F 222-01

INITIAL / 6 MTH FOLLOW-UP / SURVEILLANCE / RE- /


ASSESSMENT PLAN FOR ISO/IEC 17024:2012
(define which and delete rest)
Organization:

Address:

Company representative:

Assessment date:

Lead Assessor:

TechnicalAssessor/Experts(s):

Lead Assessor
Opening meeting and objectives of assessment.

Time
08:30

Assessment of the implementation of the


ISO/IEC 17024:2012 system and effective
implementation of the transition plan. (refer to
SANAS form F89):
-

SANAS
No:

Technical Assessor
Opening meeting and objectives of assessment.
Assessment of personnel certification schemes in
line with the SANAS form F178):
-

General Requirements
Structural Requirements
Resource Requirements
Information Requirements
Personnel Certification schemes

Application for Certification and Review


Assessment process
Examination process
Certification decisions
Maintaining Certification
Re-certification
Security measures

Lunch

12:00

Lunch

Assessors meeting

12:30

Assessors meeting

Continued assessment of implementation of


system throughout the facility.

12:45

Continued assessment of technical competence of


facility.

Preparation of report for closing meeting

14:45

Preparation of report for closing meeting

Closing meeting with management

15:00

Technical feedback to management

NOTE: The above times are approximate and may be subject to change