Professional Documents
Culture Documents
Client
Client Ref. No.:
Scope of Work:
Reference No.:
Revision No.:
Date:
Abbreviations
PGCC
QP
AI
F.R Pad
TDC
Applicable Standards
API 650
ASTM A240 SS316
ASME Sec II, Part c
ASME Sec V
ASME Sec VIII, Div.1
ASME Sec IX
ASME B16.5
ASME Sec X
SNT-TC-1A
1.0
Design
1.1
Clients P.O
Data Sheet
PGCCs
Design
Calculation
Design Manager
/Design Engineer
QCP.REF.100.14
00
1.2
Preparation of
Engineering
drawing and
detail drawings.
2.0
Material Purchase
2.1
Material
Requisition
2.2
Purchase Order
3.0
Material Control
3.1
Material list of
PGCC procured
Materials (Shell
plates, bottom
Compliance with
design
conditions,
Client
Specification &
Data Sheet
Technical and
Quality
Requirements
as per
Contract/Drawin
gs
Purchasing Data
Complete
Material Size
identification,
test cert. as per
API 650
Reference No.:
Revision No.:
Date:
Clients P.O
Data Sheet
PGCC
Drawing
Design Manager
/Design Engineer
Drawing,
Technical
Delivery
Conditions(TD
C)
Matching
Drawing, Clients
spec & Technical
delivery
conditions.
Material
Requisition
Design Engineer,
Draftsman
Buying
enquiry and
offer from
vendor, client
approval
vendor list
Vendors offer
match with the
requirements,
Substitutions
offered are
approved by
TEPQ
Purchase
order
technical
Query
Requests
(in case of
substitution
s)
Purchaser,
Project Engineer
& Operation
Manager
Mill test
certificates,
Dimensiona
l inspection
Material
controller &
Material QC
Inspector
QCP.REF.100.14
00
plates, top
plates, pipes,
fittings, etc..)
3.2
Dished Heads
3.3
Material Storage
3.4
Material issue
3.5
Internal
Installation items
(,
3.6
Anodes
Reference No.:
Revision No.:
Date:
for pressure
part
report if
required &
NDT Report
(If
applicable)
Clearly
identified,
MCN, PO# and
Stored/
Segregated to
prevent
contamination
and damage
Issue against
authorization
only
Identification
marking
traceability to
MTC
--
Material
Controller &
QCnspector
Material Issue
Slip
Issue against
authorization
only
Material
requisition
issue Slip
Material
Controller,
Supervisor
Project Engineer
Dimension, trial
assembly at
floor,
MTC Review
As per client PO
and da
Sub-vendors
drawing &
Doc#
Sub-Vendors
Drawing & Doc#
Subcontractors
inspection
reports
Sub-contractors
& Project
Engineer.
QCP.REF.100.14
00
4..0
Welding control
4.1
Welding
Procedure
Specification
(WPS)
4.2
Welder
Qualification
records (WPQR)
4.3
Weld Map
4.4
Welding
Consumables
5.0
NDE Testing
Reference No.:
Revision No.:
Date:
Covers full
range of
parameters,
processes and
meets CODE
requirements
Covers full
range of
parameters and
process to be
welded
Size ,Batch No
& Test
Certification. API
650 for S. steel
material
consumables;
and 3.1B for all
other material
consumables
WPS
Welding
Engineer
API 650, GS EP
Welder
Qualificatio
n
certificates
Welding
Engineer
PG/WC/001,AS
ME Sec. II part
C & GS EP PVV
611
Consumabl
e Batch
Certificates
Welding
Engineer
Meets
API 650
Drawing &
job specific
WPS
/Procedure
API 650
requirements
and job range
QCP.REF.100.14
00
5.1
NDE Testing
5.1.1
NDE Procedures
5.1.2
NDE Personal
Qualification
Reference No.:
Revision No.:
Date:
Covers full
range of
parameters and
processes and
meets CODE
requirements
Covers all
methods of NDE
applicable to
the degree of
competence
required
API 650 GS EP
PVV
Meets CODE
requirements and
covers job range
PGs Written
practice ASNT
Meets CODE
requirements and
covers job range
Covers Full
Range of
parameters
QC Manager/QC
Engineer
NDE
personnel
QC Manager/QC
Engineer
Qualificatio
n
Certificates
5.2
Procedures
5.2.1
QC Procedures
6.0
Manufacturing Of 4903F
6.1
Prefabrication
Activities(Sheet,
Nozzles and
Saddles)
QC Manager/QC
Engineer
QCP.REF.100.14
00
Reference No.:
Revision No.:
Date:
QCP.REF.100.14
00
6.1.1
Identification,
marking, cutting
and weld
preparation of
shell plates.
As per drawing
dimensions
within
tolerances.
Drawing, API
650 (UW-31),
Inspection
Request &
Material
Summary
sheet.
Supervisor & QC
Inspector
6.1.2
Fit up of shell
long seams along
with Production
Test Coupon (2
Coupons for each
WPS)
As per drawing
dimensions
within
tolerances.
API 650.
API 650
Inspection
report
Supervisor & QC
Inspector.
6.1.3
Mechanical test
on one two
Production Test
Coupon.
100% weld visual
And dimension
inspection on
Shell and
manhole long
seams joints.
Fit-up and
Welding WPS and
Qualified welders
As per concern
PQRs
mechanical
characteristics.
All relevant
drawing dim.
Concern WPS
& PQR.
Lab Test
Report
Project Engineer
& QC Welding
Inspector
Drawing API
650, GS EP
PVV 611 Rev:
06 &
MG/NDE/VT/00
6
WPS, list of
qualified and
approved
Weld Map.
Drawing
API 650, GS EP
PVV 611 Rev: 06
&
MG/NDE/VT/)006
Inspection
Request
(Form no
MSF 012)
Supervisor & QC
Inspector
Weld Visual
Request
(Form no
MSF 012)
Inspection
Request
(Form no
Supervisor & QC
Inspector
Supervisor & QC
Inspector
6.1.4
6.1.5
6.1.6
Flush Grinding of
Inside Welding
Penetration.
Welding per
WPS and
Qualified
welders.
Smooth
merging of
surface with
Drawing
shell surface.
6.1.7
10% RT on Shell
long seam joints.
Absence of
Internal defects.
6.1.8
100% RT on
Manhole long
seam joints.
Identification,
marking &
cutting and weld
preparation of
nozzle neck,
flange & fittings.
Absence of
Internal defects.
Manhole nozzle
and other Nozzle
neck with W.N
flange fit up (for
all nozzle)
Welding of
Manhole nozzle
and other nozzle
neck with flange.
6.1.1
0
6.1.1
1
6.1.1
2
Reference No.:
Revision No.:
Date:
QCP.REF.100.14
00
MSF 012)
PG/NDE/RT/00
4 API 650, GS
EP PVV 211
Rev: 06 & GS
EP PVV 611
Rev:06
PG/NDE/RT/00
API 650
API 650,
PG/NDE/RT/004,
GS EP PVV 211
Rev:06 & GS EP
PVV 611 Rev:06
RT Report
(Form No
MSF/014)
Level II
Inspector, QC
Inspector
API 650,
PG/NDE/RT/00
RT Report
As per drawing
dimensions
within
tolerances.
Drawing,
API
Drawing,
API 650
Inspection
Request &
Material
Summary
sheet
Level II
Inspector, QC
Inspector
Supervisor & QC
Inspector
As per drawing
dimensions
within
tolerances.
API 650
Inspection
request
Supervisor & QC
Inspector
Welding per
WPS and
Qualified
welders.
WPS, list of
qualified
welders and
approved
Weld Map.
API 650
Weld Visual
Request
Supervisor & QC
Inspector
6.1.1
3
Reference No.:
Revision No.:
Date:
QCP.REF.100.14
00
100% visual
inspection on
Manhole nozzle
neck and other
Nozzle neck with
Flange welds.
Flush Grinding of
Inside Welding
Penetration
Absence of
defects & all
relevant
drawing dim.
Drawing API
650, &
PG/NDE/VT/00
Inspection
Request
Supervisor & QC
Inspector
Smooth
merging of
surfaces
Drawing
Drawing
Inspection
Request
Supervisor & QC
Inspector
Absence of
Internal defects.
PG/NDE/RT/00,
API 650,
API 650,
PG/NDE/RT/00,
RT Report
Level II
Inspector, QC
Inspector
6.2.1
6
10% RT on
Nozzle with
flange for above
NPS 10 on
circular seam
joints.
Closing Seam Fit
Up
Drawing, API
650
Inspection
Report
Supervisor & QC
Inspector
6.2.1
7
Welding &
Closing Seam
As per drawing
dimensions
within
tolerances
Welding per
WPS and
Qualified
Welders
API 650
Weld Visual
Request
Supervisor & QC
Inspector
6.2.1
8
Weld Visual
Inspection 100%
Inspection
Request
Supervisor & QC
Inspector
6.2.1
9
10% Radiography
for Circular seam
WPS, list of
qualified
welder sand
approved weld
map
Drawing, API
650 &
PG/NDE/VT/00
PG/NDE/RT/00,
API 650
API 650,
PG/NDE/RT/00
RT Report
Level II
Inspector, QC
6.1.1
4
6.1.1
5
Weld Quality to
meet Code
requirement
Absence of
internal defects
Reference No.:
Revision No.:
Date:
welding
6.2.2
0
QCP.REF.100.14
00
Inspector
Spot RT on all
Long seam and
circular seam
intersecting
location. (100%
"T" section/ "+"
Section
100% MPT on all
Category "D"
Joints
Pneumatic
testing of R.F.
pad Nozzles at
1.0 Barg
External
Attachment
Fit up of saddle
support with
Vessel
Absence of
Internal defects
PG/NDE/RT/00,
API 650
API 650,
PG/NDE/RT/00
RT Report
Level II
Inspector, QC
Inspector
Weld Quality to
meet Code
Requirement
Integrity of
welds and leak
PG/NDE/MT/00
API 650
API 650,
PG/NDE/MT/00
MPT Report
Level II Inspector
Proc#
PG/PRTST/00
Proc#
PG/PRTST/00
Inspection
Report
QC Inspector
As per drawing
dimensions
API 650
Weld Visual
Request
Supervisor & QC
Inspector
6.3.2
Welding of saddle
support with
Vessel
Welding per
WPS and
Qualified
Welders
API 650
Weld Visual
Request
Supervisor & QC
Inspector
6.3.3
100% Visual
Inspection
Absence of
Defects
WPS, list of
qualified
welders and
approved weld
map
WPS, list of
qualified
welders and
approved weld
map
Drawing API
650 &
PG/NDE/VT/00
Weld
History
Sheet
Level II
Inspector/ QC
Inspector
6.2.2
1
6.2.2
2
6.3
6.3.1
6.3.4
6.3.5
6.3.6
6.3.7
6.3.8
Reference No.:
Revision No.:
Date:
QCP.REF.100.14
00
Ad per drawing
dimensions
WPS, list of
qualified
welders and
approved weld
map
API 650
Weld Visual
Request
Supervisor & QC
Inspector
Welding per
WPS and
Qualified
Welders
API 650
Weld Visual
Request
Supervisor & QC
Inspector
Weld
History
Sheet
Level II
Inspector/QC
Inspector
API 650,
PG/NDE/UT/00 &
PG/NDE/MT/00
UT Report
Level II
Inspector/QC
Inspector
Absence of
defects
WPS ,list of
qualified
welders and
approved weld
map
Drawing,
ASME Section
V Article 9 &
PG/NDE/VT/00
6
ASME Section
V,
PG/NDE/UT/00
&
PG/NDE/MT/00
PG/NDE/MT/00
ASME Sec V
Article 7
API 650,
Appendix 6,
PG/NDE/MT/00
MPT Report
Level II
Inspector/QC
Inspector
Absence of
defects
Absence of
Internal defects
Reference No.:
Revision No.:
Date:
QCP.REF.100.14
00
7.0
7.1
Flush Grinding of
All Inside Welding
Penetration
Smooth
merging of
surfaces
Drawing
Drawing
Inspection
Request
Supervisor & QC
Inspector
7.2
Final
Dimensional,
Visual Inspection
before internal
Trial assembly
Dimension
Check, Free of
visual defect
and distortion
Drawing API
650
QC Inspector
7.3
Trial assembly
internals
Dimension,
Location,
Orientation
Drawing
Drawing
Weld
History
Sheet/
Dimensiona
l Inspection
Report
Inspection
Report
Project
Engineer/QC
Inspector
7.4
Weighing of
Vessel
Final Weight of
vessel with full
internal
arrangements
Drawing
Horizontal lifting
and weight within
design limits and
hook load
specified
Inspection
Report
Project
Engineer/QC
Inspector
Removal of all
internal
attachments
Reference No.:
Revision No.:
Date:
7.5
Dismantling of all
internal items
and insulated
parts
Drawing
8.1
Hydro test
@required
pressure in
Vertical position.
The integrity of
vessel
8.2
Draining of hydro
test water
Proper venting,
complete
draining.
QCP.REF.100.14
00
Drawing
Project Engineer
API 650&
Proc#
PG/PRTEST/00
Pressure
Test Report
Supervisor & QC
Inspector
Proc#
PG/PRTEST/00
Proc#
PG/PRTEST/00
Project
Engineer/Supervi
sor/ QC
Inspector
9.1
Dimensional
inspection after
the completion of
Hydro test
10
Fixing of ASME
Name Plate &
Signing of MDR
10.1
Reference No.:
Revision No.:
Date:
QCP.REF.100.14
00
Dimensional
Check
Drawing, API
650
Weld
History
Sheet/
Dimensiona
l
Inspection
Report
QC Inspector
As per Drawing
Name
Plate/
Photograph
QC Inspector &
AI
10.2
Name Plate
attachment
vessel
As Per Drawing
Drawing API
650
QC Inspector &
AI
10.3
Manufacturer's
Data Report
Prepared per
requirement of
API 650
API 650
Manufactur
er's Data
Report
Quality Engineer
& AI
11.0
Release Note
11.1
Acceptance,
Inspection and
Release Note
12.0
As Built Dossier
12.1
As Built Dossier
and Records
Reference No.:
Revision No.:
Date:
QCP.REF.100.14
00
Contractual
requirements
fulfilled
Drawing, API
650
Final
Acceptance
/ Release
Note
Quality manager
All Required
Tests
completed, all
NCRs closed
out, all required
documentation
collated
Contractual
requirement
Contractual
requirement and
API 650
Manufactur
er Data
Dossier
(MDD)
Quality manager