% 11-Feb-16

17-Jun-16
16-Jun-16

17-Jun-16, Reservoir Production


RSV Cleaning Process/Proceso de limpieza
RSV Coating Process/Process de Revestimiento

87
88

Reservoir Production
A2740
RSV Cleaning Process/Proceso de limpieza

89

A2750

RSV Coating Process/Process de Revestimiento127

0% 11-Feb-16

16-Jun-16

90

A2760

RSV Inspection Process /Proceso de Inspeccion127

0% 12-Feb-16

17-Jun-16

RSV Inspection Process /Proceso de Inspeccion

Actual Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

summary

Page 1 of 1

TASK filter: no complet activities.